Movable steel pipe transportation track device
Technical Field
The utility model relates to the technical field of hydraulic and hydroelectric engineering construction, in particular to a movable steel pipe transportation track device for tunnel chamber construction.
Background
At present, when the steel pipe is installed in a tunnel hole and the installation position of the steel pipe is higher than the ground by more than one meter, the steel pipe cannot adopt the unloading mode of a conventional overhead anchor in a cavity, and the following problems exist in the hoisting of the pressure steel pipe in place by using an automobile crane for the installation of the cavity steel pipe with such an elevation difference by using the automobile crane:
1. The automobile crane is used for unloading and hoisting in the grotto, the large crane arm and the wall of the grotto are easy to collide, and great potential safety hazards exist.
2. The steel pipe is hoisted by using the automobile crane, so that the equipment occupancy rate is high and the cost is high.
3. In the process of hoisting the automobile, the pressure steel pipe shakes greatly, and a large construction safety risk exists.
4. The hoisting position of the automobile crane needs to be replaced repeatedly, and the construction efficiency is low.
Disclosure of utility model
The utility model aims to solve the hoisting problem in the background technology, and provides a movable pressure steel pipe transportation track device for replacing an automobile crane with a Tian anchor crane, so that the technical effect of using Tian anchors to carry out steel pipe crane in tunnel chambers is realized.
The technical scheme is that the movable steel pipe transportation rail device comprises two rail beams 2 and a rail 1 arranged on the rail beams 2, wherein the rail beams 2 are provided with a plurality of triangular supports 3, two triangular supports 3 which are parallel to each other are in a group, a transverse support 4 is connected between the two triangular supports 3 in the same group, the transverse support 4 comprises a cross rod 41 connected with the two triangular supports 3 in the same group and a vertical rod 42 connected with the bottom of the rail beams 2, the bottom end of the vertical rod 42 is in threaded connection with a telescopic base 5, the telescopic base 5 is provided with universal wheels 6 for device movement, the two rail beams 2 are detachably connected with a plurality of transverse connecting beams 7 through bolts, and the front part of the rail beams 2 is also provided with a vertical column 12 for extending and supporting.
Further, the front end of the track beam 2 is provided with a track beam horizontal lifting lug 21 for fixing on site, and the front end of the device is fixed on a construction site.
Further, the horizontal lifting lug 21 of the track beam is provided with a pin hole, the track beam 2 is fixed on site through the track beam pin shaft 10 which is inserted into the pin hole and anchored with a site structure, the track beam 2 can rotate along the track beam pin shaft 10, and a lifting operation space is reserved for the rear end before lifting.
Further, the track beam 2 is provided with a track beam vertical lifting lug 22 at the joint with the connecting beam 7, the connecting beam 7 is connected to the track beam vertical lifting lug 22 through bolts, and the connecting beam 7 can be quickly assembled and disassembled with the track beam 2.
Further, the triangular support frame 3 comprises a vertical support 32, a horizontal base 33 and two inclined supports 31 which are connected with each other, the included angles between the two inclined supports 31 and the vertical support 32 are 30 degrees, and the vertical support 32, the horizontal base 33 and the two inclined supports 31 are connected through welding, so that the structural strength and stability of the device are improved.
Further, the upright rod 42 is made of steel pipe, the bottom is provided with internal threads for being connected with the telescopic base 5 in a threaded mode, and the cross rod 41 is connected with the upright rod 42 in a welded mode.
Further, the triangular supports 3 arranged on each track beam 2 are at least two groups, so that the structural strength and stability of the device are improved.
Further, the number of the connecting beams 7 connecting the two track beams 2 is at least four, so that the structural strength and stability of the device are improved.
Further, the steel pipe installation rail car can move on the rail 1 and is used for steel pipe transportation and installation.
The device has the advantages that the device stably supports the track by adopting a plurality of groups of triangular supports, rapidly and flexibly installs the track in a tunnel chamber through the telescopic base and the universal wheels, is provided with the vertical lifting lugs of the track beam and the horizontal lifting lugs of the track beam for on-site anchoring and fixing of the device, and is matched with the fact that when a Tian anchor is adopted for unloading, only vertical displacement is generated in the steel pipe hoisting process, so that transverse shaking of the steel pipe is effectively avoided, safety of the steel pipe hoisting process is improved, the device adopts a rail car for steel pipe transportation, running stability and safety are high, and construction efficiency is greatly improved.
The utility model has the advantages of quick disassembly and assembly, high stability, good safety, flexible use, strong universality, repeated use, greatly reduced engineering construction cost and good application and popularization value in the technical field of water conservancy and hydropower construction.
Drawings
FIG. 1 is a schematic diagram of the structure of the present utility model;
FIG. 2 is a top view of the present utility model;
FIG. 3 is a front view of the present utility model;
FIG. 4 is a side view of the present utility model;
Fig. 5 is a schematic representation of an implementation of the present utility model.
Reference numerals:
1-track, 2-track beam, 3-triangular support frame, 4-transverse support frame, 5-telescopic base, 6-universal wheel, 7-connecting beam, 8-wheel frame, 9-wheel pin, 10-track beam pin, 11-step structure, 12-upright post, 21-track beam horizontal lifting lug, 22-track beam vertical lifting lug, 31-inclined support, 32-vertical support, 33-horizontal base, 41-cross bar and 42-upright post.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model. In the description of the present utility model, it should be understood that the terms "upper," "lower," "bottom," "end," "rear," "bottom," "inner," "outer," and the like indicate orientations or positional relationships based on the orientation or positional relationships shown in the drawings, merely to facilitate description of the present utility model, and do not indicate or imply that the devices or elements referred to must have a particular orientation, be configured and operated in a particular orientation, and thus should not be construed as limiting the present utility model.
In order that the above-recited objects, features and advantages of the present utility model will become more readily apparent, a more particular description of the utility model will be rendered by reference to the appended drawings and appended detailed description.
As shown in fig. 1-5, a movable steel pipe transportation rail device, including two track beams 2 and install track 1 on track beam 2, track beam 2 is equipped with a plurality of tripod 3, and two of mutually parallel tripod 3 are a set of, are connected with horizontal support frame 4 between two tripod 3 of same group, horizontal support frame 4 is including connecting the pole 41 with two tripod 3 of same group and connecting the pole 42 of track beam 2 bottom, pole 42 bottom threaded connection has telescopic base 5, telescopic base 5 installs the universal wheel 6 that is used for the device to remove, and two track beams 2 can dismantle through the bolt and be connected with a plurality of horizontal contact beam 7, track beam 2 front portion still is equipped with the stand 12 that is used for extending the support.
In this embodiment, the front end of the track beam 2 is provided with a track beam horizontal lifting lug 21 for fixing on site, and the front end of the device is fixed on a construction site.
The universal wheel 6 is connected with the base 5 through a wheel frame 8 and a wheel pin shaft 9.
The embodiment further comprises a track beam pin shaft 10, the track beam horizontal lifting lug 21 is provided with a pin hole, the track beam 2 is fixed on site through the track beam pin shaft 10 which is inserted into the pin hole and anchored with a site structure, and the track beam 2 can rotate along the track beam pin shaft 10 to vacate a hoisting operation space for the rear end.
The track beam 2 is provided with a track beam vertical lifting lug 22 at the joint with the connecting beam 7, and the connecting beam 7 is connected on the track beam vertical lifting lug 22 through bolts.
The triangular support frame 3 comprises a vertical support 32, a horizontal base 33 and two inclined supports (31) which are connected with each other, the included angles between the two inclined supports 31 and the vertical support 32 are 30 degrees, and the vertical support 32, the horizontal base 33 and the two inclined supports 31 are connected through welding, so that the structural strength and the stability of the device are improved.
The vertical rod 42 is made of steel pipes, the bottom of the vertical rod 42 is provided with internal threads for being connected with the telescopic base 5 in a threaded mode, and the cross rod 41 is connected with the vertical rod 42 in a welded mode.
The triangular supports 3 arranged on each track beam 2 are at least two groups, so that the structural strength and stability of the device are improved.
At least four connecting beams 7 are used for connecting the two track beams 2, so that the structural strength and stability of the device are improved.
The steel pipe installation rail car is capable of moving on the rail 1 and used for steel pipe transportation and installation.
The implementation process comprises the following steps:
the following description is made by the construction process of the steel pipe installation of a large pumped storage power station.
The construction site is provided with a vertical anchor at a proper position, a movable steel pipe transportation rail device is moved to a corresponding position on a cast-in-place step structure 11, the front end of a rail 1 is horizontally placed on the step structure 11, a rail beam 2 is placed on a lower level step, two holes are vertically formed on the lower level step of the step structure 11 according to the track gauge of a steel pipe installation rail car, a rail beam pin shaft 10 is inserted into the holes through a pin hole formed in a rail beam horizontal lifting lug 21, the front ends are fixed on site, after the front ends of the two rail beams 2 are fixed, a connecting beam 7 is not installed, a telescopic base 5 is screwed out, and a universal wheel 6 is downwards lower than a horizontal base 33 and is supported by a transverse supporting frame 4.
The rear ends of the two track beams 2 are closed by rotating the universal wheels 6 along the track beam pin shafts 10, so that the two tracks 1 are in a V-shaped state, a hoisting operation space at the rear end of the device is vacated, a trailer for transporting the steel pipes is backed up to a space anchor unloading position, after the steel pipe transport trailer is backed up to the unloading position at the rear end of the device, the steel pipes are vertically lifted to hover in the sky by the space anchors, the trailer is removed, the rear ends of the track beams 2 are moved by the universal wheels 6, the track 1 is unfolded along a tunnel portal from the steel pipes to the hovering position, the track 1 is in a II shape, the track gauge is kept, and the connecting beams 7 are all connected and installed on the track beam vertical lifting lugs 22 of the two track beams 2, as shown in fig. 5, so that the parallel track of the two tracks 1 is completed.
The steel pipe installation railcar is installed on the track 1 and moves to the position right below the hovering steel pipe, the steel pipe is hung on the steel pipe installation railcar through a Tian anchor, and then the steel pipe is transported to an installation position by the steel pipe installation railcar for construction.
After the pipeline construction is completed, the connecting beam 7 is removed, and then the track beam pin shaft 10 is removed to be separated from the step structure 11, so that the track device can be moved out for subsequent construction.
The vertical anchor is used for lifting the steel pipe in the steel pipe lifting process and lifting the steel pipe to the steel pipe installation railcar through the vertical anchor, the steel pipe is displaced in the vertical direction, transverse shaking of the steel pipe is effectively avoided, stability and safety of the steel pipe lifting process are improved, running stability and safety of the device are high, stable transportation of the steel pipe is carried out through the steel pipe installation railcar moving on the track 1, and construction efficiency is high, cost is low, and safety is high.