Shock-absorbing pump pipe fixing device suitable for assembled structure
Technical Field
The utility model belongs to the technical direction of concrete pumping, and particularly relates to a shock absorption pump pipe fixing device suitable for an assembled structure.
Background
When the main structure of the building engineering is constructed, because of the limitation of the site and the working surface, the pump truck can not meet the requirements of the height and the length of concrete pumping, so that a pump pipe is required to be connected in actual construction. At present, most houses begin to popularize the assembled wall board, so that the conventional fixing mode of the embedded shear wall is not suitable for the assembled building, and therefore, a shock absorption pump pipe fixing device suitable for the assembled structure is needed to solve the above-mentioned problems.
Disclosure of utility model
The utility model aims at solving the problems in the prior art by aiming at the prior device, namely a shock absorption pump pipe fixing device suitable for an assembled structure.
In order to solve the technical problems, the utility model provides the technical scheme that the shock absorption pump pipe fixing device suitable for the assembled structure comprises a floor bottom plate and a floor top plate, steel pipe vertical rods are arranged between the floor bottom plate and the floor top plate, steel pipe cross beams are arranged on the outer walls of the steel pipe vertical rods and the steel pipe cross beams, steel pipe fasteners are arranged on the outer walls of the steel pipe vertical rods and the steel pipe cross beams, pump pipes are arranged in the steel pipe cross beams, square lumber is arranged on the outer walls of the pump pipes, and the function of conveniently installing the pump pipe clamp is realized by arranging the floor bottom plate, the floor top plate, the steel pipe vertical rods, the steel pipe cross beams, the steel pipe fasteners, the pump pipes and the square lumber, so that the problem that the pump pipe clamp cannot be installed in an assembled building shear wall is effectively solved, and the working requirements of people are met.
Furthermore, the steel pipe pole setting is provided with four, and is square distribution between four steel pipe pole settings, has made things convenient for carrying out support work.
Furthermore, the four steel pipe vertical rods are connected through the steel pipe fasteners, so that the steel pipe vertical rods can be conveniently assembled.
Furthermore, the steel pipe cross beams are four, and the four steel pipe cross beams are distributed in a diamond shape, so that the support work is facilitated.
Furthermore, the two ends of the four steel pipe cross beams are connected with the steel pipe vertical rods through steel pipe fasteners, so that the steel pipe cross beams are conveniently fixed.
Still further, the square timber is provided with four, and four square timber are equiangular distribution along the axial central line of pump line, and four square timber are fixed in the inner wall of steel pipe crossbeam, have made things convenient for clamping and shock attenuation through the square timber.
Compared with the prior art, the utility model has the beneficial effects that,
(1) Through being provided with floor bottom plate, floor roof, steel pipe pole setting, steel pipe crossbeam, steel pipe fastener, pump line and square timber, realized having made things convenient for the function of installation pump line clamp to solve the unable installation pump line clamp problem of assembled building shear force wall effectively, and then satisfied people's work demand, be worth using widely.
Drawings
The accompanying drawings are included to provide a further understanding of the utility model and are incorporated in and constitute a part of this specification, illustrate the utility model and together with the embodiments of the utility model, serve to explain the utility model. In the drawings:
FIG. 1 is a schematic view of the overall structure of the present utility model;
Fig. 2 is a schematic top view of the present utility model.
In the figure, 1, a floor soleplate; 2, a floor top plate, 3, a steel pipe vertical rod, 4, a steel pipe cross beam, 5, a steel pipe fastener, 6, a pump pipe, 7 and square timber.
Detailed Description
The technical scheme of the present utility model is further described in non-limiting detail below with reference to the preferred embodiments and the accompanying drawings. It will be apparent that the described embodiments are only some, but not all, embodiments of the utility model. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1-2, the utility model provides a shock absorption pump pipe fixing device suitable for an assembled structure, which comprises a floor bottom plate 1 and a floor top plate 2, wherein a steel pipe vertical rod 3 is arranged between the floor bottom plate 1 and the floor top plate 2, a steel pipe cross beam 4 is arranged on the outer wall of the steel pipe vertical rod 3, steel pipe fasteners 5 are arranged on the outer walls of the steel pipe vertical rod 3 and the steel pipe cross beam 4, a pump pipe 6 is arranged in the steel pipe cross beam 4, square lumber 7 is arranged on the outer wall of the pump pipe 6, and the function of conveniently installing the pump pipe clamp is realized by arranging the floor bottom plate 1, the floor top plate 2, the steel pipe vertical rod 3, the steel pipe cross beam 4, the steel pipe fasteners 5, the pump pipe 6 and the square lumber 7, so that the problem that the pump pipe clamp cannot be installed in an assembled building shear wall is effectively solved, and further the working requirements of people are met.
Furthermore, the four steel pipe vertical rods 3 are arranged, and the four steel pipe vertical rods 3 are distributed in a square shape, so that supporting work is facilitated.
Furthermore, the four steel pipe vertical rods 3 are connected through the steel pipe fasteners 5, so that the steel pipe vertical rods 3 can be conveniently assembled.
Furthermore, the four steel pipe cross beams 4 are arranged, and the four steel pipe cross beams 4 are distributed in a diamond shape, so that the support work is facilitated.
Furthermore, two ends of the four steel pipe cross beams 4 are connected with the steel pipe vertical rods 3 through the steel pipe fasteners 5, so that the steel pipe cross beams 4 are conveniently fixed.
Still further, square timber 7 is provided with four, and four square timber 7 are equiangular distribution along the axial central line of pump line 6, and four square timber 7 are fixed in the inner wall of steel pipe crossbeam 4, have made things convenient for clamping and shock attenuation through square timber 7.
When in use. Firstly, the steel pipe vertical rods 3 are fixedly assembled through the steel pipe fasteners 5, then the top and the bottom of the steel pipe vertical rods 3 are fixed into the floor bottom plate 1 and the floor top plate 2 through expansion bolts, then the steel pipe cross beam 4 is fixed to the outer wall of the steel pipe vertical rods 3 through the steel pipe fasteners 5, and the square timber 7 is fixed to the inner wall of the steel pipe cross beam 4, so that the pump pipe 6 is clamped through the square timber 7, the damping effect is achieved, and the problem that the pump pipe clamp cannot be installed on the assembled building shear wall is effectively solved.
In the description of the present utility model, it should be understood that the directions or positional relationships indicated by the terms "upper", "lower", "front", "rear", "left", "right", etc. are based on the directions or positional relationships shown in the drawings, are merely for convenience of describing the present utility model, and do not indicate or imply that the apparatus or elements referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus should not be construed as limiting the present utility model.
Finally, it should be pointed out that the above embodiments are only intended to illustrate the technical solution of the utility model, not to limit it. Although the present utility model has been described in detail with reference to the foregoing embodiments, those skilled in the art will understand that modifications may be made to the technical solutions described in the foregoing embodiments, or equivalents may be substituted for some of the technical features thereof, without departing from the spirit and scope of the technical solutions of the embodiments of the present utility model.