CN222771834U - A temporary construction frame for building construction - Google Patents
A temporary construction frame for building construction Download PDFInfo
- Publication number
- CN222771834U CN222771834U CN202421577502.6U CN202421577502U CN222771834U CN 222771834 U CN222771834 U CN 222771834U CN 202421577502 U CN202421577502 U CN 202421577502U CN 222771834 U CN222771834 U CN 222771834U
- Authority
- CN
- China
- Prior art keywords
- lifting table
- construction
- frame
- lifting
- construction frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Movable Scaffolding (AREA)
Abstract
The utility model discloses a temporary construction frame for a house building, which comprises a base, wherein a construction frame body is arranged on one side of the top of the base, a lifting table is arranged on the other side of the base, a connecting frame is connected between the construction frame body and the lifting table, lifting boxes capable of lifting are arranged on the side walls of the lifting table, the construction frame body is provided with multiple layers according to the construction height and comprises a vertical rod, the connecting frame comprises telescopic blocks, the connecting frame is of a 匚 -shaped design, and the inner wall of the connecting frame is provided with the telescopic blocks through springs. This temporary scaffold is built in room is provided with the curb plate of both sides and is used for the protection to the whole side of scaffold body, avoids personnel to have the possibility of falling from both sides to be connected with the link between scaffold body and the promotion platform, shrink when the hoist box is driven to rise to the flexible piece in the link simultaneously, make the bell in the flexible piece rock and produce the bell, suggestion this layer personnel's material has been delivered.
Description
Technical Field
The utility model relates to the technical field of building construction frames, in particular to a temporary building construction frame.
Background
The construction frame used in the house construction engineering is also called a scaffold and is a working platform which is erected for ensuring that each construction process is carried out smoothly. The scaffold is divided into an outer scaffold and an inner scaffold according to the set-up positions, and is divided into a wood scaffold, a bamboo scaffold and a steel pipe scaffold according to different materials.
The utility model patent with the bulletin number of CN 217975283U discloses a house construction frame, which comprises a bottom plate, wherein a frame main body is arranged at the upper end of the bottom plate, one side of the frame main body is provided with a lifting assembly, the lifting assembly comprises two groups of fixing columns fixedly connected with the bottom plate, one sides of the two groups of fixing columns are fixedly connected with sliding rails together, the front end of the sliding rails is provided with an adjusting assembly, the adjusting assembly comprises a sliding block, the front end of the sliding block is fixedly connected with a connecting plate, the front end of the connecting plate is fixedly connected with a connecting rod, the front end of the connecting rod is fixedly connected with a rotating plate, and the inner side of the rotating plate is provided with a steel wire rope.
However, the technical scheme has certain defects that when the technical scheme is used, when workpieces are conveyed to the highest layer, materials connected with the end parts of the steel wire ropes can only move to the position which is parallel to the highest layer, the side surface of the main body of the construction frame is not protected, people need to squat down and take materials from the side surface when taking the materials, and certain danger exists in the process of taking the materials after lifting.
Disclosure of utility model
The utility model aims to provide a temporary construction frame for building construction, which aims to solve the problems in the background technology.
In order to achieve the aim, the utility model provides the technical scheme that the temporary construction frame for the house building comprises a base,
A construction frame body is arranged on one side of the top of the base, a lifting table is arranged on the other side of the base, a connecting frame is connected between the construction frame body and the lifting table, and a lifting box capable of lifting is arranged on the side wall of the lifting table;
The construction frame comprises a construction frame body and is characterized in that multiple layers of construction frame bodies are arranged according to construction heights, the construction frame body comprises vertical rods, the vertical rods are distributed in a rectangular shape, transverse operation platforms are arranged among the vertical rods, inclined ladders are further arranged among the vertical rods, and side plates are arranged among the vertical rods on the same side;
The connecting frame comprises a telescopic block, the connecting frame is of a '匚' shape, the inner wall of the connecting frame is provided with the telescopic block through a spring, and a bell is arranged in the telescopic block.
Through adopting above-mentioned technical scheme, when using, personnel go up the eminence through the inclined ladder after, the curb plate plays the protective effect of both sides, when the hoist box is carrying material or work piece and is rising, passes the fluting in the link to the position of compression flexible piece makes the bell in the flexible piece produce and rocks and make a sound, and then reminds the staff on this layer to have the hoist box to pass through, still can know the hoist box arrival after making things convenient for personnel to be realized by the curb plate separation.
According to the utility model, the lifting table comprises connecting plates, the top and the bottom of the lifting table are provided with the connecting plates, a plurality of lifting tables are fixed through matching of screw holes on the connecting plates and bolts after being butted, the tops of two sides of the lifting table are provided with mounting seats I, through grooves are formed in the lifting table in a penetrating mode, and longitudinal T-shaped guide grooves are formed in the side walls, close to the connecting frames, of the lifting table.
Through adopting above-mentioned technical scheme, when installing the elevating platform, dock and improve the height of whole elevating platform with bolt fastening through a plurality of connecting plates to the installation of mount pad two is convenient for in the design of mount pad one, and the convenient pass of receiving the rope of design of logical groove, the convenient direction to the hanging box of design of T shape guide way.
As a further scheme of the utility model, steering mechanisms are arranged on two side walls of the lifting table at the top, each steering mechanism comprises a second mounting seat, each second mounting seat is aligned with one first mounting seat, and a rotating wheel is rotatably arranged on each second mounting seat.
Through adopting above-mentioned technical scheme, when using, through the direction of motion of turning wheel regulation receipts winding rope, and then conveniently stimulate the lift of hanging box.
As a further scheme of the utility model, a winding disc is arranged at the top of the base, a motor is arranged at the back of the winding disc, a winding rope is wound on the winding disc, and the end part of the winding rope bypasses the steering mechanism and is connected with the hanging box.
Through adopting above-mentioned technical scheme, the motor drive rolling dish at rolling dish back rotates, and then realizes the rolling or unreeling of rolling rope.
As a further scheme of the utility model, the hanging box comprises a sliding block, the side wall, close to the lifting table, of the hanging box is provided with the sliding block, and the sliding block is slidably arranged in the T-shaped guide groove.
Through adopting above-mentioned technical scheme, when using, through the design of slider in T shape guide way, play direction and spacing effect to the lift of hanging the case, produce when avoiding hanging the case to go up and down and rock.
Compared with the prior art, the temporary construction frame for the house building has the beneficial effects that the temporary construction frame for the house building,
The side plates on two sides are used for protecting the whole side face of the construction frame body, the possibility that personnel fall from two sides is avoided, the connection frame is connected between the construction frame body and the lifting table, and meanwhile, the telescopic blocks in the connection frame shrink when the hanging box is driven to lift, so that the bell in the telescopic blocks shakes and produces ringing, and the layer of personnel is prompted that materials are delivered;
In addition, this house is built interim scaffold and is still provided with T shape guide way and slider, slider slidable mounting in T shape guide way, when the hoist box goes up and down, plays spacing guide's effect to the hoist box, produces when avoiding hoist box to rise and rocks.
Drawings
FIG. 1 is a schematic elevational view of the present utility model;
FIG. 2 is a schematic perspective view of a lifting platform and a connecting frame according to the present utility model;
Fig. 3 is a schematic perspective view of the hanging box of the present utility model.
In the figure, 1, a base; 2, a construction frame body, 201, a vertical rod, 202, an operation platform, 203, an inclined ladder, 204, a side plate, 3, a lifting platform, 301, a connecting plate, 302, a first installation seat, 303, a through groove, 304, a T-shaped guide groove, 4, a connecting frame, 401, a telescopic block, 5, a winding disc, 6, a steering mechanism, 601, a second installation seat, 602, a rotating wheel, 7, a winding rope, 8, a hanging box, 801 and a sliding block.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1-3, the present utility model provides a temporary construction frame for building, comprising a base 1,
A construction frame body 2 is arranged on one side of the top of the base 1, a lifting table 3 is arranged on the other side of the base 1, a connecting frame 4 is connected between the construction frame body 2 and the lifting table 3, and a lifting box 8 capable of lifting is arranged on the side wall of the lifting table 3;
the construction frame body 2 is provided with multiple layers according to the construction height, the construction frame body 2 comprises vertical rods 201, the vertical rods 201 are distributed in a rectangular shape, a transverse operation platform 202 is arranged between the vertical rods 201, an inclined ladder 203 is also arranged between the vertical rods 201, and a side plate 204 is arranged between the vertical rods 201 on the same side;
The connecting frame 4 comprises a telescopic block 401, the connecting frame 4 is of a 匚 -shaped design, the inner wall of the connecting frame 4 is provided with the telescopic block 401 through a spring, and a bell is arranged in the telescopic block 401;
Specifically, install the reinforced diagonal bar on the scaffold body 2, improve the intensity of whole scaffold body 2, telescopic block 401 is triangle-shaped design, conveniently compresses telescopic block 401.
Referring to fig. 2, further, the lifting platform 3 includes a connecting plate 301, the top and bottom of the lifting platform 3 are provided with the connecting plate 301, the plurality of lifting platforms 3 are fixed by matching screw holes and bolts on the connecting plate 301 after being butted, the top of two sides of the lifting platform 3 is provided with a mounting seat 302, the lifting platform 3 is provided with a through groove 303 in a penetrating manner, and the side wall of the lifting platform 3, which is close to the connecting frame 4, is provided with a longitudinal T-shaped guide groove 304.
Referring to fig. 1, further, both side walls of the top lifting platform 3 are provided with a steering mechanism 6, the steering mechanism 6 includes a second mounting seat 601, the second mounting seat 601 is aligned with the first mounting seat 302, and a rotating wheel 602 is rotatably mounted on the second mounting seat 601.
Referring to fig. 1, further, a winding disc 5 is installed at the top of the base 1, a motor is installed at the back of the winding disc 5, a winding rope 7 is wound on the winding disc 5, and the end part of the winding rope 7 bypasses the steering mechanism 6 and is connected with a hanging box 8;
specifically, the winding rope 7 passes through the through groove 303 to contact with the rotating wheel 602 at the other side after passing through the rotating wheel 602, and is fixedly connected with the top of the hanging box 8 downwards.
Referring to fig. 3, further, the hanging box 8 includes a sliding block 801, the side wall of the hanging box 8 close to the lifting table 3 is provided with the sliding block 801, and the sliding block 801 is slidably mounted in the T-shaped guide groove 304;
Specifically, the thickness of the hanging box 8 matches the space in the connecting frame 4.
The temporary construction frame for the house is characterized in that when the temporary construction frame for the house is used, side plates 204 on two sides are used for protecting the whole side face of a construction frame body 2, the possibility that personnel fall from two sides is avoided, a connecting frame 4 is connected between the construction frame body 2 and a lifting table 3, meanwhile, a telescopic block 401 in the connecting frame 4 contracts when a hanging box 8 is driven to be lifted, bell in the telescopic block 401 shakes and produces ringing, the layer of personnel is prompted to send materials, a sliding block 801 is slidably arranged in a T-shaped guide groove 304, the hanging box 8 is limited and guided when the hanging box 8 is lifted, shaking is avoided when the hanging box 8 is lifted, and the contents which are not described in detail in the specification belong to the prior art known to the person skilled in the art.
The terms "center," "longitudinal," "transverse," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," and the like are used for descriptive simplicity and convenience only and not as an indication or implying that the apparatus or element being referred to must have a particular orientation, be constructed and operated for a particular orientation, based on the orientation or positional relationship illustrated in the drawings, and thus should not be construed as limiting the scope of the present utility model.
Although the present utility model has been described with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described, or equivalents may be substituted for elements thereof, and any modifications, equivalents, improvements and changes may be made without departing from the spirit and principles of the present utility model.
Claims (5)
1. Temporary scaffold is built in room, including base (1), its characterized in that:
A construction frame body (2) is arranged on one side of the top of the base (1), a lifting table (3) is arranged on the other side of the base (1), a connecting frame (4) is connected between the construction frame body (2) and the lifting table (3), and a lifting box (8) capable of lifting is arranged on the side wall of the lifting table (3);
The construction frame comprises a construction frame body (2), wherein multiple layers are arranged according to construction heights, the construction frame body (2) comprises vertical rods (201), the vertical rods (201) are distributed in a rectangular shape, transverse operation platforms (202) are arranged among the vertical rods (201), inclined ladders (203) are further arranged among the vertical rods (201), and side plates (204) are arranged among the vertical rods (201) on the same side;
The connecting frame (4) comprises a telescopic block (401), the connecting frame (4) is of a '匚' shape, the telescopic block (401) is mounted on the inner wall of the connecting frame (4) through a spring, and a bell is mounted in the telescopic block (401).
2. The temporary construction frame for building construction according to claim 1, wherein the lifting table (3) comprises a connecting plate (301), the connecting plate (301) is installed at the top and the bottom of the lifting table (3), a plurality of lifting tables (3) are fixed through matching of screw holes and bolts on the connecting plate (301) after being butted, mounting seats I (302) are arranged at the tops of two sides of the lifting table (3), through grooves (303) are formed in the lifting table (3) in a penetrating mode, and longitudinal T-shaped guide grooves (304) are formed in the side walls, close to the connecting frame (4), of the lifting table (3).
3. The temporary construction frame for building construction according to claim 2, wherein steering mechanisms (6) are arranged on two side walls of the lifting table (3) at the top, the steering mechanisms (6) comprise a second mounting seat (601), the second mounting seat (601) is aligned with the first mounting seat (302), and a rotating wheel (602) is rotatably arranged on the second mounting seat (601).
4. The temporary construction frame for building construction according to claim 3, wherein the top of the base (1) is provided with a winding disc (5), the back of the winding disc (5) is provided with a motor, the winding disc (5) is wound with a winding rope (7), and the end part of the winding rope (7) bypasses the steering mechanism (6) and is connected with the hanging box (8).
5. The temporary construction frame for building construction according to claim 4, wherein the hanging box (8) comprises a sliding block (801), the sliding block (801) is arranged on the side wall, close to the lifting table (3), of the hanging box (8), and the sliding block (801) is slidably arranged in the T-shaped guide groove (304).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202421577502.6U CN222771834U (en) | 2024-07-04 | 2024-07-04 | A temporary construction frame for building construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202421577502.6U CN222771834U (en) | 2024-07-04 | 2024-07-04 | A temporary construction frame for building construction |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN222771834U true CN222771834U (en) | 2025-04-18 |
Family
ID=95343644
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202421577502.6U Active CN222771834U (en) | 2024-07-04 | 2024-07-04 | A temporary construction frame for building construction |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN222771834U (en) |
-
2024
- 2024-07-04 CN CN202421577502.6U patent/CN222771834U/en active Active
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110424270B (en) | Anti-falling device for urban bridge construction | |
| CN110173103B (en) | Attached detachable multifunctional aerial work platform | |
| CN212151270U (en) | Moving platform type hanging basket platform | |
| CN210105344U (en) | Over-and-under type construction platform of unloading | |
| CN113062578B (en) | Liftable mobile operation platform | |
| CN218292712U (en) | But height-adjusting's scaffold frame for house construction | |
| CN212581394U (en) | Portable small-size material transport device | |
| KR102520583B1 (en) | Gondola Working Platform | |
| CN215978364U (en) | A remove measure frame for installing wall profiled sheet | |
| CN209837719U (en) | Over-and-under type construction is with platform of unloading | |
| CN213894834U (en) | A Truss Bridge Based on Attached Lifting Platform | |
| CN217299716U (en) | Scaffold for building maintenance convenient to delivery goods | |
| CN209259612U (en) | A kind of feeding device for construction | |
| CN223661330U (en) | A double-layer suspended platform | |
| CN219548369U (en) | Novel construction hanging basket | |
| CN112627487A (en) | Climbing frame attachment structure suitable for decorative constructional column | |
| CN113463899A (en) | Self-sealing gravity climbing wall type self-climbing operation platform | |
| CN218406380U (en) | Construction scaffold | |
| CN217868003U (en) | Double-mast type aluminum alloy lifting platform | |
| JP3174677B2 (en) | Tower-like structure erection equipment | |
| JP2531228Y2 (en) | Lift for building construction and repair | |
| CN223805818U (en) | An auxiliary device for the rapid up-and-down sliding installation of exterior wall panels | |
| CN212224906U (en) | Movable protective fence for building construction | |
| CN217458638U (en) | Material lifting device for building construction with good stability | |
| CN221319144U (en) | Lifting device for conveying building materials |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |