Pipeline hanging bracket for I-shaped steel beam
Technical Field
The utility model belongs to the technical field of building tool, concretely relates to pipeline gallows for on I-steel beam.
Background
In the construction process of the steel structure factory building, a hanging bracket is connected to the bottom of the I-shaped steel beam during pipeline installation, the hanging bracket is fixedly connected with the I-shaped steel beam, and the lower part of the hanging bracket is used for connecting and fixing a pipeline.
The prior art CN216158488U discloses a pipeline installation gallows under I-beam, and the installation gallows is equipped with I-beam hanger and pipeline hanger, is equipped with the pipeline fastener in the pipeline hanger, is connected through adjusting screw and adjusting nut between I-beam hanger and the pipeline hanger. The novel steel I-beam hanger can conveniently adjust the distance between the pipeline or the pipeline and the steel I-beam while meeting the requirement of fixing the pipeline or the pipeline, but still has the defect of poor universality, and is characterized in that the width of the steel I-beam hanger cannot be adjusted according to the width of the steel I-beam, the inner diameter of a pipeline clamp cannot be adjusted according to the outer diameter of the pipeline, and therefore the steel I-beam hanger cannot be suitable for the installation of the steel I-beams with various widths and the pipelines with various outer diameters. In addition, although the installation height of the pipeline or the pipeline can be adjusted, the stability of the pipeline and the pipeline can be reduced along with the increase of the downward moving distance of the pipeline or the pipeline, and the pipeline are easy to shake.
Disclosure of utility model
The utility model discloses a pipeline gallows for on I-steel girder aims at solving the following problem among the prior art, and current patent can not be according to the width adjustment I-steel girder hanger's width of I-steel girder, can not be according to the internal diameter of the external diameter adjustment pipeline fastener of pipeline to can not be applicable to the I-steel girder of multiple width and the pipeline installation of multiple external diameter. In addition, although the installation height of the pipeline or the pipeline can be adjusted, the stability of the pipeline or the pipeline itself is reduced and the pipeline or the pipeline is easy to shake along with the increase of the downward moving distance of the pipeline or the pipeline.
In order to achieve the above purpose, the technical scheme of the utility model is:
The utility model provides a pipeline gallows for on I-beam, includes I-beam mounting bracket, link, pipeline mounting bracket, I-beam mounting bracket be horizontal telescopic structure to be connected fixedly with the flange board of I-beam bottom both sides, link and I-beam mounting bracket pass through first bolt and nut and connect fixedly, the bottom of link and pipeline mounting bracket top pass through second bolt and nut and connect fixedly, the pipeline mounting bracket in be equipped with telescopic fixture, first bolt and second bolt configuration have telescopic fastening mechanism.
Preferably, the I-steel beam mounting frame comprises 2 first C-shaped steel which are oppositely arranged, the 2 first C-shaped steel is used for being clamped on flange plates on two sides of the bottom end of the I-steel beam, an L-shaped steel plate is integrally formed at the bottom end of the first C-shaped steel, a vertical section of the L-shaped steel plate is fixedly connected with the connecting frame through a first bolt and a nut, the end part of the horizontal section is integrally formed with the end part of a side plate at the bottom of the first C-shaped steel, and the first C-shaped steel is fixedly connected with the flange plates through a positioning bolt.
Preferably, the connecting frame is made of first U-shaped steel, the vertical section of the L-shaped steel plate and the side wall of the first U-shaped steel are provided with first connecting holes relatively, the first bolts penetrate through the 2 first connecting holes, nuts are arranged at the tail ends of the first bolts, and telescopic fastening mechanisms are arranged on the first bolts between the 2 first connecting holes.
Preferably, the pipeline mounting frame including locating the second U shaped steel at top and connect in the staple bolt structure of second U shaped steel bottom, the opening up of first U shaped steel, the opening of second U shaped steel is downwards, the bottom of first U shaped steel and the top of second U shaped steel be equipped with the second connecting hole relatively, first U shaped steel and second U shaped steel pass through the second bolt and the spiro union of 2 second connecting holes and be connected at the nut of second bolt tip, be equipped with telescopic fastening mechanism on the second bolt between 2 second connecting holes.
Preferably, the anchor ear structure include relative first anchor ear arm, the second anchor ear arm that sets up from top to bottom, the top of first anchor ear arm and 2 free ends welded fastening of second U shaped steel, first anchor ear arm and second anchor ear arm pass through third bolt and nut connection and fix.
Preferably, the telescopic clamping mechanism comprises arc clamping plates which are respectively arranged on the inner sides of the first hoop arm and the second hoop arm, a fourth bolt is arranged at the outer side end of the arc clamping plate, the fourth bolt penetrates through the middle part of the first hoop arm or the second hoop arm and is in threaded connection with the first hoop arm or the second hoop arm, and the tail end of the fourth bolt is rotationally connected with the outer surface of the arc clamping plate.
Preferably, the inner surface of the arc-shaped clamping plate is provided with an elastic rubber layer.
Preferably, the telescopic fastening mechanism comprises a first sleeve, a second sleeve and a third sleeve, wherein the first sleeve is in threaded connection with a first bolt or a second bolt, external threads with opposite rotation directions are arranged at two ends of the outer surface of the first sleeve, the second sleeve and the third sleeve are respectively in threaded connection with two ends of the outer surface of the first sleeve, one ends, far away from the first sleeve, of the second sleeve and the third sleeve are compression surfaces, and stiffening rib plates are arranged on one sides, facing the compression surfaces, of the outer surfaces of the second sleeve and the third sleeve.
The utility model relates to a pipeline gallows for on I-steel girder has the beneficial effect:
The utility model discloses can realize the firm connection with the I-steel beam of different width to can adapt to the pipeline of different external diameters fixed, through setting up telescopic fastening mechanism, can make the stable relation of connection of keeping between I-steel beam mounting bracket, link, the pipeline mounting bracket three, be favorable to the stability of pipeline in-process of use position.
Drawings
Fig. 1 is a schematic diagram of the main structure of the present invention.
Fig. 2 is a schematic diagram of the overall structure of the present invention.
1. I-shaped steel beam, 2, a first C-shaped steel, 3, L-shaped steel plates, 4, a first bolt, 5, a first U-shaped steel, 6, a second U-shaped steel, 7, a second bolt, 8, a first anchor ear arm, 9, a second anchor ear arm, 10, a third bolt, 11, a first sleeve, 12, a second sleeve, 13, a third sleeve, 14, a stiffening rib plate, 15, an arc-shaped clamping plate and 16, and a fourth bolt.
Detailed Description
The following description is of the preferred embodiments of the present invention and is not intended to limit the scope of the invention, but is intended to cover any modifications, equivalents, improvements, etc. within the spirit and principles of the present invention.
The following examples are to be understood as being a separate representation of part of the novel structures or methods and also as being a combination of the examples with each other to illustrate the meaning of the novel structures or methods of greater scope.
Example 1
A pipeline gallows for on I-beam, as shown in fig. 1, 2, including I-beam mounting bracket, link, pipeline mounting bracket, I-beam mounting bracket be horizontal telescopic structure, the convenience is connected with the I-beam bottom of multiple width, is connected fixedly with the flange plate of I-beam 1 bottom both sides during the connection, link and I-beam mounting bracket pass through first bolt 4 and nut and connect fixedly, the bottom and the pipeline mounting bracket top of link pass through second bolt 7 and nut and connect fixedly, the pipeline mounting bracket in be equipped with telescopic fixture for the pipeline of the fixed different external diameters of centre gripping, first bolt and second bolt configuration have telescopic fastening mechanism to be convenient for adjust the height of pipeline or the span of I-beam mounting bracket.
Example 2
As shown in fig. 1 and 2, the i-beam mounting frame comprises 2 first C-shaped steel 2,2 first C-shaped steel 3, which are oppositely arranged, and are used for being clamped on flange plates on two sides of the bottom end of the i-beam 1, an L-shaped steel plate 3 is integrally formed at the bottom end of the first C-shaped steel 2, a vertical section of the L-shaped steel plate 3 is fixedly connected with a connecting frame through a first bolt 4 and a nut, the end part of the horizontal section is integrally formed with the end part of a side plate at the bottom of the first C-shaped steel 2, and the first C-shaped steel is fixedly connected with the flange plates through a positioning bolt.
As shown in fig. 1 and 2, the connecting frame is made of a first U-shaped steel 5, first connecting holes (not shown in the drawings) are formed in the vertical section of the L-shaped steel plate 3 and the side wall of the first U-shaped steel 5, the first bolts 4 penetrate through the 2 first connecting holes, nuts are arranged at the tail ends of the first bolts 4, and telescopic fastening mechanisms are arranged on the first bolts between the 2 first connecting holes.
Example 3
As shown in fig. 1 and 2, the pipe mounting rack comprises a second U-shaped steel 6 arranged at the top and a hoop structure connected to the bottom of the second U-shaped steel 6, the opening of the first U-shaped steel 5 faces upwards, the opening of the second U-shaped steel 6 faces downwards, a second connecting hole (not shown in the figure) is relatively formed in the bottom end of the first U-shaped steel 5 and the top end of the second U-shaped steel 6, the first U-shaped steel 5 and the second U-shaped steel 6 are connected through a second bolt 7 penetrating through 2 second connecting holes and a nut screwed at the end part of the second bolt 7, and a telescopic fastening mechanism is arranged on the second bolt between the 2 second connecting holes.
Example 4
As shown in fig. 1 and 2, the hoop structure comprises a first hoop arm 8 and a second hoop arm 9 which are arranged vertically and oppositely, the top of the first hoop arm 8 is welded and fixed with 2 free ends of the second U-shaped steel 6, and the first hoop arm 8 and the second hoop arm 9 are connected and fixed through a third bolt 10 and a nut.
As shown in fig. 2, the telescopic clamping mechanism comprises arc clamping plates 15 respectively arranged on the inner sides of the first hoop arm 8 and the second hoop arm 9, a fourth bolt 16 is arranged at the outer side end of the arc clamping plates 15, the fourth bolt 16 penetrates through the middle part of the first hoop arm 8 or the second hoop arm 9 and is in threaded connection with the first hoop arm 8 or the second hoop arm 9, the tail end of the fourth bolt 16 is rotationally connected with the outer surface of the arc clamping plates 15, and the position of the arc clamping plates 15 can be adjusted by rotating the fourth bolt 16, so that the clamping fixation of pipelines with different outer diameters is realized.
As shown in FIG. 2, an elastic rubber layer (not shown) is provided on the inner surface of the arc clamping plate 15, so as to protect the pipeline.
Example 5
As shown in fig. 2, the telescopic fastening mechanism comprises a first sleeve 11, a second sleeve 12 and a third sleeve 13, the first sleeve 11 is in threaded connection with the first bolt 4 or the second bolt 7, external threads with opposite rotation directions are arranged at two ends of the outer surface of the first sleeve 11, the second sleeve and the third sleeve are respectively in threaded connection with two ends of the outer surface of the first sleeve 11, one ends, far away from the first sleeve 11, of the second sleeve and the third sleeve are compression surfaces, and stiffening rib plates 14 are arranged on one sides, facing the compression surfaces, of the outer surfaces of the second sleeve and the third sleeve.
When the novel pipeline fixing device is used, as shown in fig. 2, the pipeline is clamped between 2 arc clamping plates, the fourth bolt is rotated to lock the pipeline, the pipeline is adjusted to a set height through adjusting the nut on the second bolt, then, the pipeline is rotated to the designed direction, the second sleeve and the third sleeve of the telescopic fastening mechanism on the second bolt are rotated, the pressurizing surfaces of the second sleeve and the third sleeve are respectively pressed and fixed with the top of the second U-shaped steel 6 and the bottom of the first U-shaped steel 5, the first U-shaped steel 5 and the second U-shaped steel 6 are relatively fixed with the second screw through the pressurizing and fixing, and meanwhile, the first U-shaped steel 5 and the second U-shaped steel 6 can be relatively fixed due to the action of the stiffening rib plates, so that the accurate stability of pipeline positioning is ensured.
Similarly, it can be understood that by adjusting the telescopic fastening mechanism on the first bolt, the vertical section of the L-shaped steel plate 3 and the side wall of the first U-shaped steel can be stably connected, and the 2C-shaped steel can still keep a stable connection relationship with the first U-shaped steel under the condition of span change, so that the connection with the i-shaped steel beams 1 with different widths is applicable.