CN222614541U - Combined factory building steel structure - Google Patents

Combined factory building steel structure Download PDF

Info

Publication number
CN222614541U
CN222614541U CN202421304869.0U CN202421304869U CN222614541U CN 222614541 U CN222614541 U CN 222614541U CN 202421304869 U CN202421304869 U CN 202421304869U CN 222614541 U CN222614541 U CN 222614541U
Authority
CN
China
Prior art keywords
block
connecting block
fixedly connected
wall
steel structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202421304869.0U
Other languages
Chinese (zh)
Inventor
楼龙飞
杨锡辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Baohong Steel Structure Manufacturing Co ltd
Original Assignee
Zhejiang Baohong Steel Structure Manufacturing Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Baohong Steel Structure Manufacturing Co ltd filed Critical Zhejiang Baohong Steel Structure Manufacturing Co ltd
Priority to CN202421304869.0U priority Critical patent/CN222614541U/en
Application granted granted Critical
Publication of CN222614541U publication Critical patent/CN222614541U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to the field of combined plant steel, and discloses a combined plant steel structure which comprises a second connecting block, wherein the left end of the second connecting block is connected with a support column through a first installation component, the top end of the support column is fixedly connected with a first connecting block, the left end of the first connecting block is connected with a cross beam through a second installation component, the top end of the support column is provided with a clamping groove, the inner walls of the support columns are all slidingly connected with limiting blocks, one outward end of each limiting block is fixedly connected with a fixed rod, one opposite end of each fixed rod is fixedly connected with two telescopic rods, and one opposite end of each fixed rod is fixedly connected with a spring corresponding to the inside of each telescopic rod. According to the utility model, the cross beam is firstly formed into a whole through the first connecting block, then the whole is hoisted to enable the first connecting block to be inserted into the clamping groove which is aligned with the top end of the support column, the first connecting block is fixed on the top end of the support column, the installation of the whole house beam is completed, and the cross beams do not need to be hoisted one by one for installation, so that the installation is more convenient.

Description

Combined factory building steel structure
Technical Field
The utility model relates to the field of combined plant steel, in particular to a combined plant steel structure.
Background
As the steel yield of China is increased, a plurality of steel structure plants are adopted, and the steel structure plants can be divided into light and heavy steel structure plants, industrial and civil building facilities constructed by steel are called steel structures, and the steel structure buildings have the advantages of high strength, light dead weight, good integral rigidity and the like, so the steel structure buildings are suitable for constructing large-span, ultrahigh and extra heavy buildings, and are especially suitable for constructing industrial plants.
Through searching, a combined factory building steel structure with bulletin number CN219412032U comprises a bottom plate, wherein the bottom plate is fixedly connected with the bottom of a first supporting rod at the position close to the front end of the bottom plate, a first sliding rod is sleeved at the position close to the top inside the first supporting rod, the top of the first sliding rod is fixedly connected with the bottom of a first fixing plate, the top of the first fixing plate is fixedly connected with the bottom of a fixing cross beam at the position close to the front end of the bottom of the first fixing plate, and fixing grooves are formed in the top of the fixing cross beam close to the left side and the right side;
based on above-mentioned patent, through set up the fixed slot in the crossbeam inside that bracing piece top is fixed, thereby the structural design of fixed pin inserts at the fixed slot inside, thereby realized fixing the crossbeam through mortise and tenon structure and assemble more convenient function, solved in the past and adopted bolted connection comparatively troublesome and fixed longer problem of consuming time when fixed, improved the stability of fixed crossbeam and reduce installation time, but need to hoist supporting beam one by one and install comparatively troublesome in the installation, factory building length is limited by the bottom plate length and can't be adjusted according to actual requirement simultaneously.
Disclosure of utility model
The utility model aims to solve the defects in the prior art, and provides a combined factory building steel structure, which can assemble a beam into a whole, then directly hoist the whole, and is more convenient to install.
In order to achieve the above purpose, the present utility model provides the following technical solutions:
the utility model provides a combination formula factory building steel construction, includes connecting block two, connecting block two left ends are connected with the support column through first installation component, the equal fixedly connected with connecting block in support column top is first, connecting block one left end is connected with the crossbeam through the second installation component, the support column top all is provided with the draw-in groove, the equal sliding connection of support column inner wall has the stopper, the equal fixedly connected with dead lever of outside one end of stopper, the equal fixedly connected with telescopic link of dead lever looks back to the back of the body one end, the dead lever is the equal fixedly connected with spring of telescopic link inside corresponding to the one end of being carried back to the back of the body mutually.
Further, the first installation component is including being located two left end fixed connection's of connecting block U-shaped piece II, two inner walls of U-shaped piece all are provided with bolt II, two equal fixedly connected with fixture block II of two right-hand member of connecting block, equal fixed connection in two tops of connecting block of support column bottom.
Further, the second installation component is including being located the U-shaped piece one of connecting block one left end fixed connection, U-shaped piece one inner wall all is provided with bolt one, the equal fixedly connected with fixture block one of connecting block one right-hand member, the equal fixedly connected with in connecting block one top of crossbeam bottom, the equal fixedly connected with fixed block in connecting block one bottom.
Further, the telescopic link other end is all fixed connection at the support column relative one end, the equal fixed connection of spring other end is at the support column relative one end.
Further, the second outer wall of the bolt is arranged on the second inner wall of the clamping block.
Further, the outer walls of the bolts are arranged on the inner walls of the clamping blocks.
Further, the fixed block inner wall all sets up at the stopper outer wall, the fixed block outer wall all sets up at the draw-in groove inner wall.
The utility model has the following beneficial effects:
1. According to the utility model, the structure is realized by matching the first connecting block with the first U-shaped block, the first bolt, the first clamping block, the fixed block, the clamping groove and the limiting block, so that the cross beam can be assembled into a whole in advance, and then the whole is directly hoisted, so that the installation is more convenient.
2. According to the utility model, the second connecting block is matched with the second U-shaped block, the second bolt and the second clamping block, so that the structure can adjust the length of the factory building according to the actual field requirement.
Drawings
FIG. 1 is a perspective view of a steel structure of a combined plant according to the present utility model;
FIG. 2 is a cross-sectional view of a middle support column of a combined plant steel structure according to the present utility model;
fig. 3 is an enlarged view at a in fig. 2.
Legend description:
1. The device comprises a support column, a first connecting block, a third connecting block, a cross beam, a first U-shaped block, a first 5, a first bolt, a first 6, a first clamping block, a second 7, a second connecting block, a second 8, a second U-shaped block, a second 9, a second bolt, a second 10, a second clamping block, a second 11, a fixed block, a second 12, a clamping groove, a second 13, a limiting block, a second 14, a fixed rod, a second 15, a spring, a second 16 and a telescopic rod.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
1-3, The combined factory building steel structure comprises a second connecting block 7, wherein the left end of the second connecting block 7 is fixedly connected with a second pin 9 on the inner wall of a second U-shaped block 8,U, the right end of the second connecting block 7 is fixedly connected with a second clamping block 10, the outer wall of the second pin 9 is arranged on the inner wall of the second clamping block 10, the bottom ends of support columns 1 are fixedly connected to the top ends of the second connecting block 7, and the top ends of the support columns 1 are fixedly connected with a first connecting block 2;
Specifically, the second clamping block 10 of the second connecting block 7 is inserted into the second U-shaped block 8 of the second connecting block 7, then the second bolt 9 is inserted into the holes in the second U-shaped block 8 and the second clamping block 10 to fix the second connecting block 7, the process is repeated until the length of the second connecting block 7 reaches the expected required length of the factory building, and the length of the factory building can be freely adjusted according to requirements.
The left end of the connecting block I2 is fixedly connected with the inner wall of the U-shaped block I4,U, the inner wall of the U-shaped block I4 is provided with a bolt I5, the right end of the connecting block I2 is fixedly connected with a clamping block I6, the outer wall of the bolt I5 is arranged on the inner wall of the clamping block I6, the bottom end of the cross beam 3 is fixedly connected with the top end of the connecting block I2, the bottom end of the connecting block I2 is fixedly connected with a fixed block 11, the inner wall of the fixed block 11 is arranged on the outer wall of a limiting block 13, the outer wall of the fixed block 11 is arranged on the inner wall of a clamping groove 12, the top end of a supporting column 1 is provided with a clamping groove 12, the inner wall of the supporting column 1 is fixedly connected with a limiting block 13, one end of the limiting block 13 outwards is fixedly connected with a fixed rod 14, one end of the fixed rod 14 opposite to the other end is fixedly connected with two telescopic rods 16, one end of the fixed rod 14 opposite to the other end is fixedly connected with a spring 15 corresponding to the inner part of the telescopic rod 16, the other end of the telescopic rod 16 is fixedly connected to the opposite end of the supporting column 1, and the other end of the spring 15 is fixedly connected to the opposite end of the telescopic rod 1;
Specifically, insert the fixture block one 6 of one connecting block one 2 into the U-shaped piece one 4 of another connecting block one 2, then insert the bolt one 5 into the hole on fixture block one 6 and U-shaped piece one 4 and fix two connecting blocks one 2, make crossbeam 3 on connecting block one 2 form a whole, can hoist this whole and make fixed block 11 of connecting block one 2 bottom all align draw-in groove 12 on support column 1 top, then insert fixed block 11 in draw-in groove 12, fixed block 11 will promote the inside stopper 13 of draw-in groove 12 to outside removal, until fixed block 11 inserts in draw-in groove 12 completely, stopper 13 will reset under telescopic link 16 elasticity effect at this moment and insert fixed block 11, fix connecting block one 2 on support column 1 top, accomplish the installation of whole roof beam, need not to hoist crossbeam 3 one by one and install, it is more convenient.
The working principle is that the clamping block two 10 of the connecting block two 7 is inserted into the U-shaped block two 8 of the other connecting block two 7, then the bolt two 9 is inserted into holes on the U-shaped block two 8 and the clamping block two 10 to fix the two connecting blocks two 7, the process is repeated until the length of the connecting block two 7 reaches the expected length of a factory building, the length of the factory building can be freely adjusted according to requirements, the clamping block one 6 of the connecting block one 2 is inserted into the U-shaped block one 4 of the other connecting block one 2, then the bolt one 5 is inserted into the holes on the clamping block one 6 and the U-shaped block one 4 to fix the two connecting blocks one 2, so that the cross beams 3 on the connecting block one 2 form a whole, the whole is hoisted, the fixing blocks 11 at the bottom ends of the connecting block one 2 are aligned with the clamping grooves 12 at the top ends of the supporting columns 1, then the fixing blocks 11 are inserted into the clamping grooves 12, the fixing blocks 11 are pushed to move outwards until the fixing blocks 11 are completely inserted into the clamping grooves 12, at the moment, the limiting blocks 13 are reset and inserted into the fixing blocks 11 under the elastic action of the telescopic rod 16, the top ends of the supporting columns 1 are fixed, the whole cross beams 3 are installed conveniently, and the cross beams 3 are installed conveniently.
It should be noted that the foregoing description is only a preferred embodiment of the present utility model, and although the present utility model has been described in detail with reference to the foregoing embodiments, it should be understood that modifications, equivalents, improvements and modifications to the technical solution described in the foregoing embodiments may occur to those skilled in the art, and all modifications, equivalents, and improvements are intended to be included within the spirit and principle of the present utility model.

Claims (7)

1.一种组合式厂房钢结构,包括连接块二(7),其特征在于:所述连接块二(7)左端通过第一安装组件连接有支撑柱(1),所述支撑柱(1)顶端均固定连接有连接块一(2),所述连接块一(2)左端通过第二安装组件连接有横梁(3),所述支撑柱(1)顶端均设置有卡槽(12),所述支撑柱(1)内壁均滑动连接有限位块(13),所述限位块(13)向外一端均固定连接有固定杆(14),所述固定杆(14)相背一端均固定连接有两个伸缩杆(16),所述固定杆(14)相背一端对应伸缩杆(16)内部均固定连接有弹簧(15)。1. A modular factory building steel structure, comprising a connecting block 2 (7), characterized in that: the left end of the connecting block 2 (7) is connected to a support column (1) through a first mounting assembly, the top of the supporting column (1) is fixedly connected to a connecting block 1 (2), the left end of the connecting block 1 (2) is connected to a crossbeam (3) through a second mounting assembly, the top of the supporting column (1) is provided with a slot (12), the inner wall of the supporting column (1) is slidably connected to a limit block (13), the outer end of the limit block (13) is fixedly connected to a fixed rod (14), the opposite end of the fixed rod (14) is fixedly connected to two telescopic rods (16), and the opposite end of the fixed rod (14) is fixedly connected to the inside of the corresponding telescopic rod (16) with a spring (15). 2.根据权利要求1所述的一种组合式厂房钢结构,其特征在于:所述第一安装组件包括位于连接块二(7)左端固定连接的U形块二(8),所述U形块二(8)内壁均设置有插销二(9),所述连接块二(7)右端均固定连接有卡块二(10),所述支撑柱(1)底端均固定连接在连接块二(7)顶端。2. A modular factory building steel structure according to claim 1, characterized in that: the first installation component includes a U-shaped block 2 (8) fixedly connected to the left end of the connecting block 2 (7), the inner wall of the U-shaped block 2 (8) is provided with a latch 2 (9), the right end of the connecting block 2 (7) is fixedly connected with a clamping block 2 (10), and the bottom end of the support column (1) is fixedly connected to the top of the connecting block 2 (7). 3.根据权利要求1所述的一种组合式厂房钢结构,其特征在于:所述第二安装组件包括位于连接块一(2)左端固定连接的U形块一(4),所述U形块一(4)内壁均设置有插销一(5),所述连接块一(2)右端均固定连接有卡块一(6),所述横梁(3)底端均固定连接在连接块一(2)顶端,所述连接块一(2)底端均固定连接有固定块(11)。3. A modular factory building steel structure according to claim 1, characterized in that: the second mounting assembly includes a U-shaped block (4) fixedly connected to the left end of the connecting block (2), the inner wall of the U-shaped block (4) is provided with a latch (5), the right end of the connecting block (2) is fixedly connected to a clamping block (6), the bottom end of the crossbeam (3) is fixedly connected to the top of the connecting block (2), and the bottom end of the connecting block (2) is fixedly connected to a fixing block (11). 4.根据权利要求1所述的一种组合式厂房钢结构,其特征在于:所述伸缩杆(16)另一端均固定连接在支撑柱(1)相对一端,所述弹簧(15)另一端均固定连接在支撑柱(1)相对一端。4. A modular factory building steel structure according to claim 1, characterized in that the other end of the telescopic rod (16) is fixedly connected to the opposite end of the support column (1), and the other end of the spring (15) is fixedly connected to the opposite end of the support column (1). 5.根据权利要求2所述的一种组合式厂房钢结构,其特征在于:所述插销二(9)外壁均设置在卡块二(10)内壁。5. A modular factory building steel structure according to claim 2, characterized in that the outer wall of the second latch (9) is arranged on the inner wall of the second clamping block (10). 6.根据权利要求3所述的一种组合式厂房钢结构,其特征在于:所述插销一(5)外壁均设置在卡块一(6)内壁。6. A modular factory building steel structure according to claim 3, characterized in that the outer wall of the latch (5) is arranged on the inner wall of the block (6). 7.根据权利要求3所述的一种组合式厂房钢结构,其特征在于:所述固定块(11)内壁均设置在限位块(13)外壁,所述固定块(11)外壁均设置在卡槽(12)内壁。7. A modular factory building steel structure according to claim 3, characterized in that the inner wall of the fixing block (11) is arranged on the outer wall of the limiting block (13), and the outer wall of the fixing block (11) is arranged on the inner wall of the slot (12).
CN202421304869.0U 2024-06-10 2024-06-10 Combined factory building steel structure Active CN222614541U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202421304869.0U CN222614541U (en) 2024-06-10 2024-06-10 Combined factory building steel structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202421304869.0U CN222614541U (en) 2024-06-10 2024-06-10 Combined factory building steel structure

Publications (1)

Publication Number Publication Date
CN222614541U true CN222614541U (en) 2025-03-14

Family

ID=94880299

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202421304869.0U Active CN222614541U (en) 2024-06-10 2024-06-10 Combined factory building steel structure

Country Status (1)

Country Link
CN (1) CN222614541U (en)

Similar Documents

Publication Publication Date Title
CN113062474A (en) H-shaped steel and square pipe assembled joint and construction method
CN114411970A (en) Beam column node structure of steel construction assembly type structure
CN216075605U (en) Prefabricated post and precast beam connection structure of assembly type building frame structure
CN114382174A (en) Environment-friendly energy-saving assembled steel structure house frame
CN219863658U (en) Assembled truss
CN218952419U (en) A super high-rise building structure with a strong outer frame with diagonal bracing
CN215802220U (en) Large-scale assembled house steel construction
CN215211577U (en) Beam column node structure easy to build
CN113463757A (en) Environment-friendly energy-saving assembled steel structure house frame
CN223661350U (en) A novel scaffolding steel pipe crossbar connection assembly
CN222962561U (en) An easy-to-install aluminum bracket
CN222822539U (en) A steel beam fixing structure
CN223738728U (en) Modular steel structure connection nodes for easy assembly
CN219491279U (en) H-shaped steel structure connecting and fixing mechanism
CN212802196U (en) Roof structure of a modular wooden house
CN222009713U (en) Assembled building structure roof beam reinforced structure
CN213653750U (en) Stepped connecting structure for connecting beams of super high-rise building
CN223119497U (en) Energy-saving and environment-friendly construction template for cast-in-place concrete structure
CN218911756U (en) Combined steel structure frame
CN222183689U (en) An assembled steel structure node connector
CN222414201U (en) Be used for ground storehouse roof to stride steel vestibule greatly to assemble bed-jig back-up frock
CN223879229U (en) Elevator derrick
CN222206804U (en) Bucket arch structure based on archaize building
CN220888948U (en) Steel construction for assembled building
CN220267286U (en) Steel construction engineering reinforcing block

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant