CN222588564U - Boiler water wall ground assembly device - Google Patents
Boiler water wall ground assembly device Download PDFInfo
- Publication number
- CN222588564U CN222588564U CN202420851144.7U CN202420851144U CN222588564U CN 222588564 U CN222588564 U CN 222588564U CN 202420851144 U CN202420851144 U CN 202420851144U CN 222588564 U CN222588564 U CN 222588564U
- Authority
- CN
- China
- Prior art keywords
- support
- supports
- boiler water
- assembly device
- clamp
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a boiler water-cooled wall ground assembly device which comprises two supports, clamps, hooking pieces, a stress beam, an upper jack and connecting rods, wherein the two supports are placed in parallel, each support comprises a plurality of supporting legs which are placed longitudinally, the tops of the supporting legs are connected through support beams, the clamps used for clamping the end parts of a tube screen are arranged above the support beams, the plurality of connecting rods are connected between the two supports transversely, the hooking pieces which are arranged longitudinally are in a group, the inner sides of the two supports are respectively provided with one group of hooking pieces, the bottoms of the hooking pieces are hooked on the connecting rods, the tops of the two hooking pieces in the group are connected with the stress beam, and the upper jack is arranged at the lower part of the stress beam and the upper part of the tube screen. The pipe screen is fastened through the clamp and the support, the hooking piece, the stress beam and the connecting rod form a stress frame of the upper jack, and the dislocation of the pipe orifice is corrected through the jack and the wedge, so that the structure is simple.
Description
Technical Field
The utility model relates to the technical field of boiler water wall installation, in particular to a boiler water wall ground assembling device.
Background
The water-cooled wall ground pairing can effectively reduce overhead work and ensure welding quality. When the water-cooled wall is assembled on the ground, the tube panels are connected in rows, so that the deviation exists mostly when the fine alignment is performed after the preliminary alignment of the gate, and the method mainly comprises transverse deviation and longitudinal deviation.
Therefore, in order to ensure the quality of water-cooled wall assembly and improve the speed of pipe screen alignment, it is necessary to provide a boiler water-cooled wall ground assembly platform, which is adopted in water-cooled wall ground assembly alignment.
Disclosure of utility model
The utility model aims to solve the technical problem of providing a boiler water wall ground assembling device, so that the alignment, assembling and welding of the pipe orifice of the boiler water wall pipe screen can be rapidly completed on the ground.
In order to solve the technical problems, the utility model adopts the following technical scheme:
The boiler water wall ground assembling device comprises a support, a clamp, a hooking piece, a stress beam, an upper jack and a connecting rod;
The support is arranged in parallel, each support comprises a plurality of support legs which are longitudinally arranged, the top parts of the support legs in the same support are connected through support beam, and a clamp for clamping the end part of the tube panel is arranged above the support beam;
A group of hooking pieces are arranged between two supports at two sides of the butt welding seam of the tube panel, the bottom of each hooking piece is hooked on the connecting rod, and the top of each hooking piece is connected with the stress beam;
The upper jack is arranged at the lower part of the stress beam and the upper part of the tube panel.
Further, the clamp is a bar-shaped clamping plate, and the bar-shaped clamping plate is fastened with the base cross beam through a locking bolt.
Further, the hooking piece comprises a plate body, the bottom of the plate body is L-shaped, and a square hole for fixing the end part of the stress beam is formed in the top of the plate body.
Further, the device also comprises a lower jack arranged on the ground between the two supports.
Further, the pipe screen comprises a wedge which can be inserted into a gap between adjacent pipe screens.
Compared with the prior art, the boiler water wall ground pairing device provided by the utility model has the advantages that the tube screen is fastened through the clamp and the support, the hooking piece, the stress beam and the connecting rod form the stress frame of the upper jack, and the dislocation of the tube orifice is corrected through the jack and the wedge, so that the structure is simple.
The utility model reduces the labor and mechanical consumption during the alignment of the tube panels, improves the construction efficiency, is simple to operate, and can adapt to the alignment correction requirements of water-cooled walls with various lengths by arranging the number of the supports.
Drawings
The accompanying drawings, which are included to provide a further understanding of the utility model and are incorporated in and constitute a part of this specification, illustrate embodiments of the utility model and together with the description serve to explain the utility model.
FIG. 1 is a schematic diagram of the front structure of a boiler water wall ground pairing device provided by the utility model, wherein a part A is a tube panel welded junction;
FIG. 2 is a schematic view of the structure of the stand, clamp and lower jack;
FIG. 3 is a schematic illustration of the use of an upper jack and wedge;
Fig. 4 is a schematic structural view of the hooking member, wherein (a) is a front view and (b) is a side view.
In the figure, 1-support, 2-clamp, 3-hook, 4-stress beam, 5-upper jack, 6-connecting rod, 7-lower jack, 8-support leg, 9-support beam, 10-tube panel, 11-locking bolt and 12-wedge.
Detailed Description
For a better understanding of the present utility model, reference will be made to the following description of the utility model taken in conjunction with the accompanying drawings and examples. The features of the embodiments and examples of the present utility model may be combined with each other without any conflict.
The utility model provides a boiler water wall ground assembly device, which comprises a support 1, a clamp 2, a hooking piece 3, a stress beam 4, an upper jack 5 and a connecting rod 6.
Two supports 1 are placed in parallel, and each support 1 comprises a plurality of supporting legs 8 placed longitudinally, and the tops of the supporting legs 8 are connected through a support beam 9, and a clamp 2 for clamping the end part of a tube panel 10 is arranged above the support beam 9. A plurality of connecting rods 6 are transversely connected between the two supports 1.
Every two longitudinally arranged hooking pieces 3 are in a group, and the inner sides of the two supports 1 are respectively provided with a group of hooking pieces. The bottom of the hooking piece 3 is hooked on the connecting rod 6, and the tops of the two hooking pieces 3 in one group are connected with the stress beam 4.
The support frames 1 are placed in parallel, each support frame 1 comprises a plurality of support legs 9 placed longitudinally, the tops of the support legs 8 in the same support frame 1 are connected through support frame beams 9, a clamp 2 used for clamping the end part of a tube panel 10 is arranged above the support frame beams 9, and a connecting rod 6 is connected between the support legs 8 of the two support frames 1 on two sides of a butt welding line of the tube panel 10 in a transverse mode.
A group of hooking pieces 3 are arranged between the two supports 1 at two sides of the butt welding seam of the pipe screen 10, the two hooking pieces 3 are in a group, the bottom of each hooking piece 3 is hooked on the connecting rod 6, the top of each hooking piece 3 is connected with the stress beam 4, and the upper jack 5 is arranged at the lower part of the stress beam 4 and at the upper part of the pipe screen 10.
In this embodiment, the support 1 is a steel support, and the upper surface of the support 1 is provided with a horizontal support beam 9. As shown in fig. 1, the supports 1 are all placed longitudinally, the tube panels 10 to be assembled are placed on two or more supports 1, the ends of the tube panels 10 are clamped and fixed by the clamps 2 and the support cross beams 9, and the welded junctions of one group of tube panels 10 are near the middle parts of the two supports 1.
The supporting legs 8 of the two supports 1 on the two sides of the butt welding line of the pipe screen 10 are fixedly connected through 6 connecting rods so as to bear the tensile force of the hooking piece 3. The lower part of the hooking piece 3 is hooked on the connecting rod 6, and the stress beam 4 traverses two hooking pieces 3 in one group to form a stable stress frame. As shown in fig. 3, the top end of the upper jack 5 is propped against the bottom of the stress beam 4, the lower end of the upper jack 5 is arranged on the tube panel 10, the upper jack 5 acts on the tube panel 10 of the water-cooled wall reversely through the stress frame, and the upper jack 5 is lifted to provide the pressure correction tube panel forward longitudinal deviation. The boiler water wall ground assembling device provided by the embodiment can quickly finish the alignment, assembling and welding of the pipe orifice of the boiler water wall pipe screen on the ground.
In a relatively specific embodiment, the clamp 2 is a bar-shaped clamping plate, and channel steel can be used as the bar-shaped clamping plate, as shown in fig. 1 and 2, and the bar-shaped clamping plate and the base beam 9 are fastened by a locking bolt 11 to fix the tube panel 10.
As shown in fig. 4, the hooking member 3 includes a plate body, the bottom of the plate body is L-shaped, and a square hole for fixing the end of the stress beam is formed at the top of the plate body.
In a preferred embodiment, it also comprises a lower jack 7 arranged on the ground between the two supports 1. The top end of the lower jack 7 props against the bottom of the tube panel 10, and the lower jack 5 is matched with the upper jack to correct the positive longitudinal deviation of the tube panel.
In another preferred embodiment, a wedge 12 (fig. 3) is also included that is insertable into the gap between adjacent tube panels 10. The wedge 12, when inserted into the slit, provides the motive force for the correction orifice to adjust for the lateral deflection of the tube panel.
The scope of the present utility model is not limited to the above embodiments, but various modifications and alterations of the present utility model will become apparent to those skilled in the art, and any modifications, improvements and equivalents within the spirit and principle of the present utility model are intended to be included in the scope of the present utility model.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202420851144.7U CN222588564U (en) | 2024-04-23 | 2024-04-23 | Boiler water wall ground assembly device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202420851144.7U CN222588564U (en) | 2024-04-23 | 2024-04-23 | Boiler water wall ground assembly device |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN222588564U true CN222588564U (en) | 2025-03-11 |
Family
ID=94853259
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202420851144.7U Active CN222588564U (en) | 2024-04-23 | 2024-04-23 | Boiler water wall ground assembly device |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN222588564U (en) |
-
2024
- 2024-04-23 CN CN202420851144.7U patent/CN222588564U/en active Active
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN113062474A (en) | H-shaped steel and square pipe assembled joint and construction method | |
| CN110409806B (en) | Early-dismantling head and template supporting system | |
| CN223223616U (en) | T beam web stirrup installation bed-jig | |
| CN217631274U (en) | Bracket template system that supports is exempted from to piece together soon | |
| CN120587862B (en) | Offshore wind power full-rotation multi-angle pile driver fork frame preparation process | |
| CN218758782U (en) | Beam mold supports reinforcing apparatus | |
| CN216687220U (en) | Support frame convenient to fix quickly for tower crane | |
| CN218362893U (en) | Welding tool for cross beam of carrier roller set of belt conveyor | |
| CN216184761U (en) | Adjustable transportation bed-jig of steel case roof beam | |
| CN212153747U (en) | Connecting node structure of box type support and box type cross beam | |
| CN211735104U (en) | Prefabricated rain-proof sunshade shed frame of festival section case roof beam | |
| CN215055557U (en) | A steel structure safety rope fixing device | |
| CN115012652A (en) | Assembly type support-free bracket template assembling system and construction method thereof | |
| CN210648912U (en) | Special brazing clamp for flow-concentrating liquid cooling plate | |
| CN222936448U (en) | Butt joint device for hoisting side beams of steel skeleton | |
| CN223447065U (en) | An auxiliary device for facilitating the connection and positioning of steel arch frames | |
| CN219978195U (en) | Flaw detection frame of ultra-large bearing ring | |
| CN219632970U (en) | Auxiliary structure for machining and assembling of steel pipe arch rib end support device | |
| CN215519928U (en) | Building engineering strutting arrangement | |
| CN215594401U (en) | Pre-embedded anchoring mechanism for heavy bracket | |
| CN217782797U (en) | High-altitude construction operation platform suitable for lattice column | |
| CN221502664U (en) | Scaffold for construction | |
| CN222295685U (en) | Adjustable support frame for building template | |
| CN218148874U (en) | Assembly type building connection structure | |
| CN222083601U (en) | A support device for installing steel bars of a cap |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |