CN222083602U - A steel structure tower crane foundation on an existing building - Google Patents

A steel structure tower crane foundation on an existing building Download PDF

Info

Publication number
CN222083602U
CN222083602U CN202323410803.8U CN202323410803U CN222083602U CN 222083602 U CN222083602 U CN 222083602U CN 202323410803 U CN202323410803 U CN 202323410803U CN 222083602 U CN222083602 U CN 222083602U
Authority
CN
China
Prior art keywords
steel
tower crane
welding
crane foundation
existing building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202323410803.8U
Other languages
Chinese (zh)
Inventor
周亦良
江鹏
程世玉
艾子森
唐晓鹤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuli Construction Group Co Ltd
Original Assignee
Fuli Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuli Construction Group Co Ltd filed Critical Fuli Construction Group Co Ltd
Priority to CN202323410803.8U priority Critical patent/CN222083602U/en
Application granted granted Critical
Publication of CN222083602U publication Critical patent/CN222083602U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

本实用新型公开了一种既有建筑上钢结构塔吊基础,属于建筑工程技术领域;塔吊基础钢梁采用焊接方式与设置在框架柱侧的连接钢板连接固定;塔吊基础包括:钢主梁、钢次梁、连梁、圆形钢垫板和加劲板;主梁和次梁形状为钢箱型梁,连梁为工字钢;连接钢板、钢主梁、钢次梁、连梁及圆形钢垫板均在加工厂提前加工完成;连接钢板通过连接钢筋对拉设置于框架柱两侧;钢主梁端部采用焊接与连接钢板连接固定;两根钢次梁并排设置,采用焊接与主梁腹板侧连接连接;塔吊基座及上、下侧垫板与箱形次梁上、下翼缘对应开螺栓孔,采用螺栓穿透钢次梁下翼缘连接,用以安装塔吊;最终将塔吊基础与框架柱形成整体,用以支承塔吊荷载。

The utility model discloses a steel structure tower crane foundation on an existing building, belonging to the technical field of building engineering; the tower crane foundation steel beam is connected and fixed with a connecting steel plate arranged on a frame column side by welding; the tower crane foundation comprises: a steel main beam, a steel secondary beam, a connecting beam, a circular steel pad and a stiffening plate; the main beam and the secondary beam are in the shape of a steel box beam, and the connecting beam is an I-beam; the connecting steel plate, the steel main beam, the steel secondary beam, the connecting beam and the circular steel pad are all processed in advance in a processing plant; the connecting steel plate is arranged on both sides of the frame column by connecting steel bars; the end of the steel main beam is connected and fixed with the connecting steel plate by welding; two steel secondary beams are arranged side by side, and are connected with the main beam web side by welding; bolt holes are correspondingly opened on the tower crane base and the upper and lower side pads and the upper and lower flanges of the box-shaped secondary beam, and bolts are penetrated through the lower flange of the steel secondary beam for connection, so as to install the tower crane; finally, the tower crane foundation and the frame column are formed into a whole to support the tower crane load.

Description

Steel construction tower crane foundation on existing building
Technical Field
The utility model relates to a tower crane foundation with an upper steel structure of an existing building, and belongs to the technical field of building engineering.
Background
If the reinforced concrete tower crane foundation is arranged on the floor of the existing building, the floor of the existing building needs to be reinforced due to the large dead weight of the concrete, the cost is high, the reinforced concrete foundation cannot be reused, and the waste is serious.
Disclosure of utility model
The utility model aims to solve the problems and provide the tower crane foundation with the steel structure on the existing building.
The utility model realizes the above purpose through the following technical scheme:
a tower crane foundation with a steel structure for an existing building comprises a steel main beam, a steel secondary beam, a connecting beam, a round steel backing plate and a stiffening plate.
The steel structure tower crane foundation is arranged. The first connecting steel plate and the second connecting steel plate are oppositely pulled to be arranged on two sides of one frame column and are fixed with connecting steel bars in the frame column in a plug welding manner, the first connecting steel plate and the second connecting steel plate are flush with the outer surface of the frame column, and the connecting steel bars are transversely fixed on main steel bars of the frame column;
the two steel main beams which are arranged in parallel are box-shaped steel beams, and the two ends of the two steel main beams are fixedly connected with the first connecting steel plate by welding;
Two steel secondary beams which are arranged in parallel are box-shaped steel beams which are vertical to the steel main beams, and two ends of the steel secondary beams are welded and connected with two main beam webs;
The four steel connecting beams are arranged in parallel up and down in pairs and are perpendicular to the steel secondary beams, two ends of the four steel connecting beams are fixedly connected with two steel secondary beam webs by welding, and the integrity of a steel structure foundation is improved;
The four round steel backing plates are correspondingly welded and fixed on the upper flanges and the lower flanges of the two steel secondary beams and are used for connecting foundation sections of the tower crane through high-strength bolts;
The steel structure processing plant is used for prefabricating and processing the connecting steel plates, the steel main beams, the steel secondary beams, the tie beams, the round steel backing plates and the stiffening plates in advance;
By adopting the technical scheme, the utility model has the following effects that the problem of difficult installation of the tower crane foundation on the existing building can be effectively solved in the field of new construction of the existing building, especially in the engineering construction of difficult vertical transportation and large mechanical use amount. In addition, the tower crane foundation and the frame column on the original building form a whole, so that the construction safety is improved, the steel structure foundation is constructed quickly, the steel members can be recycled after the building is completed, the construction cost is saved, and the method is worthy of popularization.
Drawings
FIG. 1 is a top plan view of a tower crane foundation of an existing building steel structure in accordance with the present utility model
FIG. 2 is a front view of a tower crane foundation of an existing building steel structure in accordance with the present utility model
Detailed Description
The utility model is further described below with reference to the accompanying drawings:
The tower crane foundation with the steel structure on the existing building comprises four frame columns (1), wherein a first connecting steel plate (101) and a second connecting steel plate (102) are arranged on the side of each frame column, connecting steel bars (103) are arranged in the frame columns and are fixed with the first connecting steel plate (101) and the second connecting steel plate (102) in a plug welding way, two ends of a steel main beam (2) are connected and fixed with the first connecting steel plate (101) by adopting welding, and a welding seam is a full penetration welding seam;
in the structure shown in the figure 1, vertical stiffening plates (7) are arranged in the steel main beam (2) at intervals along the length direction, and vertical stiffening plates (8) are arranged in the steel secondary beam (3) at intervals along the length direction, wherein the stiffening plates (7) are fixedly connected with an upper flange plate, a lower flange plate and a web plate of the steel main beam (2) by adopting welding, and welding seams are fillet welds;
The two ends of the upper and lower connecting beams (4) are fixedly connected with the web sides of the steel secondary beams (3) by adopting welding, and the welding seams are fillet welding;
The transverse stiffening plates (6) are vertically arranged at intervals at the connection positions of the steel main beams and the steel secondary beams, the stiffening plates are right-angled triangles, two right-angled sides are fixedly connected with the steel main beams and the steel secondary beam webs by welding, and the welding seams are fillet welds;
in addition, in the utility model, all the connecting steel plates, the steel main beams, the steel secondary beams, the tie beams and the round steel backing plates are prefabricated and processed in advance by a steel structure processing factory, so that the processing precision of steel components is improved, the installation efficiency of on-site steel components is improved, and the influence on the construction period is reduced.
The foregoing has shown and described the basic principles, principal features and advantages of the utility model. It will be understood by those skilled in the art that the present utility model is not limited to the embodiments described above, and that the above embodiments and descriptions are merely illustrative of the principles of the present utility model, and various changes and modifications may be made without departing from the spirit and scope of the utility model, which is defined in the appended claims. The scope of the utility model is defined by the appended claims and their equivalents.

Claims (6)

1.一种既有建筑上钢结构塔吊基础,安装在四根框架柱处,其特征在于所述钢结构塔吊基础包括:两根钢主梁通过焊接方式与设置在框架柱侧的第一连接钢板连接固定;两根钢次梁两端通过焊接方式固定在钢主梁腹板处;圆形钢垫板对应固定在所述两根钢次梁的上、下翼缘,用于通过高强螺栓,以连接塔吊的基础节。1. A steel structure tower crane foundation on an existing building, installed at four frame columns, characterized in that the steel structure tower crane foundation comprises: two steel main beams are connected and fixed to a first connecting steel plate arranged on the side of the frame column by welding; two ends of two steel secondary beams are fixed to the web of the steel main beams by welding; circular steel pads are correspondingly fixed to the upper and lower flanges of the two steel secondary beams, and are used to connect the foundation section of the tower crane through high-strength bolts. 2.如权利要求1所述的一种既有建筑上钢结构塔吊基础,其特征在于,第一连接钢板和第二连接钢板对拉设置在一根框架柱的两侧,连接钢筋在框架柱内部,连接钢筋与第一连接钢板、第二连接钢板采用塞焊固定。2. A steel structure tower crane foundation on an existing building as described in claim 1, characterized in that the first connecting steel plate and the second connecting steel plate are arranged on both sides of a frame column, the connecting steel bars are inside the frame column, and the connecting steel bars are fixed to the first connecting steel plate and the second connecting steel plate by plug welding. 3.如权利要求1所述的一种既有建筑上钢结构塔吊基础,其特征在于,所述每根钢主梁、钢次梁为箱型钢梁,包括沿钢主梁、钢次梁的轴线对称布置的多个加劲板,加劲板形状为矩形,加劲板四边采用焊接与钢主梁、次梁的上下翼缘板及腹板连接固定。3. A steel structure tower crane foundation on an existing building as described in claim 1, characterized in that each of the steel main beam and steel secondary beam is a box-type steel beam, including a plurality of stiffening plates symmetrically arranged along the axis of the steel main beam and the steel secondary beam, the stiffening plates are rectangular in shape, and the four sides of the stiffening plates are connected and fixed to the upper and lower flange plates and webs of the steel main beam and the secondary beam by welding. 4.如权利要求1所述的一种既有建筑上钢结构塔吊基础,其特征在于,四根连梁之间两两分层平行布置,采用焊接与钢次梁腹板连接固定。4. A steel structure tower crane foundation on an existing building as described in claim 1, characterized in that the four connecting beams are arranged in layers and parallel in pairs, and are connected and fixed to the web of the steel secondary beam by welding. 5.如权利要求1所述的一种既有建筑上钢结构塔吊基础,其特征在于,四个圆形钢垫板,对应固定在所述两根钢次梁的上、下翼缘板,用于通过高强螺栓,以连接塔吊的基础节。5. A steel structure tower crane foundation on an existing building as described in claim 1, characterized in that four circular steel pads are fixed to the upper and lower flange plates of the two steel secondary beams respectively, and are used to connect the foundation sections of the tower crane through high-strength bolts. 6.如权利要求1所述的一种既有建筑上钢结构塔吊基础,其特征在于,钢主梁、钢次梁连接处横向间隔布置加劲板,加劲板形状为直角三角形,直角边采用焊接方式与钢主梁、钢次梁腹板连接固定。6. A steel structure tower crane foundation on an existing building as described in claim 1, characterized in that stiffening plates are arranged at intervals laterally at the connection between the steel main beam and the steel secondary beam, the stiffening plates are in the shape of a right-angled triangle, and the right-angled sides are connected and fixed to the webs of the steel main beam and the steel secondary beam by welding.
CN202323410803.8U 2023-12-14 2023-12-14 A steel structure tower crane foundation on an existing building Active CN222083602U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202323410803.8U CN222083602U (en) 2023-12-14 2023-12-14 A steel structure tower crane foundation on an existing building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202323410803.8U CN222083602U (en) 2023-12-14 2023-12-14 A steel structure tower crane foundation on an existing building

Publications (1)

Publication Number Publication Date
CN222083602U true CN222083602U (en) 2024-11-29

Family

ID=93602435

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202323410803.8U Active CN222083602U (en) 2023-12-14 2023-12-14 A steel structure tower crane foundation on an existing building

Country Status (1)

Country Link
CN (1) CN222083602U (en)

Similar Documents

Publication Publication Date Title
CN107090925B (en) Reinforced precast reinforced concrete shear wall, structural system and construction method thereof
CN102979177B (en) Industrialized assembled multi-story high-rise steel structure eccentrically-braced system
CN102979178B (en) Industrialized multi-story high-rise assembled steel structure frame - eccentrically-braced system
CN102979172A (en) Industrialized assembled multi-story high-rise steel structure prestressed centrally-braced system
CN103031926B (en) With the double-T compound beam and preparation method thereof of pre-stressed steel pipe concrete plug
CN110607867A (en) Non-dismantling mold laminated slab
CN108518003A (en) Detachable prefabricated assembled steel-concrete composite beam plate
CN111411687A (en) A new assembly system
CN102979173B (en) Industrialized assembled multi-story high-rise steel structure prestressed eccentrically-braced system
CN114922286A (en) Assembly type replaceable energy consumption hybrid connection node and installation method
CN107882179A (en) Modular prefabricated steel-concrete combined frame structure
CN116104206A (en) A steel node connecting PEC columns and steel composite beams
CN104652661A (en) Semirigid frame-external recycled concrete wall panel and fabrication method
CN104032829A (en) Modularized high-rise assembled steel structure pre-stressed eccentric support system
CN112267569B (en) Connection node between top of steel column and corrugated steel plate concrete composite slab and construction method
CN207228330U (en) A kind of prefabricated assembled frame combined using steel core concrete column and girder steel
CN221756343U (en) Detachable shared beam making pedestal for prefabricated box beams
CN222083602U (en) A steel structure tower crane foundation on an existing building
CN211143440U (en) Assembled bidirectional steel bar truss floor
CN209779860U (en) An assembled steel frame structure node
CN218643645U (en) A fully assembled reinforced concrete floor slab connected by steel-concrete composite structure
CN202990244U (en) Dual-T shaped composite beam with prestress concrete filled steel tube core bar
CN207194175U (en) A kind of prefabricated assembled bean column node box
CN209339331U (en) A steel pipe concrete column and steel beam connection structure
CN203007973U (en) Combined type tower crane foundation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant