CN2220574Y - Double-pipe prefabricated insulating pipe - Google Patents
Double-pipe prefabricated insulating pipe Download PDFInfo
- Publication number
- CN2220574Y CN2220574Y CN 95215867 CN95215867U CN2220574Y CN 2220574 Y CN2220574 Y CN 2220574Y CN 95215867 CN95215867 CN 95215867 CN 95215867 U CN95215867 U CN 95215867U CN 2220574 Y CN2220574 Y CN 2220574Y
- Authority
- CN
- China
- Prior art keywords
- pipe
- utility
- model
- parallel
- steel pipes
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Rigid Pipes And Flexible Pipes (AREA)
Abstract
The utility model relates to a double-pipe prefabricated heat insulation pipe. The utility model is characterized in that heat transporting steel pipes are two parallel steel pipes; a bracket is arranged between the two steel pipes; a steel baffle plate is welded on a direction which is parallel with the direction of the length of the two steel pipes for fixing the bracket in a system. The utility model can be a parallel bent pipe and a parallel three-way pipe. The utility model has the advantages of low heat insulation material dosage requested by the utility model compare with two single pipes, small volume, better heat insulation structural performance, convenient bracket manufacture, and no influence for the normal running of pipelines. Besides, the utility model reduces earthworks in site operation correspondingly and can bear pressure between steel pipes. The utility model is suitable for heat supply and insulation pipes which have a medium temperature below 150DEG. C.
Description
The utility model belongs to the heat preservation pipe prefabricated of piping adiabatic apparatus, particularly a kind of parallel double tube.
At present, constantly enlarge in the Heat Supply Engineering and use heat preservation pipe prefabricatedly, its advantage is: can directly buried installation, save the conventional heat retaining operation that in trench, carries out, and improve work efficiency, reduce the trench excavated volume; The thermal insulation layer of whole pipe-line system is an integral seamless, and the pipeline thermal loss is few; Have anticorrosion, water resistance, can prolong pipeline working life.But, be single heat supply water pipe and add the heat preservation pipe prefabricated of insulation and protective coating formation, for parallel lay-up water return pipeline is arranged, need the insulation measure equally, therefore, it is big to lay the occupation of land volume, and the thermal insulating material consumption is many, and the laid processes construction is loaded down with trivial details.
The purpose of this utility model is, designs and produces the heat preservation pipe prefabricated of a kind of parallel double tube, and heat supply water pipe and return pipe are arranged in same thermal insulation layer and the protective coating, takes up an area of volume, convenient construction to save thermal insulating material, to reduce.
Of the present utility model two-tube heat preservation pipe prefabricated, by defeated hot steel pipe, thermal insulation layer, protective coating is formed, and it is characterized in that, defeated hot steel pipe is parallel two steel pipes, between two steel pipes support is set, on the length direction of parallel two steel pipes, is welded with the Steel Lagging that system's fixed support is used.
Of the present utility model two-tube heat preservation pipe prefabricated, can be parallel bend pipe, parallel three-way pipe.
Using method of the present utility model is: keep spacing with support between the steel pipe with two isometric parallel placements, the Steel Lagging of using at the stage casing of parallel steel tube welding system fixed support; At the coated polyurethane rigid foam of the outer wall of parallel steel tube thermal insulation layer, coated again high density polyethylene (HDPE) or glass fibre reinforced plastics protective coating are fixed; During use, feed high-temperature-hot-water or steam in the steel pipe, by backwater, reach heat insulation effect in another root steel pipe.
The utility model has the advantages that, two-tube heat preservation pipe prefabricated needed thermal insulating material is lower than two heat preservation pipe prefabricated consumptions of single tube; Reduce the corresponding site operation earthwork that reduced at underground shared volume; Because two-tube in advance in same thermal insulation layer, its insulating structure performance is good, the thermal loss in pipeline further reduces; Adopt support between two-tube, easy to make, can bear pressure between the steel pipe, and not influence pipeline and normally move, be applicable to that medium temperature is at the heat supply thermal insulation pipe below 150 ℃.
Below in conjunction with drawings and Examples, the utility model will be further described:
Fig. 1 is two-tube heat preservation pipe prefabricated organigram;
Fig. 2 is the A-A sectional drawing of Fig. 1;
Fig. 3 is the B-B sectional drawing of Fig. 1.
As seen from the figure, two-tube heat preservation pipe prefabricated, by defeated hot steel pipe 1, thermal insulation layer 2, protective coating 3 is formed, and it is characterized in that, defeated hot steel pipe is parallel two steel pipes, between two steel pipes support 4 is set, and is welded with the Steel Lagging 5 that system's fixed support is used on the length direction of parallel two steel pipes.
Claims (3)
1, a kind of two-tube heat preservation pipe prefabricated, by defeated hot steel pipe, thermal insulation layer, protective coating is formed, and it is characterized in that, defeated hot steel pipe is parallel two steel pipes, between two steel pipes support is set, on the length direction of parallel two steel pipes, is welded with the Steel Lagging that system's fixed support is used.
2, as claimed in claim 1 two-tube heat preservation pipe prefabricated, it is characterized in that, two-tube heat preservation pipe prefabricated be parallel bend pipe.
3, as claimed in claim 1 two-tube heat preservation pipe prefabricated, it is characterized in that, two-tube heat preservation pipe prefabricated be parallel three-way pipe.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN 95215867 CN2220574Y (en) | 1995-07-12 | 1995-07-12 | Double-pipe prefabricated insulating pipe |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN 95215867 CN2220574Y (en) | 1995-07-12 | 1995-07-12 | Double-pipe prefabricated insulating pipe |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN2220574Y true CN2220574Y (en) | 1996-02-21 |
Family
ID=33865102
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN 95215867 Expired - Fee Related CN2220574Y (en) | 1995-07-12 | 1995-07-12 | Double-pipe prefabricated insulating pipe |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN2220574Y (en) |
Cited By (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104266021A (en) * | 2014-10-08 | 2015-01-07 | 哈尔滨朗格斯特节能科技有限公司 | Intelligent prefabricated direct burial thermal insulation pipe steel pipe double pipe fitting tapered pipeline and manufacture method |
| CN104373730A (en) * | 2014-10-31 | 2015-02-25 | 哈尔滨朗格斯特节能科技有限公司 | Fixing device and method for intelligent prefabricated directly-buried thermal insulation pipe double pipe elbow alarm lines |
| CN104373685A (en) * | 2014-10-31 | 2015-02-25 | 哈尔滨朗格斯特节能科技有限公司 | Intelligent prefabricated directly-buried insulating pipe steel pipe double-pipe crossing tee joint and fixing method for alarm cables |
| CN104373687A (en) * | 2014-10-31 | 2015-02-25 | 哈尔滨朗格斯特节能科技有限公司 | Crosslinked polyethylene double-pipe parallel tee joint of intelligent insulating pipe and fixing method for alarm cables of tee joint |
| CN104455878A (en) * | 2014-10-08 | 2015-03-25 | 哈尔滨朗格斯特节能科技有限公司 | Working steel tube double-tube tube fitting bend of intelligent prefabricated direct buried heating insulating tube and manufacturing method |
| CN104482309A (en) * | 2014-10-31 | 2015-04-01 | 哈尔滨朗格斯特节能科技有限公司 | Intelligent thermal insulation double pipe parallel tee alarm line fixing device and fixing method |
| CN104653932A (en) * | 2014-10-31 | 2015-05-27 | 哈尔滨朗格斯特节能科技有限公司 | Intelligent prefabrication direct burial crosslinked polyethylene thermal insulation pipe double-barreled elbow alarm line fixing method |
| CN108548051A (en) * | 2018-05-05 | 2018-09-18 | 芜湖君如保温材料有限公司 | A kind of two-flap type threeway heat-preserving bent pipe accessory |
| CN109058584A (en) * | 2018-09-26 | 2018-12-21 | 山西理工红日节能服务有限公司 | Heat supply pipeline barrier detour method and heat preservation pipe prefabricated detour device |
-
1995
- 1995-07-12 CN CN 95215867 patent/CN2220574Y/en not_active Expired - Fee Related
Cited By (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104266021A (en) * | 2014-10-08 | 2015-01-07 | 哈尔滨朗格斯特节能科技有限公司 | Intelligent prefabricated direct burial thermal insulation pipe steel pipe double pipe fitting tapered pipeline and manufacture method |
| CN104455878A (en) * | 2014-10-08 | 2015-03-25 | 哈尔滨朗格斯特节能科技有限公司 | Working steel tube double-tube tube fitting bend of intelligent prefabricated direct buried heating insulating tube and manufacturing method |
| CN104373730A (en) * | 2014-10-31 | 2015-02-25 | 哈尔滨朗格斯特节能科技有限公司 | Fixing device and method for intelligent prefabricated directly-buried thermal insulation pipe double pipe elbow alarm lines |
| CN104373685A (en) * | 2014-10-31 | 2015-02-25 | 哈尔滨朗格斯特节能科技有限公司 | Intelligent prefabricated directly-buried insulating pipe steel pipe double-pipe crossing tee joint and fixing method for alarm cables |
| CN104373687A (en) * | 2014-10-31 | 2015-02-25 | 哈尔滨朗格斯特节能科技有限公司 | Crosslinked polyethylene double-pipe parallel tee joint of intelligent insulating pipe and fixing method for alarm cables of tee joint |
| CN104482309A (en) * | 2014-10-31 | 2015-04-01 | 哈尔滨朗格斯特节能科技有限公司 | Intelligent thermal insulation double pipe parallel tee alarm line fixing device and fixing method |
| CN104653932A (en) * | 2014-10-31 | 2015-05-27 | 哈尔滨朗格斯特节能科技有限公司 | Intelligent prefabrication direct burial crosslinked polyethylene thermal insulation pipe double-barreled elbow alarm line fixing method |
| CN104373685B (en) * | 2014-10-31 | 2017-10-13 | 哈尔滨朗格斯特节能科技有限公司 | Fixing method for alarm line of intelligent prefabricated direct-buried insulating pipe steel pipe double-pipe crossing tee joint |
| CN104373687B (en) * | 2014-10-31 | 2017-11-24 | 哈尔滨朗格斯特节能科技有限公司 | Method for fixing alarm line of intelligent thermal insulation pipe crosslinked polyethylene double-pipe parallel tee joint |
| CN108548051A (en) * | 2018-05-05 | 2018-09-18 | 芜湖君如保温材料有限公司 | A kind of two-flap type threeway heat-preserving bent pipe accessory |
| CN109058584A (en) * | 2018-09-26 | 2018-12-21 | 山西理工红日节能服务有限公司 | Heat supply pipeline barrier detour method and heat preservation pipe prefabricated detour device |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN2220574Y (en) | Double-pipe prefabricated insulating pipe | |
| CN2564837Y (en) | Vacuum thermal insulation pipeline | |
| CN207907540U (en) | A kind of earth source heat pump energy stake | |
| CN100450894C (en) | Space heating device for high-condensation oil product floating roof oil tank | |
| CN101737560A (en) | Ordinary state uncompensated direct burying method of high-temperature hot water pipeline | |
| CN210624981U (en) | Geothermal continuous heat exchange pipeline and heat exchange system | |
| CN115013995A (en) | Novel middle-deep buried pipe heat exchanger | |
| CN215412572U (en) | Novel heat preservation and heat tracing integrated pipe | |
| CN214331903U (en) | PPR composite heat-insulating pipe | |
| CN100335839C (en) | Steel-enclosing-steel high temperature resistant direct burial anticorrosive insulating system | |
| CN2787977Y (en) | Cross-wall combined elbow for underground pipe heat exchanger | |
| CN2242384Y (en) | Directly buried type laying transition pipe section | |
| CN210532722U (en) | Buried heat exchanger | |
| CN110778794A (en) | Prefabricated polyurethane is adiabatic sliding support of formula of preassembleing for heat preservation pipe | |
| CN216924837U (en) | Buried well flow balance adjustment horizontal connecting pipe of shallow soil source heat pump system | |
| CN101324295A (en) | Steel faucet prestress steel cylinder concrete thermal insulation pipe | |
| CN110486961A (en) | A kind of underground heat Continuous Heat Transfer pipeline and heat-exchange system | |
| CN215635678U (en) | Circular drain coil compensator applied to direct-buried steam pipeline | |
| CN207796342U (en) | It is easily installed the feed pipe of docking | |
| CN222848886U (en) | Installation assembly for natural compensation section of direct-buried steam pipeline | |
| CN219493337U (en) | Polyethylene-wound ductile iron directly-buried anti-corrosion heat-insulation pipe | |
| CN2683984Y (en) | Steel lagging direct burial anticorrosive insulating pipe for steel vapor | |
| CN222316197U (en) | Plastic outer stripe water supply and drainage pipe | |
| CN220930520U (en) | Rotary compensator arrangement structure for low overhead long-distance steam transmission pipeline | |
| CN203948137U (en) | For the circulating water pipeline layout of three tower unifications, two machine one towers |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| C19 | Lapse of patent right due to non-payment of the annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |