CN221722291U - Template clamp for building construction - Google Patents

Template clamp for building construction Download PDF

Info

Publication number
CN221722291U
CN221722291U CN202420275307.1U CN202420275307U CN221722291U CN 221722291 U CN221722291 U CN 221722291U CN 202420275307 U CN202420275307 U CN 202420275307U CN 221722291 U CN221722291 U CN 221722291U
Authority
CN
China
Prior art keywords
rod
female
screw rod
telescopic cavity
sub
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202420275307.1U
Other languages
Chinese (zh)
Inventor
马胜廷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Lanling County Fangxing Engineering Quality Testing Co ltd
Original Assignee
Lanling County Fangxing Engineering Quality Testing Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lanling County Fangxing Engineering Quality Testing Co ltd filed Critical Lanling County Fangxing Engineering Quality Testing Co ltd
Priority to CN202420275307.1U priority Critical patent/CN221722291U/en
Application granted granted Critical
Publication of CN221722291U publication Critical patent/CN221722291U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a template clamp for building construction, and belongs to the technical field of building construction equipment. The beam template clamp solves the problems that in the prior art, a worker is required to pull the beam template clamp upwards by hand during clamping, the beam template clamp is easy to topple during clamping, the labor intensity of the worker is high, and the distance between two adjacent beam templates is not standard. The novel telescopic screw rod mainly comprises a female rod, a first telescopic cavity is formed in the female rod, a sub rod is inserted into the first telescopic cavity, a second telescopic cavity is formed in the sub rod, a screw rod is rotatably installed in the first telescopic cavity of the female rod, one end of the screw rod extends out of the female rod and is provided with a screw rod head, the other end of the screw rod is inserted into the second telescopic cavity of the sub rod, one end, close to the female rod, of the sub rod is provided with a sub rod threaded hole matched with the screw rod, the other end of the sub rod is provided with a movable clamping plate, and one end, close to the screw rod head, of the female rod is provided with a fixed clamping plate; the bottom demountable installation of female pole has the bracing piece, and the bracing piece sets up perpendicularly with female pole, and the one end of female pole is equipped with the sleeve.

Description

建筑施工用模板夹具Formwork clamps for building construction

技术领域Technical Field

本实用新型属于建筑施工设备技术领域,具体地说,尤其涉及一种建筑施工用模板夹具。The utility model belongs to the technical field of building construction equipment, and in particular relates to a template clamp for building construction.

背景技术Background Art

在混凝土浇筑时需要用到大量模板以形成混凝土浇筑腔,例如方柱、梁、墙板等等,在通过模板形成浇筑腔浇筑混凝土时,一般都需要用到夹具来固定模板,夹具可以有效避免在浇筑混凝土时,模板出现变形、开缝等情况。如专利公开号CN216276915U,名称为一种建筑梁模夹具的专利,公开了一种梁夹具,上述专利公开的梁夹具以及市场中常见的梁夹具在使用时,均存在不便于前期安装的缺点,在安装时一般需要工人先将两侧梁夹具向上插入到梁模板的两侧,即梁模板在两侧夹板之间,然后再将两侧夹板夹紧,在夹紧的过程中,需要工人一边用手向上拖住夹具,一边进行夹紧,夹紧时不仅夹具容易出现倾倒,而且工人的劳动强度大,模板夹紧效率低,特别是对于宽度较大的夹具。而且在向梁模板上安装梁夹具时,往往需要每隔一定距离安装一个,例如可以按每隔50厘米安装一个梁夹具,当前一般都是通过工人目测间隔距离后安装,而且还是向上托举安装,使相邻两个梁夹具之间的间隔距离不规范。When pouring concrete, a large number of templates are needed to form a concrete pouring cavity, such as square columns, beams, wall panels, etc. When pouring concrete through the template to form a pouring cavity, a clamp is generally needed to fix the template. The clamp can effectively prevent the template from being deformed, cracked, etc. when pouring concrete. For example, patent publication number CN216276915U, a patent named a building beam mold clamp, discloses a beam clamp. The beam clamp disclosed in the above patent and the common beam clamps in the market have the disadvantage of being inconvenient for early installation when used. During installation, workers are generally required to first insert the two-side beam clamps upward into the two sides of the beam template, that is, the beam template is between the two side clamps, and then clamp the two side clamps. During the clamping process, the worker needs to drag the clamp upward with his hand while clamping. When clamping, not only is the clamp prone to tipping over, but the worker's labor intensity is also high, and the template clamping efficiency is low, especially for a clamp with a larger width. Moreover, when installing beam clamps on the beam formwork, it is often necessary to install one at a certain distance, for example, a beam clamp can be installed every 50 centimeters. Currently, workers generally install them after visually measuring the distance, and they are also installed by lifting upwards, so that the distance between two adjacent beam clamps is not standardized.

发明内容Summary of the invention

本实用新型目的是提供一种建筑施工用模板夹具,以克服现有技术中梁模板夹具在夹紧时需要工人一边用手向上拖住,一边进行夹紧时,容易倾倒,工人劳动强度大,以及相邻两个梁模板之间的距离不规范的缺陷。The utility model aims to provide a template clamp for construction, so as to overcome the defects of the prior art that the beam template clamp needs workers to hold it upward with their hands when clamping, which is easy to tip over, the labor intensity of workers is high, and the distance between two adjacent beam templates is not standardized.

本实用新型是采用以下技术方案实现的,一种建筑施工用模板夹具,包括母杆,所述母杆上开设第一伸缩腔,所述第一伸缩腔内插入子杆,子杆上开设第二伸缩腔,所述母杆的第一伸缩腔中转动安装丝杆,丝杆的一端伸出母杆并安装丝杆头,丝杆的另一端插入子杆的第二伸缩腔,子杆靠近母杆一端开设与丝杆配合的子杆螺纹孔,子杆的另一端安装动夹板,母杆靠近丝杆头的一端安装定夹板;所述母杆的底部可拆卸安装有支撑杆,支撑杆与母杆垂直设置,母杆的一端设有套筒。The utility model is implemented by adopting the following technical scheme: a template clamp for construction, comprising a mother rod, a first telescopic cavity is provided on the mother rod, a child rod is inserted into the first telescopic cavity, a second telescopic cavity is provided on the child rod, a screw rod is rotatably installed in the first telescopic cavity of the mother rod, one end of the screw rod extends out of the mother rod and is installed with a screw rod head, the other end of the screw rod is inserted into the second telescopic cavity of the child rod, a child rod threaded hole matching with the screw rod is provided at one end of the child rod close to the mother rod, a movable clamp is installed at the other end of the child rod, and a fixed clamp is installed at one end of the mother rod close to the screw rod head; a support rod is detachably installed at the bottom of the mother rod, the support rod is vertically arranged with the mother rod, and a sleeve is provided at one end of the mother rod.

进一步地,所述母杆的底部安装支撑块,支撑块上开设支撑螺纹孔,支撑杆的中部开设与支撑螺纹孔配合的外螺纹。Furthermore, a support block is installed at the bottom of the mother rod, a support threaded hole is provided on the support block, and an external thread matching with the support threaded hole is provided in the middle of the support rod.

进一步地,所述母杆的底部可拆卸安装有两个支撑杆。Furthermore, two support rods are detachably mounted on the bottom of the mother rod.

进一步地,所述子杆的顶面上设有距离刻度。Furthermore, a distance scale is provided on the top surface of the sub-rod.

进一步地,所述支撑杆的长度是50-80厘米。Furthermore, the length of the support rod is 50-80 cm.

进一步地,所述母杆的第一伸缩腔内安装轴承座,轴承座内安装轴承,所述丝杆穿过轴承并与轴承的内圈固定连接。Furthermore, a bearing seat is installed in the first telescopic cavity of the female rod, a bearing is installed in the bearing seat, and the screw rod passes through the bearing and is fixedly connected to the inner ring of the bearing.

进一步地,所所述丝杆头上开设穿孔;所述穿孔内开设内螺纹。Furthermore, a through hole is provided on the screw rod head; and an internal thread is provided in the through hole.

进一步地,所述动夹板和定夹板均包括竖板,竖板的两侧分别安装斜撑板。Furthermore, the movable clamping plate and the fixed clamping plate both include vertical plates, and diagonal support plates are respectively installed on both sides of the vertical plates.

与现有技术相比,本实用新型的有益效果是:Compared with the prior art, the beneficial effects of the utility model are:

1、本实用新型通过在母杆的底部安装支撑杆,支撑杆可起到暂时支撑相邻的梁夹具的作用,在安装转动丝杆时,工人可不必一边用力托举梁夹具,一边转动丝杆,不仅降低了工人的劳动强度,而且安装更加规范,通过支撑杆的长度来限定相邻两个梁夹具之间的间距,使梁夹具在安装时,相邻两个梁模板之间的夹具可以保持在一定距离。1. The utility model installs a support rod at the bottom of the mother rod, and the support rod can play the role of temporarily supporting adjacent beam clamps. When installing the rotating screw rod, workers do not need to lift the beam clamp with force while rotating the screw rod, which not only reduces the labor intensity of workers but also makes the installation more standardized. The distance between two adjacent beam clamps is limited by the length of the support rod, so that when the beam clamps are installed, the clamps between two adjacent beam templates can be kept at a certain distance.

2、本实用新型对梁模板的夹紧更加方便,而且夹紧更加牢固,在夹紧时,工人只需要通过电动螺丝刀等工具转动丝杆头,并通过丝杆头转动丝杆,丝杆转动时通过子杆螺纹孔驱动子杆沿母杆的第一伸缩腔伸缩,子杆驱动其上的动夹板伸缩,以实现夹紧和松开。2. The utility model makes it more convenient to clamp the beam formwork, and the clamping is more secure. When clamping, the worker only needs to rotate the screw head through a tool such as an electric screwdriver, and rotate the screw through the screw head. When the screw rotates, the sub-rod is driven to extend and retract along the first telescopic cavity of the mother rod through the sub-rod threaded hole, and the sub-rod drives the movable clamp thereon to extend and retract to achieve clamping and loosening.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

图1是本实用新型的结构示意图;Fig. 1 is a schematic diagram of the structure of the utility model;

图2是本实用新型未安装支撑杆时的结构示意图;Figure 2 is a schematic diagram of the structure of the utility model when the support rod is not installed;

图3是本实用新型的部分剖视图;FIG3 is a partial cross-sectional view of the present utility model;

图4是本实用新型的使用状态图。FIG. 4 is a diagram showing the use state of the present utility model.

图中:1、母杆;2、第一伸缩腔;3、子杆;4、第二伸缩腔;5、丝杆;6、丝杆头;7、子杆螺纹孔;8、动夹板;9、定夹板;10、支撑杆;11、套筒;12、支撑块;13、支撑螺纹孔;14、距离刻度;15、轴承座;16、穿孔;17、竖板;18、斜撑板。In the figure: 1. mother rod; 2. first telescopic cavity; 3. sub-rod; 4. second telescopic cavity; 5. screw rod; 6. screw rod head; 7. sub-rod threaded hole; 8. movable clamping plate; 9. fixed clamping plate; 10. support rod; 11. sleeve; 12. support block; 13. support threaded hole; 14. distance scale; 15. bearing seat; 16. through hole; 17. vertical plate; 18. diagonal support plate.

具体实施方式DETAILED DESCRIPTION

为了使本技术领域的人员更好地理解本实用新型中的技术方案,下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都应当属于本实用新型保护的范围。In order to enable those skilled in the art to better understand the technical solutions in the present invention, the following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

一种建筑施工用模板夹具,包括母杆1,所述母杆1上开设第一伸缩腔2,所述第一伸缩腔2内插入子杆3,子杆3上开设第二伸缩腔4,所述母杆1的第一伸缩腔2中转动安装丝杆5,丝杆5的一端伸出母杆1并安装丝杆头6,丝杆5的另一端插入子杆3的第二伸缩腔4,子杆3靠近母杆1一端开设与丝杆5配合的子杆螺纹孔7,子杆3的另一端安装动夹板8,母杆1靠近丝杆头6的一端安装定夹板9;所述母杆1的底部可拆卸安装有支撑杆10,支撑杆10与母杆1垂直设置,母杆1的一端设有套筒11。A template clamp for construction, including a mother rod 1, a first telescopic cavity 2 is provided on the mother rod 1, a child rod 3 is inserted into the first telescopic cavity 2, a second telescopic cavity 4 is provided on the child rod 3, a screw rod 5 is rotatably installed in the first telescopic cavity 2 of the mother rod 1, one end of the screw rod 5 extends out of the mother rod 1 and is installed with a screw rod head 6, the other end of the screw rod 5 is inserted into the second telescopic cavity 4 of the child rod 3, a child rod threaded hole 7 matching with the screw rod 5 is provided at one end of the child rod 3 close to the mother rod 1, a movable clamping plate 8 is installed at the other end of the child rod 3, and a fixed clamping plate 9 is installed at one end of the mother rod 1 close to the screw rod head 6; a support rod 10 is detachably installed at the bottom of the mother rod 1, the support rod 10 is vertically arranged with the mother rod 1, and a sleeve 11 is provided at one end of the mother rod 1.

本实用新型所述子杆3插入母杆1中,并沿母杆1的第一伸缩腔2移动,在实现夹紧或者松开时,工人通过螺丝刀等工具转动丝杆头6,进而转动丝杆5,丝杆5转动时会通过与子杆螺纹孔7的配合,驱动子杆3沿母杆1的第一伸缩腔2伸缩,丝杆5的一端在子杆3的第二伸缩腔4中;当子杆3在移动时,子杆3上的动夹板8与母杆1上的定夹板9之间的距离会变小或者变大,以实现夹紧梁模板或者松开梁模板;所述丝杆5只能相对母杆1转动,而不能相对母杆1沿轴向运动。The sub-rod 3 of the utility model is inserted into the mother rod 1 and moves along the first telescopic cavity 2 of the mother rod 1. When clamping or loosening is achieved, the worker rotates the screw head 6 with a tool such as a screwdriver, and then rotates the screw 5. When the screw 5 rotates, it will cooperate with the threaded hole 7 of the sub-rod to drive the sub-rod 3 to extend and retract along the first telescopic cavity 2 of the mother rod 1, and one end of the screw 5 is in the second telescopic cavity 4 of the sub-rod 3; when the sub-rod 3 moves, the distance between the movable clamping plate 8 on the sub-rod 3 and the fixed clamping plate 9 on the mother rod 1 will become smaller or larger, so as to clamp the beam template or loosen the beam template; the screw 5 can only rotate relative to the mother rod 1, and cannot move axially relative to the mother rod 1.

本实用新型通过在母杆1的底部安装支撑杆10,可方便在长度较长的梁模板上安装梁夹具,梁模板上两个相邻梁夹具之间的距离可以是50厘米,在安装支撑杆10时,使母杆1在支撑杆10的中部,母杆1的一端设有套筒11,相邻两根支撑杆10在配合时,支撑杆10未设有套筒11的一端可插入到相邻支撑杆10的套筒11中,以实现相邻两根支撑杆10之间的链接。所述支撑杆10可起到暂时支撑相邻梁夹具的作用,而且由于支撑杆10两侧伸出母杆1的距离一定,所以支撑杆10还能起到很好的确定相邻两个梁夹具之间距离的作用,使梁夹具的安装更加规范。The utility model can conveniently install the beam clamp on the beam template with a long length by installing the support rod 10 at the bottom of the mother rod 1. The distance between two adjacent beam clamps on the beam template can be 50 cm. When installing the support rod 10, the mother rod 1 is in the middle of the support rod 10. One end of the mother rod 1 is provided with a sleeve 11. When two adjacent support rods 10 are matched, the end of the support rod 10 without the sleeve 11 can be inserted into the sleeve 11 of the adjacent support rod 10 to achieve the connection between the two adjacent support rods 10. The support rod 10 can play the role of temporarily supporting the adjacent beam clamps, and because the distance between the two sides of the support rod 10 extending out of the mother rod 1 is certain, the support rod 10 can also play a good role in determining the distance between the two adjacent beam clamps, so that the installation of the beam clamp is more standardized.

所述母杆1的底部安装支撑块12,支撑块12上开设支撑螺纹孔13,支撑杆10的中部开设与支撑螺纹孔13配合的外螺纹。A support block 12 is installed at the bottom of the mother rod 1 , a support threaded hole 13 is provided on the support block 12 , and an external thread matching the support threaded hole 13 is provided in the middle of the support rod 10 .

本实用新型通过在支撑杆10的中部开设外螺纹,而且支撑杆10中间的外螺纹凸出支撑杆10的圆周面,支撑杆10未设有套筒11的一端可插入到支撑螺纹孔13中,直到支撑杆10上的外螺纹与支撑螺纹孔13接触,通过继续转动支撑杆10,使支撑杆10螺纹连接在支撑块12上,进而实现支撑杆10与母杆1的连接。The utility model provides an external thread in the middle of the support rod 10, and the external thread in the middle of the support rod 10 protrudes from the circumferential surface of the support rod 10, and the end of the support rod 10 without the sleeve 11 can be inserted into the support threaded hole 13 until the external thread on the support rod 10 contacts the support threaded hole 13, and by continuing to rotate the support rod 10, the support rod 10 is threadedly connected to the support block 12, thereby realizing the connection between the support rod 10 and the mother rod 1.

所述母杆1的底部可拆卸安装有两个支撑杆10。Two support rods 10 are detachably mounted on the bottom of the mother rod 1 .

本实用新型通过安装两个支撑杆10,可更好的支撑相邻的模板夹具。The utility model can better support adjacent template clamps by installing two support rods 10.

所述子杆3的顶面上设有距离刻度14。A distance scale 14 is provided on the top surface of the sub-rod 3 .

本实用新型通过设置距离刻度14,可方便人们观察子杆3伸出母杆1的长度。The utility model can facilitate people to observe the length of the sub-rod 3 extending from the mother rod 1 by setting the distance scale 14.

所述支撑杆10的长度是50-80厘米。The length of the support rod 10 is 50-80 cm.

本实用新型所述支撑杆10的长度可设计为65厘米,所述套筒11的长度可设计为10厘米。The length of the support rod 10 of the utility model can be designed to be 65 cm, and the length of the sleeve 11 can be designed to be 10 cm.

所述母杆1的第一伸缩腔2内安装轴承座15,轴承座15内安装轴承,所述丝杆5穿过轴承并与轴承的内圈固定连接。A bearing seat 15 is installed in the first telescopic cavity 2 of the female rod 1, a bearing is installed in the bearing seat 15, and the screw rod 5 passes through the bearing and is fixedly connected to the inner ring of the bearing.

本实用新型通过在第一伸缩腔2内安装轴承座15,可很好的限制丝杆5的轴向移动,我们可在丝杆5的一端开设环形槽,母杆1在第一伸缩腔2中安装插入环形槽的环状凸沿,通过环状凸沿和环形槽的配合也可以起到限制丝杆5轴向移动的目的。The utility model can effectively limit the axial movement of the screw rod 5 by installing the bearing seat 15 in the first telescopic cavity 2. We can open an annular groove at one end of the screw rod 5, and the mother rod 1 is installed in the first telescopic cavity 2 with an annular convex edge inserted into the annular groove. The cooperation of the annular convex edge and the annular groove can also limit the axial movement of the screw rod 5.

所述丝杆头6上开设穿孔16;所述穿孔16内开设内螺纹。The screw rod head 6 is provided with a through hole 16 ; the through hole 16 is provided with an internal thread.

本实用新型通过造丝杆头6上开设穿孔16,可方便工人在不使用电动螺丝刀的情况下,将转动杆插入到穿孔16中,方便工人转动丝杆头6,通过在穿孔16内开设内螺纹,可方便转动杆与丝杆头6螺纹连接。The utility model provides a through hole 16 on the screw rod head 6, so that workers can insert the rotating rod into the through hole 16 without using an electric screwdriver, so as to facilitate the workers to rotate the screw rod head 6. By providing an internal thread in the through hole 16, the rotating rod can be conveniently threadedly connected with the screw rod head 6.

所述动夹板8和定夹板9均包括竖板17,竖板17的两侧分别安装斜撑板18。The movable clamping plate 8 and the fixed clamping plate 9 both include a vertical plate 17 , and diagonal support plates 18 are respectively installed on both sides of the vertical plate 17 .

本实用新型所述动夹板8上的竖板17和斜撑板18分别与母杆1固定连接,定夹板9上的竖板17和斜撑板18分别与子杆3固定连接。The vertical plate 17 and the diagonal support plate 18 on the movable clamping plate 8 of the utility model are respectively fixedly connected to the mother rod 1, and the vertical plate 17 and the diagonal support plate 18 on the fixed clamping plate 9 are respectively fixedly connected to the sub-rod 3.

本实用新型的安装过程:Installation process of this utility model:

在安装时,我们可先将其中一个梁夹具安装到梁模板上,这个梁夹具夹紧梁模板后,再将支撑杆10螺纹连接到这个梁夹具上的支撑螺纹孔13中;During installation, we can first install one of the beam clamps on the beam template. After the beam clamp clamps the beam template, the support rod 10 is threadedly connected to the support threaded hole 13 on the beam clamp.

然后在安装相邻的梁夹具时,先将支撑杆10安装到这个相邻的梁夹具的支撑螺纹孔13中,然后托举相邻梁夹具,使梁模板在相邻梁夹具的动夹板8和定夹板9之间,再使相邻梁夹具上的支撑杆10的一端插入已固定梁夹具上的支撑杆10上的套筒11中,已固定梁夹具可起到暂时支撑相邻梁夹具的目的,这样工人在转动丝杆5时,可不必用力托举梁夹具,而只需要用手扶住梁夹具即可,而且可通过支撑杆10来确定相邻两个梁夹具之间的间距。Then, when installing the adjacent beam clamps, first install the support rod 10 into the support threaded hole 13 of the adjacent beam clamp, and then lift the adjacent beam clamp so that the beam template is between the movable clamp 8 and the fixed clamp 9 of the adjacent beam clamp, and then insert one end of the support rod 10 on the adjacent beam clamp into the sleeve 11 on the support rod 10 on the fixed beam clamp. The fixed beam clamp can serve the purpose of temporarily supporting the adjacent beam clamp. In this way, when the worker rotates the screw 5, he does not need to lift the beam clamp with force, but only needs to hold the beam clamp with his hand, and the support rod 10 can be used to determine the distance between the two adjacent beam clamps.

Claims (8)

1. The utility model provides a template anchor clamps for construction which characterized in that: the novel telescopic screw rod comprises a female rod (1), a first telescopic cavity (2) is formed in the female rod (1), a secondary rod (3) is inserted into the first telescopic cavity (2), a second telescopic cavity (4) is formed in the secondary rod (3), a screw rod (5) is rotatably mounted in the first telescopic cavity (2) of the female rod (1), one end of the screw rod (5) extends out of the female rod (1) and is provided with a screw rod head (6), the other end of the screw rod (5) is inserted into the second telescopic cavity (4) of the secondary rod (3), a secondary rod threaded hole (7) matched with the screw rod (5) is formed in one end, close to the female rod (1), of the secondary rod (3), a movable clamping plate (8) is mounted at the other end, close to the screw rod head (6), of the female rod (1), and a fixed clamping plate (9) is mounted at one end, close to the screw rod head (6); the bottom of female pole (1) demountable installation has bracing piece (10), and bracing piece (10) set up perpendicularly with female pole (1), and one end of female pole (1) is equipped with sleeve (11).
2. The template jig for construction according to claim 1, wherein: the bottom of the female rod (1) is provided with a supporting block (12), the supporting block (12) is provided with a supporting threaded hole (13), and the middle part of the supporting rod (10) is provided with external threads matched with the supporting threaded hole (13).
3. The template jig for construction according to claim 1, wherein: two support rods (10) are detachably arranged at the bottom of the female rod (1).
4. The template jig for construction according to claim 1, wherein: the top surface of the sub-rod (3) is provided with a distance scale (14).
5. The template jig for construction according to claim 1, wherein: the length of the supporting rod (10) is 50-80 cm.
6. The template jig for construction according to claim 1, wherein: a bearing seat (15) is arranged in a first telescopic cavity (2) of the female rod (1), a bearing is arranged in the bearing seat (15), and the screw rod (5) penetrates through the bearing and is fixedly connected with the inner ring of the bearing.
7. The template jig for construction according to claim 1, wherein: a through hole (16) is formed in the screw rod head (6); an internal thread is arranged in the perforation (16).
8. The template jig for construction according to claim 1, wherein: the movable clamping plate (8) and the fixed clamping plate (9) comprise vertical plates (17), and inclined supporting plates (18) are respectively arranged on two sides of each vertical plate (17).
CN202420275307.1U 2024-02-05 2024-02-05 Template clamp for building construction Active CN221722291U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202420275307.1U CN221722291U (en) 2024-02-05 2024-02-05 Template clamp for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202420275307.1U CN221722291U (en) 2024-02-05 2024-02-05 Template clamp for building construction

Publications (1)

Publication Number Publication Date
CN221722291U true CN221722291U (en) 2024-09-17

Family

ID=92680925

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202420275307.1U Active CN221722291U (en) 2024-02-05 2024-02-05 Template clamp for building construction

Country Status (1)

Country Link
CN (1) CN221722291U (en)

Similar Documents

Publication Publication Date Title
CN201050194Y (en) Adjustable form removal support frame
CN212174258U (en) A twist-lock type windproof device for large equipment
CN221722291U (en) Template clamp for building construction
CN218205711U (en) Hang and pick board die block structure convenient to form removal
CN211201214U (en) Vertical prefabricated component positioner of assembled building concrete
CN204402044U (en) A kind of extension type cutting Split bolt sleeve and the concrete instrument of polishing
CN206000028U (en) A kind of combination built-in fitting of steel building
CN107246146B (en) Supporting bracket for building and use method thereof
CN212897551U (en) Structure for preventing concrete leakage of wall and column
CN219235618U (en) Concrete mold for easy demoulding of concrete
CN219710991U (en) Construction formwork easy dismounting device
CN216339045U (en) Slidingtype anticollision barrier template
CN215168022U (en) Adjustable building template fixing frame
CN211143754U (en) Supporting structure for aluminum template
CN221799178U (en) A building formwork support frame
CN221256171U (en) Novel reinforcing structure for connecting diagonal bracing with template
CN115822241A (en) Formwork support without chiseling and its construction method
CN210910563U (en) Fixing device for prefabricated concrete member preformed hole
CN221799152U (en) A new type of structural column template positioning equipment
CN219569543U (en) Conveniently-disassembled template
CN207714728U (en) A kind of removable anchor part
CN221919482U (en) A detachable water conservancy construction cofferdam
CN221481503U (en) High formwork early-dismantling frame
CN213391196U (en) T-shaped folding template structure
CN220847603U (en) Foundation pit supporting device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant