CN221721389U - Jacking system for double-cantilever bent cap construction - Google Patents

Jacking system for double-cantilever bent cap construction Download PDF

Info

Publication number
CN221721389U
CN221721389U CN202420290772.2U CN202420290772U CN221721389U CN 221721389 U CN221721389 U CN 221721389U CN 202420290772 U CN202420290772 U CN 202420290772U CN 221721389 U CN221721389 U CN 221721389U
Authority
CN
China
Prior art keywords
cap beam
support
construction
beam formwork
standard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202420290772.2U
Other languages
Chinese (zh)
Inventor
李龙
刘志华
罗良
阳柯
秦明清
李天菊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Topoda Machinery Technology Co ltd
Guangdong Gufucheng Engineering Development Co ltd
Original Assignee
Sichuan Topoda Machinery Technology Co ltd
Guangdong Gufucheng Engineering Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Topoda Machinery Technology Co ltd, Guangdong Gufucheng Engineering Development Co ltd filed Critical Sichuan Topoda Machinery Technology Co ltd
Priority to CN202420290772.2U priority Critical patent/CN221721389U/en
Application granted granted Critical
Publication of CN221721389U publication Critical patent/CN221721389U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model provides a jacking system for double-cantilever bent cap construction, which comprises a jacking oil cylinder, a plurality of standard support sections and a plurality of attachment hoops, wherein the jacking oil cylinder is connected with the standard support sections; the standard support sections are detachably connected from top to bottom in sequence, and the uppermost standard support section is propped against a capping beam template support unit to be jacked; the attaching hoop sections detachably lock the corresponding standard support sections on the bridge pier columns which are constructed completely; one end of the jacking oil cylinder is detachably arranged on the bent cap template support unit, and the other end of the jacking oil cylinder is detachably arranged on the standard support section; the jacking oil cylinders can drive the capping beam template support units to move up and down along the bridge pier columns by changing the number of the standard support sections and connecting the jacking oil cylinders with the standard support sections at different height positions. The jacking system can be suitable for modularized construction, improves the construction efficiency and reduces the construction cost of the bent cap.

Description

一种双悬臂盖梁施工用的顶升系统A jacking system for double cantilever cap beam construction

技术领域Technical Field

本发明涉及桥梁悬臂盖梁的浇筑施工技术领域,尤其是涉及一种双悬臂盖梁施工用的顶升系统。The invention relates to the technical field of pouring construction of a bridge cantilever cap beam, and in particular to a jacking system for the construction of a double cantilever cap beam.

背景技术Background Art

悬臂盖梁是一种桥梁结构,主要由支座、上部结构和下部结构组成,悬挑端没有支撑,中间有空隙,盖梁的施工采用一段一段地浇筑的方式,一段完成后再移动支架和模具等,进行下一段悬臂的浇筑。A cantilever cap beam is a bridge structure mainly composed of a support, an upper structure and a lower structure. There is no support at the cantilever end and there is a gap in the middle. The cap beam is constructed by casting in sections. After one section is completed, the bracket and mold are moved to cast the next section of the cantilever.

现有技术中,悬臂盖梁的施工通常使用穿心棒或固定抱箍等作为支撑,然后高位吊装贝雷梁、分配梁、底模、侧模,而后浇筑的方式。In the prior art, the construction of cantilever cap beams usually uses through rods or fixed clamps as supports, and then the Bailey beam, distribution beam, bottom formwork, and side formwork are hoisted at a high position, and then poured.

穿心钢棒法,是在墩柱预留孔洞以安装牛腿,以牛腿为起点向上搭建支架,并从地面搭设爬梯通道,爬梯通道每隔一段距离与墩柱进行附着。抱箍法,是指采用抱箍箍紧墩柱,以抱箍为起点向上搭建支架,从地面搭设爬梯通道,爬梯通道每隔一段距离与墩柱进行附着。The through-steel rod method is to reserve holes in the pier column to install the corbel, build a bracket upwards from the corbel as the starting point, and set up a ladder channel from the ground, and the ladder channel is attached to the pier column at intervals. The hoop method refers to using a hoop to tighten the pier column, build a bracket upwards from the hoop as the starting point, and set up a ladder channel from the ground, and the ladder channel is attached to the pier column at intervals.

采用上述两种方法,存在以下缺点:The above two methods have the following disadvantages:

1、两种方式零部件比较松散,需要吊装大量的散件。1. The parts of both methods are relatively loose, and a large number of parts need to be hoisted.

2、需要长时间配置独立的吊车,且由于需要吊车进行吊装的零件太零散,因此吊车占用时间较长,导致施工周期较长,施工成本高。2. It takes a long time to configure an independent crane, and because the parts that need to be lifted by the crane are too scattered, the crane takes a long time, resulting in a long construction period and high construction costs.

3、部件多为高位安装作业,存在较大的安全隐患。3. Most components are installed at high positions, which poses a great safety hazard.

4、一组墩柱及盖梁施工完后,所有设备部件需逐一转运至下一组工位,费时费工。4. After the construction of a group of piers and cap beams is completed, all equipment components need to be transported one by one to the next group of workstations, which is time-consuming and labor-intensive.

因此,在盖梁的施工过程中,根据现场施工的需求,急需一种支架和底模、侧模等可在低位模块化安装后,并能整体上升、下降和平移的盖梁施工系统,以减少散件的高空安装作业、降低吊车占用时长、提高施工效率、缩短工期、提高施工的安全系数。Therefore, during the construction of the cap beam, according to the needs of on-site construction, there is an urgent need for a cap beam construction system in which the bracket, bottom formwork, side formwork, etc. can be installed in a low-position modular manner and can rise, fall and translate as a whole, so as to reduce the high-altitude installation work of scattered parts, reduce the occupancy time of cranes, improve construction efficiency, shorten the construction period, and improve the safety factor of construction.

然后由于双悬臂盖梁的结构特殊性,现有的桥梁盖梁施工用的顶升系统都不能满足模块化的施工,也无法做到安全有效的顶升。Then, due to the structural particularity of the double-cantilever cap beam, the existing jacking systems used in the construction of bridge cap beams cannot meet the requirements of modular construction, nor can they achieve safe and effective jacking.

发明内容Summary of the invention

为解决现有技术中的问题,本发明提供一种可以适用于模块化施工、提高施工效率、降低施工成本的双悬臂盖梁施工用的顶升系统。In order to solve the problems in the prior art, the present invention provides a jacking system for double-cantilever cap beam construction which can be applicable to modular construction, improve construction efficiency and reduce construction costs.

为实现上述目的,本发明提供如下技术方案:一种双悬臂盖梁施工用的顶升系统,所述顶升系统包括顶升油缸、多个标准支撑节、多个附着抱箍;所述多个标准支撑节从上到下依次可拆卸连接,最上端的标准支撑节与待顶升的盖梁模板支架单元相抵;所述附着抱箍分段将对应标准支撑节可拆卸的锁紧在已施工完成的桥梁墩柱上;所述顶升油缸一端可拆卸的安装在待顶升的盖梁模板支架单元上,顶升油缸另一端可拆卸的安装在标准支撑节上;通过改变所述标准支撑节的数量,以及顶升油缸连接不同高度位置的标准支撑节,可实现顶升油缸带动盖梁模板支架单元沿桥梁墩柱进行上下运动。To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a jacking system for the construction of a double-cantilever cap beam, the jacking system comprising a jacking cylinder, a plurality of standard support sections, and a plurality of attachment hoops; the plurality of standard support sections are detachably connected in sequence from top to bottom, and the uppermost standard support section is against the cap beam formwork support unit to be jacked; the attachment hoop segments detachably lock the corresponding standard support sections on the completed bridge piers; one end of the jacking cylinder is detachably mounted on the cap beam formwork support unit to be jacked, and the other end of the jacking cylinder is detachably mounted on the standard support section; by changing the number of the standard support sections and connecting the jacking cylinder to the standard support sections at different heights, the jacking cylinder can drive the cap beam formwork support unit to move up and down along the bridge piers.

优选的技术方案,所述顶升系统还包括多个长度不一的调节支撑节,调节支撑节从上到下依次可拆卸的安装于所述盖梁模板支架单元与最上端的标准支撑节之间。According to a preferred technical solution, the jacking system further comprises a plurality of adjustable support sections of different lengths, and the adjustable support sections are detachably installed in sequence from top to bottom between the cap beam formwork support unit and the uppermost standard support section.

优选的技术方案,其还包括卸落块,所述卸落块安装于所述盖梁模板之间单元与最上端的调节支撑节之间。A preferred technical solution also includes a unloading block, which is installed between the unit between the cap beam formwork and the uppermost adjustment support node.

优选的技术方案,所述盖梁模板支架单元包括盖梁模板支架,所述盖梁模板支架上设置有滑轨,该滑轨上设置有多个可沿滑轨滑动的滑车;所述滑车可用于装载标准支撑节、附着抱箍、调节支撑节或者卸落块。According to a preferred technical solution, the cap beam formwork support unit comprises a cap beam formwork support, on which a slide rail is arranged, on which a plurality of pulleys which can slide along the slide rail are arranged; the pulleys can be used to load standard support sections, attach clamps, adjust support sections or unload blocks.

与现有技术相比,本发明的有益效果是:Compared with the prior art, the present invention has the following beneficial effects:

1、采用顶升系统将盖梁模板支架单元和模块化盖梁模板单元整体升至工作高度,不但降低了高空作业风险,而且也极大的提升了施工时的作业效率。1. The jacking system is used to lift the cap beam formwork support unit and the modular cap beam formwork unit to the working height as a whole, which not only reduces the risk of high-altitude operations, but also greatly improves the operation efficiency during construction.

2、低位模块化安装后,利用顶升油缸整体将盖梁模板支架及其上面搭载的装备抬升至工作高度,盖梁模板支架单元和盖梁模板的部件全部低位安装,提高工作效率,降低高空作业安全风险。2. After the low-position modular installation, the cap beam formwork support and the equipment mounted on it are lifted to the working height as a whole using the lifting cylinder. The cap beam formwork support unit and the components of the cap beam formwork are all installed at a low position to improve work efficiency and reduce the safety risks of high-altitude operations.

3、顶升系统结构更简单,拆卸方便;且标准支撑节(采用标准长度,有利于规范统一)、卸落块(方便拆卸,且能适应一定高度调整)、调节支撑节(采用不同尺寸的长度,配合标准支撑节调整高度)配合使用可达到施工所需要的任意高度,适应高度范围广,几乎可以停留在任意桥墩的高度工作面,适应桥梁的高度能力强,有利于节约成本。3. The jacking system has a simpler structure and is easy to disassemble. The standard support sections (standard length is used, which is conducive to standardization and unification), unloading blocks (easy to disassemble and can adapt to a certain height adjustment), and adjustable support sections (different lengths are used to adjust the height with standard support sections) can be used together to achieve any height required for construction. It has a wide range of heights and can almost stay at the height working surface of any pier. It has a strong ability to adapt to the height of the bridge, which is conducive to cost savings.

综上所述,本发明的顶升系统可以适用于双悬臂盖梁施工,使桥梁盖梁的施工成本大幅下降,施工效率大幅提高,高空作业大幅减少、安全性大幅提高,施工人员的作业环境得到极大改善。In summary, the jacking system of the present invention can be applied to the construction of double-cantilever cap beams, which can significantly reduce the construction cost of bridge cap beams, greatly improve construction efficiency, significantly reduce high-altitude operations, greatly improve safety, and greatly improve the working environment of construction workers.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

图1为一种双悬臂盖梁施工系统的整体结构正视图。FIG. 1 is a front view of the overall structure of a double cantilever cap beam construction system.

图2为一种双悬臂盖梁施工系统的整体结构三维视图。FIG. 2 is a three-dimensional view of the overall structure of a double cantilever cap beam construction system.

图3为一种双悬臂盖梁施工系统的底座结构示意图。FIG. 3 is a schematic diagram of the base structure of a double cantilever cap beam construction system.

图4为盖梁模板支架的结构示意图。FIG. 4 is a schematic diagram of the structure of the cap beam formwork support.

图5为活动片架的结构示意图。FIG. 5 is a schematic structural diagram of a movable sheet frame.

图6为本实用新型顶升系统的标准支撑节的结构示意图。FIG. 6 is a schematic structural diagram of a standard support section of the jacking system of the present invention.

图7为滑车的结构示意图。FIG. 7 is a schematic structural diagram of a pulley.

图8为弹性导向轮的结构示意图。FIG. 8 is a schematic structural diagram of an elastic guide wheel.

图9为弹性导向轮的三维结构示意图。FIG. 9 is a schematic diagram of the three-dimensional structure of the elastic guide wheel.

图10为盖梁模板支架的局部结构示意图。Figure 10 is a schematic diagram of the partial structure of the cap beam formwork support.

图11为本实用新型顶升系统的卸落块的正视图。FIG. 11 is a front view of the unloading block of the jacking system of the present invention.

图12为卸落块的三维结构示意图。FIG. 12 is a schematic diagram of the three-dimensional structure of the unloading block.

图13为模块化盖梁模板单元在盖梁模板支架上的连接结构示意图。Figure 13 is a schematic diagram of the connection structure of the modular cap beam formwork unit on the cap beam formwork support.

图14为图12中的A部放大图。FIG. 14 is an enlarged view of portion A in FIG. 12 .

图15为模块化盖梁模板单元的整体结构示意图。Figure 15 is a schematic diagram of the overall structure of the modular cap beam formwork unit.

图16为模块化盖梁模板单元取出底模板和拉杆后的结构示意图。Figure 16 is a schematic diagram of the structure of the modular cap beam formwork unit after the bottom formwork and tie rods are removed.

图17为图15中的B部放大图。FIG. 17 is an enlarged view of portion B in FIG. 15 .

图18为盖梁模板支架单元和模块化盖梁模板单元在低位的安装状态图。Figure 18 is a diagram showing the installation status of the cap beam formwork support unit and the modular cap beam formwork unit at a low position.

图19至图22为盖梁模板支架和模块化盖梁模板单元沿桥梁墩柱向上逐步爬升的过程图。Figures 19 to 22 are process diagrams showing the cap beam formwork support and the modular cap beam formwork unit gradually climbing upward along the bridge pier.

图23为盖梁模板支架和模块化盖梁模板单元下降至平移连接支架上的状态正视图。Figure 23 is a front view of the state where the cap beam formwork support and the modular cap beam formwork unit are lowered onto the translation connection support.

图24为盖梁模板支架和模块化盖梁模板单元下降至平移连接支架上的状态俯视图。Figure 24 is a top view of the state where the cap beam formwork support and the modular cap beam formwork unit are lowered onto the translation connection support.

图25为安装好加强支撑架后的状态三维视图。FIG. 25 is a three-dimensional view of the state after the reinforcing support frame is installed.

图26为安装好加强支撑架后的状态俯视图。FIG. 26 is a top view of the state after the reinforcing support frame is installed.

图27为去除掉活动片架后的状态三维视图。Figure 27 is a three-dimensional view of the state after removing the movable film frame.

图28为去除掉活动片架后的状态俯视图。Figure 28 is a top view of the state after the movable sheet frame is removed.

图29为双悬臂盖梁整体平移出桥梁墩柱后的状态图。Figure 29 is a diagram showing the state of the double cantilever cap beam after it has been completely translated out of the bridge pier.

图30为双悬臂盖梁整体平移出桥梁墩柱后安装好活动片架后的状态图。Figure 30 shows the state of the double cantilever cap beam after it has been completely translated out of the bridge pier and the movable frame has been installed.

具体实施方式DETAILED DESCRIPTION

参照附图对本实用新型一种双悬臂盖梁施工用的顶升系统的的实施例进一步说明。The embodiment of the jacking system for the construction of a double cantilever cap beam of the utility model is further described with reference to the accompanying drawings.

实施例1Example 1

如图1至图30所示,一种双悬臂盖梁施工系统包括盖梁模板支架单元1、模块化盖梁模板单元2、顶升系统3;所述模块化盖梁模板单元2可拆卸的安装在盖梁模板支架单元1上;在本实施中本双悬臂盖梁施工系统还配置有平面万向平移系统4。As shown in Figures 1 to 30, a double cantilever cap beam construction system includes a cap beam formwork support unit 1, a modular cap beam formwork unit 2, and a jacking system 3; the modular cap beam formwork unit 2 is detachably installed on the cap beam formwork support unit 1; in this embodiment, the double cantilever cap beam construction system is also configured with a planar universal translation system 4.

所述顶升系统3包括顶升油缸31、多个标准支撑节32、多个附着抱箍33;所述多个标准支撑节32从上到下依次可拆卸连接,最上端的标准支撑节32与所述盖梁模板支架单元1相抵;所述附着抱箍33分段将对应标准支撑节32可拆卸的锁紧在已施工完成的桥梁墩柱04上;所述顶升油缸31一端可拆卸的安装在盖梁模板支架单元1上,顶升油缸31另一端可拆卸的安装在标准支撑节32上;通过改变所述标准支撑节32的数量,以及顶升油缸31连接不同高度位置的标准支撑节32,可实现顶升油缸31带动所述盖梁模板支架单元1沿桥梁墩柱04进行上下运动。The jacking system 3 includes a jacking cylinder 31, a plurality of standard support nodes 32, and a plurality of attachment hoops 33; the plurality of standard support nodes 32 are detachably connected from top to bottom in sequence, and the uppermost standard support node 32 is abutted against the cap beam formwork support unit 1; the attachment hoop 33 divides the corresponding standard support node 32 into sections and detachably locks it on the completed bridge pier 04; one end of the jacking cylinder 31 is detachably mounted on the cap beam formwork support unit 1, and the other end of the jacking cylinder 31 is detachably mounted on the standard support node 32; by changing the number of the standard support nodes 32, and connecting the jacking cylinder 31 to the standard support nodes 32 at different heights, the jacking cylinder 31 can drive the cap beam formwork support unit 1 to move up and down along the bridge pier 04.

所述顶升系统3还包括多个长度不一的调节支撑节34,调节支撑节34从上到下依次可拆卸的安装于所述盖梁模板支架单元1与最上端的标准支撑节32之间。The jacking system 3 also includes a plurality of adjustable support sections 34 of different lengths, and the adjustable support sections 34 are detachably installed in sequence from top to bottom between the cap beam formwork support unit 1 and the uppermost standard support section 32 .

双悬臂盖梁施工系统还包括卸落块35,所述卸落块35安装于所述盖梁模板支架单元1与最上端的调节支撑节34之间。如图11和图12,所述卸落块35整体呈“工”字形,包括上调节块35、下调节块36和中间调节块37;中间调节块37有两块,分别设于所述上调节块35与下调节块36之间的左、右两侧;且上调节块35、下调节块36与两个中间调节块37之间通过朝向“工”字形中心的斜面接触,所述两个中间调节块37之间穿设有用于调整两个中间调节块37之间距离的调节螺杆39,通过转动调节螺杆39,进而调整两个中间调节块37之间的开合距离,从而使上调节块35与下调节块36之间的竖直距离改变。当两个中间调节块37远离时,上调节块36与下调节块37之间垂直距离变小;当两个中间调节块37靠近时,上调节块36与下调节块37之间垂直距离变大。当需要下降整个盖梁模板支架单元1时,通过设置卸落块35,可使卸落块35的高度微调,卸落块35上表面降低2cm,从而使得更方便拆卸调节支撑节34。The double cantilever cap beam construction system also includes a drop block 35, which is installed between the cap beam formwork support unit 1 and the uppermost adjustment support section 34. As shown in Figures 11 and 12, the drop block 35 is in the shape of an "I" as a whole, including an upper adjustment block 35, a lower adjustment block 36 and an intermediate adjustment block 37; there are two intermediate adjustment blocks 37, which are respectively arranged on the left and right sides between the upper adjustment block 35 and the lower adjustment block 36; and the upper adjustment block 35, the lower adjustment block 36 and the two intermediate adjustment blocks 37 are in contact through an inclined surface toward the center of the "I" shape, and an adjustment screw 39 for adjusting the distance between the two intermediate adjustment blocks 37 is inserted between the two intermediate adjustment blocks 37. By rotating the adjustment screw 39, the opening and closing distance between the two intermediate adjustment blocks 37 is adjusted, thereby changing the vertical distance between the upper adjustment block 35 and the lower adjustment block 36. When the two middle adjustment blocks 37 are far away from each other, the vertical distance between the upper adjustment block 36 and the lower adjustment block 37 becomes smaller; when the two middle adjustment blocks 37 are close to each other, the vertical distance between the upper adjustment block 36 and the lower adjustment block 37 becomes larger. When the entire cap beam formwork support unit 1 needs to be lowered, the height of the unloading block 35 can be finely adjusted by setting the unloading block 35, and the upper surface of the unloading block 35 is lowered by 2 cm, so that it is more convenient to disassemble and adjust the support section 34.

所述盖梁模板支架单元1包括盖梁模板支架11,所述盖梁模板支架11上设置有滑轨12,该滑轨12上设置有多个可沿滑轨12滑动的滑车13;所述滑车13可用于装载标准支撑节32、附着抱箍33、调节支撑节34或者卸落块35。The cap beam formwork support unit 1 includes a cap beam formwork support 11, on which a slide rail 12 is arranged, and on which a plurality of pulleys 13 that can slide along the slide rail 12 are arranged; the pulley 13 can be used to load a standard support section 32, an attachment clamp 33, an adjustment support section 34 or a unloading block 35.

所述盖梁模板支架11还设置有可拆卸的活动片架14;所述盖梁模板支架单元1还包括与盖梁模板支架11的活动片架14相匹配使用的可拆卸的加强凹支架15,加强凹支架15至少具有一个容纳对应桥梁墩柱的让位空间;通过交替安装/拆卸对应的加强凹支架15与活动片架14,可将所述盖梁模板支架11与所述模块化盖梁模板单元2整体移出或者移入对应的桥梁墩柱04。The cap beam formwork support 11 is also provided with a detachable movable sheet frame 14; the cap beam formwork support unit 1 also includes a detachable reinforcing recessed support 15 used in matching with the movable sheet frame 14 of the cap beam formwork support 11, and the reinforcing recessed support 15 has at least one makeshift space for accommodating the corresponding bridge pier; by alternately installing/disassembling the corresponding reinforcing recessed support 15 and the movable sheet frame 14, the cap beam formwork support 11 and the modular cap beam formwork unit 2 can be moved out or moved into the corresponding bridge pier 04 as a whole.

当需要将盖梁模板支架11与模块化盖梁模板单元2整体移出桥梁墩柱04时,首先将加强凹支架15安装在对应盖梁模板支架11上,然后拆卸掉对应的活动片架14,利用加强凹支架15的让位空间即可移动盖梁模板支架11与模块化盖梁模板单元1使之整体远离对应桥梁墩柱04,移动到位后,再安装上对应的活动片架14,拆卸掉对应加强凹支架15,即可将所述盖梁模板支架11与所述模块化盖梁模板单元2整体移出对应桥梁墩柱04;When it is necessary to move the cap beam formwork support 11 and the modular cap beam formwork unit 2 out of the bridge pier 04 as a whole, first install the reinforcing recessed support 15 on the corresponding cap beam formwork support 11, then remove the corresponding movable sheet frame 14, and use the space left by the reinforcing recessed support 15 to move the cap beam formwork support 11 and the modular cap beam formwork unit 1 away from the corresponding bridge pier 04 as a whole. After moving into place, install the corresponding movable sheet frame 14, remove the corresponding reinforcing recessed support 15, and then move the cap beam formwork support 11 and the modular cap beam formwork unit 2 out of the corresponding bridge pier 04 as a whole.

当需要将盖梁模板支架11与模块化盖梁模板单元2整体移入桥梁墩柱04时,首先让对应桥梁墩柱04位于对应加强凹支架15的让位空间内,再将加强凹支架15安装在对应盖梁模板支架11上,然后拆卸掉对应的活动片架14,利用加强凹支架15的让位空间即可移动盖梁模板支架11与模块化盖梁模板单元2并使之整体靠近对应桥梁墩柱04,移动到位后,再安装上对应的活动片架14,拆卸掉对应加强凹支架15,即可将所述盖梁模板支架11与所述模块化盖梁模板单元2整体移入对应桥梁墩柱04。When it is necessary to move the cap beam formwork support 11 and the modular cap beam formwork unit 2 as a whole into the bridge pier 04, first make the corresponding bridge pier 04 located in the making way space of the corresponding reinforced recessed support 15, then install the reinforced recessed support 15 on the corresponding cap beam formwork support 11, and then remove the corresponding movable sheet frame 14. The cap beam formwork support 11 and the modular cap beam formwork unit 2 can be moved and brought as a whole close to the corresponding bridge pier 04 by utilizing the making way space of the reinforced recessed support 15. After moving into place, install the corresponding movable sheet frame 14, remove the corresponding reinforced recessed support 15, and then the cap beam formwork support 11 and the modular cap beam formwork unit 2 can be moved as a whole into the corresponding bridge pier 04.

所述盖梁模板支架单元1安装有多个弹性导向轮16;顶升油缸31带动所述盖梁模板支架单元1沿桥梁墩柱04进行上下运动时,所述弹性导向轮16沿桥梁墩柱05的表面进行滚动,对盖梁模板支架单元1进行导向。The cap beam formwork support unit 1 is equipped with a plurality of elastic guide wheels 16 ; when the lifting cylinder 31 drives the cap beam formwork support unit 1 to move up and down along the bridge pier 04 , the elastic guide wheels 16 roll along the surface of the bridge pier 05 to guide the cap beam formwork support unit 1 .

所述模块化盖梁模板单元2,如图15至图17所示,其包括分配梁21、底模板22、侧模板23;所述分配梁21可拆卸的安装在盖梁模板支架单元1上;所述底模板22安装在分配梁21上;所述侧模板23安装在分配梁21上,且分别位于底模板22两侧;多个模块化盖梁模板单元2依次相互拼接,且首尾模块化盖梁模板单元2设置有挡板5,形成完整的盖梁模板6。所述模块化盖梁模板单元2还可以包括位于顶部用于拉紧两个侧模板23的拉杆24。The modular cap beam template unit 2, as shown in Figures 15 to 17, includes a distribution beam 21, a bottom template 22, and a side template 23; the distribution beam 21 is detachably mounted on the cap beam template support unit 1; the bottom template 22 is mounted on the distribution beam 21; the side templates 23 are mounted on the distribution beam 21 and are respectively located on both sides of the bottom template 22; multiple modular cap beam template units 2 are sequentially spliced with each other, and the first and last modular cap beam template units 2 are provided with baffles 5 to form a complete cap beam template 6. The modular cap beam template unit 2 may also include a tie rod 24 located at the top for tightening the two side templates 23.

所述侧模板23设置有扶正装置,所述扶正装置包括伸缩支撑杆25、滚动模块26、固定装置27;所述分配梁21为双槽钢,该双槽钢上设有多个安装固定装置27的安装孔,所述固定装置27可根据需要固定在双槽钢的对应安装孔上;所述伸缩支撑杆25一端与侧模板23铰接,伸缩支撑杆25另一端与所述滚动模块26铰接;所述滚动模块26可沿所述分配梁21滚动,且所述滚动模块26一端与侧模板23铰接,滚动模块26另一端与固定装置27相抵;所述侧模板23在未固定安装于分配梁21上时,可沿所述分配梁21滑动;所述固定装置27设置有螺纹调节顶杆28,转动所述螺纹调节顶杆28可顶动所述滚动模块26在分配梁21上移动,实现对侧模板23的调整。The side formwork 23 is provided with a straightening device, which includes a telescopic support rod 25, a rolling module 26, and a fixing device 27; the distribution beam 21 is a double-channel steel, which is provided with a plurality of mounting holes for mounting the fixing device 27, and the fixing device 27 can be fixed on the corresponding mounting holes of the double-channel steel as needed; one end of the telescopic support rod 25 is hinged to the side formwork 23, and the other end of the telescopic support rod 25 is hinged to the rolling module 26; the rolling module 26 can roll along the distribution beam 21, and one end of the rolling module 26 is hinged to the side formwork 23, and the other end of the rolling module 26 is against the fixing device 27; when the side formwork 23 is not fixedly installed on the distribution beam 21, it can slide along the distribution beam 21; the fixing device 27 is provided with a threaded adjustment push rod 28, and rotating the threaded adjustment push rod 28 can push the rolling module 26 to move on the distribution beam 21, so as to adjust the side formwork 23.

所述模块化盖梁模板单元2与盖梁模板支架11之间通过固定夹持装置8固定,如图13和图14所示,所述固定夹持装置8包括夹板81、上夹块82、下夹块83,上夹块82和下夹块83均穿设于夹板81的两端,且上夹块82和下夹块83之间穿设有紧固螺钉。上夹块82向下压紧在分配梁21的槽钢上,下夹块83向上压紧在盖梁模板支架11上部的钢结构型材上,从而将模块化盖梁模板单元2固定于盖梁模板支架11上。The modular cap beam template unit 2 is fixed to the cap beam template support 11 by a fixing clamping device 8, as shown in Figures 13 and 14, the fixing clamping device 8 includes a clamping plate 81, an upper clamping block 82, and a lower clamping block 83. The upper clamping block 82 and the lower clamping block 83 are both inserted at both ends of the clamping plate 81, and a fastening screw is inserted between the upper clamping block 82 and the lower clamping block 83. The upper clamping block 82 is pressed downward on the channel steel of the distribution beam 21, and the lower clamping block 83 is pressed upward on the steel structure profile on the upper part of the cap beam template support 11, thereby fixing the modular cap beam template unit 2 on the cap beam template support 11.

如图3所示,为桥梁盖梁施工系统的工作状态。本实施例中额外配置有底座08,底座08置于地面(在其它实施例可以有底座,也可以将地面足够硬化处理后直接安装标准支撑节),由螺纹拉杆07拉紧并抱紧桥梁桥墩04。底座08上顺序放置连接座09、底部的调节支撑节34、标准支撑节32,各标准支撑节32由附着抱箍33的螺纹拉杆07拉紧于桥梁墩柱04上,使其固定。所述盖梁模板支架单元1置于卸落块35上,侧模板23置于盖梁模板支架11上。平面万向平移系统4和平移连接支架7置于地面,待平移时使用。As shown in Figure 3, it is the working state of the bridge cap beam construction system. In this embodiment, a base 08 is additionally configured, and the base 08 is placed on the ground (in other embodiments, there may be a base, or the ground may be hardened sufficiently and the standard support section may be directly installed), and the bridge pier 04 is tightened and clamped by the threaded tie rod 07. The connecting seat 09, the bottom adjustment support section 34, and the standard support section 32 are placed on the base 08 in sequence, and each standard support section 32 is tightened on the bridge pier 04 by the threaded tie rod 07 with the clamp 33 attached to fix it. The cap beam formwork support unit 1 is placed on the unloading block 35, and the side formwork 23 is placed on the cap beam formwork support 11. The planar universal translation system 4 and the translation connection bracket 7 are placed on the ground to be used for translation.

本发明一种双悬臂盖梁施工系统的工作过程如下:The working process of a double cantilever cap beam construction system of the present invention is as follows:

步骤S1,如图18,低位安装盖梁模板支架单元1、模块化盖梁模板单元2Step S1, as shown in FIG18, the cap beam template support unit 1 and the modular cap beam template unit 2 are installed at a low position.

在桥梁墩柱04低位,根据实际需要组装好顶升系统的标准支撑节32、顶升油缸31、以及对应附着抱箍33;组装好盖梁模板支架单元1;将模块化盖梁模板单元2拼装到盖梁模板支架11上;根据实际需要让滑车13装载一定量的标准支撑节32、附着抱箍33、调节支撑节34以及卸落块35;At the lower position of the bridge pier 04, assemble the standard support section 32, the jacking cylinder 31, and the corresponding attachment hoop 33 of the jacking system according to actual needs; assemble the cap beam template support unit 1; assemble the modular cap beam template unit 2 to the cap beam template support 11; load a certain amount of standard support sections 32, attachment hoops 33, adjustment support sections 34, and unloading blocks 35 on the pulley 13 according to actual needs;

步骤S2,如图19至图22,盖梁模板支架单元1的爬升Step S2, as shown in Figures 19 to 22, the cap beam formwork support unit 1 is climbed

S2a、顶升油缸31顶升一个行程,带动盖梁模板支架单元1沿桥梁墩柱04爬升至预设位置;从滑车13上取下标准支撑节32,以及对应附着抱箍33;将从滑车13上取下的标准支撑节32固定连接到前述已组装好的最上端的标准支撑节32上,并通过对应附着抱箍33锁紧在桥梁墩柱04上;顶升油缸31缩回让盖梁模板支架单元1暂时支撑在当前最上端的标准支撑节32上;将顶升油缸31另一端从较低的标准支撑节32上拆下,重新安装在较高的标准支撑节32上后,顶升油缸31再次顶升带动盖梁模板支架单元1沿桥梁墩柱04向上爬升;S2a, the lifting cylinder 31 lifts a stroke, driving the cap beam formwork support unit 1 to climb to the preset position along the bridge pier 04; removes the standard support section 32 and the corresponding attachment clamp 33 from the pulley 13; the standard support section 32 removed from the pulley 13 is fixedly connected to the aforementioned uppermost standard support section 32 that has been assembled, and is locked on the bridge pier 04 through the corresponding attachment clamp 33; the lifting cylinder 31 retracts to allow the cap beam formwork support unit 1 to be temporarily supported on the current uppermost standard support section 32; the other end of the lifting cylinder 31 is removed from the lower standard support section 32, and after being reinstalled on the higher standard support section 32, the lifting cylinder 31 lifts again to drive the cap beam formwork support unit 1 to climb upward along the bridge pier 04;

S2b、重复步骤S2a直至将盖梁模板支架单元1升降至桥墩预定位置后,根据实际需要从滑车13上取下调节支撑节34和/或卸落块35,将盖梁模板支架单元1调节至盖梁施工高度,进行当前工位的盖梁施工;S2b, repeat step S2a until the cap beam template support unit 1 is lifted to the predetermined position of the pier, remove the adjustment support section 34 and/or the unloading block 35 from the pulley 13 according to actual needs, adjust the cap beam template support unit 1 to the cap beam construction height, and carry out the cap beam construction at the current workstation;

步骤S3,如图23和图24,盖梁模板支架单元1的下降Step S3, as shown in Figures 23 and 24, the cap beam formwork support unit 1 is lowered

S3a、当前工位的盖梁施工完成后,依次拆卸卸落块35和/或调节支撑节34、和/或标准支撑节32,通过从上往下逐次改变顶升油缸31与不同高度的标准支撑节32的连接,逐次实现对从上到下的标准支撑节32进行拆除,以及带动盖梁模板支架单元1的下降;S3a, after the cap beam construction of the current station is completed, the unloading block 35 and/or the adjustment support section 34, and/or the standard support section 32 are dismantled in sequence, and the standard support sections 32 from top to bottom are dismantled one by one by changing the connection between the jacking cylinder 31 and the standard support sections 32 of different heights from top to bottom, and the cap beam formwork support unit 1 is driven to descend;

步骤S4,如图25至图30,将盖梁模板支架单元1移至下一工位Step S4, as shown in Figures 25 to 30, move the cap beam formwork support unit 1 to the next station

当盖梁模板支架单元1下降至既定位置后,其坐落在地面上的万向平移系统4上;将加强凹支架15安装在对应的盖梁模板支架11上,然后拆卸掉对应的活动片架14,即可利用加强凹支架15的让位空间,采用万向平移系统4,移动盖梁模板支架11与模块化盖梁模板单元2,使之整体远离当前工位的桥梁墩柱,移动到位后,再安装上对应的活动片架14,拆卸掉对应的加强凹支架15,将所述盖梁模板支架11与所述模块化盖梁模板单元2整体移出当前工位的桥梁墩柱04;When the cap beam formwork support unit 1 is lowered to a predetermined position, it is seated on the universal translation system 4 on the ground; the reinforced recessed support 15 is installed on the corresponding cap beam formwork support 11, and then the corresponding movable sheet frame 14 is disassembled, and the space left by the reinforced recessed support 15 can be utilized to adopt the universal translation system 4 to move the cap beam formwork support 11 and the modular cap beam formwork unit 2 as a whole away from the bridge pier of the current work station, and after moving into position, the corresponding movable sheet frame 14 is installed, and the corresponding reinforced recessed support 15 is disassembled, and the cap beam formwork support 11 and the modular cap beam formwork unit 2 are moved as a whole out of the bridge pier 04 of the current work station;

将盖梁模板支架11与模块化盖梁模板单元2整体移入下一工位的桥梁墩柱时,首先让对应桥梁墩柱04位于对应加强凹支架15的让位空间内,再将加强凹支架15安装在对应的盖梁模板支架11上,然后拆卸掉对应的活动片架14,利用加强凹支架15的让位空间即可移动盖梁模板支架11与模块化盖梁模板单元2,使之整体靠近对应桥梁墩柱,移动到位后,再安装上对应的活动片架14,拆卸掉对应加强凹支架15,即可将所述盖梁模板支架11与所述模块化盖梁模板单元2整体移入下一工位的对应桥梁墩柱,以便进行盖梁施工;When the cap beam formwork support 11 and the modular cap beam formwork unit 2 are moved as a whole into the bridge pier of the next station, firstly, the corresponding bridge pier 04 is positioned in the making way space of the corresponding reinforced recessed support 15, and then the reinforced recessed support 15 is installed on the corresponding cap beam formwork support 11, and then the corresponding movable sheet frame 14 is removed, and the cap beam formwork support 11 and the modular cap beam formwork unit 2 can be moved as a whole close to the corresponding bridge pier by using the making way space of the reinforced recessed support 15, and then the corresponding movable sheet frame 14 is installed after being moved into position, and the corresponding reinforced recessed support 15 is removed, and then the cap beam formwork support 11 and the modular cap beam formwork unit 2 can be moved as a whole into the corresponding bridge pier of the next station, so as to carry out the cap beam construction;

重复步骤S2至步骤S4直至完成整个盖梁施工。Repeat steps S2 to S4 until the entire cap beam construction is completed.

以上仅为本发明的较佳实施例而已,并不用以限制本发明,应当指出的是,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。The above are only preferred embodiments of the present invention and are not intended to limit the present invention. It should be pointed out that any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims (4)

1.一种双悬臂盖梁施工用的顶升系统,其特征在于:所述顶升系统包括顶升油缸、多个标准支撑节、多个附着抱箍;所述多个标准支撑节从上到下依次可拆卸连接,最上端的标准支撑节与待顶升的盖梁模板支架单元相抵;所述附着抱箍分段将对应标准支撑节可拆卸的锁紧在已施工完成的桥梁墩柱上;所述顶升油缸一端可拆卸的安装在待顶升的盖梁模板支架单元上,顶升油缸另一端可拆卸的安装在标准支撑节上;通过改变所述标准支撑节的数量,以及顶升油缸连接不同高度位置的标准支撑节,可实现顶升油缸带动盖梁模板支架单元沿桥梁墩柱进行上下运动。1. A jacking system for the construction of a double-cantilever cap beam, characterized in that: the jacking system comprises a jacking cylinder, a plurality of standard support sections, and a plurality of attachment hoops; the plurality of standard support sections are detachably connected in sequence from top to bottom, and the uppermost standard support section is against the cap beam formwork support unit to be jacked; the attachment hoop segments detachably lock the corresponding standard support sections on the completed bridge piers; one end of the jacking cylinder is detachably mounted on the cap beam formwork support unit to be jacked, and the other end of the jacking cylinder is detachably mounted on the standard support section; by changing the number of the standard support sections and connecting the jacking cylinder to the standard support sections at different heights, the jacking cylinder can drive the cap beam formwork support unit to move up and down along the bridge piers. 2.根据权利要求1所述的一种双悬臂盖梁施工用的顶升系统,其特征在于:所述顶升系统还包括多个长度不一的调节支撑节,调节支撑节从上到下依次可拆卸的安装于所述盖梁模板支架单元与最上端的标准支撑节之间。2. According to claim 1, a jacking system for the construction of a double cantilever cap beam is characterized in that: the jacking system also includes a plurality of adjustable support sections of different lengths, and the adjustable support sections are detachably installed in sequence from top to bottom between the cap beam formwork support unit and the uppermost standard support section. 3.根据权利要求2所述的一种双悬臂盖梁施工用的顶升系统,其特征在于:其还包括卸落块,所述卸落块安装于所述盖梁模板之间单元与最上端的调节支撑节之间。3. A jacking system for the construction of a double cantilever cap beam according to claim 2, characterized in that it also includes a unloading block, which is installed between the unit between the cap beam formwork and the uppermost adjustment support node. 4.根据权利要求1所述的一种双悬臂盖梁施工用的顶升系统,其特征在于:所述盖梁模板支架单元包括盖梁模板支架,所述盖梁模板支架上设置有滑轨,该滑轨上设置有多个可沿滑轨滑动的滑车;所述滑车可用于装载标准支撑节、附着抱箍、调节支撑节或者卸落块。4. A jacking system for the construction of a double cantilever cap beam according to claim 1, characterized in that: the cap beam formwork support unit includes a cap beam formwork support, the cap beam formwork support is provided with a slide rail, and the slide rail is provided with a plurality of pulleys that can slide along the slide rail; the pulley can be used to load standard support sections, attach clamps, adjust support sections or unload blocks.
CN202420290772.2U 2024-02-08 2024-02-08 Jacking system for double-cantilever bent cap construction Active CN221721389U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202420290772.2U CN221721389U (en) 2024-02-08 2024-02-08 Jacking system for double-cantilever bent cap construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202420290772.2U CN221721389U (en) 2024-02-08 2024-02-08 Jacking system for double-cantilever bent cap construction

Publications (1)

Publication Number Publication Date
CN221721389U true CN221721389U (en) 2024-09-17

Family

ID=92693692

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202420290772.2U Active CN221721389U (en) 2024-02-08 2024-02-08 Jacking system for double-cantilever bent cap construction

Country Status (1)

Country Link
CN (1) CN221721389U (en)

Similar Documents

Publication Publication Date Title
CN110056374B (en) Construction device and construction method for variable-section tunnel
CN111749140B (en) A truss integral lifting bridge high pier climbing formwork device and construction method
CN205653708U (en) Work platform that inclined plane climbed follows
JP3804883B2 (en) Concrete high structure construction apparatus and concrete oblique column construction method
CN109279480A (en) A kind of steel structure lift shaft splicing apparatus and method
CN116065500A (en) Cable-stayed bridge tower girder synchronous system and construction method
CN114197860B (en) Double-layer climbing formwork system for rapid construction and climbing formwork construction method
CN101457587B (en) Template mutually lifting climbing apparatus and method
CN221721389U (en) Jacking system for double-cantilever bent cap construction
CN117779634A (en) Double-cantilever bent cap construction system and construction method thereof
CN221721390U (en) A modular cap beam formwork unit for double cantilever cap beam construction
CN221740959U (en) Double-cantilever bent cap construction system
CN106836146B (en) Hydraulic self-lifting cantilever heavy arch dam template working platform
CN209908521U (en) Construction device for variable cross-section tunnel
CN209958161U (en) Track beam linear adjustment equipment
CN111519661A (en) A laterally slidable vertical wall construction mobile formwork and construction method thereof
CN216765625U (en) Integral hydraulic creeping formwork structure for double-column pier construction
JPH05280012A (en) Movable formwork process and device used therefor
CN215210543U (en) Lifting operation platform
CN221989116U (en) A cap beam formwork support unit for double cantilever cap beam construction
CN104372948A (en) Elevator shaft formwork lifting frame
CN115807388A (en) An intelligent hydraulic tower jacking system for thin-walled pier
CN110202684B (en) Z-shaped prefabricated PC beam forming construction method
CN114261006A (en) Structure for fixing and dismantling prefabricated box girder template and construction method
CN114232555B (en) High and large construction structure and method for integrally transferred dock buttress wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant