CN221662413U - A tripod for rapid lifting and sinking of ring beams - Google Patents

A tripod for rapid lifting and sinking of ring beams Download PDF

Info

Publication number
CN221662413U
CN221662413U CN202322823294.5U CN202322823294U CN221662413U CN 221662413 U CN221662413 U CN 221662413U CN 202322823294 U CN202322823294 U CN 202322823294U CN 221662413 U CN221662413 U CN 221662413U
Authority
CN
China
Prior art keywords
ring
triangular prism
triangular
prism structure
tripod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322823294.5U
Other languages
Chinese (zh)
Inventor
田伟
曹志鹏
陈启航
卢登文
张新宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Engineering Division Corp Ltd
Original Assignee
China Construction Fourth Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Engineering Division Corp Ltd filed Critical China Construction Fourth Engineering Division Corp Ltd
Priority to CN202322823294.5U priority Critical patent/CN221662413U/en
Application granted granted Critical
Publication of CN221662413U publication Critical patent/CN221662413U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model discloses a tripod for rapid lifting and ring beam sinking construction, which comprises a hanging bracket, wherein the middle part of the hanging bracket comprises three I-beams vertically arranged into a triangular prism structure, the outer side wall of the top of the triangular prism structure is provided with a tensile outer ring which is connected with each I-beam, one side of each I-beam, which is far away from the central axis of the triangular prism structure, is provided with a hanging hook, and one side of each I-beam, which is close to the central axis of the triangular prism structure, is provided with a supporting inner ring connected with each I-beam; the triangular support structure can ensure the most stable support effect, the triangular support effect is the most stable, the bearing level of the triangular support structure can be ensured to reach ton level by adopting the I-steel, the tensile outer ring is used for preventing the damage to the triangular support due to the outward expansion force during hoisting, the support inner ring can ensure that the I-steel has a stable triangular structure during use, and the lifting hook can be used for effectively fixing the pull chain block.

Description

一种快速起吊及沉环梁施工的三角架A tripod for rapid lifting and sinking of ring beams

技术领域Technical Field

本实用新型涉及环梁起吊技术领域,更具体地说,它涉及一种快速起吊及沉环梁施工的三角架。The utility model relates to the technical field of ring beam lifting, and more specifically, to a tripod for fast lifting and sinking of ring beam construction.

背景技术Background Art

在常规的环梁以及环梁的周边梁的吊装时,首先需要在钢管柱周边先支设环梁的底模和周边梁的侧模,在常规吊装的时候就需要将侧模的一侧拆开,然后捆扎钢筋等待钢筋捆扎完成后再进行封模,这样传统的方式下来手续非常复杂、多项零星施工和重复施工。When hoisting a conventional ring beam and the surrounding beams of the ring beam, it is first necessary to set up the bottom formwork of the ring beam and the side formwork of the surrounding beam around the steel pipe column. During conventional hoisting, it is necessary to disassemble one side of the side formwork, and then tie the steel bars and wait for the steel bars to be tied before sealing the formwork. This traditional method has very complicated procedures, multiple sporadic constructions and repeated construction.

实用新型内容Utility Model Content

本实用新型的目的是提供一种快速起吊及沉环梁施工的三角架,一种能够同时起吊环梁与周边梁的装置。The utility model aims to provide a tripod for rapid lifting and sinking of a ring beam, a device capable of lifting a ring beam and a peripheral beam at the same time.

本实用新型的上述技术目的是通过以下技术方案得以实现的:一种快速起吊及沉环梁施工的三角架,吊架,吊架包括,吊架的中部包括三根竖直排列成三棱柱结构的工字钢,所述三棱柱结构顶部外侧壁上设置有抗拉外环且所述抗拉外环与每根所述工字钢连接,每根所述工字钢远离三棱柱结构中轴线的一侧均设置有吊钩,每根所述工字钢靠近三棱柱结构中轴线的一侧设置与每根工字钢连接的支撑内环。The above-mentioned technical purpose of the utility model is achieved through the following technical scheme: a tripod for rapid lifting and sinking ring beam construction, a hanger, the hanger including, the middle part of the hanger including three I-beams vertically arranged into a triangular prism structure, a tensile outer ring is arranged on the outer wall of the top of the triangular prism structure and the tensile outer ring is connected to each of the I-beams, a hook is arranged on the side of each of the I-beams away from the central axis of the triangular prism structure, and a supporting inner ring connected to each I-beam is arranged on the side of each of the I-beams close to the central axis of the triangular prism structure.

通过采用三棱柱结构能够保证最稳定的支撑效果,三角支撑效果最稳固,通过采用工字钢能够保证其承重级别能够达到吨级而抗拉外环是防止在吊装时的外扩力对本三角架损坏,支撑内环能够保证工字钢在使用时有稳固的三角结构,通过设置吊钩能够有效的对手拉葫芦的固定。The use of a triangular prism structure can ensure the most stable support effect, and the triangular support effect is the most stable. The use of I-beams can ensure that the load-bearing level can reach the ton level, and the tensile outer ring prevents the outward expansion force during lifting from damaging the tripod. The supporting inner ring can ensure that the I-beam has a stable triangular structure when in use. By setting a hook, the hand chain hoist can be effectively fixed.

本实用新型进一步设置为:所述工字钢分为竖直部以及一体成型于竖直部长边的两个接触部,若干所述工字钢的竖直部延长面相交处为三棱柱结构的中轴线。The utility model is further configured as follows: the I-beam is divided into a vertical portion and two contact portions integrally formed on the vertical long sides, and the intersection of the extended surfaces of the vertical portions of several of the I-beams is the central axis of the triangular prism structure.

通过采用将竖直部延长面相交处作为三棱柱结构的中轴线能够保证工字钢保证以两个平面面对三棱柱结构的中心和外壁处,以保证其他零件的焊接便捷以及安装位置。By using the intersection of the extended surfaces of the vertical parts as the central axis of the triangular prism structure, the I-beam can be guaranteed to face the center and outer wall of the triangular prism structure with two planes, so as to ensure the convenience of welding and installation of other parts.

本实用新型进一步设置为:所述工字钢远离抗拉外环的竖直部上开设有卡槽。The utility model is further configured as follows: a clamping groove is provided on the vertical portion of the I-beam away from the tensile outer ring.

通过采用卡槽的开设是为了更方便的与钢管柱的连接,工字钢的底部通过钢管柱卡接后还能够使其卡接部分给与对抗外扩支撑的力度。The purpose of opening the card slot is to facilitate the connection with the steel pipe column. After the bottom of the I-beam is clamped by the steel pipe column, the clamping part can also provide a force to resist outward expansion support.

本实用新型进一步设置为:所述三棱柱结构内至少存在两个间隔设置的支撑内环。The utility model is further configured as follows: there are at least two spaced supporting inner rings in the triangular prism structure.

通过采用多个支撑内环能够保证吊装时的加大支撑力度。By adopting multiple supporting inner rings, it is possible to ensure greater supporting strength during lifting.

本实用新型进一步设置为:所述支撑内环为三角形结构。The utility model is further configured as follows: the supporting inner ring is a triangular structure.

通过采用支撑内环为三角形结构最稳定并且能够符合直接支撑工字钢的情况而且三角结构的设置最为简便支撑效果好。The use of a triangular structure as the inner support ring is the most stable and can meet the requirements of directly supporting the I-beam. The triangular structure is also the simplest to set up and has a good supporting effect.

本实用新型进一步设置为:所述卡槽的深度为15cm-30cm。The utility model is further configured as follows: the depth of the card slot is 15cm-30cm.

通过采用卡槽开设深度范围,能够保证卡槽在开设后能够有效的保证。By adopting the card slot opening depth range, it can be ensured that the card slot can be effectively secured after opening.

综上所述,本实用新型具有以下有益效果:通过采用三棱柱结构能够保证最稳定的支撑效果,三角支撑效果最稳固,通过采用工字钢能够保证其承重级别能够达到吨级而抗拉外环是防止在吊装时的外扩力对本三角架损坏,支撑内环能够保证工字钢在使用时有稳固的三角结构,通过设置吊钩能够有效的对手拉葫芦的固定。In summary, the utility model has the following beneficial effects: by adopting the triangular prism structure, the most stable supporting effect can be guaranteed, the triangular supporting effect is the most stable, by adopting the I-beam, the load-bearing level can be guaranteed to reach the ton level, and the tensile outer ring prevents the outward expansion force during lifting from damaging the tripod, and the supporting inner ring can ensure that the I-beam has a stable triangular structure when in use, and by setting the hook, the hand chain hoist can be effectively fixed.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

图1是本实用新型实施例中的立体图;FIG1 is a perspective view of an embodiment of the present utility model;

图2是本实用新型实施例中的俯视图;FIG2 is a top view of an embodiment of the utility model;

图3是本实用新型实施例中的安装示意图。FIG. 3 is a schematic diagram of installation in an embodiment of the utility model.

图中:1、抗拉外环;2、吊钩;3、工字钢;4、支撑内环;5、卡槽。In the figure: 1. tensile outer ring; 2. hook; 3. I-beam; 4. supporting inner ring; 5. slot.

具体实施方式DETAILED DESCRIPTION

为使本实用新型实施方式的目的、技术方案和优点更加清楚,下面将结合本实用新型实施方式中的附图,对本实用新型实施方式中的技术方案进行清楚、完整地描述,显然,所描述的实施方式是本实用新型一部分实施方式,而不是全部的实施方式。基于本实用新型中的实施方式,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施方式,都属于本实用新型保护的范围。因此,以下对在附图中提供的本实用新型的实施方式的详细描述并非旨在限制要求保护的本实用新型的范围,而是仅仅表示本实用新型的选定实施方式。In order to make the purpose, technical scheme and advantages of the embodiments of the utility model clearer, the technical scheme in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model. Therefore, the following detailed description of the embodiments of the utility model provided in the drawings is not intended to limit the scope of the utility model for which protection is claimed, but merely represents selected embodiments of the utility model.

在本实用新型的描述中,术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征。In the description of the present invention, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features.

以下结合附图1-3对本实用新型作进一步详细说明。The utility model is further described in detail below in conjunction with Figures 1-3.

实施例Example

在常规的环梁以及环梁的周边梁的吊装时,首先需要在钢管柱周边先支设环梁的底模和周边梁的侧模,在常规吊装的时候就需要将底模的一侧和侧模的一侧拆开,然后捆扎钢筋等待钢筋捆扎完成后再进行封模,这样传统的方式下来手续非常复杂、多项零星施工和重复施工。When hoisting a conventional ring beam and the surrounding beams of the ring beam, it is first necessary to set up the bottom formwork of the ring beam and the side formwork of the surrounding beam around the steel pipe column. During conventional hoisting, it is necessary to disassemble one side of the bottom formwork and one side of the side formwork, and then tie the steel bars and wait for the steel bars to be tied before sealing the formwork. This traditional method has very complicated procedures, multiple sporadic constructions and repeated construction.

随着新型结构体系不断发展成熟,钢管柱上环梁钢筋绑扎弊病日渐凸显,如何创新设计方案实现钢筋绑扎方式的突破,降低钢筋绑扎难度、简化施工工序、节约成本成为一个关键性的问题。As new structural systems continue to develop and mature, the drawbacks of steel ring beam reinforcement binding on steel pipe columns have become increasingly prominent. How to innovate design solutions to achieve breakthroughs in reinforcement binding methods, reduce the difficulty of reinforcement binding, simplify construction procedures, and save costs has become a key issue.

如图1、图2所示,一种快速起吊及沉环梁施工的三角架,包括吊架,吊架的整体结构呈三棱柱结构,三棱柱结构才能稳固的对吊装时做出稳定的支撑效果。As shown in FIG. 1 and FIG. 2 , a tripod for rapid lifting and sinking of ring beams includes a hanger. The overall structure of the hanger is a triangular prism structure. The triangular prism structure can provide a stable supporting effect during lifting.

吊架包括三根竖直排列成三棱柱结构的工字钢3,工字钢3的底部设置有卡槽5,通过卡槽5直接卡接到钢管柱上从而实现稳定的连接方式以保证吊装环梁以及周边梁的时候稳定的支撑。The hanger includes three I-beams 3 arranged vertically in a triangular prism structure. A slot 5 is provided at the bottom of the I-beam 3, which is directly connected to the steel pipe column through the slot 5 to achieve a stable connection method to ensure stable support when hoisting the ring beam and peripheral beams.

作为优选:为了保证卡槽5的卡接稳定性,卡槽5的深度为15cm-30cm,宽度为4cm-8cm,其中在本方案中卡槽5的深度最好是20cm、宽度最好是5cm。Preferably, in order to ensure the connection stability of the card slot 5, the depth of the card slot 5 is 15cm-30cm, and the width is 4cm-8cm. In this solution, the depth of the card slot 5 is preferably 20cm, and the width is preferably 5cm.

三棱柱结构的外侧棱部固定设置有抗拉外环1,所述外环的内侧部分与工字钢3固定连接。A tensile outer ring 1 is fixedly provided on the outer edge of the triangular prism structure, and the inner part of the outer ring is fixedly connected to the I-beam 3.

三棱柱结构的内侧棱部设置有支撑内环4,且支撑内环4呈三角形结构,三根工字钢3分别设置在支撑内环4的三角处形成三棱柱结构。The inner edge of the triangular prism structure is provided with a supporting inner ring 4, and the supporting inner ring 4 is a triangular structure. Three I-beams 3 are respectively arranged at the triangular positions of the supporting inner ring 4 to form a triangular prism structure.

吊架整体高约150cm,在吊架内至少设置有两个支撑内环4。The overall height of the hanger is about 150 cm, and at least two supporting inner rings 4 are arranged in the hanger.

通过上述设置后能够有效的解决传统工艺流程的繁琐复杂、以及工期长成本高的问题。The above settings can effectively solve the problems of cumbersome and complicated traditional process flow, long construction period and high cost.

作为优选:为了考虑到工地上最常见的为钢筋,可以在工地上将相同标号的钢筋作为支撑杆,将三根相同长短的支撑杆焊接成三角形结构从而组合成支撑内环4。As a preference, in order to take into account that steel bars are the most common on construction sites, steel bars of the same grade may be used as support rods on the construction site, and three support rods of the same length may be welded into a triangular structure to form a support inner ring 4 .

本方案中的工字钢3为工地上常见的工字钢3结构,将工字钢3分为竖直部和接触部,在竖直部的两个长边上均一体成型设置接触部并且接触部与竖直部相互垂直,竖直部的长边位于接触部的中部。The I-beam 3 in this scheme is a common I-beam 3 structure on construction sites, and the I-beam 3 is divided into a vertical portion and a contact portion. The contact portion is integrally formed on both long sides of the vertical portion and the contact portion is perpendicular to the vertical portion, and the long side of the vertical portion is located in the middle of the contact portion.

三棱柱结构的中轴线位于每根工字钢3的竖直部的延长面的共同相交线上。The central axis of the triangular prism structure is located on the common intersection line of the extended surfaces of the vertical portions of each I-beam 3 .

工字钢3远离三棱柱结构中轴线的接触部与抗拉外环1固定连接,工字钢3靠近三棱柱结构中轴线的接触部与支撑内环4的角部固定连接。The contact portion of the I-beam 3 away from the central axis of the triangular prism structure is fixedly connected to the tensile outer ring 1 , and the contact portion of the I-beam 3 close to the central axis of the triangular prism structure is fixedly connected to the corner of the supporting inner ring 4 .

为了更好的为手拉葫芦提供固定点,在三棱柱结构远离中轴线的接触部上均固定设置有吊钩2且吊钩2位于抗拉外环1靠近卡槽5的一侧。In order to better provide a fixing point for the hand chain hoist, a hook 2 is fixedly provided on the contact portion of the triangular prism structure away from the central axis, and the hook 2 is located on the side of the tensile outer ring 1 close to the slot 5.

作为优选:若环梁重量过大时,可以适当的增加工字钢3的数量,以及其余的拉结固定点。As a preference, if the weight of the ring beam is too heavy, the number of I-beams 3 and the remaining anchoring points can be appropriately increased.

工作原理:第一步、将环梁套住钢管柱放至楼面模板上,环梁下垫钢管,防止环梁掉入模板内;Working principle: Step 1: Put the ring beam around the steel pipe column and place it on the floor formwork, and pad the steel pipe under the ring beam to prevent the ring beam from falling into the formwork;

第二步、将三角架的卡槽5卡入同一根钢管柱上;Step 2: Insert the tripod's slot 5 into the same steel pipe column;

第三步、将三个手拉葫芦的一端分别挂在三角架的三个吊钩2上,另一端钩在环梁上;Step 3: Hang one end of the three hand chain hoists on the three hooks 2 of the tripod respectively, and hook the other end on the ring beam;

第四步、三个手拉葫芦均匀受力,平稳吊起环梁至合适位置,然后进行周边梁钢筋绑扎;Step 4: The three hand hoists are evenly loaded to steadily lift the ring beam to the appropriate position, and then tie the surrounding beam reinforcement;

第五步、梁钢筋绑扎完成之后,在外围且一侧的环梁按照先后顺序依次沉入模板中,下沉过程中需三个手拉葫芦同时均匀受力下沉。Step 5. After the beam reinforcement is tied, the ring beams on the outside and one side are sunk into the formwork in sequence. During the sinking process, three hand winches are required to evenly bear the force and sink at the same time.

以上所述仅为本实用新型的优选实施方式而已,并不用于限制本实用新型,对于本领域的技术人员来说,本实用新型可以有各种更改和变化。凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。The above description is only the preferred implementation of the utility model, and is not intended to limit the utility model. For those skilled in the art, the utility model can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims (6)

1.一种快速起吊及沉环梁施工的三角架,其特征是:吊架,吊架包括,吊架的中部包括三根竖直排列成三棱柱结构的工字钢(3);1. A tripod for rapid lifting and sinking of ring beams, characterized by: a hanger, the hanger comprising, in the middle of the hanger, three I-beams (3) vertically arranged in a triangular prism structure; 所述三棱柱结构顶部外侧壁上设置有抗拉外环(1)且所述抗拉外环(1)与每根所述工字钢(3)连接;A tensile outer ring (1) is provided on the outer side wall of the top of the triangular prism structure, and the tensile outer ring (1) is connected to each of the I-beams (3); 每根所述工字钢(3)远离三棱柱结构中轴线的一侧均设置有吊钩(2);A hook (2) is provided on one side of each I-beam (3) away from the central axis of the triangular prism structure; 每根所述工字钢(3)靠近三棱柱结构中轴线的一侧设置与每根工字钢(3)连接的支撑内环(4)。A supporting inner ring (4) connected to each I-beam (3) is provided on one side of each I-beam (3) close to the central axis of the triangular prism structure. 2.根据权利要求1所述的一种快速起吊及沉环梁施工的三角架,其特征是:所述工字钢(3)分为竖直部以及一体成型于竖直部长边的两个接触部,若干所述工字钢(3)的竖直部延长面相交处为三棱柱结构的中轴线。2. According to the tripod for rapid lifting and sinking of ring beams construction described in claim 1, it is characterized in that: the I-beam (3) is divided into a vertical part and two contact parts integrally formed on the vertical long side, and the intersection of the extended surfaces of the vertical parts of several of the I-beams (3) is the central axis of the triangular prism structure. 3.根据权利要求2所述的一种快速起吊及沉环梁施工的三角架,其特征是:所述工字钢(3)远离抗拉外环(1)的竖直部上开设有卡槽(5)。3. A tripod for rapid lifting and sinking of ring beams according to claim 2, characterized in that a slot (5) is provided on the vertical portion of the I-beam (3) away from the tensile outer ring (1). 4.根据权利要求1所述的一种快速起吊及沉环梁施工的三角架,其特征是:所述三棱柱结构内至少存在两个间隔设置的支撑内环(4)。4. A tripod for rapid lifting and sinking of ring beams according to claim 1, characterized in that: there are at least two spaced-apart supporting inner rings (4) in the triangular prism structure. 5.根据权利要求1所述的一种快速起吊及沉环梁施工的三角架,其特征是:所述支撑内环(4)为三角形结构。5. A tripod for rapid lifting and sinking of ring beams according to claim 1, characterized in that the supporting inner ring (4) is a triangular structure. 6.根据权利要求3所述的一种快速起吊及沉环梁施工的三角架,其特征是:所述卡槽(5)的深度为15cm-30cm。6. A tripod for rapid lifting and sinking of ring beams according to claim 3, characterized in that the depth of the slot (5) is 15cm-30cm.
CN202322823294.5U 2023-10-20 2023-10-20 A tripod for rapid lifting and sinking of ring beams Active CN221662413U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322823294.5U CN221662413U (en) 2023-10-20 2023-10-20 A tripod for rapid lifting and sinking of ring beams

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322823294.5U CN221662413U (en) 2023-10-20 2023-10-20 A tripod for rapid lifting and sinking of ring beams

Publications (1)

Publication Number Publication Date
CN221662413U true CN221662413U (en) 2024-09-06

Family

ID=92577574

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322823294.5U Active CN221662413U (en) 2023-10-20 2023-10-20 A tripod for rapid lifting and sinking of ring beams

Country Status (1)

Country Link
CN (1) CN221662413U (en)

Similar Documents

Publication Publication Date Title
CN106276577B (en) A kind of suspension bracket and operating method of framework isolated footing
CN205932941U (en) A device for handling of precast box girder template
CN109081247A (en) A kind of hanging method of vestibule large-span steel girder
WO2023173676A1 (en) Space truss support platform, system and method for super-deep slurry wall
CN221662413U (en) A tripod for rapid lifting and sinking of ring beams
CN203497959U (en) Support structure without inclined rod for tower crane
CN216475048U (en) Novel steel reinforcement cage hanging system
CN218264865U (en) A triangular hanging basket support structure
CN218714838U (en) Self-lifting heavy-load construction platform
CN212405177U (en) Suspended enclosing purlin supporting system
CN217458425U (en) Lifting appliance for lifting bridge deck concrete baffle
CN215167862U (en) A non-counterweight hanging basket for parapet
CN116281560A (en) Hanging beam steel frame for T beam hoisting, hanging beam system and T beam prefabrication and hoisting method
CN203320922U (en) Supporting device for forming of elevator shaft template
CN223175658U (en) A lifting device for concrete retaining wall formwork
CN210064931U (en) Prefabricated T roof beam template hoist device
CN219045209U (en) Concrete embedded part for civil engineering
CN219259294U (en) I-steel or H-steel lifting appliance
CN223307959U (en) A floor slab strength detection device for engineering construction
CN213173755U (en) Beam column type support steel-pipe pile pothook
CN221796748U (en) Portable bored pile steel reinforcement cage hoist device
CN221720275U (en) A cap beam lifting auxiliary device
CN218292018U (en) Unsettled tower crane foundation base supports reinforced structure
CN215107150U (en) Stiff beam pouring support structure
CN221523557U (en) Steel reinforcement cage hoist and mount and fixing system