CN221546860U - Pile drawing device for building engineering concrete pipe piles - Google Patents
Pile drawing device for building engineering concrete pipe piles Download PDFInfo
- Publication number
- CN221546860U CN221546860U CN202420186423.6U CN202420186423U CN221546860U CN 221546860 U CN221546860 U CN 221546860U CN 202420186423 U CN202420186423 U CN 202420186423U CN 221546860 U CN221546860 U CN 221546860U
- Authority
- CN
- China
- Prior art keywords
- fixedly connected
- shell
- concrete pipe
- supporting table
- movable
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000004567 concrete Substances 0.000 title claims abstract description 21
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 20
- 238000005553 drilling Methods 0.000 claims description 13
- 238000010276 construction Methods 0.000 claims description 9
- 238000004146 energy storage Methods 0.000 claims description 8
- 230000000149 penetrating effect Effects 0.000 claims 2
- 239000007788 liquid Substances 0.000 description 5
- 238000000034 method Methods 0.000 description 5
- 230000000694 effects Effects 0.000 description 4
- 239000007921 spray Substances 0.000 description 4
- 239000002689 soil Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 239000012535 impurity Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 238000005507 spraying Methods 0.000 description 1
Landscapes
- Earth Drilling (AREA)
Abstract
The utility model discloses a pile drawing device for a concrete pipe pile of a building engineering, which belongs to the technical field of building engineering and comprises a supporting table, a lifting assembly and a movable table, wherein the lifting assembly is fixedly connected to the upper surface of the supporting table, the movable table is fixedly connected to the side surface of the lifting assembly, a drill rod is arranged at the lower end of the movable table, a through hole is formed in the surface of the supporting table, the position of the drill rod corresponds to the position of the through hole, and a water storage tank is fixedly connected to the upper surface of the supporting table.
Description
Technical Field
The utility model relates to the technical field of constructional engineering, in particular to a pile drawing device for a concrete pipe pile in constructional engineering.
Background
Currently, in the field of construction engineering, a pile-drawing process is generally required for concrete pipes. Pile driving refers to the process of digging the space position of the pile foundation under the ground, where reinforced concrete needs to be poured, the pile foundation with the diameter of more than one meter is generally manually driven, the pile foundation with the diameter of less than one meter is mechanically driven, and the pile driving device is needed for mechanical pile driving.
The existing pile driving device is characterized in that after the pile driving device works, a large amount of soil residues are adhered to the surface of a drill rod, the existing pile driving device generally does not use the drill rod, the soil residues on the surface of the drill rod cannot be cleaned conveniently, and the following device is provided for solving the problems.
Disclosure of utility model
Technical problem to be solved
Aiming at the defects of the prior art, the utility model aims to provide a pile-drawing device for a concrete pipe pile in construction engineering, which has the characteristic of cleaning the surface of a drill rod.
Technical proposal
In order to achieve the above purpose, the utility model provides a pile drawing device for a concrete pipe pile in construction engineering, which comprises a supporting table, a lifting assembly and a movable table, wherein the lifting assembly is fixedly connected to the upper surface of the supporting table, the movable table is fixedly connected to the side surface of the lifting assembly, a drill rod is arranged at the lower end of the movable table, through holes are formed in the surface of the supporting table, the positions of the drill rod correspond to the positions of the through holes, a water storage tank is fixedly connected to the upper surface of the supporting table, a first liquid guide pipe is fixedly connected to the side surface of the water storage tank, a water suction pump is fixedly connected to the upper surface of the supporting table, the other end of the first liquid guide pipe is fixedly connected to the side surface of the water suction pump, a second liquid guide pipe is fixedly connected to the side surface of the water suction pump, a mud baffle is fixedly connected to the upper end of the through holes, a splitter plate is fixedly connected to the inner wall of the mud baffle, high-pressure spray heads are fixedly connected to the side surfaces of the splitter plate, and the high-pressure spray heads are multiple and are symmetrically arranged on the inner wall of the splitter plate.
When the construction engineering concrete pipe pile is drawn out and put, through setting up storage water tank, suction pump and high pressure shower nozzle, when people need clear up the drilling rod surface, people at first operate through control switch control suction pump, simultaneously under the cooperation of first catheter and second catheter, can transmit the clear water to the flow distribution plate to finally spout through high pressure shower nozzle, can clear up the debris of drilling rod surface adhesion, improved the practicality of device.
Further, the movable table upper surface fixedly connected with support frame, the inside fixedly connected with second motor of support frame, the output shaft other end fixedly connected with second pivot of second motor, the second pivot wears to be equipped with on the movable table surface, the second pivot wears to establish in the second bearing, the lower extreme fixed connection of second pivot is in the drilling rod upper end.
Further, the lifting assembly comprises a shell, the inside fixedly connected with of shell is at the brace table upper surface, the inside fixedly connected with first motor of shell, the output shaft upper end fixedly connected with screw thread post of first motor, the first pivot of the other end fixedly connected with of screw thread post, shell inner wall fixedly connected with first bearing, establish in first bearing is worn to the upper end of first pivot, the surface screw thread of screw thread post is connected with screw cap, screw cap side fixedly connected with connecting rod, the movable groove has been seted up on the shell surface, the connecting rod wears to establish in the movable groove, the other end fixedly connected with of connecting rod is in the movable table side.
Further, the shell side fixedly connected with slide bar, slide bar surface sliding connection has the sliding sleeve, sliding sleeve fixed connection is in the movable table side, slide bar and sliding sleeve respectively have two sets of to the symmetry sets up in the shell side.
Further, the lower surface of the supporting table is fixedly connected with a wheel set, the side face of the wheel set is provided with brake pads, and the number of the wheel sets is four, and the wheel sets are arranged at the lower end of the supporting table in a rectangular mode.
Further, an energy storage bin is arranged in the supporting table, a storage battery is fixedly connected in the energy storage bin, a control switch is fixedly connected to the front surface of the supporting table, a pushing handle is fixedly connected to the upper surface of the supporting table, and a control switch is fixedly connected to the front surface of the supporting table.
Advantageous effects
In summary, the utility model has the following beneficial effects:
1. According to the pile-drawing device for the concrete pipe pile of the building engineering, when people need to clean the surface of a drill rod, the water storage tank, the water suction pump and the high-pressure spray head are arranged, the water suction pump is controlled to operate by the control switch, clear water is transferred to the flow distribution disc under the cooperation of the first liquid guide pipe and the second liquid guide pipe, and finally impurities adhered to the surface of the drill rod are cleaned by spraying through the high-pressure spray head, so that the practicability of the device is improved;
2. According to the pile drawing device for the building engineering concrete pipe pile, by arranging the lifting assembly and the drill rod, when people need to draw piles at the designated positions, the people only need to control the second motor to operate through the control switch so as to drive the drill rod to rotate, and meanwhile, the first motor is controlled to operate through the control switch so as to drive the threaded column to rotate, and under the cooperation of the threaded column and the threaded cap, the movable table carrying the drill rod is driven to move, so that the purpose of drawing piles at the designated positions is achieved;
3. This a pile device is drawn to building engineering concrete pipe pile through setting up the fender, under the effect of fender, avoids the device to draw the produced earth of in-process of stake everywhere to the assigned position and splashes, has improved the practicality of device.
Drawings
In order to more clearly illustrate the embodiments of the present utility model or the technical solutions in the prior art, the drawings required for the description of the embodiments or the prior art will be briefly described, and it is apparent that the drawings in the following description are only one embodiment of the present utility model, and other drawings can be obtained according to the drawings without inventive effort for a person skilled in the art.
FIG. 1 is a schematic elevational view in cross-section of the present utility model;
FIG. 2 is a schematic diagram of the front view of the present utility model;
fig. 3 is a schematic cross-sectional view of a lifting assembly according to the present utility model.
The marks in the drawings are:
1. A support table; 2. a lifting assembly; 201. a housing; 202. a first motor; 203. a threaded column; 204. a first rotating shaft; 205. a first bearing; 206. a threaded cap; 207. a connecting rod; 208. a movable groove; 209. a slide bar; 210. a sliding sleeve; 3. a movable table; 4. a support frame; 5. a second motor; 6. a second rotating shaft; 7. a second bearing; 8. a drill rod; 9. a through hole; 10. a water storage tank; 11. a first catheter; 12. a water pump; 13. a second catheter; 14. a mud guard; 15. a diverter tray; 16. a high pressure nozzle; 17. a pushing handle; 18. an energy storage bin; 19. a storage battery; 20. a wheel set; 21. a brake pad; 22. and controlling the switch.
Detailed Description
In order to make the technical means, the creation characteristics, the achievement of the purpose and the effect of the present utility model easy to understand, the technical solutions in the embodiments of the present utility model are clearly and completely described below to further illustrate the present utility model, and it is obvious that the described embodiments are only some embodiments of the present utility model, not all versions.
Examples:
the utility model is described in further detail below with reference to fig. 1-3.
Referring to fig. 1-3, the present utility model provides a technical solution: the utility model provides a pile device is drawn to building engineering concrete pipe pile, including supporting bench 1, lifting unit 2 and movable platform 3, lifting unit 2 fixed connection is at supporting bench 1 upper surface, movable platform 3 fixed connection is in lifting unit 2 side, the movable platform 3 lower extreme is provided with drilling rod 8, through-hole 9 has been seted up on supporting bench 1 surface, the position of drilling rod 8 corresponds with the position of through-hole 9, supporting bench 1 upper surface fixedly connected with storage water tank 10, storage water tank 10 side fixedly connected with first catheter 11, supporting bench 1 upper surface fixedly connected with suction pump 12, the other end fixedly connected with of first catheter 11 is in suction pump 12's side, suction pump 12's side fixedly connected with second catheter 13;
Through adopting above-mentioned technical scheme, this pile device is drawn to building engineering concrete pipe pile through setting up storage water tank 10, suction pump 12 and high pressure shower nozzle 16, when people need clear up drilling rod 8 surface, people at first operate through control switch 22 control suction pump 12, simultaneously under the cooperation of first catheter 11 and second catheter 13, can transmit the clear water to flow distribution plate 15 to finally spout through high pressure shower nozzle 16, can clear up drilling rod 8 surface adhesion's debris, improved the practicality of the device.
The upper end fixedly connected with fender 14 of through-hole 9, fender 14 inner wall fixedly connected with flow distribution plate 15, the side fixedly connected with high-pressure shower nozzle 16 of flow distribution plate 15, high-pressure shower nozzle 16 is a plurality of to the symmetry sets up at flow distribution plate 15 inner wall.
Through adopting above-mentioned technical scheme, this pile device is drawn to building engineering concrete pipe pile through setting up fender 14, under the effect of fender 14, avoids the device to draw the produced earth of in-process of stake to the assigned position and splashes everywhere, has improved the practicality of device.
Specifically, the upper surface fixedly connected with support frame 4 of movable table 3, the inside fixedly connected with second motor 5 of support frame 4, the output shaft other end fixedly connected with second pivot 6 of second motor 5, movable table 3 surface wears to be equipped with second bearing 7, and second pivot 6 wears to establish in second bearing 7, and the lower extreme fixed connection of second pivot 6 is in drilling rod 8 upper end.
Specifically, lifting assembly 2 includes shell 201, the inside fixed connection of shell 201 is at brace table 1 upper surface, the inside fixedly connected with first motor 202 of shell 201, the output shaft upper end fixedly connected with screw thread post 203 of first motor 202, the first pivot 204 of the other end fixedly connected with of screw thread post 203, shell 201 inner wall fixedly connected with first bearing 205, the upper end of first pivot 204 wears to establish in first bearing 205, the surface screw thread of screw thread post 203 is connected with screw cap 206, screw cap 206 side fixedly connected with connecting rod 207, movable groove 208 has been seted up on the shell 201 surface, connecting rod 207 wears to establish in movable groove 208, the other end fixedly connected with of connecting rod 207 is in the 3 sides of movable table.
Through adopting above-mentioned technical scheme, this building engineering concrete tubular pile draws a device, through setting up lifting unit 2 and drilling rod 8, when people need draw the stake to the assigned position, people only need to operate through control switch 22 control second motor 5 to drive drilling rod 8 and rotate, simultaneously through control switch 22 control first motor 202 operation, thereby drive screw thread post 203 and rotate, under the cooperation of screw thread post 203 and screw cap 206, thereby drive the movable table 3 that carries drilling rod 8 and remove, thereby reach the purpose of drawing the stake to the assigned position.
Specifically, the side surface of the casing 201 is fixedly connected with a sliding rod 209, the surface of the sliding rod 209 is slidably connected with a sliding sleeve 210, the sliding sleeve 210 is fixedly connected to the side surface of the movable table 3, and two groups of sliding rods 209 and 210 are respectively and symmetrically arranged on the side surface of the casing 201.
Specifically, the lower surface of the supporting table 1 is fixedly connected with a wheel set 20, the side surface of the wheel set 20 is provided with brake pads 21, and the wheel sets 20 are four in total and are arranged at the lower end of the supporting table 1 in a rectangular shape.
Specifically, the energy storage bin 18 is arranged in the supporting table 1, the storage battery 19 is fixedly connected in the energy storage bin 18, the control switch 22 is fixedly connected to the front surface of the supporting table 1, the pushing handle 17 is fixedly connected to the upper surface of the supporting table 1, and the control switch 22 is fixedly connected to the front surface of the supporting table 1.
The working principle of the utility model is as follows: when the device is used, people only need to push the device, under the cooperation of the wheel set 20, people move the device to a position suitable for the device, when people need to fix the device, people only need to adjust the brake block 21 arranged on the side surface of the wheel set 20 to a braking state, so that the device can keep a stable working state in the normal operation process, when people need to pick up piles at a designated position, people only need to control the second motor 5 to operate through the control switch 22, so as to drive the drill rod 8 to rotate, and meanwhile, the control switch 22 controls the first motor 202 to operate, so as to drive the threaded column 203 to rotate, under the cooperation of the threaded column 203 and the threaded cap 206, so as to drive the movable table 3 carrying the drill rod 8 to move, thereby achieving the aim of picking up piles at the designated position.
The present embodiment is only for explanation of the present utility model and is not to be construed as limiting the present utility model, and modifications to the present embodiment, which may not creatively contribute to the present utility model as required by those skilled in the art after reading the present specification, are all protected by patent laws within the scope of claims of the present utility model.
Claims (6)
1. The utility model provides a pile device is drawn to building engineering concrete tubular pile, includes brace table (1), lifting unit (2) and movable table (3), its characterized in that: lifting unit (2) fixed connection is in brace table (1) upper surface, movable table (3) fixed connection is in lifting unit (2) side, movable table (3) lower extreme is provided with drilling rod (8), through-hole (9) have been seted up on brace table (1) surface, the position of drilling rod (8) is corresponding with the position of through-hole (9), surface fixedly connected with storage water tank (10) on brace table (1), first catheter (11) of storage water tank (10) side fixedly connected with, brace table (1) upper surface fixedly connected with suction pump (12), the other end fixed connection of first catheter (11) is in the side of suction pump (12), the side fixedly connected with second catheter (13) of suction pump (12), through-hole (9) upper end fixedly connected with fender (14), the side fixedly connected with high-pressure shower nozzle (16) of baffle (14) inner wall fixedly connected with flow distribution disc (15), high-pressure shower nozzle (16) have to set up at a plurality of inner walls (15) altogether.
2. A construction concrete pipe pile driving device according to claim 1, characterized in that: the movable table (3) is fixedly connected with a supporting frame (4) on the upper surface, a second motor (5) is fixedly connected inside the supporting frame (4), a second rotating shaft (6) is fixedly connected to the other end of an output shaft of the second motor (5), a second bearing (7) is arranged on the surface of the movable table (3) in a penetrating mode, the second rotating shaft (6) is arranged in the second bearing (7) in a penetrating mode, and the lower end of the second rotating shaft (6) is fixedly connected to the upper end of a drill rod (8).
3. A construction concrete pipe pile driving device according to claim 1, characterized in that: lifting component (2) are including shell (201), the inside fixed connection of shell (201) is at brace table (1) upper surface, the inside fixedly connected with first motor (202) of shell (201), output shaft upper end fixedly connected with screw thread post (203) of first motor (202), the other end fixedly connected with first pivot (204) of screw thread post (203), shell (201) inner wall fixedly connected with first bearing (205), establish in first bearing (205) the upper end of first pivot (204) is worn, the surface threaded connection of screw thread post (203) has screw cap (206), screw cap (206) side fixedly connected with connecting rod (207), movable groove (208) have been seted up on shell (201) surface, connecting rod (207) wear to establish in movable groove (208), the other end fixedly connected with of connecting rod (207) is in movable table (3) side.
4. A construction concrete pipe pile driving device according to claim 3, wherein: the sliding rod (209) is fixedly connected to the side face of the shell (201), the sliding sleeve (210) is connected to the surface of the sliding rod (209) in a sliding mode, the sliding sleeve (210) is fixedly connected to the side face of the movable table (3), and the sliding rod (209) and the sliding sleeve (210) are respectively provided with two groups and symmetrically arranged on the side face of the shell (201).
5. A construction concrete pipe pile driving device according to claim 1, characterized in that: the wheel set (20) is fixedly connected to the lower surface of the supporting table (1), the side face of the wheel set (20) is provided with brake pads (21), and the number of the wheel sets (20) is four, and the wheel sets are arranged at the lower end of the supporting table (1) in a rectangular mode.
6. A construction concrete pipe pile driving device according to claim 1, characterized in that: the novel energy storage device is characterized in that an energy storage bin (18) is formed in the supporting table (1), a storage battery (19) is fixedly connected to the inside of the energy storage bin (18), a control switch (22) is fixedly connected to the front surface of the supporting table (1), a pushing handle (17) is fixedly connected to the upper surface of the supporting table (1), and a control switch (22) is fixedly connected to the front surface of the supporting table (1).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202420186423.6U CN221546860U (en) | 2024-01-25 | 2024-01-25 | Pile drawing device for building engineering concrete pipe piles |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202420186423.6U CN221546860U (en) | 2024-01-25 | 2024-01-25 | Pile drawing device for building engineering concrete pipe piles |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN221546860U true CN221546860U (en) | 2024-08-16 |
Family
ID=92258481
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202420186423.6U Active CN221546860U (en) | 2024-01-25 | 2024-01-25 | Pile drawing device for building engineering concrete pipe piles |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN221546860U (en) |
-
2024
- 2024-01-25 CN CN202420186423.6U patent/CN221546860U/en active Active
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN111962658A (en) | Intelligent municipal road sewer decontamination dredging device and method | |
| CN221546860U (en) | Pile drawing device for building engineering concrete pipe piles | |
| CN213805561U (en) | Hydraulic engineering desilting device | |
| CN222499941U (en) | Broken construction mechanism of concrete | |
| CN216076993U (en) | Pile driver convenient for cleaning silt for building construction | |
| CN214627950U (en) | Auxiliary device based on sepiolite soil improvement | |
| CN209875050U (en) | Novel street lamp installation construction tool | |
| CN209636891U (en) | A kind of dredging device for water conservancy projects | |
| CN115198824A (en) | Prevent big pipe diameter desilting robot that topples | |
| CN220747059U (en) | Hydraulic engineering desilting equipment | |
| CN220225502U (en) | Ditcher for water supply and drainage pipeline engineering | |
| CN208088489U (en) | A kind of underground piping silt cleaning device | |
| CN221311621U (en) | Construction tool cleaning equipment who facilitates use | |
| CN215051849U (en) | Road construction is with leveling device | |
| CN208105350U (en) | Follow-on silt removing dredging device | |
| CN219059887U (en) | A cleaning device for water conservancy and hydropower engineering dams | |
| CN220918554U (en) | Building construction precipitation structure | |
| CN221626975U (en) | Slope leveling device for river channel embankment engineering construction | |
| CN216197855U (en) | Multi-functional water conservancy construction equipment convenient to maintain | |
| CN220528883U (en) | A drainage and irrigation mechanical device | |
| CN221094806U (en) | Road construction joint cutting device | |
| CN216405588U (en) | A comprehensive cycle control system for garden vegetation irrigation and garden water integration | |
| CN220394487U (en) | Sampling equipment for foundation detection | |
| CN220953585U (en) | Desilting device with sludge collection function | |
| CN221524774U (en) | A concrete pipe pile digging device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |