CN221372596U - Curtain wall assembling structure - Google Patents

Curtain wall assembling structure Download PDF

Info

Publication number
CN221372596U
CN221372596U CN202323223391.7U CN202323223391U CN221372596U CN 221372596 U CN221372596 U CN 221372596U CN 202323223391 U CN202323223391 U CN 202323223391U CN 221372596 U CN221372596 U CN 221372596U
Authority
CN
China
Prior art keywords
connecting piece
curtain wall
clamping
side wall
along
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202323223391.7U
Other languages
Chinese (zh)
Inventor
居官玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Daju Construction Engineering Group Co ltd
Original Assignee
Shanghai Daju Construction Engineering Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Daju Construction Engineering Group Co ltd filed Critical Shanghai Daju Construction Engineering Group Co ltd
Priority to CN202323223391.7U priority Critical patent/CN221372596U/en
Application granted granted Critical
Publication of CN221372596U publication Critical patent/CN221372596U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

The utility model discloses a curtain wall assembling structure, which comprises: the elastic first connecting piece is provided with a clamping groove which is provided with an opening, and the clamping groove is gradually reduced along a first direction; the second connecting piece is used for installing curtain wall boards, clamping bulges are convexly arranged along the second direction of the second connecting piece, and the clamping bulges are clamped with the opening; wherein the first direction and the second direction are perpendicular to each other. The utility model solves the problems that the prior curtain wall in the background technology is usually connected with each other through a plurality of fasteners such as bolts and the like when being installed, the assembly, the disassembly and the combination are very inconvenient, the on-site assembly construction efficiency of the curtain wall is lower, and meanwhile, when a single curtain wall plate is damaged, the single curtain wall plate cannot be quickly disassembled and replaced.

Description

Curtain wall assembling structure
Technical Field
The utility model relates to a curtain wall assembling structure, and belongs to the technical field of curtain wall installation.
Background
The curtain wall is a shielding wall surface, can be used for a solid wall surface, can also be used for supporting and building a wall, forms a combined wall body like a curtain, is mainly used for landscape decoration, does not bear load, and is mainly installed through a steel frame. However, the curtain wall similar to the enclosure wall is usually connected with each other through a plurality of fasteners such as bolts during installation, so that the assembly, disassembly and assembly are inconvenient, the on-site assembly construction efficiency of the curtain wall is low, and meanwhile, when a single curtain wall plate is damaged, the single curtain wall plate cannot be rapidly disassembled and replaced.
Disclosure of utility model
The utility model aims to provide a curtain wall assembling structure, which solves the problems that the existing curtain wall in the background art is usually connected with each other through a plurality of fasteners such as bolts and the like, the assembling, the disassembling and the assembling are inconvenient, the site assembling and the construction efficiency of a curtain wall plate are low, and meanwhile, when a single curtain wall plate is damaged, the single curtain wall plate cannot be quickly disassembled and replaced.
In order to achieve the above purpose, the present utility model provides the following technical solutions:
Curtain wall assembly structure includes:
The elastic first connecting piece is provided with a clamping groove which is provided with an opening, and the clamping groove is gradually reduced along a first direction;
The second connecting piece is used for installing curtain wall boards, clamping bulges are convexly arranged along the second direction of the second connecting piece, and the clamping bulges are clamped with the opening;
wherein the first direction and the second direction are perpendicular to each other.
As a preferred example, further comprising:
The third connecting piece is clamped in the clamping groove, the side wall of the third connecting piece along the second direction is abutted against the second connecting piece, so that the second connecting piece is clamped together with the opening, and the clamping protrusion is arranged on one side, away from the third connecting piece, of the second connecting piece.
As a preferred example, the third connector includes:
The first side wall and the second side wall are respectively fixed at two ends of the connecting plate along the second direction;
The second connecting piece is abutted with the first side wall;
Or the second connecting piece is abutted with the second side wall.
As a preferable example, the number of the second connecting pieces is two, and two of the second connecting pieces are symmetrically arranged with respect to the third connecting piece;
One of the two second connecting pieces is abutted with the first side wall, and the other of the two second connecting pieces is abutted with the second side wall.
As a preferred example, the third connector further includes a first clamping plate and a second clamping plate;
The first clamping plate is connected to one side of the first side wall, which is away from the second side wall, and is arranged at an angle with the first clamping plate, and the first clamping plate is clamped with the inner wall of the clamping groove;
the second clamping plate is connected to one side of the second side wall, which is away from the first side wall, and is arranged at an angle with the second clamping plate, and the second clamping plate is clamped with the inner wall of the clamping groove.
As a preferred example, further comprising:
And one end of the fastener along the first direction is abutted with the first connection, the other end of the fastener along the first direction is abutted with the second connection piece, and the fastener is used for limiting the movement of the second connection piece along the first direction relative to the second connection piece.
As a preferable example, the opening is convexly provided with an elastic plate along the second direction, and one end of the fastener, which is far away from the second connecting piece, is abutted with the elastic plate.
As a preferable example, the number of the clamping grooves is two, and the two clamping grooves are symmetrically arranged at two ends of the first connecting piece along the first direction.
As a preferred example, a buffer pad is disposed between the second connectors respectively engaged with the two clamping grooves along the first direction.
As a preferred example, the cushion pad is detachably connected.
The beneficial effects of the utility model are as follows:
When the curtain wall plate assembly device is used, the curtain wall plate is fixedly connected to the second connecting piece before leaving a factory, the second connecting piece, the first connecting piece and the third connecting piece which are assembled with the curtain wall plate are transported to a construction site, the second connecting piece is inserted into the clamping groove through one end of the clamping groove of the first connecting piece, the third connecting piece is inserted from one end of the clamping groove and penetrates through the space between the two second connecting pieces, and then a fastening piece is inserted between the elastic plate of the first connecting piece and the second connecting piece, so that the curtain wall plate assembly device is assembled. When the curtain wall assembly structure needs to be disassembled, the fastener, the third connecting piece and the like can be sequentially pulled out from one end of the curtain wall assembly structure. Finally, the beneficial effects that the construction efficiency is improved when workers install curtain wall boards on site, and meanwhile, when a single curtain wall board is damaged, the single curtain wall board can be quickly detached and replaced are achieved.
Drawings
FIG. 1 is a schematic perspective view of the present utility model;
FIG. 2 is a schematic perspective view of a first connector according to the present utility model;
FIG. 3 is a schematic perspective view of a second connector according to the present utility model;
FIG. 4 is a schematic perspective view of a third connector according to the present utility model;
FIG. 5 is a schematic perspective view of a cushion according to the present utility model;
fig. 6 is an end elevational schematic of the present utility model.
In the figure: curtain wall panel 1, first connector 2, draw-in groove 201, elastic board 202, opening 203, second connector 3, joint protruding 301, spread-out groove 302, third connector 4, first lateral wall 401, connecting plate 402, second lateral wall 403, first joint board 404, second joint board 405, fastener 5, blotter 6.
Detailed Description
The utility model will be further described with reference to the following detailed drawings, in order to make the technical means, the creation characteristics, the achievement of the purpose and the effect of the utility model easy to understand.
In the present utility model, unless explicitly specified and limited otherwise, the terms "mounted," "connected," "secured," and the like are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally formed; can be directly connected or indirectly connected through an intermediate medium, and can be communicated with the inside of two elements or the interaction relationship of the two elements. The specific meaning of the above terms in the present utility model can be understood by those of ordinary skill in the art according to the specific circumstances.
In the present utility model, unless expressly stated or limited otherwise, a first feature "above" or "below" a second feature may include both the first and second features being in direct contact, as well as the first and second features not being in direct contact but being in contact with each other through additional features therebetween. Moreover, a first feature being "above," "over" and "on" a second feature includes the first feature being directly above and obliquely above the second feature, or simply indicating that the first feature is higher in level than the second feature. The first feature being "under", "below" and "beneath" the second feature includes the first feature being directly under and obliquely below the second feature, or simply means that the first feature is less level than the second feature.
The following disclosure provides many different embodiments, or examples, for implementing different structures of embodiments of the utility model. In order to simplify the disclosure of embodiments of the present utility model, components and arrangements of specific examples are described below. They are, of course, merely examples and are not intended to limit the utility model. Furthermore, embodiments of the present utility model may repeat reference numerals and/or letters in the various examples, which are for the purpose of brevity and clarity, and do not in itself indicate a relationship between the various embodiments and/or arrangements discussed. In addition, embodiments of the present utility model provide examples of various specific processes and materials, but one of ordinary skill in the art will recognize the application of other processes and/or the use of other materials.
Referring to fig. 1-6, the present application provides a curtain wall assembling structure, which includes a first connecting member 2 and a second connecting member 3, wherein the first connecting member 2 has elasticity, a clamping groove 201 is provided on the first connecting member 2, the clamping groove 201 has an opening 203, and the clamping groove 201 is gradually reduced along a first direction. The second connecting piece 3 is used for installing the curtain wall board 1, the second connecting piece 3 is convexly provided with a clamping protrusion 301 along the second direction, and the clamping protrusion 301 is clamped with the opening 203. Wherein the first direction and the second direction are perpendicular to each other.
It should be noted that the first connecting member 2 may be made of an elastic material so that the first connecting member 2 can be elastically deformed, and preferably, the first connecting member 2 is made of 301 stainless steel elastic metal. The bottom wall of the clamping groove 201 is spaced from the opening 203 along the first direction, and the clamping groove 201 is gradually reduced along the direction of the bottom wall of the clamping groove 201 pointing to the opening 203 of the clamping groove 201, i.e. the cross section of the clamping groove 201 is dovetail-shaped.
For convenience of explanation, in the present application, the first direction is the vertical direction in fig. 6, and the second direction is the horizontal direction in fig. 6.
Because the open 203 can generate elastic deformation, when the clamping protrusion 301 on the second connecting piece 3 is clamped with the open 203, the first connecting piece 2 generates elastic deformation, so that the first connecting piece 2 applies an elastic force to the second connecting piece 3 in the second direction, the clamping protrusion 301 and the open 203 are clamped, and the second connecting piece 3 is prevented from falling from the clamping groove 201.
In order to further improve the stability of the engagement between the second connector 3 and the clamping groove 201, in another embodiment of the present application, the curtain wall assembly structure further includes a third connector 4. The specific third connecting piece is clamped in the clamping groove 201, and the side wall of the third connecting piece 4 along the second direction is abutted against the second connecting piece 3, so that the third connecting piece 4 and the opening 203 jointly clamp the second connecting piece 3, wherein the clamping protrusion 301 is disposed on one side of the second connecting piece 3 away from the third connecting piece 4.
Specifically, in this embodiment, referring to fig. 1 and 4, the third connecting member 4 includes a first side wall 401, a connecting plate 402, and a second side wall 403, where the first side wall 401 and the second side wall 403 are respectively fixed to two ends of the connecting plate 402 along the second direction.
When the third connector 4 is engaged in the slot 201, the first sidewall 401 is located on the right side of the second sidewall 403.
In one embodiment of the present application, when the number of the second connecting pieces 3 is one, one side of the second connecting piece 3 along the second direction is abutted against the first side wall 401, and the clamping protrusion 301 on the second connection is clamped with the right side inner wall of the opening 203; or one side of the second connecting piece 3 along the second direction is abutted against the second side wall 403, and the clamping protrusion 301 on the second connection is clamped with the left inner wall of the opening 203.
Through the technical scheme of the third connecting piece 4 joint in the groove after the second connecting piece 3 and the draw-in groove 201 joint, compare with the technical scheme of the direct joint of second connecting piece 3 in the draw-in groove 201, the third connecting piece 4 can increase the uncovered 203 of draw-in groove 201 in the second direction size to make first connecting piece 2 produce bigger elastic deformation in its elastic deformation scope, and then improve the elasticity that first connecting piece 2 applyed second connecting piece 3 in the second direction, thereby further improve the reliability of the joint at the protruding 301 of joint and uncovered 203 position.
In one implementation of the present application, the third connector 4 further includes a first clamping plate 404 and a second clamping plate 405.
Specifically, in this embodiment, referring to fig. 4 and 6, the first clamping plate 404 is connected to a side of the first side wall 401 facing away from the second side wall 403, and is disposed at an angle with respect to the first clamping plate 404, where the angle is between 90 ° and 135 °, and the first clamping plate 404 is clamped to the inner wall on the right side of the clamping groove 201. The second clamping plate 405 is connected to a side of the second side wall 403 away from the first side wall 401, and is disposed at an angle with the second clamping plate 405, where the angle is between 90 ° and 135 °, and the second clamping plate 405 is clamped with the inner wall on the left side of the clamping groove 201.
Through the inner wall joint of first joint board 404 and draw-in groove 201 right side, and the inner wall joint of second joint board 405 and draw-in groove 201 left side, third connecting piece 4 can effectually prevent that third connecting piece 4 from coming off in first direction.
In order to increase the number of curtain walls to which the first connection can be attached, in another embodiment of the application,
The number of the second connecting pieces 3 is two.
In particular, in this embodiment, the third connecting piece 4 is located between two second connecting pieces 3, and two of said second connecting pieces 3 are symmetrically arranged with respect to said third connecting piece 4. One of the two second connectors 3 abuts against the first side wall 401, and the other of the two second connectors abuts against the second side wall 403.
Two second connectors 3 are engaged in one clamping groove 201, so that two curtain wall panels 1 can be installed in one clamping groove 201.
In order to solve the problem of the movement of the second connector 3 in the first direction, which corresponds to the movement of the first connector 2, in another embodiment of the application the curtain wall construction further comprises a fastener 5.
Specifically, referring to fig. 1 and 6, in this embodiment, one end of the fastener 5 in the first direction abuts against the first connection, and the other end in the first direction abuts against the second connection member 3 to limit movement of the second connection member 3 relative to the second connection member 3 in the first direction.
In one embodiment of the present application, the opening 203 is provided with an elastic plate 202 protruding along the second direction, and an end of the fastening member 5 away from the second connecting member 3 abuts against the elastic plate 202.
In order that both ends of the first connection member 2 in the first direction may be mounted with the curtain wall panel 1, in one embodiment of the present application, the number of the clip grooves 201 is two, and two clip grooves 201 are symmetrically disposed at both ends of the first connection member 2 in the first direction. By providing the first connector 2 to the clamping grooves 201 at both ends thereof in the first direction, more curtain wall panels 1 can be installed on the second connector 3 on the clamping grooves 201 at both ends. And a buffer cushion 6 is arranged between the second connecting pieces 3 which are respectively clamped with the two clamping grooves 201 along the first direction. The connecting grooves 302 are formed in the specific second connecting pieces 3, the clamping strips are arranged on the buffer pads 6, the buffer pads 6 are detachably connected to the connecting grooves 302 through the connecting strips, the second connecting pieces 3 can be further prevented from being damaged due to abutting connection caused by vibration between the two second connecting pieces 3 in the first direction, and the shock absorption effect is achieved.
Principle of: when the curtain wall wallboard 1 is used, the curtain wall wallboard 1 is fixedly connected to the second connecting piece 3 before leaving the factory, then the second connecting piece 3, the first connecting piece 2 and the third connecting piece 4 which are assembled with the curtain wall wallboard 1 are transported to a construction site, the second connecting piece 3 is inserted into the clamping groove 201 through one end of the clamping groove 201 of the first connecting piece 2, the third connecting piece 4 is inserted from one end of the clamping groove 201 and penetrates through the space between the two second connecting pieces 3, and then the fastener 5 is inserted between the elastic plate 202 of the first connecting piece 2 and the second connecting piece 3, so that the assembly is completed. When the curtain wall assembly structure needs to be disassembled, the fastener 5, the third connecting piece 4 and the like can be sequentially pulled out from one end of the curtain wall assembly structure. Finally, the beneficial effects that the construction efficiency is improved when workers install the curtain wall plate 1 on site, and meanwhile, when a single curtain wall plate is damaged, the single curtain wall plate can be quickly detached and replaced are achieved.
The foregoing has shown and described the basic principles and main features of the present utility model and the advantages of the present utility model. It will be appreciated by persons skilled in the art that the present utility model is not limited to the embodiments described above, but is capable of numerous variations and modifications without departing from the spirit and scope of the utility model as hereinafter claimed. The scope of the utility model is defined by the appended claims and equivalents thereof.

Claims (10)

1. Curtain wall spliced structure, its characterized in that includes:
The elastic first connecting piece is provided with a clamping groove which is provided with an opening, and the clamping groove is gradually reduced along a first direction;
The second connecting piece is used for installing curtain wall boards, clamping bulges are convexly arranged along the second direction of the second connecting piece, and the clamping bulges are clamped with the opening;
wherein the first direction and the second direction are perpendicular to each other.
2. The curtain wall construction of claim 1, further comprising:
The third connecting piece is clamped in the clamping groove, the side wall of the third connecting piece along the second direction is abutted against the second connecting piece, so that the second connecting piece is clamped together with the opening, and the clamping protrusion is arranged on one side, away from the third connecting piece, of the second connecting piece.
3. The curtain wall construction according to claim 2, wherein the third connection member comprises:
The first side wall and the second side wall are respectively fixed at two ends of the connecting plate along the second direction;
The second connecting piece is abutted with the first side wall;
Or the second connecting piece is abutted with the second side wall.
4. The curtain wall construction of claim 3, wherein:
The number of the second connecting pieces is two, and the two second connecting pieces are symmetrically arranged relative to the third connecting piece;
One of the two second connecting pieces is abutted with the first side wall, and the other of the two second connecting pieces is abutted with the second side wall.
5. The curtain wall construction according to claim 3 or 4, wherein:
The third connecting piece further comprises a first clamping plate and a second clamping plate;
The first clamping plate is connected to one side of the first side wall, which is away from the second side wall, and is arranged at an angle with the first clamping plate, and the first clamping plate is clamped with the inner wall of the clamping groove;
the second clamping plate is connected to one side of the second side wall, which is away from the first side wall, and is arranged at an angle with the second clamping plate, and the second clamping plate is clamped with the inner wall of the clamping groove.
6. The curtain wall construction of claim 5, further comprising:
And one end of the fastener along the first direction is abutted with the first connection, the other end of the fastener along the first direction is abutted with the second connection piece, and the fastener is used for limiting the movement of the second connection piece along the first direction relative to the second connection piece.
7. The curtain wall construction of claim 6, wherein:
The opening is convexly provided with an elastic plate along the second direction, and one end, away from the second connecting piece, of the fastening piece is abutted with the elastic plate.
8. The curtain wall construction of claim 7, wherein:
The number of the clamping grooves is two, and the two clamping grooves are symmetrically arranged at two ends of the first connecting piece along the first direction.
9. The curtain wall construction of claim 8, wherein:
and a buffer cushion is arranged between the second connecting pieces which are respectively clamped with the two clamping grooves along the first direction.
10. The curtain wall construction of claim 9, wherein: the cushion pad is detachably connected.
CN202323223391.7U 2023-11-29 2023-11-29 Curtain wall assembling structure Active CN221372596U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202323223391.7U CN221372596U (en) 2023-11-29 2023-11-29 Curtain wall assembling structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202323223391.7U CN221372596U (en) 2023-11-29 2023-11-29 Curtain wall assembling structure

Publications (1)

Publication Number Publication Date
CN221372596U true CN221372596U (en) 2024-07-19

Family

ID=91888515

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202323223391.7U Active CN221372596U (en) 2023-11-29 2023-11-29 Curtain wall assembling structure

Country Status (1)

Country Link
CN (1) CN221372596U (en)

Similar Documents

Publication Publication Date Title
CN221372596U (en) Curtain wall assembling structure
CN111851807B (en) A connection structure of prefabricated building curtain wall components
CN211447568U (en) An indoor and outdoor soundproof decorative wall panel installation structure
CN212129775U (en) Assembled veneer wall structure
CN212026927U (en) Wallboard mounting system
CN210195097U (en) Anchor part of external wall insulation integrated board
CN212224509U (en) Wood veneer component
CN221143206U (en) Indoor curtain wall convenient to installation
CN220203011U (en) Wallboard connection structure
KR101347559B1 (en) fixture device for soundproofing plate
CN221837883U (en) A leveling assembly for assembled stiffened steel plate shear wall
CN210395780U (en) Backplate structure between unitized curtain wall layer
CN210288751U (en) A wooden sliding friction damper with variable damping force
CN220035881U (en) Integrated wallboard assembly and integrated kitchen and toilet system
CN223104027U (en) An assembled perforated aluminum plate
CN219316119U (en) Mirror surface stainless steel honeycomb plate mounting system
CN206616814U (en) A kind of wall board erecting device
CN220747511U (en) Wall surface mounting structure
CN222227795U (en) Energy-saving and environment-friendly building wall panel installation structure
CN222500798U (en) Corrugated lighting board mounting frame structure
CN220318899U (en) Glass curtain wall capable of being installed rapidly
CN223358453U (en) A splicing structure of high-strength building wall panels
CN219938248U (en) Fixtures for photovoltaic systems and photovoltaic systems
CN214329493U (en) Mounting structure of curtain
CN222847622U (en) Curtain wall installation structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant