CN221321709U - High slope cable machine mobile construction platform based on concrete embedded pier - Google Patents

High slope cable machine mobile construction platform based on concrete embedded pier Download PDF

Info

Publication number
CN221321709U
CN221321709U CN202323353382.XU CN202323353382U CN221321709U CN 221321709 U CN221321709 U CN 221321709U CN 202323353382 U CN202323353382 U CN 202323353382U CN 221321709 U CN221321709 U CN 221321709U
Authority
CN
China
Prior art keywords
concrete
slope
cable machine
embedded
high slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202323353382.XU
Other languages
Chinese (zh)
Inventor
刘路
胡永福
董庆煊
杨念东
张建博
张文毅
葛小博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Huaneng Lancang River Hydropower Co Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Huaneng Lancang River Hydropower Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd, Huaneng Lancang River Hydropower Co Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN202323353382.XU priority Critical patent/CN221321709U/en
Application granted granted Critical
Publication of CN221321709U publication Critical patent/CN221321709U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本实用新型提供了一种基于混凝土嵌固墩的高边坡缆机移动施工平台,涉及高边坡施工平台技术领域,技术包括移动作业平台,移动作业平台与缆机收放系统连接,缆机收放系统安装在混凝土嵌固结构上。本实用新型具体使用时在需要支护的高边坡上,根据需求开挖若干嵌固槽,将混凝土墩嵌固在嵌固槽中,并浇筑混凝土;将移动作业平台安装有滑轮一侧与高边坡接触,通过缆机实现移动作业平台的上下移动,当到达工作面时安装并固定锚杆,以增加安全性;本实用新型构造简单,现场施工制作方便,相比搭设脚手架大幅缩短了施工周期,且在面对复杂的高边坡支护不及时的施工工况,可及时开展补救工作。

The utility model provides a high-slope cable mobile construction platform based on concrete embedded piers, which relates to the technical field of high-slope construction platforms. The technology includes a mobile work platform, which is connected to a cable retracting system, and the cable retracting system is installed on a concrete embedded structure. When the utility model is used, on a high slope that needs to be supported, a number of embedded grooves are excavated according to demand, the concrete piers are embedded in the embedded grooves, and concrete is poured; the mobile work platform is installed with a pulley on one side to contact the high slope, and the mobile work platform is moved up and down by the cable, and the anchor rod is installed and fixed when it reaches the working surface to increase safety; the utility model has a simple structure and is easy to construct on site. Compared with setting up scaffolding, the construction period is greatly shortened, and in the face of complex high slope support The construction condition is not timely, remedial work can be carried out in time.

Description

一种基于混凝土嵌固墩的高边坡缆机移动施工平台A high slope cable mobile construction platform based on concrete embedded piers

技术领域Technical Field

本实用新型涉及高边坡施工平台技术领域,特别是一种基于混凝土嵌固墩的高边坡缆机移动施工平台。The utility model relates to the technical field of high-slope construction platforms, in particular to a high-slope cableway mobile construction platform based on concrete embedded piers.

背景技术Background technique

在工程实践中,各类高边坡施工作业时要求即时开挖及时支护,但实际工程中往往不能做到,现有技术中常用搭设脚手架的方式开展高边坡支护工作然而因实际场地地势、岩性和分级开挖等限制原因,脚手架搭设难度过大从而制约工期,因为需要一种新的施工辅助手段。In engineering practice, all kinds of high slope construction work require immediate excavation and timely support, but this is often not possible in actual projects. In the existing technology, scaffolding is often used to carry out high slope support work. However, due to the actual site topography, rock properties and graded excavation, the scaffolding is too difficult to set up, which restricts the construction period. Therefore, a new construction auxiliary means is needed.

公开号为CN109403357A的文件公开了一种移动式高边坡施工平台简易装置包括四轮底座和围栏工作平台;四轮底座通过角度控制杆和围栏工作平台连接;所述围栏工作平台的一侧连接有提升机构。本发明主体结构由钢管扣接而成,通过调整钢管长度、扣件位置即可控制装置的尺寸、平台与坡面的夹角,从而适用于各类施工和较大坡度范围,保证边坡施工平台平衡。经分析该公开文件中虽提出了一种移动式施工平台,但并未明确移动施工作业平台与地面的固定方式,并且在施工作业中该移动式高边坡施工平台并不能临时固定在高边坡上,因此这部分结构需要进行改进。The document with the publication number CN109403357A discloses a simple mobile high-slope construction platform device including a four-wheel base and a fence work platform; the four-wheel base is connected to the fence work platform through an angle control rod; one side of the fence work platform is connected to a lifting mechanism. The main structure of the present invention is made of steel pipes, and the size of the device and the angle between the platform and the slope can be controlled by adjusting the length of the steel pipe and the position of the fasteners, so that it is suitable for various types of construction and a large slope range, ensuring the balance of the slope construction platform. After analysis, although a mobile construction platform is proposed in the public document, the fixing method of the mobile construction work platform and the ground is not clear, and the mobile high-slope construction platform cannot be temporarily fixed on the high slope during construction, so this part of the structure needs to be improved.

实用新型内容Utility Model Content

本实用新型提供一种基于混凝土嵌固墩的高边坡缆机移动施工平台,目的在于至少解决一个背景技术中提及的现有技术存在的技术问题。The utility model provides a high slope cable crane mobile construction platform based on concrete embedded piers, aiming to solve at least one technical problem existing in the prior art mentioned in the background technology.

本实用新型提供如下技术方案,实现上述目的:The utility model provides the following technical solutions to achieve the above objectives:

一种基于混凝土嵌固墩的高边坡缆机移动施工平台,包括高边坡,所述高边坡的顶部设置有一组与混凝土墩匹配的嵌固槽;高边坡的侧边设置有移动作业平台,移动作业平台与缆机收放系统连接,缆机收放系统安装在混凝土嵌固结构上,所述混凝土嵌固结构包括若干混凝土墩,混凝土墩内设置有若干插筋,插筋的底部从混凝土墩内伸出,混凝土墩和插筋设置在嵌固槽中。A high-slope cable crane mobile construction platform based on concrete embedded piers comprises a high slope, wherein a group of embedded grooves matching the concrete piers are arranged on the top of the high slope; a mobile working platform is arranged on the side of the high slope, the mobile working platform is connected to a cable crane retracting and releasing system, the cable crane retracting and releasing system is installed on the concrete embedded structure, the concrete embedded structure comprises a plurality of concrete piers, a plurality of dowel bars are arranged in the concrete piers, the bottoms of the dowel bars extend out from the concrete piers, and the concrete piers and the dowel bars are arranged in the embedded grooves.

更进一步的,所述缆机收放系统包括若干缆机,每个缆机通过钢绞线连接移动作业平台的顶部外侧,缆机皆固定安装在混凝土墩上。Furthermore, the cable crane retracting and releasing system includes a plurality of cables, each of which is connected to the top outer side of the mobile working platform through a steel strand, and the cables are all fixedly mounted on a concrete pier.

更进一步的,所述混凝土墩设有两个,混凝土墩上各设有一个缆机。Furthermore, there are two concrete piers, each of which is provided with a cable crane.

更进一步的,所述移动作业平台的顶部内侧设置有若干固定锚杆。Furthermore, a plurality of fixed anchor rods are arranged on the inner side of the top of the mobile working platform.

更进一步的,所述固定锚杆与高边坡活动连接。Furthermore, the fixed anchor rod is movably connected to the high slope.

更进一步的,所述移动作业平台的内侧设置有若干组滑轮。Furthermore, a plurality of pulleys are arranged on the inner side of the mobile working platform.

更进一步的,所述移动作业平台的内侧的左端和右端各设置有一组滑轮。Furthermore, a set of pulleys is respectively provided at the left end and the right end of the inner side of the mobile working platform.

有益效果Beneficial Effects

本实用新型包括三大部分组成,混凝土墩嵌固结构、移动作业平台和缆机收放系统,具体使用时在需要支护的高边坡上,根据需求开挖若干嵌固槽,将混凝土墩嵌固在嵌固槽中,并浇筑混凝土;将移动作业平台安装有滑轮一侧与高边坡接触,通过缆机实现移动作业平台的上下移动,当到达工作面时安装并固定锚杆,以增加安全性;本实用新型构造简单,现场施工制作方便,相比搭设脚手架大幅缩短了施工周期,且在面对复杂的高边坡支护不及时的施工工况,可及时开展补救工作。The utility model comprises three major parts: a concrete pier embedding structure, a mobile working platform and a cable crane retracting and releasing system. When in use, a number of embedding grooves are excavated according to needs on a high slope that needs support, the concrete piers are embedded in the embedding grooves, and concrete is poured; one side of the mobile working platform is installed with a pulley in contact with the high slope, and the mobile working platform is moved up and down by a cable crane, and anchor rods are installed and fixed when the working surface is reached to increase safety; the utility model has a simple structure and is convenient for on-site construction and production. Compared with setting up scaffolds, the construction period is greatly shortened, and remedial work can be carried out in time in the face of complex construction conditions where high slope support is not timely.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

为了更清楚地说明本实用新型实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍。显而易见地,下面描述中的附图涉及的仅仅是本实用新型的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动性的前提下,还可以根据这些附图获得其它的附图。In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the prior art descriptions. Obviously, the drawings described below only relate to some embodiments of the utility model, and for ordinary technicians in this field, other drawings can be obtained based on these drawings without creative labor.

图1为本实用新型的结构示意图;Fig. 1 is a schematic diagram of the structure of the utility model;

图2为本实用新型移动作业平台的结构示意图;FIG2 is a schematic diagram of the structure of the mobile working platform of the utility model;

附图标记:1-高边坡;2-嵌固槽;3-插筋;4-混凝土墩;5-缆机;6-钢绞线;7-移动作业平台;8-固定锚杆;9-滑轮。Figure numerals: 1-high slope; 2-embedded groove; 3-inserted reinforcement; 4-concrete pier; 5-cable crane; 6-steel strand; 7-mobile working platform; 8-fixed anchor rod; 9-pulley.

具体实施方式Detailed ways

为了使本技术领域的人员更好地理解本实用新型方案,下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述。In order to enable those skilled in the art to better understand the solution of the present invention, the technical solution in the embodiment of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiment of the present invention.

需要说明的是在本实用新型中:术语“包括”和“具有”以及他们的任何变形,意图在于覆盖不排他的包含,例如,包含了一系列步骤或单元的过程、方法、系统、产品或设备不必限于清楚地列出的那些步骤或单元,而是可包括没有清楚地列出的或对于这些过程、方法、产品或设备固有的其它步骤或单元;术语“上”、“下”、“左”、“右”、“前”、“后”、“顶”、“底”、“内”、“外”、“中”、“竖直”、“水平”、“横向”、“纵向”等指示的方位或位置关系为基于附图所示的方位或位置关系,这些术语主要是为了更好地描述本实用新型及其实施例,并非用于限定所指示的装置、元件或组成部分必须具有特定方位,或以特定方位进行构造和操作;术语“第一”、“第二”等是用于区别类似的对象,而不必用于描述特定的顺序或先后次序;术语“安装”、“设置”、“设有”、“连接”、“相连”、“套接”等应做广义理解;例如,可以是固定连接,可拆卸连接,或整体式构造;可以是机械连接,或电连接;可以是直接相连,或者是通过中间媒介间接相连,又或者是两个装置、元件或组成部分之间内部的连通。并且,部分术语除了可以用于表示方位或位置关系以外,还可能用于表示其他含义,例如术语“上”在某些情况下也可能用于表示某种依附关系或连接关系。对于本领域普通技术人员而言,可以根据具体情况理解这些术语在本实用新型中的具体含义。It should be noted that in the present invention: the terms "include" and "have" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or apparatus comprising a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units not clearly listed or inherent to these processes, methods, products or apparatuses; the directions or positional relationships indicated by the terms "upper", "lower", "left", "right", "front", "back", "top", "bottom", "inside", "outside", "middle", "vertical", "horizontal", "lateral", "longitudinal" and the like are based on the directions or positional relationships shown in the drawings. These The terms are mainly used to better describe the utility model and its embodiments, and are not used to limit the indicated devices, elements or components to have a specific orientation, or to be constructed and operated in a specific orientation; the terms "first", "second", etc. are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence; the terms "install", "set", "provided with", "connected", "connected", "sleeved", etc. should be understood in a broad sense; for example, it can be a fixed connection, a detachable connection, or an integral structure; it can be a mechanical connection, or an electrical connection; it can be directly connected, or indirectly connected through an intermediate medium, or it can be an internal connection between two devices, elements or components. In addition, some terms can be used to express other meanings in addition to indicating orientation or positional relationships. For example, the term "on" may also be used to express a certain dependency or connection relationship in some cases. For ordinary technicians in this field, the specific meanings of these terms in the utility model can be understood according to specific circumstances.

实施例。一种基于混凝土嵌固墩的高边坡缆机移动施工平台,结构参考图1-2,包括高边坡1,高边坡1的顶部设置有一组与混凝土墩4匹配的嵌固槽2;高边坡1的侧边设置有移动作业平台7,移动作业平台7与缆机收放系统连接,缆机收放系统安装在混凝土嵌固结构上,所述混凝土嵌固结构包括若干混凝土墩4,混凝土墩4内设置有若干插筋3,插筋3的底部从混凝土墩4内伸出,混凝土墩4和插筋3设置在嵌固槽2中。Embodiment. A high-slope cable mobile construction platform based on concrete embedded piers, with reference to FIG1-2 for structure, comprises a high slope 1, a group of embedded grooves 2 matching with concrete piers 4 are arranged on the top of the high slope 1; a mobile working platform 7 is arranged on the side of the high slope 1, the mobile working platform 7 is connected to a cable crane retracting and releasing system, and the cable crane retracting and releasing system is installed on the concrete embedded structure, the concrete embedded structure comprises a plurality of concrete piers 4, a plurality of dowels 3 are arranged in the concrete piers 4, the bottom of the dowels 3 extend out from the concrete piers 4, and the concrete piers 4 and the dowels 3 are arranged in the embedded grooves 2.

所述缆机收放系统包括若干缆机5,每个缆机5通过钢绞线6连接移动作业平台7的顶部外侧,缆机5皆固定安装在混凝土墩4上。The cable crane retracting and releasing system includes a plurality of cables 5 , each of which is connected to the top outer side of a mobile working platform 7 via a steel strand 6 , and the cables 5 are all fixedly mounted on a concrete pier 4 .

所述混凝土墩4设有两个,混凝土墩4上各设有一个缆机5。There are two concrete piers 4 , each of which is provided with a cable car 5 .

所述移动作业平台7的顶部内侧设置有若干固定锚杆8。A plurality of fixed anchor rods 8 are arranged on the inner side of the top of the mobile working platform 7 .

所述固定锚杆8与高边坡1活动连接。The fixed anchor rod 8 is movably connected to the high slope 1 .

所述移动作业平台7的内侧设置有若干组滑轮9。A plurality of pulleys 9 are arranged on the inner side of the mobile working platform 7 .

所述移动作业平台7的内侧的左端和右端各设置有一组滑轮9。A set of pulleys 9 is respectively provided at the left and right ends of the inner side of the mobile working platform 7 .

本实用新型的使用方法:在需要支护的高边坡上,根据需求开挖若干嵌固槽2,制作混凝土墩4,制作时设置若干插筋3并保持插筋3伸出混凝土墩4的底部,待混凝土墩4凝固后将插筋3朝下与混凝土墩4一起放入嵌固槽2中并浇筑混凝土,待混凝土凝固后,在混凝土墩4上安装缆机5,缆机5通过钢绞线6连接移动作业平台7,将移动作业平台7安装有滑轮9一侧与高边坡接触,通过缆机5实现移动作业平台7的上下移动,当到达工作面时安装并固定锚杆8,即可开始支护工作。The method of using the utility model is as follows: on a high slope that needs to be supported, a number of embedded grooves 2 are excavated according to needs, and concrete piers 4 are made. During the making, a number of dowel bars 3 are arranged and kept extending out of the bottom of the concrete pier 4. After the concrete pier 4 solidifies, the dowel bars 3 are placed downward together with the concrete pier 4 into the embedded grooves 2 and concrete is poured. After the concrete solidifies, a cable crane 5 is installed on the concrete pier 4. The cable crane 5 is connected to a mobile working platform 7 through a steel strand 6. The mobile working platform 7 is installed with a pulley 9 on one side in contact with the high slope. The mobile working platform 7 is moved up and down by the cable crane 5. When the working surface is reached, the anchor rod 8 is installed and fixed, and the support work can begin.

显然,以上所述仅为本实用新型的一部分的实施例,而不是全部的实施例。以上实施例并不用于限制本实用新型,对于本领域的技术人员来说,本实用新型可以有各种更改和变化。凡在本实用新型的精神和原则之内,本领域普通技术人员可作出的任何组合、修改、等同替换、改进等所有其他实施例,都应当在本实用新型的保护范围之内。Obviously, the above is only a part of the embodiments of the utility model, not all of the embodiments. The above embodiments are not used to limit the utility model. For those skilled in the art, the utility model can have various changes and variations. Any combination, modification, equivalent replacement, improvement and all other embodiments that can be made by ordinary technicians in the field within the spirit and principle of the utility model should be within the protection scope of the utility model.

Claims (7)

1. High side slope cable machine removes construction platform based on concrete builds in mound, including high side slope (1), its characterized in that: the top of the high slope (1) is provided with a group of embedded grooves (2) matched with the concrete piers (4); the side of high side slope (1) is provided with removal operation platform (7), and removal operation platform (7) receive and releases the system with the cable machine and is connected, and cable machine receive and releases the system installation on concrete builds in the structure, concrete builds in the structure and includes a plurality of concrete piers (4), is provided with a plurality of dowel bars (3) in the concrete piers (4), stretches out in concrete piers (4) from the bottom of dowel bars (3), and concrete piers (4) and dowel bars (3) set up in the built-in groove (2).
2. The concrete-embedded pier-based high slope cable machine mobile construction platform according to claim 1, wherein: the cable machine winding and unwinding system comprises a plurality of cable machines (5), each cable machine (5) is connected with the outer side of the top of the movable operation platform (7) through a steel strand (6), and the cable machines (5) are fixedly installed on the concrete piers (4).
3. The concrete-embedded pier-based high slope cable machine mobile construction platform according to claim 2, wherein: two concrete piers (4) are arranged, and each concrete pier (4) is provided with a cable machine (5).
4. The concrete-embedded pier-based high slope cable machine mobile construction platform according to claim 1, wherein: the inner side of the top of the movable working platform (7) is provided with a plurality of fixed anchor rods (8).
5. The concrete-embedded pier-based high slope cable machine mobile construction platform according to claim 4, wherein: the fixed anchor rod (8) is movably connected with the high slope (1).
6. The concrete-embedded pier-based high slope cable machine mobile construction platform according to claim 1, wherein: the inner side of the movable working platform (7) is provided with a plurality of groups of pulleys (9).
7. The concrete-embedded pier-based high slope cable machine mobile construction platform according to claim 6, wherein: the left end and the right end of the inner side of the movable working platform (7) are respectively provided with a group of pulleys (9).
CN202323353382.XU 2023-12-11 2023-12-11 High slope cable machine mobile construction platform based on concrete embedded pier Active CN221321709U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202323353382.XU CN221321709U (en) 2023-12-11 2023-12-11 High slope cable machine mobile construction platform based on concrete embedded pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202323353382.XU CN221321709U (en) 2023-12-11 2023-12-11 High slope cable machine mobile construction platform based on concrete embedded pier

Publications (1)

Publication Number Publication Date
CN221321709U true CN221321709U (en) 2024-07-12

Family

ID=91783381

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202323353382.XU Active CN221321709U (en) 2023-12-11 2023-12-11 High slope cable machine mobile construction platform based on concrete embedded pier

Country Status (1)

Country Link
CN (1) CN221321709U (en)

Similar Documents

Publication Publication Date Title
CN104631333B (en) Arch bridge needle beam, stringer and floorings cast-in-place construction travelling bridge and method
KR101028868B1 (en) Bridge side span temporary lifting device and bridge side span construction method using the same
CN204982667U (en) Prestressing force rubber tube poling machine
CN102913248B (en) The overall upset hanging template of wholecircle and formwork erection, release method
CN104975719A (en) Novel material distribution device and construction method for pouring floor concrete by using same
CN104531931B (en) Method for installing dust removal pipeline at lower part of blast furnace casting house
CN110685433A (en) Chimney construction device and construction method applying hydraulic lifting and rollover technology
CN111749140A (en) A truss integral lift bridge high pier climbing formwork device and construction method
CN109457814B (en) Construction method for top cover of high-rise and large-diameter building based on Bailey truss structure
CN111749259B (en) A construction method suitable for rock-embedded construction of offshore wind power high pile cap foundation
CN108005684A (en) Separated steel mould trolley and its construction method
CN113356215B (en) A construction method and cutting device for cutting rock platform of crane beam on rock wall of underground workshop
CN221321709U (en) High slope cable machine mobile construction platform based on concrete embedded pier
CN107829408B (en) Rectangular aqueduct construction steel mould trolley
CN209260715U (en) A kind of sliding form apparatus pouring small area and small size inclination concrete slab
CN114991126B (en) Non-prestress post-inserted composite anchor cable anti-pulling pile construction equipment
CN215516375U (en) Manhole hoisting device for foundation reinforcement cage
CN203755173U (en) Formwork device used for hydraulic climbing of bridge high pier
CN107288640A (en) A kind of steady rope self-supporting modularization vertical shaft driving and masonry construction device of nothing
CN105696609A (en) Steel hanging box lowering system and installation method thereof
CN115162218A (en) Rigid frame arch bridge dismantling process
CN212105891U (en) A steel mould platform truck for tailing storehouse water drainage tank concrete is integrally cast
CN215760498U (en) A concrete formwork demolition machine for housing construction
CN108821127A (en) The devices and methods therefor of disassembly lifting open type TBM in a kind of hole
CN204224987U (en) A kind of continuous girder bridge multiple pipeline installation structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Anhui Fengpu Construction Engineering Co.,Ltd.

Assignor: Huaneng Upper Lancang Hydropower Co.,Ltd. Banda Hydropower Project Construction Administration

Contract record no.: X2025980007067

Denomination of utility model: A high slope cable crane mobile construction platform based on concrete embedded piers

Granted publication date: 20240712

License type: Common License

Record date: 20250415

Assignee: Tibet Construction Engineering Co.,Ltd. of No 9 Hydropower Bureau

Assignor: Huaneng Upper Lancang Hydropower Co.,Ltd. Banda Hydropower Project Construction Administration

Contract record no.: X2025980006748

Denomination of utility model: A high slope cable crane mobile construction platform based on concrete embedded piers

Granted publication date: 20240712

License type: Common License

Record date: 20250411

Assignee: Yunnan Hongchang Construction Co.,Ltd.

Assignor: Huaneng Upper Lancang Hydropower Co.,Ltd. Banda Hydropower Project Construction Administration

Contract record no.: X2025980006742

Denomination of utility model: A high slope cable crane mobile construction platform based on concrete embedded piers

Granted publication date: 20240712

License type: Common License

Record date: 20250410

EE01 Entry into force of recordation of patent licensing contract