CN221143539U - Combined steel template mounting device - Google Patents

Combined steel template mounting device Download PDF

Info

Publication number
CN221143539U
CN221143539U CN202322690419.1U CN202322690419U CN221143539U CN 221143539 U CN221143539 U CN 221143539U CN 202322690419 U CN202322690419 U CN 202322690419U CN 221143539 U CN221143539 U CN 221143539U
Authority
CN
China
Prior art keywords
steel formwork
side wall
base
front side
combined steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322690419.1U
Other languages
Chinese (zh)
Inventor
徐磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Moheng Steel Structure Co ltd
Original Assignee
Wuhan Chenqihan Road And Bridge Equipment Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Chenqihan Road And Bridge Equipment Co ltd filed Critical Wuhan Chenqihan Road And Bridge Equipment Co ltd
Priority to CN202322690419.1U priority Critical patent/CN221143539U/en
Application granted granted Critical
Publication of CN221143539U publication Critical patent/CN221143539U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本实用新型公开了一种组合式钢模板安装装置,包括底座,所述底座的底部安装有多个锁止万向轮,所述底座上贯穿转动连接有竖杆,所述竖杆由安装在底座底部的第一驱动电机驱动,所述竖杆的前侧壁竖直滑动连接有T型安装板,所述T型安装板的前侧壁安装有气缸,所述气缸的伸缩端端部安装有第二驱动电机,所述第二驱动电机的输出端固定连接有承载板。本实用新型结构设计合理,通过多个夹持板共同作用,能够对钢模板进行稳固固定,承载板对钢模板进行支撑,减少其发生变形现象,有利于对钢模板进行安装,并且能够根据实际安装需求对钢模板的高度、朝向、位置以及角度进行调整,有利于安装工作的进行。

The utility model discloses a combined steel formwork installation device, including a base, a plurality of locking universal wheels are installed at the bottom of the base, a vertical rod is rotatably connected to the base, the vertical rod is driven by a first drive motor installed at the bottom of the base, the front side wall of the vertical rod is vertically slidably connected to a T-shaped mounting plate, a cylinder is installed at the front side wall of the T-shaped mounting plate, a second drive motor is installed at the telescopic end of the cylinder, and a bearing plate is fixedly connected to the output end of the second drive motor. The utility model has a reasonable structural design, and can stably fix the steel formwork through the joint action of a plurality of clamping plates, and the bearing plate supports the steel formwork to reduce its deformation, which is conducive to the installation of the steel formwork, and can adjust the height, orientation, position and angle of the steel formwork according to actual installation requirements, which is conducive to the installation work.

Description

Combined steel template mounting device
Technical Field
The utility model relates to the technical field of steel template installation, in particular to a combined steel template installation device.
Background
The steel template is used for concrete pouring and forming, and besides the steel template, a wood template, a plywood template and the like are also used. The steel form is widely applied to the constructional engineering by the characteristics of repeated use, beautiful concrete pouring and forming, and the like. The novel combined steel template has the advantages of high component strength, good durability, high manufacturing precision and the like, and is widely applied to the engineering at present.
The combined steel template is formed by splicing and installing a plurality of steel templates, in the installation process, the steel templates are sometimes required to be erected, the positions of the steel templates are required to be adjusted and then installed, one end of each steel template is directly pulled up by a crane to be erected by the traditional erection method, the steel templates are easy to deform and influence the using effect because the steel templates are not supported in the erection process, and therefore, the combined steel template installation device is designed to solve the problems.
Disclosure of utility model
The utility model aims to solve the problems in the prior art, and provides a combined steel template mounting device which can stably fix a steel template through the combined action of a plurality of clamping plates, supports the steel template by a bearing plate, reduces deformation phenomenon of the steel template, is beneficial to mounting the steel template, can adjust the height, the direction, the position and the angle of the steel template according to mounting requirements, and is beneficial to mounting work.
In order to achieve the above purpose, the present utility model adopts the following technical scheme:
The utility model provides a modular steel form installation device, includes the base, a plurality of locking universal wheels are installed to the bottom of base, run through on the base and rotate and be connected with the montant, the montant is by installing the first driving motor drive in the base bottom, the vertical sliding connection of the preceding lateral wall of montant has T type mounting panel, the cylinder is installed to the preceding lateral wall of T type mounting panel, the second driving motor is installed to the flexible end tip of cylinder, the output fixedly connected with loading board of second driving motor, the symmetry is equipped with two sets of clamping components that fix the steel form on the loading board, two sets of clamping components are by first servo motor drive.
Preferably, the vertical spout has been seted up to the preceding lateral wall of montant, T type mounting panel sliding connection is in vertical spout and rather than looks adaptation, the interior bottom rotation of vertical spout is connected with the threaded rod, the threaded rod screw thread runs through T type mounting panel, the threaded rod is driven by the second servo motor of installing in the montant upper end.
Preferably, the front side wall of the T-shaped mounting plate is symmetrically and fixedly connected with two telescopic rods, the rear side wall of the bearing plate is provided with an annular chute, and the telescopic ends of the two telescopic rods extend into the annular chute and are in sliding connection with the annular chute.
Preferably, the clamping assembly comprises an inserted bar which is fixedly connected to the bearing plate in a penetrating mode, two clamping plates which are in sliding connection with the inserted bar are symmetrically sleeved on the inserted bar, a double-head screw rod is connected to the bearing plate in a penetrating and rotating mode, and two ends of the double-head screw rod penetrate through the two clamping plates in a threaded mode respectively.
Preferably, the first servo motor is arranged on the front side wall of the bearing plate, and a driving belt is wound between the first servo motor and the two double-headed screws.
Preferably, the two ends of the inserted link are fixedly connected with reinforcing plates, and the double-headed screw is rotationally connected with the reinforcing plates.
Compared with the prior art, the utility model has the beneficial effects that:
1. This combination formula steel form installation device places the steel form that will install on the loading board and is located between a plurality of grip blocks, and two double-end screw rods can rotate in step with first servo motor's output shaft, make two grip blocks relative each other be close to around, and then a plurality of grip blocks can the combined action, stabilize fixedly to the steel form, and the loading board supports the steel form, reduces its emergence deformation phenomenon, is favorable to installing the steel form.
2. This combination formula steel form installation device, locking universal wheel can remove the steel form to the position that needs the installation, and the vertical removal of T type mounting panel can adjust the height of loading board, and first driving motor drives the montant and rotates, can adjust the orientation of loading board, and the cylinder drives the loading board and reciprocates and to remove the position that can adjust the steel form, and the second driving motor drives the loading board and rotates and to adjust the angle of steel form, is favorable to the going on of installation work.
Drawings
FIG. 1 is a schematic diagram of a front view of a combined steel form mounting apparatus according to the present utility model;
FIG. 2 is a schematic top cross-sectional view of a modular steel form mounting apparatus according to the present utility model;
Fig. 3 is a schematic top view of a combined steel form mounting device according to the present utility model.
In the figure: 1. a base; 2. locking the universal wheel; 3. a vertical rod; 4. a first driving motor; 5. a T-shaped mounting plate; 6. a threaded rod; 7. a second servo motor; 8. a cylinder; 9. a second driving motor; 10. a carrying plate; 11. a telescopic rod; 12. a rod; 13. a clamping plate; 14. a double-ended screw; 15. a first servo motor; 16. a driving belt.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments.
Referring to fig. 1-3, a combined steel template installation device comprises a base 1, a plurality of locking universal wheels 2 are installed at the bottom of the base 1, the device can be moved, the base 1 and the vertical rods 3 are gravity plates, stability of the device can be guaranteed, rollover phenomenon of the gravity center of the device in the installation process of the steel template is avoided, the vertical rods 3 are connected to the base 1 in a penetrating and rotating mode, the vertical rods 3 are semicircular, the upper end of the base 1 is fixedly connected with a plurality of reinforcing plates which are propped against the vertical rods 3, the vertical rods 3 can play a supporting role on the vertical rods 3, stability is guaranteed, the vertical rods 3 are rotationally connected with the reinforcing plates, the vertical rods 3 are driven by a first driving motor 4 installed at the bottom of the base 1, the front side walls of the vertical rods 3 are vertically and slidably connected with T-shaped installation plates 5, vertical sliding grooves are formed in the front side walls of the vertical rods 3, threaded rods 6 are rotationally connected with the inner bottoms of the vertical sliding grooves, the threaded rods 6 penetrate through the T-shaped installation plates 5, the threaded rods 6 are driven by a second servo motor 7 installed at the upper ends of the vertical rods 3, and the second servo motor 7 can drive the threaded rods 6 to be meshed with the vertical sliding grooves 5 under the action of the vertical threaded rods;
The cylinder 8 is arranged on the front side wall of the T-shaped mounting plate 5, the second driving motor 9 is arranged at the end part of the telescopic end of the cylinder 8, the bearing plate 10 is fixedly connected with the output end of the second driving motor 9, the two telescopic rods 11 are symmetrically and fixedly connected with the front side wall of the T-shaped mounting plate 5, the annular sliding groove is formed in the rear side wall of the bearing plate 10, the telescopic ends of the two telescopic rods 11 extend into the annular sliding groove and are in sliding connection with the annular sliding groove, the stability of the bearing plate 10 can be improved, the cylinder 8 can drive the bearing plate 10 to stretch and retract, and the second driving motor 9 can drive the bearing plate 10 to rotate to adjust the angle of the bearing plate 10;
The symmetry is equipped with two sets of clamping components that fix the steel form on the loading board 10, clamping components is including running through the inserted bar 12 of fixed connection on the loading board 10, the symmetry cover is equipped with two clamping plates 13 rather than sliding connection on the inserted bar 12, the inserted bar 12 can play direction and restriction effect to two clamping plates 13, make two clamping plates 13 slide from top to bottom, run through on the loading board 10 and rotate and be connected with double-end screw 14, the both ends of double-end screw 14 are threaded respectively and run through two clamping plates 13, when double-end screw 14 rotates, can make two clamping plates 13 be close to each other or keep away from each other, the equal fixedly connected with reinforcing plate in both ends of inserted bar 12, double-end screw 14 rotates with the reinforcing plate to be connected, the setting of reinforcing plate can ensure the stability of double-end screw 14, two sets of clamping components are all driven by first servo motor 15, all around being equipped with drive belt 16 between first servo motor 15 and the two double-end screw 14, all the cover is equipped with the roller rather than the adaptation on the output shaft of double-end screw 14, drive belt 16 corresponding drive belt 16 can rotate between two double-end screw 14 and drive shaft 15.
The utility model can explain its functional principle by the following modes of operation:
In the utility model, when the steel template is required to be installed, in an initial state, the T-shaped mounting plate 5 is positioned at the inner bottom of the vertical chute, the steel template required to be installed is placed on the bearing plate 10 and positioned among the clamping plates 13, the first servo motor 15 is started, under the connection action of the transmission belt 16, the two double-headed screws 14 can synchronously rotate with the output shaft of the first servo motor 15, further under the meshing action of the two double-headed screws 14, the two clamping plates 13 which are opposite front and back can mutually approach, the clamping plates 13 can jointly act, the steel template can be firmly fixed, and the steel template can be moved to the position required to be installed through the locking universal wheels 2;
the second servo motor 7 drives the threaded rod 6 to rotate, can make the vertical height of adjusting the loading board 10 that removes of T type mounting panel 5 under the screw thread meshing effect of threaded rod 6, first driving motor 4 drives montant 3 and rotates, can adjust the orientation of loading board 10, and then can rotate the steel form to the position that needs the installation, and cylinder 8 drives loading board 10 back-and-forth movement and can adjust the position of steel form, and second driving motor 9 drives the loading board 10 and rotates and to adjust the angle of steel form, makes the steel form erect, is favorable to the going on of installation work.
The foregoing is only a preferred embodiment of the present utility model, but the scope of the present utility model is not limited thereto, and any person skilled in the art, who is within the scope of the present utility model, should make equivalent substitutions or modifications according to the technical scheme of the present utility model and the inventive concept thereof, and should be covered by the scope of the present utility model.

Claims (6)

1.一种组合式钢模板安装装置,包括底座(1),其特征在于,所述底座(1)的底部安装有多个锁止万向轮(2),所述底座(1)上贯穿转动连接有竖杆(3),所述竖杆(3)由安装在底座(1)底部的第一驱动电机(4)驱动,所述竖杆(3)的前侧壁竖直滑动连接有T型安装板(5),所述T型安装板(5)的前侧壁安装有气缸(8),所述气缸(8)的伸缩端端部安装有第二驱动电机(9),所述第二驱动电机(9)的输出端固定连接有承载板(10),所述承载板(10)上对称设有两组对钢模板进行固定的夹持组件,两组所述夹持组件均由第一伺服电机(15)驱动。1. A combined steel formwork installation device, comprising a base (1), characterized in that a plurality of locking universal wheels (2) are installed at the bottom of the base (1), a vertical rod (3) is rotatably connected to the base (1), the vertical rod (3) is driven by a first drive motor (4) installed at the bottom of the base (1), a front side wall of the vertical rod (3) is vertically slidably connected to a T-shaped mounting plate (5), a cylinder (8) is installed on the front side wall of the T-shaped mounting plate (5), a second drive motor (9) is installed at the telescopic end of the cylinder (8), an output end of the second drive motor (9) is fixedly connected to a bearing plate (10), two groups of clamping assemblies for fixing the steel formwork are symmetrically arranged on the bearing plate (10), and the two groups of clamping assemblies are driven by a first servo motor (15). 2.根据权利要求1所述的一种组合式钢模板安装装置,其特征在于,所述竖杆(3)的前侧壁开设有竖直滑槽,所述T型安装板(5)滑动连接在竖直滑槽内并与其相适配,所述竖直滑槽的内底部转动连接有螺纹杆(6),所述螺纹杆(6)螺纹贯穿T型安装板(5),所述螺纹杆(6)由安装在竖杆(3)上端的第二伺服电机(7)驱动。2. A combined steel formwork installation device according to claim 1, characterized in that a vertical slide groove is opened on the front side wall of the vertical rod (3), the T-shaped mounting plate (5) is slidably connected in the vertical slide groove and adapted thereto, and a threaded rod (6) is rotatably connected to the inner bottom of the vertical slide groove, the threaded rod (6) is threadedly passed through the T-shaped mounting plate (5), and the threaded rod (6) is driven by a second servo motor (7) installed at the upper end of the vertical rod (3). 3.根据权利要求1所述的一种组合式钢模板安装装置,其特征在于,所述T型安装板(5)的前侧壁对称固定连接有两个伸缩杆(11),所述承载板(10)的后侧壁开设有环形滑槽,两个所述伸缩杆(11)的伸缩端均延伸至环形滑槽内并与其滑动连接。3. A combined steel formwork installation device according to claim 1, characterized in that the front side wall of the T-shaped mounting plate (5) is symmetrically fixedly connected to two telescopic rods (11), and the rear side wall of the bearing plate (10) is provided with an annular groove, and the telescopic ends of the two telescopic rods (11) both extend into the annular groove and are slidably connected thereto. 4.根据权利要求1所述的一种组合式钢模板安装装置,其特征在于,所述夹持组件包括贯穿固定连接在承载板(10)上的插杆(12),所述插杆(12)上对称套设有两个与其滑动连接的夹持板(13),所述承载板(10)上贯穿转动连接有双头螺杆(14),所述双头螺杆(14)的两端分别螺纹贯穿两个夹持板(13)。4. A combined steel formwork installation device according to claim 1, characterized in that the clamping assembly includes an insertion rod (12) that is fixedly connected to a supporting plate (10), and two clamping plates (13) that are symmetrically sleeved on the insertion rod (12) and are slidably connected to the insertion rod (12), and a double-headed screw (14) is rotatably connected to the supporting plate (10), and both ends of the double-headed screw (14) are respectively threaded through the two clamping plates (13). 5.根据权利要求4所述的一种组合式钢模板安装装置,其特征在于,所述第一伺服电机(15)安装在承载板(10)的前侧壁,所述第一伺服电机(15)与两个双头螺杆(14)之间均绕设有传动带(16)。5. A combined steel formwork installation device according to claim 4, characterized in that the first servo motor (15) is installed on the front side wall of the bearing plate (10), and a transmission belt (16) is wound between the first servo motor (15) and the two double-headed screws (14). 6.根据权利要求4所述的一种组合式钢模板安装装置,其特征在于,所述插杆(12)的两端均固定连接有加固板,所述双头螺杆(14)与加固板转动连接。6. A combined steel formwork installation device according to claim 4, characterized in that both ends of the insertion rod (12) are fixedly connected to a reinforcement plate, and the double-headed screw (14) is rotatably connected to the reinforcement plate.
CN202322690419.1U 2023-10-08 2023-10-08 Combined steel template mounting device Active CN221143539U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322690419.1U CN221143539U (en) 2023-10-08 2023-10-08 Combined steel template mounting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322690419.1U CN221143539U (en) 2023-10-08 2023-10-08 Combined steel template mounting device

Publications (1)

Publication Number Publication Date
CN221143539U true CN221143539U (en) 2024-06-14

Family

ID=91390701

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322690419.1U Active CN221143539U (en) 2023-10-08 2023-10-08 Combined steel template mounting device

Country Status (1)

Country Link
CN (1) CN221143539U (en)

Similar Documents

Publication Publication Date Title
CN117231011A (en) Assembled building wallboard splicing construction device and construction method
CN221722398U (en) House building structure beam bottom reinforcing apparatus
CN220565705U (en) Support knot of post-cast strip template
CN221972941U (en) Adjustable mobile scaffolding for building construction
CN219857216U (en) Transfer device for constructional engineering steel structural member
CN218715445U (en) Girder support frame
CN210067434U (en) A kind of mould lifting system for building
CN220599179U (en) Frame post template reinforcing apparatus is built in room
CN222478130U (en) Shear wall template supporting structure
CN221837943U (en) Assembled building template
CN224078695U (en) Building engineering template fixing device
CN222140471U (en) Beam structure
CN217782830U (en) Concrete building template for civil engineering
CN223003813U (en) Movable supporting mechanism for repairing outer wall of ancient building
CN223689317U (en) A reinforcing component for building exterior wall formwork
CN217975334U (en) Steel pipe reinforcing apparatus
CN217417805U (en) Construction elevator well protective structure is built in room
CN223481654U (en) Large-scale steel structure bridge support that slides
CN223893781U (en) A type of wall formwork fixing bracket for building construction
CN221682420U (en) A scaffolding that is easy to disassemble and assemble
CN217079603U (en) Automatic assembly platform for assembly type steel structure
CN221461904U (en) A beam fixing structure
CN219219783U (en) A climbing frame for jacking up and overturning a towering thin-walled structure
CN222375996U (en) A template clamping device for building reinforcement
CN220814976U (en) High-rise shear wall column perpendicularity control device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20250911

Address after: 430000 Room G09, 2nd Floor, Unit 2, Building A4, Phase I, Zhoudafu (Wuhan) Jewelry Culture Industrial Park Project, Jianhua Village and Xinchun Village, Hengdian Street, Huangpi District, Wuhan City, Hubei Province

Patentee after: Wuhan qianyida Management Consulting Co.,Ltd.

Country or region after: China

Address before: No. 115, Dongsheng Road, Luohan Village, Luohansi Street, Huangpi District, Wuhan, Hubei 430000

Patentee before: Wuhan Chenqihan Road and Bridge Equipment Co.,Ltd.

Country or region before: China

TR01 Transfer of patent right

Effective date of registration: 20260730

Address after: No. 280, Bashanzhai Village, Lijiaji Street, Huangpi District, Wuhan City, 430000 Hubei Province

Patentee after: Hubei Moheng Steel Structure Co.,Ltd.

Country or region after: China

Address before: 430000 Room G09, 2nd Floor, Unit 2, Building A4, Phase I, Zhoudafu (Wuhan) Jewelry Culture Industrial Park Project, Jianhua Village and Xinchun Village, Hengdian Street, Huangpi District, Wuhan City, Hubei Province

Patentee before: Wuhan qianyida Management Consulting Co.,Ltd.

Country or region before: China