CN221052935U CN202321957828.7U CN202321957828U CN221052935U CN 221052935 U CN221052935 U CN 221052935U CN 202321957828 U CN202321957828 U CN 202321957828U CN 221052935 U CN221052935 U CN 221052935U
Authority
CN
China
Prior art keywords
aluminum alloy
upright post
shaped steel
building curtain
toughened glass
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321957828.7U
Other languages
Chinese (zh)
Inventor
连凯
陈萍娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Tanjian Construction Technology Group Co ltd
Original Assignee
Chuzhou Asus Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chuzhou Asus Construction Engineering Co ltd filed Critical Chuzhou Asus Construction Engineering Co ltd
Priority to CN202321957828.7U priority Critical patent/CN221052935U/en
Application granted granted Critical
Publication of CN221052935U publication Critical patent/CN221052935U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

The utility model belongs to the technical field of building curtain walls, in particular to a novel sound insulation building curtain wall, which comprises hollow toughened glass and a mounting mechanism arranged above the hollow toughened glass, wherein the mounting mechanism comprises a clamping assembly and a splicing assembly; the clamping assembly comprises an aluminum alloy cushion frame, an aluminum alloy upright post, a connecting block, a clamping groove, a thread groove and a bolt, wherein the aluminum alloy cushion frame is arranged in the middle of the hollow toughened glass, and the aluminum alloy upright post is arranged on the rear end face of the aluminum alloy cushion frame.

Description

Novel building curtain gives sound insulation
Technical Field
The utility model relates to the technical field of building curtain walls, in particular to a novel sound insulation building curtain wall.
Background
The building curtain wall is a beautiful and novel building wall decoration method, and the sound insulation building curtain wall is one of the building curtain walls, and can play a certain sound insulation effect.
But current building curtain adopts simple glass panels to splice when carrying out the concatenation equipment for there is the edge gap, leads to the sound insulation effect not strong, and when carrying out the concatenation simultaneously, it is inconvenient to lead to the installation concatenation because the weight that glass self produced, consequently, proposes a novel sound insulation building curtain to above-mentioned problem.
Disclosure of utility model
In order to make up the defects in the prior art, the novel sound insulation building curtain wall is provided by the utility model, which solves the problems that when the building curtain wall is spliced and assembled, a simple glass panel is adopted to splice, so that edge gaps exist, the sound insulation effect is not strong, and meanwhile, when the building curtain wall is spliced, the installation and the splicing are inconvenient due to the weight generated by glass.
The technical scheme adopted for solving the technical problems is as follows: the novel sound-insulation building curtain wall comprises hollow toughened glass and a mounting mechanism arranged above the hollow toughened glass, wherein the mounting mechanism comprises a clamping assembly and a splicing assembly;
The clamping assembly comprises an aluminum alloy cushion frame, an aluminum alloy upright post, a connecting block, a clamping groove, a thread groove and a bolt, wherein the aluminum alloy cushion frame is arranged in the middle of the hollow toughened glass, the aluminum alloy upright post is arranged on the rear end face of the aluminum alloy cushion frame, the connecting block is arranged above the aluminum alloy upright post, the clamping groove is formed in the aluminum alloy cushion frame, the thread groove is formed in the upper part of the aluminum alloy upright post, and the bolt is arranged in the clamping groove;
The splicing assembly comprises an H-shaped steel beam, a T-shaped steel upright post and a galvanized steel pipe, wherein the H-shaped steel beam is arranged below the hollow toughened glass, the T-shaped steel upright post is connected to the middle of the H-shaped steel beam, and the galvanized steel pipe is arranged on the front end face of the T-shaped steel upright post.
The middle part of the aluminum alloy cushion frame is provided with a foam rod, a through hole is formed in the lower part of the aluminum alloy upright post, a groove is formed in the H-shaped steel cross beam, and weather-resistant sealant is arranged on the left side of the aluminum alloy cushion frame.
Preferably, the aluminum alloy upright post forms a clamping structure with the aluminum alloy pad frame through the connecting block and the clamping groove, and the connecting block is tightly attached to the clamping groove.
Preferably, the aluminum alloy cushion frame is in threaded connection with the aluminum alloy upright post through bolts.
Preferably, the galvanized steel pipe forms a clamping structure sealing cover between the plug and the through hole and the aluminum alloy upright post, and the plug is provided with two groups.
Preferably, the foam rod is fixedly connected with the aluminum alloy cushion frame, and the Hou Mifeng-resistant adhesive is in fit connection with the aluminum alloy cushion frame.
Preferably, the hollow toughened glass forms a sliding structure with the H-shaped steel beam through the groove, and the hollow toughened glass is tightly attached to the H-shaped steel beam.
The utility model has the advantages that:
1. According to the utility model, the aluminum alloy upright posts and the aluminum alloy cushion frames are connected in a clamping way through the connecting blocks, so that when the aluminum alloy cushion frames are connected and assembled, simple fixation is formed, the working strength is reduced, the assembly and the splicing between the aluminum alloy cushion frames and the aluminum alloy upright posts can be conveniently carried out by workers, then, when the hollow toughened glass is installed on the outer surface of the aluminum alloy cushion frames, the sealing property is reinforced through weather-resistant sealing glue, and the sound insulation effect is improved;
2. According to the utility model, the plug is inserted into the through hole, the aluminum alloy upright post is inserted into the galvanized steel pipe, and then the plug is fixed, so that the connection condition can be ensured, the working intensity is lightened, the assembly efficiency is improved, the foam rod is filled in the curtain wall, the effects of preventing rainwater from leaking in and saving sealant can be achieved, the hollow toughened glass slides into the H-shaped steel beam through the groove, the bonding connection is realized, the force conduction of staff can be improved, and the convenience of installation is enhanced.
Drawings
In order to more clearly illustrate the embodiments of the utility model or the technical solutions of the prior art, the drawings which are used in the description of the embodiments or the prior art will be briefly described, it being obvious that the drawings in the description below are only some embodiments of the utility model, and that other drawings can be obtained from these drawings without inventive faculty for a person skilled in the art.
FIG. 1 is a schematic diagram of the overall structure of the present utility model;
FIG. 2 is a schematic view of an aluminum alloy pillar structure according to the present utility model;
Fig. 3 is a schematic view of the structure of the aluminum alloy cross beam of the utility model.
In the figure: 1. hollow toughened glass; 2. an aluminum alloy pad frame; 3. a foam rod; 4. an aluminum alloy upright post; 5. a connecting block; 6. a clamping groove; 7. a thread groove; 8. a bolt; 9. a through hole; 10. an H-shaped steel beam; 11. t-shaped steel upright posts; 12. galvanized steel pipe; 13. a plug; 14. a groove; 15. weather-resistant sealant.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Example 1
1-3, A novel sound insulation building curtain wall comprises hollow toughened glass 1 and a mounting mechanism arranged above the hollow toughened glass 1, wherein the mounting mechanism comprises a clamping assembly and a splicing assembly;
The clamping assembly comprises an aluminum alloy cushion frame 2, an aluminum alloy upright post 4, a connecting block 5, a clamping groove 6, a thread groove 7 and a bolt 8, wherein the aluminum alloy cushion frame 2 is arranged in the middle of the hollow toughened glass 1, the aluminum alloy upright post 4 is arranged on the rear end surface of the aluminum alloy cushion frame 2, the connecting block 5 is arranged above the aluminum alloy upright post 4, the clamping groove 6 is formed in the aluminum alloy cushion frame 2, the thread groove 7 is formed above the aluminum alloy upright post 4, and the bolt 8 is arranged in the clamping groove 6;
The splicing assembly comprises an H-shaped steel beam 10, a T-shaped steel upright 11 and a galvanized steel pipe 12, wherein the H-shaped steel beam 10 is arranged below the hollow toughened glass 1, the T-shaped steel upright 11 is connected to the middle of the H-shaped steel beam 10, and the galvanized steel pipe 12 is arranged on the front end face of the T-shaped steel upright 11.
Further, the aluminum alloy upright post 4 forms a clamping structure with the aluminum alloy pad frame 2 through the connecting block 5 and the clamping groove 6, and the connecting block 5 is tightly attached to the clamping groove 6, and the aluminum alloy upright post 4 and the aluminum alloy pad frame 2 are connected in a clamping manner through the connecting block 5, so that when the aluminum alloy upright post 4 is connected and assembled, the aluminum alloy pad frame is simply fixed, the working strength is reduced, and the aluminum alloy pad frame is convenient for workers to assemble.
Further, the aluminum alloy cushion frame 2 is in threaded connection with the aluminum alloy upright post 4 through the bolts 8, and the assembly and the splicing between the aluminum alloy cushion frame 2 and the aluminum alloy upright post 4 can be reinforced through the bolts 8, so that when the hollow toughened glass 1 is installed on the outer surface of the aluminum alloy cushion frame 2, the tightness is reinforced through the weather-resistant sealant 15, and the sound insulation effect is improved.
Further, the galvanized steel pipe 12 forms a clamping structure with the aluminum alloy upright post 4 through the plug 13 and the through hole 9, and the plug 13 is provided with two groups, the aluminum alloy upright post 4 is inserted into the galvanized steel pipe 12 through inserting the plug 13 into the through hole 9, and then the galvanized steel pipe is fixed through the plug 13, so that the connection condition can be ensured, the working strength is reduced, and the assembly efficiency is improved.
Example two
Referring to fig. 1 and 3, in a first comparative example, as another embodiment of the present utility model, a foam rod 3 is installed in the middle of an aluminum alloy cushion frame 2, a through hole 9,H is formed below an aluminum alloy upright 4, a groove 14 is formed inside a section steel beam 10, and a weather-resistant sealant 15 is disposed on the left side of the aluminum alloy cushion frame 2.
Further, foam rod 3 is fixed connection with aluminum alloy pad frame 2, and weather resistant sealant 15 is the laminating with aluminum alloy pad frame 2 and is connected, and foam rod 3 fills at the curtain, can play the effect that prevents that the rainwater from leaking into and province sealant.
Further, the hollow toughened glass 1 forms a sliding structure with the H-shaped steel beam 10 through the groove 14, and the hollow toughened glass 1 is tightly attached to the H-shaped steel beam 10, so that the hollow toughened glass 1 slides into the H-shaped steel beam 10 through the groove 14, attaching connection is realized, the force conduction of workers can be improved, and the convenience of installation is enhanced.
The working principle is that firstly, the aluminum alloy upright post 4 is attached to the aluminum alloy cushion frame 2, the threaded groove 7 is formed in the clamping groove 6, the aluminum alloy upright post 4 and the aluminum alloy cushion frame 2 are connected in a threaded mode through the bolts 8 and fixed, the fixing effect is improved, the foam rod 3 is installed inside the aluminum alloy cushion frame 2, sound insulation is improved, a good waterproof effect is achieved, gaps are filled through weather-resistant sealant 15, the sound insulation effect is improved, then the connecting block 5 is placed inside the clamping groove 6, the aluminum alloy upright post 4 and the aluminum alloy cushion frame 2 are fixed, then the hollow toughened glass 1 and the groove 14 formed in the H-shaped steel beam 10 are connected in a sliding mode, the plug 13 is inserted into the through hole 9, the aluminum alloy upright post 4 is inserted into the galvanized steel pipe 12 and connected with the H-shaped steel beam 10, and the plug 13 is fixed, so that the connection condition is guaranteed, the working strength is reduced, and the assembly efficiency is improved.
In the description of the present specification, the descriptions of the terms "one embodiment," "example," "specific example," and the like, mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the present utility model. In this specification, schematic representations of the above terms do not necessarily refer to the same embodiments or examples. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
The foregoing has shown and described the basic principles, principal features and advantages of the utility model. It will be understood by those skilled in the art that the present utility model is not limited to the embodiments described above, and that the above embodiments and descriptions are merely illustrative of the principles of the present utility model, and various changes and modifications may be made without departing from the spirit and scope of the utility model, which is defined in the appended claims.

Claims (7)

1. The utility model provides a novel building curtain gives sound insulation, includes cavity toughened glass (1) and sets up the installation mechanism in cavity toughened glass (1) top, its characterized in that: the mounting mechanism comprises a clamping assembly and a splicing assembly;
The clamping assembly comprises an aluminum alloy pad frame (2), an aluminum alloy upright post (4), a connecting block (5), a clamping groove (6), a thread groove (7) and a bolt (8), wherein the aluminum alloy pad frame (2) is arranged in the middle of the hollow toughened glass (1), the aluminum alloy upright post (4) is arranged on the rear end face of the aluminum alloy pad frame (2), the connecting block (5) is arranged above the aluminum alloy upright post (4), the clamping groove (6) is formed in the aluminum alloy pad frame (2), the thread groove (7) is formed in the upper portion of the aluminum alloy upright post (4), and the bolt (8) is arranged in the clamping groove (6);
The splicing assembly comprises an H-shaped steel beam (10), a T-shaped steel upright post (11) and a galvanized steel pipe (12), wherein the H-shaped steel beam (10) is arranged below the hollow toughened glass (1), the T-shaped steel upright post (11) is connected to the middle of the H-shaped steel beam (10), and the galvanized steel pipe (12) is arranged on the front end face of the T-shaped steel upright post (11).
2. A novel sound-insulating building curtain wall according to claim 1, wherein: the aluminum alloy cushion is characterized in that a foam rod (3) is arranged in the middle of the aluminum alloy cushion frame (2), a through hole (9) is formed in the lower portion of the aluminum alloy upright post (4), a groove (14) is formed in the H-shaped steel cross beam (10), and Hou Mifeng-resistant glue (15) is arranged on the left side of the aluminum alloy cushion frame (2).
3. A novel sound-insulating building curtain wall according to claim 1, wherein: the aluminum alloy upright post (4) forms a clamping structure with the aluminum alloy pad frame (2) through the connecting block (5) and the clamping groove (6), and the connecting block (5) is tightly attached to the clamping groove (6).
4. A novel sound-insulating building curtain wall according to claim 1, wherein: the aluminum alloy cushion frame (2) is in threaded connection with the aluminum alloy upright post (4) through a bolt (8).
5. A novel sound-insulating building curtain wall according to claim 1, wherein: the galvanized steel pipe (12) forms a clamping structure with the aluminum alloy upright post (4) through the plug (13) and the through hole (9), and the plug (13) is provided with two groups.
6. A novel sound-insulating building curtain wall according to claim 2, characterized in that: the foam rod (3) is fixedly connected with the aluminum alloy cushion frame (2), and the Hou Mifeng-resistant adhesive (15) is in fit connection with the aluminum alloy cushion frame (2).
7. A novel sound-insulating building curtain wall according to claim 2, characterized in that: the hollow toughened glass (1) forms a sliding structure with the H-shaped steel beam (10) through the groove (14), and the hollow toughened glass (1) is tightly attached to the H-shaped steel beam (10).
CN202321957828.7U 2023-07-25 2023-07-25 Novel building curtain gives sound insulation Active CN221052935U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321957828.7U CN221052935U (en) 2023-07-25 2023-07-25 Novel building curtain gives sound insulation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321957828.7U CN221052935U (en) 2023-07-25 2023-07-25 Novel building curtain gives sound insulation

Publications (1)

Publication Number Publication Date
CN221052935U true CN221052935U (en) 2024-05-31

Family

ID=91204726

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321957828.7U Active CN221052935U (en) 2023-07-25 2023-07-25 Novel building curtain gives sound insulation

Country Status (1)

Country Link
CN (1) CN221052935U (en)

Similar Documents

Publication Publication Date Title
KR101060059B1 (en) Unit multi-layer panel with home space frame
CN111749378A (en) A large-span glass rib supporting curtain wall system and its installation process
CN108331217B (en) Composite unit type curtain wall system
CN103104057B (en) Full-glass self-balance glass curtain wall
CN221052935U (en) Novel building curtain gives sound insulation
CN214195149U (en) Embedded unit curtain wall window easy to install and adjust
CN107605081B (en) Horizontal bright vertical hidden glass curtain wall
CN220644740U (en) Steel frame wall body assembly filled with heat-insulating mortar
CN217811802U (en) Glass curtain wall and metal roof connecting structure
CN107620414B (en) Vertical and horizontal hidden glass curtain wall
CN214886403U (en) Multipurpose frame for mounting door and window
CN101429843B (en) Indoor combined door frame
CN210395774U (en) Box type integral assembling building curtain wall
CN211143317U (en) Sunshine room
CN212078270U (en) Prestressed hollow slab
CN213926959U (en) Quick installing the system of curtain plate
CN214195086U (en) A flush-column one-side "T"-shaped connection assembly
CN213329604U (en) High-strength energy-saving hidden frame curtain wall
CN210342341U (en) Glass fiber reinforced plastic combined supporting clamp point type glass curtain wall
CN107675820B (en) Hidden curtain wall node structure
CN109881830B (en) Box type integrally assembled building curtain wall and assembling method thereof
CN222436169U (en) Theme decoration construction structure of bridge cut-off aluminum window
CN107724578B (en) Glass curtain wall with fully hidden frame
CN2296374Y (en) Wedge joint unit plate curtain wall
CN211287255U (en) Aluminum alloy outer window structure of glass-imitated curtain wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20240807

Address after: 201619 Room 302, 3 / F, building 2, 188 Zhenye Road, Dongjing Town, Songjiang District, Shanghai

Patentee after: Shanghai Tanjian Construction Technology Group Co.,Ltd.

Country or region after: China

Address before: Room 613, 6th floor, community entrepreneurship complex building, Langya Economic Development Zone, Langya District, Chuzhou City, Anhui Province 239000

Patentee before: Chuzhou ASUS Construction Engineering Co.,Ltd.

Country or region before: China

TR01 Transfer of patent right