CN220978490U - Double-layer ceramic brick curtain wall structure - Google Patents
Double-layer ceramic brick curtain wall structure Download PDFInfo
- Publication number
- CN220978490U CN220978490U CN202322639183.9U CN202322639183U CN220978490U CN 220978490 U CN220978490 U CN 220978490U CN 202322639183 U CN202322639183 U CN 202322639183U CN 220978490 U CN220978490 U CN 220978490U
- Authority
- CN
- China
- Prior art keywords
- layer
- curtain wall
- combined
- ceramic tile
- double
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000000919 ceramic Substances 0.000 title claims abstract description 68
- 239000011449 brick Substances 0.000 title claims abstract description 27
- 238000009434 installation Methods 0.000 claims abstract description 43
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 30
- 238000000926 separation method Methods 0.000 claims description 19
- 238000005728 strengthening Methods 0.000 claims description 14
- 238000010276 construction Methods 0.000 claims 3
- 238000000034 method Methods 0.000 claims 1
- 230000009286 beneficial effect Effects 0.000 abstract description 3
- 238000005192 partition Methods 0.000 description 11
- 230000000694 effects Effects 0.000 description 6
- 238000000638 solvent extraction Methods 0.000 description 3
- 239000004927 clay Substances 0.000 description 1
- 239000002131 composite material Substances 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 239000013067 intermediate product Substances 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
Landscapes
- Finishing Walls (AREA)
Abstract
The utility model discloses a double-layer ceramic brick curtain wall structure, relates to the technical field of double-layer ceramic brick curtain walls, and aims to solve the problems that an existing ceramic brick curtain wall is mainly installed in a keel mode, and the installation mode is high in installation and disassembly difficulty and is not beneficial to user assembly. Comprising the following steps: the ceramic brick curtain wall comprises a ceramic brick curtain wall body, wherein a curtain wall display layer is arranged at the front end of the ceramic brick curtain wall body, a combined installation layer is arranged at the rear end of the curtain wall display layer, and a supporting and reinforcing layer is arranged at the rear end of the combined installation layer; further comprises: the combined mounting plates are arranged on the outer wall of the rear end face of the combined mounting layer, a plurality of the combined mounting plates are arranged at intervals up and down, and a plurality of first through holes are formed in the outer wall of the combined mounting plate; the clamping slot is arranged in the supporting and reinforcing layer, the combined mounting plate is clamped with the clamping slot, a plurality of second through holes are formed in the outer wall of the groove, and mounting screws are arranged in the second through holes.
Description
Technical Field
The utility model relates to the technical field of double-layer ceramic brick curtain walls, in particular to a double-layer ceramic brick curtain wall structure.
Background
The curtain wall is an outer wall enclosure of a building, is not bearing, is hung like a curtain, is also called as a curtain wall, and is a light wall with a decorative effect commonly used in modern large-scale and high-rise buildings. The building outer protective structure or the decorative structure is composed of a panel and a supporting structure system, can have certain displacement capacity or certain deformation capacity relative to the main structure, and does not bear the action of the main structure; ceramic brick, which is one of clay bricks, is between Tao Tuzhuan and ceramic bricks, and belongs to intermediate products. The ceramic brick curtain wall is an outer curtain wall of a building taking ceramic bricks as outer facades for enclosing.
However, the existing ceramic tile curtain wall is mainly installed in a keel mode, and the installation mode is high in installation and disassembly difficulty, so that the assembly of a user is not facilitated; therefore, the existing requirements are not met, and a double-layer ceramic tile curtain wall structure is provided.
Disclosure of utility model
The utility model aims to provide a double-layer ceramic tile curtain wall structure, which aims to solve the problems that the existing ceramic tile curtain wall in the background technology is mainly installed in a keel mode, the installation mode is high in installation and disassembly difficulty, and the assembly of users is not facilitated.
In order to achieve the above purpose, the present utility model provides the following technical solutions: a double-layer ceramic tile curtain wall structure comprising: the ceramic brick curtain wall comprises a ceramic brick curtain wall body, wherein a curtain wall display layer is arranged at the front end of the ceramic brick curtain wall body, a combined installation layer is arranged at the rear end of the curtain wall display layer, and a supporting and reinforcing layer is arranged at the rear end of the combined installation layer;
Further comprises:
The combined mounting plates are arranged on the outer wall of the rear end face of the combined mounting layer, a plurality of the combined mounting plates are arranged at intervals up and down, and a plurality of first through holes are formed in the outer wall of the combined mounting plate;
And the clamping slot is arranged in the supporting and reinforcing layer, and the combined mounting plate is clamped with the clamping slot.
Preferably, the outer walls at the upper end and the lower end of the support reinforcing layer are respectively provided with a mounting groove, the outer walls of the mounting grooves are provided with a plurality of second through holes, the second through holes are internally provided with mounting screws, and the mounting screws penetrate through the first through holes and extend to the outside of the support reinforcing layer.
Preferably, a nut is arranged at the end of the installation screw, and a nut is arranged below the nut.
Preferably, the upper and lower both ends of curtain show layer all are provided with first separation baffle, the both sides of curtain show layer all are provided with the third separation baffle.
Preferably, a second separation baffle is arranged at the middle position of the curtain wall display layer, a first ceramic brick layer is arranged above the second separation baffle, and a second Tao Zhuanceng is arranged below the second separation baffle.
Preferably, a plurality of reinforcing ribs are arranged in the first ceramic tile layer, and one end of each reinforcing rib penetrates through the second separation baffle plate, the second Tao Zhuanceng and extends to the outer portion of the first separation baffle plate.
Compared with the prior art, the utility model has the beneficial effects that:
1. According to the ceramic tile curtain wall, the curtain wall display layer, the combined mounting layer and the support reinforcing layer are arranged, the combined mounting plate, the first through hole, the clamping slot, the second through hole and the mounting screw rod have the effect of facilitating the user to assemble the curtain wall, specifically, the combined mounting plate is aligned with the clamping slot, the combined mounting plate is inserted into the clamping slot, the combined mounting layer is combined with the support reinforcing layer, after clamping, the first through hole at the combined mounting plate is aligned with the second through hole at the mounting groove, the second through hole and the first through hole penetrate through the way of inserting the mounting screw rod, the combined mounting plate is limited in the clamping slot and cannot be separated, stability and firmness between the two are improved, the combined mounting plate and the support reinforcing layer are only required to be detached, and the ceramic tile curtain wall can be assembled more conveniently through the structure, so that the user is facilitated to carry out assembly operation.
2. Utilize the strengthening rib can improve the stability and the fastness of first ceramic tile layer to combine second Tao Zhuanceng, second partition baffle department through the strengthening rib, make whole curtain show layer department more stable firm, and the extension of strengthening rib department can extend to other ceramic tile curtain departments and make up, make whole ceramic tile curtain more stable firm, the accessible sets up horizontal strengthening rib and carries out horizontal combination certainly, and convenience of customers carries out curtain assembly operation.
Drawings
FIG. 1 is a schematic diagram of the overall structure of the present utility model;
FIG. 2 is a schematic view of a partial structure of a curtain wall display layer according to the present utility model;
FIG. 3 is a schematic view of a partial structure of a composite mounting layer according to the present utility model;
FIG. 4 is a schematic view of a partial structure of a support reinforcing layer according to the present utility model;
in the figure: 1. a ceramic brick curtain wall body; 2. curtain wall display layer; 3. combining the mounting layers; 4. supporting the reinforcing layer; 5. a first separation baffle; 6. a first ceramic tile layer; 7. a second separation baffle; 8. a third separation baffle; 9. a second ceramic tile layer; 10. reinforcing ribs; 11. a combined mounting plate; 12. a first through hole; 13. a clamping slot; 14. a mounting groove; 15. a second through hole; 16. a screw cap; 17. installing a screw; 18. and (3) a nut.
Description of the embodiments
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments.
Referring to fig. 1-4, an embodiment of the present utility model is provided: a double-layer ceramic tile curtain wall structure comprising: the ceramic tile curtain wall comprises a ceramic tile curtain wall body 1, wherein a curtain wall display layer 2 is arranged at the front end of the ceramic tile curtain wall body 1, a combined installation layer 3 is arranged at the rear end of the curtain wall display layer 2, and a supporting and reinforcing layer 4 is arranged at the rear end of the combined installation layer 3;
Further comprises:
The combined mounting plates 11 are mounted on the outer wall of the rear end face of the combined mounting layer 3, a plurality of combined mounting plates 11 are arranged at intervals up and down, and a plurality of first through holes 12 are formed in the outer wall of the combined mounting plate 11;
A locking slot 13 provided inside the support reinforcing layer 4, and the combined mounting plate 11 is locked with the locking slot 13;
The ceramic tile curtain wall is composed of the curtain wall display layer 2, the combined installation layer 3 and the support reinforcing layer 4, the combined installation plate 11, the first through hole 12, the clamping slot 13, the second through hole 15 and the installation screw 17 are convenient for a user to assemble the curtain wall, specifically, the combined installation plate 11 is aligned with the clamping slot 13, the combined installation plate 11 is inserted into the clamping slot 13, the combined installation layer 3 is combined with the support reinforcing layer 4, after clamping, the first through hole 12 at the combined installation plate 11 is aligned with the second through hole 15 at the installation groove 14, the combined installation plate 11 is limited in the clamping slot 13 in a mode of inserting the installation screw 17, stability and firmness between the two are improved, only the installation screw 17 is needed to be disassembled later, the combined installation plate 3 is separated from the support reinforcing layer 4, and the ceramic tile curtain wall can be assembled more conveniently by the structure, and the ceramic tile curtain wall is beneficial to the assembling operation of the user.
Referring to fig. 1 and 4, the outer walls of the upper and lower ends of the supporting and reinforcing layer 4 are respectively provided with a mounting groove 14, the outer walls of the mounting grooves 14 are provided with a plurality of second through holes 15, the second through holes 15 are internally provided with mounting screws 17, and the mounting screws 17 penetrate through the first through holes 12 and extend to the outside of the supporting and reinforcing layer 4;
the second through hole 15 is used for aligning with the first through hole 12 and is used for inserting the installation screw 17 to be combined, the installation groove 14 is used for installing the installation screw 17 and facilitating other components at the installation screw, and the concave embedding type is adopted, so that the screw end cannot protrude outside, the attractiveness is improved, and the assembly is facilitated.
Referring to fig. 1, a nut 16 is mounted at the end of a mounting screw 17, and a nut 18 is mounted below the nut 16;
The nut 16 and the nut 18 are used for limiting the end of the mounting screw 17, so that the mounting screw 17 cannot be separated after being inserted into the interior, and the stability and the firmness of the mounting screw 17 are improved.
Referring to fig. 2, the curtain wall display layer 2 is provided with a first separation baffle 5 at the upper and lower ends, and a third separation baffle 8 at both sides of the curtain wall display layer 2;
The first partition plate 5 has an effect of vertically partitioning, and the third partition plate 8 has an effect of horizontally partitioning.
Referring to fig. 2, a second partition baffle 7 is disposed at the middle position of the curtain wall display layer 2, a first ceramic brick layer 6 is disposed above the second partition baffle 7, and a second ceramic brick layer 9 is disposed below the second partition baffle 7;
The second partition plate 7 has an effect of partitioning the first ceramic tile layer 6 and the second ceramic tile layer 9 into upper and lower double layers.
Referring to fig. 2, a plurality of reinforcing ribs 10 are disposed inside the first ceramic tile layer 6, and one end of each reinforcing rib 10 penetrates through the second partition plate 7, the second ceramic tile layer 9 and extends to the outside of the first partition plate 5;
Utilize strengthening rib 10 can improve the stability and the fastness of first ceramic tile layer 6 to combine second ceramic tile layer 9, second partition baffle 7 department through strengthening rib 10, make whole curtain show layer 2 department more stable firm, and the extension of strengthening rib 10 department can extend to other ceramic tile curtain departments and make up, make whole ceramic tile curtain more stable firm, of course the horizontal combination of strengthening rib 10 of accessible setting, convenience of customers carries out curtain assembly operation.
Working principle: the ceramic tile curtain wall is formed by arranging the curtain wall display layer 2, the combined installation layer 3 and the support reinforcing layer 4, the combined installation plate 11, the first through hole 12, the clamping slot 13, the second through hole 15 and the installation screw 17 have the effect of facilitating the user to assemble the curtain wall, specifically, the combined installation plate 11 is aligned with the clamping slot 13, the combined installation plate 11 is inserted into the clamping slot 13, the combined installation layer 3 is combined with the support reinforcing layer 4, after clamping, the first through hole 12 at the combined installation plate 11 is aligned with the second through hole 15 at the installation groove 14, and then the combined installation plate 11 is limited in the clamping slot 13 in a mode of inserting the installation screw 17 to penetrate through the second through hole 15 and the first through hole 12, so that the stability and the firmness between the two are improved, and only the installation screw 17 is required to be disassembled later, and then the combined installation layer 3 is separated from the support reinforcing layer 4, so that the ceramic tile curtain wall can be assembled more conveniently by the structure, and the user is facilitated to assemble the ceramic tile curtain wall;
Utilize strengthening rib 10 can improve the stability and the fastness of first ceramic tile layer 6 to combine second ceramic tile layer 9, second partition baffle 7 department through strengthening rib 10, make whole curtain show layer 2 department more stable firm, and the extension of strengthening rib 10 department can extend to other ceramic tile curtain departments and make up, make whole ceramic tile curtain more stable firm, of course the horizontal combination of strengthening rib 10 of accessible setting, convenience of customers carries out curtain assembly operation.
It will be evident to those skilled in the art that the utility model is not limited to the details of the foregoing illustrative embodiments, and that the present utility model may be embodied in other specific forms without departing from the spirit or essential characteristics thereof. The present embodiments are, therefore, to be considered in all respects as illustrative and not restrictive, the scope of the utility model being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Claims (6)
1. The double-layer ceramic brick curtain wall structure comprises a ceramic brick curtain wall body (1), wherein a curtain wall display layer (2) is arranged at the front end of the ceramic brick curtain wall body (1), a combined installation layer (3) is arranged at the rear end of the curtain wall display layer (2), and a supporting and reinforcing layer (4) is arranged at the rear end of the combined installation layer (3);
The method is characterized in that: further comprises:
The combined mounting plates (11) are mounted on the outer wall of the rear end face of the combined mounting layer (3), a plurality of the combined mounting plates (11) are arranged at intervals up and down, and a plurality of first through holes (12) are formed in the outer wall of the combined mounting plates (11);
And the clamping slot (13) is arranged in the supporting and reinforcing layer (4), and the combined mounting plate (11) is clamped with the clamping slot (13).
2. A double-layer ceramic tile curtain wall construction according to claim 1, wherein: the outer walls at the upper end and the lower end of the support reinforcing layer (4) are respectively provided with a mounting groove (14), the outer walls of the mounting grooves (14) are provided with a plurality of second through holes (15), the second through holes (15) are internally provided with mounting screws (17), and the mounting screws (17) penetrate through the first through holes (12) and extend to the outside of the support reinforcing layer (4).
3. A double-layer ceramic tile curtain wall construction according to claim 2, wherein: a nut (16) is arranged at the end of the mounting screw (17), and a nut (18) is arranged below the nut (16).
4. A double-layer ceramic tile curtain wall construction according to claim 1, wherein: the curtain wall display layer (2) is characterized in that first separation baffles (5) are arranged at the upper end and the lower end of the curtain wall display layer (2), and third separation baffles (8) are arranged on two sides of the curtain wall display layer (2).
5. The double-layer ceramic tile curtain wall structure according to claim 4, wherein: the curtain wall display layer (2) is characterized in that a second separation baffle (7) is arranged at the middle position of the curtain wall display layer (2), a first ceramic brick layer (6) is arranged above the second separation baffle (7), and a second ceramic brick layer (9) is arranged below the second separation baffle (7).
6. The double-layer ceramic tile curtain wall structure according to claim 5, wherein: the inside of first ceramic tile layer (6) is provided with a plurality of strengthening ribs (10), and the one end of strengthening rib (10) runs through second separation baffle (7), second ceramic tile layer (9) and extends to the outside of first separation baffle (5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322639183.9U CN220978490U (en) | 2023-09-27 | 2023-09-27 | Double-layer ceramic brick curtain wall structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322639183.9U CN220978490U (en) | 2023-09-27 | 2023-09-27 | Double-layer ceramic brick curtain wall structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN220978490U true CN220978490U (en) | 2024-05-17 |
Family
ID=91059835
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202322639183.9U Active CN220978490U (en) | 2023-09-27 | 2023-09-27 | Double-layer ceramic brick curtain wall structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN220978490U (en) |
-
2023
- 2023-09-27 CN CN202322639183.9U patent/CN220978490U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210622042U (en) | Energy-saving and heat-insulating wall unit type curtain wall structure between windows | |
CN220978490U (en) | Double-layer ceramic brick curtain wall structure | |
CN214994645U (en) | Energy-saving heat-insulating light steel assembled house | |
CN111441516B (en) | An energy-saving curtain wall | |
CN209760673U (en) | Decorative panel mounting structure convenient to dismouting | |
CN219863550U (en) | Building decoration curtain wall | |
CN218714135U (en) | Architectural decoration curtain wall with heat preservation structure | |
CN214329566U (en) | Prefabricated curtain wall | |
CN222576467U (en) | Quick-mounting aluminum alloy window frame | |
CN217592407U (en) | Sofa with rapid disassembly structure | |
CN220848110U (en) | Building green energy-saving outer wall structure | |
CN219327217U (en) | Heat preservation curtain wall assembly structure | |
CN217439406U (en) | Rock wool sound absorption wallboard convenient to replace | |
CN222526110U (en) | A fixed-strip broken bridge aluminum alloy window structure | |
CN219158083U (en) | Mounting structure of large-specification metal bridge cut-off heat insulation sandwich board | |
CN222632613U (en) | Heat preservation and insulation curtain wall for building | |
CN222701289U (en) | Frame type building curtain wall | |
CN219138074U (en) | Novel installation structure of bridge cut-off heat insulation sandwich board | |
CN219365237U (en) | Thermal insulation type decorative wallboard | |
CN220266942U (en) | Curtain wall aluminum veneer splicing structure | |
CN219080689U (en) | Green energy-saving building curtain wall convenient to installation and adjustment | |
CN218933531U (en) | Frame construction for multifunctional door and window curtain wall | |
CN210117823U (en) | Passive house environmental protection and energy saving wall body | |
CN220908982U (en) | Wall combination formula assembly structure | |
CN222314339U (en) | Windproof assembled building curtain wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |