CN220279566U - Electric hammer support and suspender drilling equipment that can fix a position - Google Patents
Electric hammer support and suspender drilling equipment that can fix a position Download PDFInfo
- Publication number
- CN220279566U CN220279566U CN202322356109.6U CN202322356109U CN220279566U CN 220279566 U CN220279566 U CN 220279566U CN 202322356109 U CN202322356109 U CN 202322356109U CN 220279566 U CN220279566 U CN 220279566U
- Authority
- CN
- China
- Prior art keywords
- electric hammer
- lifting
- limiter
- bracket
- base
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Drilling And Boring (AREA)
Abstract
Description
技术领域Technical field
本实用新型涉及建筑技术领域,尤其涉及一种可定位的电锤支架及吊杆钻孔装置。The utility model relates to the field of construction technology, and in particular to a positionable electric hammer bracket and boom drilling device.
背景技术Background technique
随着建筑装修要求和建筑空间功能需求的不断提高,房屋装修吊顶要求越来越高。对于层高比较高的建筑,吊杆钻孔常规做法需搭设操作架,验收合格后才能使用,过程中工人需站在操作架上进行吊杆钻孔,操作架占地面积大,对于狭小空间无法使用,使用过程中移动不方便,因此施工效率低且存在安全隐患。With the continuous improvement of building decoration requirements and building space functional requirements, the requirements for house decoration ceilings are getting higher and higher. For buildings with relatively high floor heights, the conventional method of drilling booms requires setting up an operating frame, which can only be used after passing the inspection. During the process, workers need to stand on the operating frame to drill the hanging rod. The operating frame occupies a large area and is difficult to use in a small space. It cannot be used and is inconvenient to move during use, so the construction efficiency is low and there are safety hazards.
现有的施工中,通常将电锤安装在可升降的支架上,通过支架的升降带动电锤上下移动进行吊杆钻孔,但在钻进过程中,电锤随着支架在竖直方向上移动,支架升降行程容易控制不准,进而导致钻孔太浅,不能满足安装需求,或钻孔太深,破坏结构板,上述情况均会影响施工进度。In existing construction, the electric hammer is usually installed on a lifting bracket. The lifting of the bracket drives the electric hammer to move up and down to drill the boom. However, during the drilling process, the electric hammer moves vertically with the bracket. Movement, the lifting stroke of the bracket is easily controlled inaccurately, which leads to the drilling being too shallow to meet the installation requirements, or the drilling being too deep, damaging the structural plate. All of the above situations will affect the construction progress.
实用新型内容Utility model content
为了解决上述问题,一方面,本实用新型提供了一种可定位的电锤支架,包括底座以及设置在底座上的升降支架,还包括用于安装电锤的安装座,所述安装座可拆卸连接在所述升降支架上,所述安装座上设有限位器,所述限位器活动设置在所述安装座上并且配置有用于驱动其相对于安装座升降的调节机构,所述限位器的升降行程满足:限位器顶端与所述安装座上所限定的电锤钻头顶端之间的高度差范围覆盖最大设计钻孔深度与最小设计钻孔深度。In order to solve the above problems, on the one hand, the utility model provides a positionable electric hammer bracket, which includes a base and a lifting bracket arranged on the base, and also includes a mounting base for installing the electric hammer, and the mounting base is detachable. Connected to the lifting bracket, a limiter is provided on the mounting base. The limiter is movably provided on the mounting base and is configured with an adjustment mechanism for driving it to rise and fall relative to the mounting base. The limiter The lifting stroke of the device satisfies: the height difference range between the top of the limiter and the top of the electric hammer drill bit defined on the mounting base covers the maximum design drilling depth and the minimum design drilling depth.
进一步地,所述调节机构包括安装架和第一紧固件,所述安装架设置在所述安装座上,所述限位器通过第一紧固件连接在所述安装架上。Further, the adjustment mechanism includes a mounting bracket and a first fastener. The mounting bracket is provided on the mounting base, and the limiter is connected to the mounting bracket through a first fastener.
进一步地,所述安装架上设有可供所述限位器穿过的通孔,所述第一紧固件与所述安装架螺纹连接且抵接在所述限位器上。Further, the mounting bracket is provided with a through hole through which the stopper can pass, and the first fastener is threadedly connected to the mounting bracket and abuts on the stopper.
进一步地,所述安装座上设有刻度标识。Further, the mounting base is provided with scale marks.
进一步地,还包括加固结构,所述加固结构包括加固板以及多个可收缩的斜撑杆,所述加固板连接在所述升降支架上,所述斜撑杆铰接在所述加固板上,多个所述斜撑杆沿升降支架周向均匀布设。Further, it also includes a reinforcement structure, the reinforcement structure includes a reinforcement plate and a plurality of retractable diagonal braces, the reinforcement plate is connected to the lifting bracket, and the diagonal braces are hinged to the reinforcement plate, A plurality of the diagonal support rods are evenly arranged along the circumferential direction of the lifting bracket.
进一步地,所述安装座与所述升降支架螺纹连接。Further, the mounting base is threadedly connected to the lifting bracket.
进一步地,所述升降支架包括下支架、上支架、连接杆以及升降摇柄,所述下支架与所述底座连接,所述连接杆的下端插入所述下支架内,所述上支架连接在所述连接杆的上端,所述升降摇柄设置在所述下支架上,所述升降摇柄和所述连接杆之间升降链条。Further, the lifting bracket includes a lower bracket, an upper bracket, a connecting rod and a lifting rocker. The lower bracket is connected to the base, the lower end of the connecting rod is inserted into the lower bracket, and the upper bracket is connected to the lower bracket. At the upper end of the connecting rod, the lifting crank is arranged on the lower bracket, and a chain is lifted between the lifting crank and the connecting rod.
进一步地,所述下支架与所述底座为一体成型结构。Further, the lower bracket and the base are an integrally formed structure.
进一步地,所述底座上连接有可锁定的行走机构。Further, a lockable traveling mechanism is connected to the base.
另一方面,本实用新型还提供了一种吊杆钻孔装置,包括电锤和支架,所述电锤设置在所述支架上,所述支架为上述所述的可定位的电锤支架。On the other hand, the utility model also provides a boom drilling device, which includes an electric hammer and a bracket. The electric hammer is arranged on the bracket, and the bracket is the above-mentioned positionable electric hammer bracket.
本实用新型由于采用以上技术方案,使之与现有技术相比,具有以下有益效果:Due to the adoption of the above technical solutions, the utility model has the following beneficial effects compared with the existing technology:
1)本实用新型提供的可定位的电锤支架,占地面积小,使用方便,成本低,在安装座上设置可调高度的限位器,限位器的升降行程覆盖最大设计钻孔深度与最小设计钻孔深度,钻孔前根据需要钻进尺寸调整限位器高度,能有效控制钻孔深度在设定深度内,且不破坏待加工件;1) The positionable electric hammer bracket provided by this utility model occupies a small area, is easy to use, and has low cost. A height-adjustable stopper is set on the mounting base, and the lifting stroke of the stopper covers the maximum designed drilling depth. With the minimum designed drilling depth, the height of the stopper is adjusted according to the required drilling size before drilling, which can effectively control the drilling depth within the set depth without damaging the workpiece to be processed;
2)本实用新型提供的可定位的电锤支架,安装座与升降支架螺纹连接,保证安装座与升降支架的整体稳定性,且便于根据电锤型号更换不同型号的安装座,适用性强;2) For the positionable electric hammer bracket provided by this utility model, the mounting base and the lifting bracket are threadedly connected to ensure the overall stability of the mounting base and the lifting bracket, and it is easy to replace different types of mounting bases according to the electric hammer model, and has strong applicability;
3)本实用新型提供的可定位的电锤支架,底座连接有行走机构,便于支架在各方向上自由移动,提高施工效率,底座可增加支架整体稳定性,大大降低安全隐患;3) The positionable electric hammer support provided by this utility model has a walking mechanism connected to the base, which facilitates the free movement of the support in all directions and improves construction efficiency. The base can increase the overall stability of the support and greatly reduce safety hazards;
4)本实用新型提供的可定位的电锤支架,下支架与底座为一体成型结构,使得支架下部的结构更加稳定,提高支架的可靠性。4) In the positionable electric hammer bracket provided by this utility model, the lower bracket and the base are integrally formed, making the structure of the lower part of the bracket more stable and improving the reliability of the bracket.
附图说明Description of drawings
为了更清楚地说明本实用新型实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本实用新型的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其它的附图。In order to explain the embodiments of the present invention or the technical solutions in the prior art more clearly, the drawings needed to be used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings in the following description These are only some embodiments of the present invention. For those of ordinary skill in the art, other drawings can be obtained based on these drawings without exerting creative efforts.
图1为本实用新型提供的可定位的电锤支架的结构示意图;Figure 1 is a schematic structural diagram of the positionable electric hammer bracket provided by the utility model;
图2为本实用新型提供的可定位的电锤支架中限位器的结构示意图;Figure 2 is a schematic structural diagram of the stopper in the positionable electric hammer bracket provided by the utility model;
图3为本实用新型提供的可定位的电锤支架中升降支架的结构示意图;Figure 3 is a schematic structural diagram of the lifting bracket in the positionable electric hammer bracket provided by the utility model;
1-底座;2-电锤;3-安装座;4-限位器;5-安装架;6-第一紧固件;7-固定件;8-下支架;9-上支架;10-连接杆;11-升降摇柄;12-升降链条;13-第二紧固件;14-滑轮;15-锁定件;16-加固板;17-斜撑杆。1-base; 2-electric hammer; 3-mounting seat; 4-limiter; 5-mounting bracket; 6-first fastener; 7-fixing piece; 8-lower bracket; 9-upper bracket; 10- Connecting rod; 11-lifting rocker; 12-lifting chain; 13-second fastener; 14-pulley; 15-locking piece; 16-reinforcement plate; 17-oblique brace.
具体实施方式Detailed ways
下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例,基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。附图中,为清晰可见,可能放大了某部分的尺寸及相对尺寸。The technical solutions in the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model. Obviously, the described embodiments are only part of the embodiments of the present utility model, not all implementations. For example, based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative efforts fall within the scope of protection of the present utility model. In the drawings, the size and relative sizes of certain parts may be exaggerated for clarity of view.
在本实用新型的描述中,除非另有明确的规定和限定,术语“连接”、“相连”应做广义解释,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是电连接;可以是直接连接,也可以通过中间媒介间接连接,可以是两个元件内部的连通或两个元件的相互作用关系,对于本领域的普通的技术人员而言,可以具体情况理解上述术语在本实用新型中的具体含义。In the description of the present utility model, unless otherwise explicitly stipulated and limited, the terms "connection" and "connection" should be interpreted in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integration; it can be The mechanical connection may also be an electrical connection; it may be a direct connection or an indirect connection through an intermediary; it may be an internal connection between two elements or an interactive relationship between two elements. For those of ordinary skill in the field, The specific meanings of the above terms in the present invention can be understood in specific situations.
在本实用新型的描述中,术语“上”、“下”、“左”、“右”、“前”、“后”、“中心”、“水平”、“竖直”、“顶”、“底”、“内”、“外”等方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述和简化操作,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本实用新型的限制。In the description of the present utility model, the terms "upper", "lower", "left", "right", "front", "back", "center", "horizontal", "vertical", "top", The orientations or positional relationships of "bottom", "inner", "outer", etc. are based on the orientations or positional relationships shown in the drawings. They are only for the convenience of description and simplified operation, and do not indicate or imply that the device or component referred to must have Specific orientations, construction and operation in specific orientations should not be construed as limitations of the present invention.
此外,在本实用新型的描述中,术语“第一”、“第二”仅仅用于在描述上加以区分,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。此外,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征。In addition, in the description of the present invention, the terms "first" and "second" are only used to make a distinction in the description, and cannot be understood as indicating or implying the relative importance or implicitly indicating the number of indicated technical features. . In addition, features defined as “first” and “second” may explicitly or implicitly include one or more of these features.
实施例1Example 1
如说明书附图1-3所示,本实用新型提供了一种可定位的电锤支架,包括底座1以及设置在底座1上的升降支架,还包括用于安装电锤2的安装座3,所述安装座3可拆卸连接在所述升降支架上,所述安装座3上设有限位器4,所述限位器4活动设置在所述安装座3上并且配置有用于驱动其相对于安装座3升降的调节机构,所述限位器4的升降行程满足:限位器4顶端与所述安装座3上所限定的电锤2钻头顶端之间的高度差范围覆盖最大设计钻孔深度与最小设计钻孔深度。As shown in Figures 1-3 of the description, the utility model provides a positionable electric hammer bracket, which includes a base 1 and a lifting bracket provided on the base 1, and also includes a mounting base 3 for installing the electric hammer 2. The mounting base 3 is detachably connected to the lifting bracket. A limiter 4 is provided on the mounting base 3. The limiter 4 is movably provided on the mounting base 3 and is configured to drive it relative to the lifting bracket. The adjustment mechanism for lifting the mounting base 3. The lifting stroke of the limiter 4 satisfies the following requirements: the height difference range between the top of the limiter 4 and the top of the drill bit of the electric hammer 2 defined on the mounting base 3 covers the maximum designed drilling. Depth and minimum design drilling depth.
具体而言,所述安装座3为L型,电锤2通过螺栓固定在安装座3上,安装座3连接在升降支架上,升降支架可驱动安装座3上下移动,进而调节电锤2的高度,适用于吊顶、吊杆、天花板等高处作业钻孔使用;本实施例中,主要用于吊杆钻孔,则待加工件为吊杆,根据设计钻孔深度调整限位器4高度,限位器4顶端与电锤2的钻头顶端之间的高度差为实际钻孔深度,若限位器4顶端与电锤2的钻头顶端之间的高度差范围是h1-h2,最小设计钻孔深度是h3,最大设计钻孔深度是h4,则因满足h1≤h3,h2≥h4,可以满足不同的钻孔需求;在钻进过程中,限位器4逐渐向吊杆,待到达设计钻孔深度,限位器4抵靠在吊杆上,电锤2停止上升,完成钻孔,此时,实际钻孔深度为设定钻孔深度,在安装座3上设置限位器4,能有效控制钻孔深度在设定范围内,避免对吊杆造成破坏。Specifically, the mounting base 3 is L-shaped. The electric hammer 2 is fixed on the mounting base 3 through bolts. The mounting base 3 is connected to the lifting bracket. The lifting bracket can drive the mounting base 3 to move up and down, thereby adjusting the movement of the electric hammer 2. Height, suitable for drilling in suspended ceilings, booms, ceilings and other high places; in this embodiment, it is mainly used for boom drilling, and the workpiece to be processed is a boom. Adjust the height of the limiter 4 according to the designed drilling depth. , the height difference between the top of the limiter 4 and the top of the drill bit of the electric hammer 2 is the actual drilling depth. If the height difference between the top of the limiter 4 and the top of the drill bit of the electric hammer 2 ranges from h1 to h2, the minimum design The drilling depth is h3, and the maximum designed drilling depth is h4. Since h1 ≤ h3 and h2 ≥ h4 are satisfied, different drilling needs can be met; during the drilling process, the limiter 4 gradually moves toward the boom until it reaches Design the drilling depth, the limiter 4 is against the boom, the electric hammer 2 stops rising, and the drilling is completed. At this time, the actual drilling depth is the set drilling depth, and the limiter 4 is set on the mounting base 3 , can effectively control the drilling depth within the set range to avoid damage to the boom.
优选的,所述调节机构可以是手动调节机构或电动调节机构,限位器4采用电动调节,则可在安装座3上设置气缸、液压杆、电动模组等直线运动机构驱动限位器4调节高度,所述限位器4上还设置有高度传感器,用于测量限位器4与电锤2的钻杆顶端的距离,高度传感器与直线运动机构连接,根据设定钻孔深度,通过高度传感器来调控直线运动机构,使得限位器4移动至设定位置。Preferably, the adjustment mechanism can be a manual adjustment mechanism or an electric adjustment mechanism. If the limiter 4 is electrically adjusted, a linear motion mechanism such as a cylinder, a hydraulic rod, and an electric module can be installed on the mounting base 3 to drive the limiter 4 To adjust the height, the limiter 4 is also provided with a height sensor for measuring the distance between the limiter 4 and the top of the drill pipe of the electric hammer 2. The height sensor is connected to the linear motion mechanism. According to the set drilling depth, The height sensor controls the linear motion mechanism so that the limiter 4 moves to the set position.
作为实施方式之一,通常一个区域的吊杆钻孔深度一致,所以限位器4不需要多次调整,为降低成本,可采用手动调节方式进行调节。首先根据设计钻孔深度,调整所述限位器4高度,通过将限位器4顶部与混凝土结构板底之间的距离控制为设计钻孔深度一致,此时,电锤的钻杆与混凝土结构板底接触,电锤2与限位器4随着升降支架一同上升,实现控制钻孔深度在有效深度;所述调节机构包括安装架5和第一紧固件6,所述安装架5设置在所述安装座3上,所述限位器4通过第一紧固件6连接在所述安装架5上。As one of the embodiments, usually the drilling depth of the boom in an area is the same, so the limiter 4 does not need to be adjusted multiple times. In order to reduce costs, manual adjustment can be used. First, adjust the height of the limiter 4 according to the designed drilling depth, and control the distance between the top of the limiter 4 and the bottom of the concrete structural plate to be consistent with the designed drilling depth. At this time, the drill rod of the electric hammer is in contact with the concrete. The bottom of the structural plate is in contact, and the electric hammer 2 and the limiter 4 rise together with the lifting bracket to control the drilling depth at an effective depth; the adjustment mechanism includes a mounting bracket 5 and a first fastener 6. The mounting bracket 5 Set on the mounting base 3 , the limiter 4 is connected to the mounting frame 5 through a first fastener 6 .
优选的,所述安装架5上设有可供所述限位器4穿过的通孔,所述第一紧固件6与所述安装架5螺纹连接且抵接在所述限位器4上;所述第一紧固件优选蝴蝶耳螺栓,便于调节,限位器4采用具有一定承载力的硬质材料制作,通过蝴蝶耳螺栓和安装架5上面的预留孔进行有效连接固定,需要调整限位器4高度时,将蝴蝶耳螺栓松动,调整好既定高度后再将蝴蝶耳螺栓紧固,进行下一步操作。Preferably, the mounting bracket 5 is provided with a through hole through which the stopper 4 can pass, and the first fastener 6 is threadedly connected to the mounting bracket 5 and abuts against the stopper. 4; the first fastener is preferably a butterfly ear bolt, which is easy to adjust. The limiter 4 is made of a hard material with a certain bearing capacity, and is effectively connected and fixed through the butterfly ear bolt and the reserved hole on the mounting frame 5. , when it is necessary to adjust the height of the limiter 4, loosen the butterfly ear bolts. After adjusting the predetermined height, tighten the butterfly ear bolts and proceed to the next step.
优选的,所述安装座3上设有刻度标识,便于调节限位器4的高度,可根据刻度标识调节限位器4的高度。Preferably, the mounting base 3 is provided with a scale mark to facilitate the adjustment of the height of the stopper 4. The height of the stopper 4 can be adjusted according to the scale mark.
优选的,所述限位器4的上表面为平面结构,当限位器4抵接在待加工件上时,可以紧贴在待加工件上,避免对待加工件造成损伤。Preferably, the upper surface of the stopper 4 has a planar structure. When the stopper 4 is in contact with the workpiece to be processed, it can be closely attached to the workpiece to be processed, thereby avoiding damage to the workpiece to be processed.
优选的,所述安装座3与所述升降支架螺纹连接;所述安装座3和升降支架其中之一设置有外螺纹,另一个设置有与外螺纹相适配的内螺纹,所述安装座3与升降支架之间通过内外螺纹连接,连接牢固,且安装简单,便于根据不同型号的电锤更换适用的安装座;优选的,所述安装座3上设置有便于安装的固定件7,通过固定件7可以方便安装座3在升降支架上安装以及拆卸。Preferably, the mounting seat 3 is threadedly connected to the lifting bracket; one of the mounting seat 3 and the lifting bracket is provided with an external thread, and the other is provided with an internal thread that matches the external thread. 3 is connected to the lifting bracket through internal and external threads, the connection is firm, and the installation is simple, making it easy to replace the suitable mounting base according to different types of electric hammers; preferably, the mounting base 3 is provided with a fixing piece 7 for easy installation. The fixing part 7 can facilitate the installation and removal of the mounting base 3 on the lifting bracket.
优化实施方式,所述升降支架包括下支架8、上支架9、连接杆10以及升降摇柄11,所述下支架8与所述底座1连接,所述连接杆10的下端插入所述下支架8内,所述上支架9连接在所述连接杆10的上端,所述升降摇柄11设置在所述下支架9上,所述升降摇柄10和所述连接杆10之间升降链条12,上支架9通过第二紧固件13固接在连接杆10上,其中第二紧固件13优选蝴蝶耳螺栓,为提高上支架9与连接杆10的连接强度,所述上支架9和连接杆10之间通过多个蝴蝶耳螺栓进行固定;转动升降摇柄10,升降链条12带动连接杆10在竖直方向上移动,进而带动安装座3升降。In the optimized embodiment, the lifting bracket includes a lower bracket 8, an upper bracket 9, a connecting rod 10 and a lifting crank 11. The lower bracket 8 is connected to the base 1, and the lower end of the connecting rod 10 is inserted into the lower bracket. 8, the upper bracket 9 is connected to the upper end of the connecting rod 10, the lifting crank 11 is provided on the lower bracket 9, and a lifting chain 12 is between the lifting crank 10 and the connecting rod 10 , the upper bracket 9 is fixed on the connecting rod 10 through the second fastener 13, wherein the second fastener 13 is preferably a butterfly ear bolt. In order to improve the connection strength between the upper bracket 9 and the connecting rod 10, the upper bracket 9 and the connecting rod 10 are The connecting rods 10 are fixed by a plurality of butterfly ear bolts; when the lifting crank 10 is turned, the lifting chain 12 drives the connecting rod 10 to move in the vertical direction, thereby driving the mounting base 3 to lift.
优选的,所述下支架8与所述底座1为一体成型结构,底座1包括多个支撑架组成,具有很好的支撑效果,所述下支架8和底座1采用具有一定强度和刚度的材料支撑,如不锈钢等,保证在钻孔时能承受顶部传下来的反力。Preferably, the lower bracket 8 and the base 1 are of an integrated structure. The base 1 is composed of multiple support frames and has a good support effect. The lower bracket 8 and the base 1 are made of materials with a certain strength and rigidity. Supports, such as stainless steel, etc., ensure that they can withstand the reaction force from the top when drilling.
优选的,所述底座1上连接有可锁定的行走机构,具体的,底座1包括朝四个方向均匀分布的支撑架,每个支撑架的底部设置有一个滑轮14,便于所述支架移动,当然,可根据需求,增加底部滑轮14数量,能增强支架的整体稳定性和移动可操作性,所述滑轮14上设置有锁定件15,便于在使用时,将滑轮14固定,避免支架在反力作用下发生移动,影响使用。Preferably, the base 1 is connected to a lockable traveling mechanism. Specifically, the base 1 includes support frames evenly distributed in four directions. A pulley 14 is provided at the bottom of each support frame to facilitate the movement of the support. Of course, the number of bottom pulleys 14 can be increased according to needs, which can enhance the overall stability and mobile operability of the stand. The pulleys 14 are provided with locking pieces 15 to facilitate fixing the pulleys 14 during use to prevent the stand from being reversed. Movement occurs under the action of force, affecting use.
优选的,还包括加固结构,所述加固结构包括加固板16以及多个可收缩的斜撑杆17,所述加固板16连接在所述下支架8上,所述斜撑杆17铰接在所述加固板16上,可调节斜撑杆17与下支架8之间的角度,且斜撑杆可伸缩,可调节斜撑杆的长度,满足不同的支撑需求,各斜撑杆可独立调节,多个所述斜撑杆17沿下支架8周向均匀布设,斜撑杆17位于底座1的相邻的两个支撑架之间,可以多角度的加固支撑强度,在钻孔施工过程中,可展开斜撑杆,分别调节各斜撑杆至合适的角度,并调节斜撑杆至合适的长度,用于进一步支撑,提高电锤支架的支撑强度,提高钻孔稳定性。Preferably, it also includes a reinforcing structure, which includes a reinforcing plate 16 and a plurality of retractable diagonal struts 17. The reinforcing plate 16 is connected to the lower bracket 8, and the diagonal struts 17 are hinged there. On the reinforcement plate 16, the angle between the diagonal brace 17 and the lower bracket 8 can be adjusted, and the diagonal brace is telescopic and the length of the diagonal brace can be adjusted to meet different support requirements. Each diagonal brace can be adjusted independently. A plurality of the diagonal struts 17 are evenly distributed along the circumferential direction of the lower bracket 8. The diagonal struts 17 are located between two adjacent support frames of the base 1, which can reinforce the support strength at multiple angles. During the drilling construction process, The diagonal struts can be deployed, and each diagonal strut can be adjusted to the appropriate angle and length for further support, improving the support strength of the electric hammer bracket and improving drilling stability.
优选的,通过设置多个可调角度以及长度的斜撑杆17,也可满足非平地段使用,如可以在楼梯上使用,满足不同的使用需求。Preferably, by arranging a plurality of diagonal braces 17 with adjustable angles and lengths, it can also be used on non-flat areas, such as on stairs, to meet different usage needs.
具体的,所述斜撑杆17包括可套设的两根钢管,两根钢管之间通过螺栓固定,其中一个钢管的一端与加固板铰接,通过需求,调整两根钢管的连接位置以至合适的长度,满足支撑需求。Specifically, the diagonal brace 17 includes two steel pipes that can be sleeved. The two steel pipes are fixed by bolts. One end of one of the steel pipes is hinged with the reinforcing plate. According to the needs, the connection position of the two steel pipes can be adjusted to the appropriate position. Length to meet support needs.
实施例2Example 2
本实用新型还提供了一种吊杆钻孔装置,包括电锤2和支架,所述电锤2设置在所述支架上,所述支架为实施例1所述的可定位的电锤支架。The utility model also provides a boom drilling device, which includes an electric hammer 2 and a bracket. The electric hammer 2 is arranged on the bracket. The bracket is the positionable electric hammer bracket described in Embodiment 1.
将电锤2固定在安装座3上,并根据需要调整限位器4的高度,将支架移动至目标位置,通过升降摇柄10移动电锤2进行钻孔加工。Fix the electric hammer 2 on the mounting base 3, adjust the height of the stopper 4 as needed, move the bracket to the target position, and move the electric hammer 2 through the lifting handle 10 for drilling.
实际使用中,在钻孔过程中,需要激光水平仪配合使用,激光水平仪在吊杆定位后,将激光水平仪固定,可显示一排吊杆位置,沿显示的吊杆位置在吊杆上间隔钻孔。In actual use, during the drilling process, a laser level is required. After positioning the boom, fix the laser level to display a row of boom positions. Drill holes on the booms at intervals along the displayed boom positions. .
同时本说明书中未作详细描述的内容均属于本领域技术人员公知的现有技术。At the same time, contents not described in detail in this specification belong to the prior art known to those skilled in the art.
本技术领域的技术人员应理解,本实用新型可以以许多其他具体形式实现而不脱离本实用新型的精神和范围。尽管已描述了本实用新型的实施例,应理解本实用新型不应限制为此实施例,本技术领域的技术人员可如所附权利要求书界定的本实用新型精神和范围之内作出变化和修改。Those skilled in the art will understand that the present invention can be implemented in many other specific forms without departing from the spirit and scope of the present invention. Although the embodiments of the present invention have been described, it should be understood that the present invention should not be limited to these embodiments, and those skilled in the art can make changes and modifications within the spirit and scope of the present invention as defined by the appended claims. Revise.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202322356109.6U CN220279566U (en) | 2023-08-31 | 2023-08-31 | Electric hammer support and suspender drilling equipment that can fix a position |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202322356109.6U CN220279566U (en) | 2023-08-31 | 2023-08-31 | Electric hammer support and suspender drilling equipment that can fix a position |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN220279566U true CN220279566U (en) | 2024-01-02 |
Family
ID=89329799
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202322356109.6U Expired - Fee Related CN220279566U (en) | 2023-08-31 | 2023-08-31 | Electric hammer support and suspender drilling equipment that can fix a position |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN220279566U (en) |
-
2023
- 2023-08-31 CN CN202322356109.6U patent/CN220279566U/en not_active Expired - Fee Related
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP2013518785A (en) | Lifting device | |
| CN106276577B (en) | A kind of suspension bracket and operating method of framework isolated footing | |
| CN103669432B (en) | A kind of jacking device for deviation rectification of steel pylon in mining area of coal mine | |
| CN114182938B (en) | Section steel inclined column installation device and construction method thereof | |
| CN207377093U (en) | A kind of scaffold | |
| CN220279566U (en) | Electric hammer support and suspender drilling equipment that can fix a position | |
| CN205294666U (en) | Building material lifting device of precision measurement height | |
| CN212428134U (en) | Assembled wall body included angle adjusting device | |
| CN210559087U (en) | Adjustable punching jack | |
| CN219492189U (en) | Ladder stand | |
| CN218669217U (en) | Drilling machine device capable of being adjusted in lifting mode | |
| CN118621703A (en) | A steel beam positioning device for steel-concrete composite beam bridge | |
| CN218492725U (en) | Vertical butt joint adjusting device of steel construction | |
| CN207960496U (en) | Be easily installed drilling tool from hoisting type horizontal boring machine | |
| CN206616845U (en) | A kind of elevating scaffold corner device for erecting pole | |
| CN216476245U (en) | Outer frame column cantilever shaping operation platform | |
| CN213742360U (en) | Quick-setting cement grouting machine for maintaining buildings | |
| CN112096097B (en) | A steel column verticality adjustment device | |
| CN108532464A (en) | Three-dimensional adjusting method for bridge high pier climbing formwork | |
| CN212477444U (en) | A positioning device for cable-stayed bridge ends | |
| CN211010595U (en) | An adjustable support device | |
| CN116146095A (en) | ladder | |
| CN204019070U (en) | Derrick assembling combination steelframe | |
| CN203702471U (en) | Butting connection device, shifting mechanism and stopping mechanism for members of fan tower | |
| CN217054356U (en) | Regulator |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20240102 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |