CN220247540U - Mounting platform is demolishd to frame even wall spare is climbed to lift - Google Patents
Mounting platform is demolishd to frame even wall spare is climbed to lift Download PDFInfo
- Publication number
- CN220247540U CN220247540U CN202321766103.XU CN202321766103U CN220247540U CN 220247540 U CN220247540 U CN 220247540U CN 202321766103 U CN202321766103 U CN 202321766103U CN 220247540 U CN220247540 U CN 220247540U
- Authority
- CN
- China
- Prior art keywords
- cross bars
- mounting platform
- upright rod
- frame
- underframe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 36
- 239000010959 steel Substances 0.000 claims abstract description 36
- 230000009194 climbing Effects 0.000 claims abstract description 7
- 125000006850 spacer group Chemical group 0.000 claims description 2
- 238000010276 construction Methods 0.000 description 8
- 238000000034 method Methods 0.000 description 7
- 239000000463 material Substances 0.000 description 5
- 230000009286 beneficial effect Effects 0.000 description 3
- 230000005540 biological transmission Effects 0.000 description 3
- 238000009435 building construction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- Types And Forms Of Lifts (AREA)
Abstract
The utility model discloses a mounting platform for dismantling a wall connecting piece of a climbing frame of an elevator, which relates to the technical field of building industry machinery, and comprises the following specific structures: a chassis, the chassis comprising: the two support cross bars are arranged at intervals; at least one steel plate net sheet, two sides of which are welded on two supporting cross bars; the upright rod units are arranged in two rows and are arranged on the underframe at intervals, and each row of upright rod units consists of a plurality of upright rods which are arranged at intervals; at least three connecting cross bars, wherein two connecting cross bars are connected with the upright rod units in a one-to-one correspondence manner, and two ends of the remaining connecting cross bars are connected with the ends of the upright rod units; the connecting cross rod, the upright rod unit and the underframe are surrounded to form a frame-shaped structure with an upper opening and an opening at one end; and one end of the steel strand is connected with the upper end of the vertical rod unit, and the other end of the steel strand is connected with the underframe. The utility model solves the technical problem that the existing lift tower frame and the wall connecting piece are difficult to disassemble.
Description
Technical Field
The utility model relates to the technical field of building industry machinery, in particular to a mounting platform for dismantling a wall connecting piece of a climbing frame of an elevator.
Background
A construction elevator (for short, a construction elevator) is a construction machine in which a ladder cage moves up and down along a guide rail frame of the construction machine and people and materials are transported up and down by the ladder cage; the fixed vertical transportation machine is mainly used for high-rise and super high-rise building construction and is also used for other high-rise structure construction.
However, after the main engineering is completed, the elevator tower and the wall connecting piece are removed. When the building is dismantled, a person stands on the scaffold (reserved or backward-lapped), firstly, the wall attaching frame is dismantled, the connection between the wall attaching frame and the attaching rod and the connection between the wall attaching frame and the guide rail frame are lifted out, then the wall connecting attaching rod is dismantled, and finally the wall attaching ear seat at the building end is dismantled. However, in the dismantling process, if the construction elevator frame body is dismantled and attached first and the scaffold of the elevator receiving platform is reserved, the problem that the single scaffold is large in risk of being dismantled and the steel pipe material is difficult to transport exists. Meanwhile, under most conditions, the scaffold of the material receiving platform is disassembled before the construction elevator is disassembled. The personnel who installs and removes in the cage top when attaching the frame, owing to the distance is far away, can only be followed the inboard dismantlement of building side by the personnel of building and wear wall screw nut, will attach wall frame together with wear wall screw, ear seat, connecting rod, whole pull out of diagonal brace again, owing to the atress angle is unpaired, leads to rocking, having impact when taking off, and the danger is big.
Disclosure of Invention
The utility model aims to provide a mounting platform for dismantling a wall connecting piece of a climbing frame of an elevator, which solves the technical problem that the climbing frame and the wall connecting piece of the elevator are difficult to dismantle in the prior art.
The embodiment of the application discloses lift climbs frame and links wall spare to demolish mounting platform includes:
a chassis, the chassis comprising:
the two support cross bars are arranged at intervals;
at least one steel plate net sheet, two sides of which are welded on the two supporting cross bars;
the upright rod units are arranged in two rows and are arranged on the underframe at intervals, and each row of upright rod units consists of a plurality of upright rods which are arranged at intervals;
at least three connecting cross bars, wherein two connecting cross bars are connected with the upright rod units in a one-to-one correspondence manner, and two ends of the remaining connecting cross bars are connected with the end parts of the upright rod units; the connecting cross rod, the upright rod unit and the underframe are surrounded to form a frame-shaped structure with an upper opening and an opening at one end;
and one end of the steel strand is connected with the upper end of the vertical rod unit, and the other end of the steel strand is connected with the underframe.
According to the method, the relevant platform is additionally arranged, the relevant components are combined into the operation platform, and the safety of the dismantling of the wall connecting piece is improved.
Based on the above technical solution, the embodiment of the present application may further be modified as follows:
further, each row of upright rod units comprises at least three upright rods, and the stability can be ensured by the aid of the plurality of upright rods.
Further, the basket bolt is connected to the steel strand, and the stability of steel strand connection is guaranteed through the basket bolt.
Further, the front end and the rear end of the side face of the supporting cross rod are respectively provided with a lifting lug, the lifting lugs are connected with the end parts of the steel strands, and the beneficial effects of the step are that the connection of the related steel strands is facilitated through the lifting lugs.
Further, the steel stranded wires are two, and the two steel stranded wires are in inverted V-shaped distribution, and the beneficial effect of the method is that the method can realize load transmission through V-shaped design and ensure structural stability.
Further, the end part of the supporting cross rod is provided with a fastening bolt and a gasket, and the stability of connection is guaranteed through the fastening bolt.
Further, the gasket is at least 10mm, and the strength can be ensured by adopting the beneficial effects of the step.
Further, the number of the connecting cross bars is six, and the connecting cross bars are divided into an upper layer structure and a lower layer structure.
One or more technical solutions provided in the embodiments of the present application at least have the following technical effects or advantages:
1. the utility model provides a dismantling the mounting platform through installing at the lift top, but safe convenient dismantles building end attached ear seat, connecting rod device.
2. The utility model provides a make things convenient for inside and outside personnel of building to flow, can send the personnel to the interior eminence labour saving and time saving of building at random, improve demolishs efficiency greatly.
3. The utility model discloses an adopt string structure, realize the lightweight, have the dead weight light, advantage with low costs.
Drawings
In order to more clearly illustrate the embodiments of the present utility model or the technical solutions in the prior art, the drawings that are needed in the description of the embodiments or the prior art will be briefly described, and it is obvious that the drawings in the description below are some embodiments of the present utility model, and other drawings can be obtained according to the drawings without inventive effort for a person skilled in the art.
FIG. 1 is a schematic view of a construction of an elevator frame wall-mount removal mounting platform according to an embodiment of the present utility model;
FIG. 2 is a left side view of FIG. 1;
FIG. 3 is a schematic illustration of the use of FIG. 1;
specific reference numerals are as follows:
1-a chassis; 2-a pole setting unit; 3-connecting the cross bars; 4-steel strand wires; 5-a basket bolt;
101-supporting a cross bar; 102-lifting lugs; 103-fastening bolts; 104-a gasket; 105-steel plate meshes;
201-vertical rod.
Detailed Description
Embodiments of the technical scheme of the present utility model will be described in detail below with reference to the accompanying drawings. The following examples are only for more clearly illustrating the technical aspects of the present utility model, and thus are merely examples, and are not intended to limit the scope of the present utility model.
It is noted that unless otherwise indicated, technical or scientific terms used herein should be given the ordinary meaning as understood by one of ordinary skill in the art to which this utility model pertains.
In this application, unless specifically stated and limited otherwise, the terms "mounted," "connected," "secured," and the like are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally formed; may be a mechanical connection; can be directly connected or indirectly connected through an intermediate medium, and can be communicated with the inside of two elements or the interaction relationship of the two elements. The specific meaning of the above terms in the present utility model can be understood by those of ordinary skill in the art according to the specific circumstances.
In order to better understand the above technical solutions, the following detailed description will refer to the accompanying drawings and specific embodiments.
Examples:
as shown in fig. 1-2, the embodiment of the application discloses a mounting platform for dismantling a wall connecting piece of a climbing frame of an elevator, which is used for increasing the overall length, thereby facilitating the disassembly and assembly of the wall connecting piece and improving the safety of staff;
the concrete structure comprises:
the underframe 1 is arranged at the side edge of a manhole of an elevator cage of the elevator; the chassis 1 includes:
the two support cross bars 101 are arranged at intervals;
at least one steel plate mesh 105, two sides of which are welded on the two supporting cross bars 101, so that the cost can be reduced, and the safety and the overall strength can be improved by utilizing the steel plate mesh 105, and when in welding, the two sides of the steel plate mesh are directly welded on the supporting cross bars 101, so that the structural strength is ensured;
the upright rod units 2 are arranged in two rows, the upright rod units 2 are arranged on the underframe 1 at intervals, each row of upright rod units 2 consists of a plurality of upright rods 201 which are arranged at intervals, and the upright rods 201 can ensure the stability of the structure;
the connecting cross bars 3 are connected with the upright rod units 2 in a one-to-one correspondence manner, and two ends of the remaining connecting cross bars 3 are connected with the end parts of the upright rod units 2; the connecting cross rod 3, the upright rod unit 2 and the underframe 1 are surrounded to form a frame-shaped structure with an upper opening and an opening at one end, the frame-shaped structure is convenient for workers to stand, and meanwhile, the upright rod unit 2 can play a role similar to a guardrail, so that the safety is improved;
one end of the steel strand 4 is connected with the upper end of the vertical rod unit 2, and the other end of the steel strand 4 is connected with the underframe 1; the application is provided with steel strand wires 4, utilizes this steel strand wires to realize the transmission of power to be favorable to realizing the lightweight of structure.
In an embodiment, each row of said pole units 2 comprises at least three of said poles 201, whereby the lateral strength can be increased by a plurality of poles 201.
Specifically, the steel strand 4 is connected with a basket bolt 5, and locking can be completed by using the basket bolt 5, so that load transmission is realized.
In yet another embodiment, the front and rear ends of the side surface of the supporting cross bar 101 are respectively provided with a lifting lug 102, the lifting lugs 102 are connected with the ends of the steel strands 4, and the lifting lugs 102 are used for guaranteeing the stability of the steel strand connection.
The number of the steel strands 4 is two, and the two steel strands 4 are distributed in an inverted V shape, so that a support similar to a triangle can be formed, and the stability of the structure is ensured.
Wherein, the tip of supporting horizontal pole 101 is provided with fastening bolt 103 and gasket 104, utilizes fastening bolt 103 and gasket 104 to mutually support, can guarantee the stability of connection to this assurance this application can stable assembly.
Wherein the spacer 104 is at least 10mm, so that sufficient strength can be ensured.
The connecting cross bars 3 are six and are divided into an upper layer structure and a lower layer structure.
As shown in fig. 3, the problem that the traditional elevator even wall spare in-process of demolishing is far away, and the risk is big has been solved to this application, and wherein, chassis, pole setting unit and connection horizontal pole mutually support and make up into the platform frame to be provided with the steel sheet net piece on the chassis, guarantee that the staff can pass safely at the during operation.
The steel strands are arranged, so that the load of the front section can be transmitted to the rear, and the light weight of the structure is realized; this application is when in actual use, is fixed the support horizontal pole of this application to people's entrance to a cave edge on the elevator cage through fastening bolt.
In the description of the present utility model, numerous specific details are set forth. However, it is understood that embodiments of the utility model may be practiced without these specific details. In some instances, well-known methods, structures and techniques have not been shown in detail in order not to obscure an understanding of this description.
In the description of the present specification, a description referring to terms "one embodiment," "some embodiments," "examples," "specific examples," or "some examples," etc., means that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the present utility model. In this specification, schematic representations of the above terms are not necessarily directed to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples. Furthermore, the different embodiments or examples described in this specification and the features of the different embodiments or examples may be combined and combined by those skilled in the art without contradiction.
Finally, it should be noted that: the above embodiments are only for illustrating the technical solution of the present utility model, and not for limiting the same; although the utility model has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical scheme described in the foregoing embodiments can be modified or some or all of the technical features thereof can be replaced by equivalents; such modifications and substitutions do not depart from the spirit of the utility model, and are intended to be included within the scope of the appended claims and description.
Claims (8)
1. The utility model provides an elevator climbs frame and links wall piece to demolish mounting platform which characterized in that includes:
a chassis, the chassis comprising:
the two support cross bars are arranged at intervals;
at least one steel plate net sheet, two sides of which are welded on the two supporting cross bars;
the upright rod units are arranged in two rows and are arranged on the underframe at intervals, and each row of upright rod units consists of a plurality of upright rods which are arranged at intervals;
at least three connecting cross bars, wherein two connecting cross bars are connected with the upright rod units in a one-to-one correspondence manner, and two ends of the remaining connecting cross bars are connected with the end parts of the upright rod units; the connecting cross rod, the upright rod unit and the underframe are surrounded to form a frame-shaped structure with an upper opening and an opening at one end;
and one end of the steel strand is connected with the upper end of the vertical rod unit, and the other end of the steel strand is connected with the underframe.
2. The lift frame wall mount removal mounting platform of claim 1, wherein each row of said pole units includes at least three of said poles.
3. The lift frame wall attachment removal mounting platform of claim 1, wherein the steel strand is attached with a stud.
4. The lifting frame wall connecting piece dismantling and installing platform according to claim 3, wherein lifting lugs are respectively arranged at the front end and the rear end of the side face of the supporting cross rod, and the lifting lugs are connected with the end parts of the steel stranded wires.
5. The elevator climbing frame wall connecting member removal mounting platform according to claim 1, wherein the number of the steel strands is two, and the two steel strands are distributed in an inverted V shape.
6. The lift frame wall attachment removal mounting platform of claim 1, wherein the ends of the support rails are provided with fastening bolts and shims.
7. The lift cradle wall mount removal mounting platform of claim 6, wherein the spacer is at least 10mm.
8. The mounting platform for removing the wall connecting piece of the climbing frame of the lifter according to claim 1, wherein the number of the connecting cross bars is six, and the connecting cross bars are divided into an upper layer structure and a lower layer structure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202321766103.XU CN220247540U (en) | 2023-07-06 | 2023-07-06 | Mounting platform is demolishd to frame even wall spare is climbed to lift |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202321766103.XU CN220247540U (en) | 2023-07-06 | 2023-07-06 | Mounting platform is demolishd to frame even wall spare is climbed to lift |
Publications (1)
Publication Number | Publication Date |
---|---|
CN220247540U true CN220247540U (en) | 2023-12-26 |
Family
ID=89266181
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202321766103.XU Active CN220247540U (en) | 2023-07-06 | 2023-07-06 | Mounting platform is demolishd to frame even wall spare is climbed to lift |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN220247540U (en) |
-
2023
- 2023-07-06 CN CN202321766103.XU patent/CN220247540U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201598820U (en) | Single-point suspension external hanging rack | |
CN214195484U (en) | All-steel attached lifting scaffold | |
CN211736298U (en) | Double-rod diagonal cantilever scaffold | |
CN213234203U (en) | Disc buckle type upright column ladder cage scaffold | |
CN210798252U (en) | Assembled outer protection frame system | |
CN215887959U (en) | Hanging flower basket of encorbelmenting is used in aqueduct construction | |
CN202954552U (en) | Steel tube concrete column high-altitude construction safety protection system | |
CN103132702A (en) | Longspan pipe truss pulling bar lifting and overhead rotating emplacing construction method | |
CN220247540U (en) | Mounting platform is demolishd to frame even wall spare is climbed to lift | |
CN211173007U (en) | Novel tripod of encorbelmenting | |
CN104278830A (en) | Integrated combined scaffold | |
CN219280494U (en) | Tower beam temporary consolidation supporting structure for bridge tower stability control | |
CN209975993U (en) | Suspension cage | |
CN113404278B (en) | Self-climbing type protection frame and climbing method thereof | |
CN204212388U (en) | Monolithic combined scaffold | |
CN217323175U (en) | Auxiliary device for converting hoisting points of reinforcement cage of underground continuous wall | |
CN215564746U (en) | Assembled steel structure ladder cage | |
CN211644382U (en) | Tower crane attached stay bar walkway platform system | |
CN210316599U (en) | A curtain ring rail for roofing truss beam position | |
CN107217912A (en) | It is a kind of to be used for the superelevation physical isolation construction method of neighbouring high ferro Business Line construction | |
CN216110020U (en) | Small-diameter super-high-rise annular steel structure construction mechanism | |
CN111979916B (en) | Cable-stayed bridge tower part suspension construction method and suspension operation platform device | |
CN211286560U (en) | Spherical node suspension adjustable operation platform | |
CN217203935U (en) | Trash rack pier template hoisting device | |
CN219118718U (en) | Climbing frame horizontal protection |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |