CN220223211U - Concrete pipeline hoist and mount auxiliary device - Google Patents

Concrete pipeline hoist and mount auxiliary device Download PDF

Info

Publication number
CN220223211U
CN220223211U CN202321646474.4U CN202321646474U CN220223211U CN 220223211 U CN220223211 U CN 220223211U CN 202321646474 U CN202321646474 U CN 202321646474U CN 220223211 U CN220223211 U CN 220223211U
Authority
CN
China
Prior art keywords
pipeline
auxiliary device
concrete
hoisting
cross beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321646474.4U
Other languages
Chinese (zh)
Inventor
麻树超
张志刚
王京志
冯建波
赵伟
丁昌亮
董帅
齐乃田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Rizhao Municipal Fabricated Urban Facilities Co ltd
Original Assignee
Rizhao Municipal Fabricated Urban Facilities Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rizhao Municipal Fabricated Urban Facilities Co ltd filed Critical Rizhao Municipal Fabricated Urban Facilities Co ltd
Priority to CN202321646474.4U priority Critical patent/CN220223211U/en
Application granted granted Critical
Publication of CN220223211U publication Critical patent/CN220223211U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model relates to a concrete pipeline hoisting auxiliary device, which belongs to the field of municipal engineering in the building industry, and comprises a cross beam, wherein one end of the cross beam is fixedly connected with one side of an L-shaped rod, so that the cross beam and the L-shaped rod form a frame with an opening on one side, and a hoisting part is arranged at the top of the cross beam, so that the hoisting part can be hoisted by a crane. The pipeline installation construction efficiency is improved, the joint of the pipeline is tightly and smoothly connected, damage to cushion concrete and the pipeline is reduced, construction of follow-up procedures such as pipeline plastering is facilitated, the water seepage condition of the pipeline is greatly reduced, and the engineering construction quality is improved.

Description

Concrete pipeline hoist and mount auxiliary device
Technical Field
The technical scheme belongs to the field of municipal engineering in the building industry, and particularly relates to an auxiliary device for installing a reinforced concrete pipeline hanging pipe in municipal drainage pipeline construction.
Background
In the construction of current municipal drainage pipeline, when bell and spigot reinforced concrete pipeline installation, pipeline hoist and mount adopt wire rope to fix, because pipeline and pipeline interface need link up closely, wire rope can't pass from pipeline inner chamber position, can only follow the side, annular fastening hoist and mount.
Applicant has found that the following problems exist with the prior art in the implementation of the embodiments of the present application;
the flat joint pipeline is compact in fit between the pipelines after the pipeline is loaded, no gap exists, the steel wire rope cannot pass through in the circumferential direction during lifting, and only after a section of the pipeline is lifted by using the hook to generate a gap, the steel wire rope can pass through, so that the steel wire rope is difficult to fix in the circumferential direction during lifting, and the process is laborious. When the pipeline is placed, the balance of the pipeline is not well controlled, and an external force needs to be manually applied, so that the pipeline level is ensured. After the pipeline is placed, because no gap exists between the pipeline and the cushion layer, the steel wire rope is difficult to pull out, and the problem that the pipeline is easy to shift is solved when the steel wire rope is pulled out, so that when the pipeline is placed, the center of the pipeline is required to be measured due to the fact that the stress points of the annular steel wire rope and the pipeline are too small, the steel wire rope is located at the center of the pipeline, and the stress uniformity is ensured. Because of various factors such as pipeline density, the pipeline balance is not well controlled when the pipeline is lifted, and an external force is required to be manually applied when the pipeline is installed, so that the pipeline level is ensured, the working efficiency is low, and the pipeline displacement is easy to cause.
Disclosure of Invention
The utility model aims to solve the problems that the working efficiency is low and the pipeline is easy to shift in the prior art, and provides an auxiliary device for hoisting a concrete pipeline, so that the purposes of saving labor, improving the working efficiency and avoiding the pipeline shift after placement are achieved.
The utility model provides a concrete pipeline hoist and mount auxiliary device, includes the crossbeam, one end and the one side fixed connection of L shape pole of crossbeam make crossbeam and L shape pole enclose into a one side open-ended frame, the top of crossbeam is equipped with the portion of lifting by crane, makes it accessible crane with lifting by crane portion.
Furthermore, the included angle between the connecting edge of the cross beam and the L-shaped rod is 100-135 degrees, and the included angle can be adjusted by a person skilled in the art according to different pipe diameters, so that the lifted pipeline is parallel to the ground as much as possible.
Further, the angle between the short side and the long side of the L-shaped bar may be adjusted to be about 90 °, but preferably, the angle between the short side and the long side of the L-shaped bar is 90 ° and the effect is best.
Preferably, the included angle between the connecting edge of the beam and the L-shaped rod is 125 degrees, but if the cost of a corresponding auxiliary tool is excessively high, which is specially customized according to different pipe diameters, the inventor realizes that the concrete pipe has good hoisting effect on concrete pipes with most pipe diameters when the included angle between the beam and the connecting edge of the L-shaped rod is 125 degrees;
however, there are still some situations that the pipe after being lifted has an excessively large included angle with the ground, and the connection work cannot be completed well, so that further, a traction part is fixed at one end of the cross beam connected with the L-shaped rod.
Preferably, the traction part is a traction rope, a traction belt, a traction chain and other traction mechanisms, so that when the included angle between the lifted pipeline and the ground is too large, the traction part is pulled to slightly adjust the angle between the concrete pipeline and the ground.
Further, the cross beam is fixedly connected with the short side of the L-shaped rod, so that a better fixing effect is achieved.
Furthermore, the fixing connection mode is welding, in order to make the connection more firm, a connection fixing piece can be adopted, the connection fixing piece is arranged on the connection joint for welding, and preferably, the connection fixing piece is a square iron sheet.
Further, the function of the lifting part in the application is that a device which can be lifted by a crane by using the auxiliary device of the application can be a structure such as a lifting ring, a lifting rope and the like which can be lifted by a crane hook;
further, the lifting part comprises two fixing parts and rope-shaped connecting pieces, the two fixing parts are respectively fixed on two sides of the cross beam, and the two fixing parts are connected together by the rope-shaped connecting pieces.
Preferably, the fixing part is a fixing ring, and the rope-shaped connector is an iron chain.
Compared with the prior art, the utility model has the following outstanding beneficial effects:
1. when the pipeline lifting device is used for lifting the pipeline, the pipeline installation time can be reduced, the installation efficiency can be improved, the construction period can be shortened, and the pipeline installation is more convenient and quick. The pipeline installation construction efficiency is improved, the labor during pipeline installation is reduced, the waiting time of machines such as a crane and the like during pipeline hoisting is reduced, and the engineering cost is saved.
2. The joint of the pipeline is tightly and smoothly connected, so that the damage to cushion concrete and the pipeline is reduced, the construction of follow-up procedures such as pipeline plastering is facilitated, the water seepage condition of the pipeline is greatly reduced, and the engineering construction quality is improved. And the damage to the finished product caused by pipeline collision and the like is reduced.
3. The pipeline is stable and does not shake during hoisting, so that the safety is improved, and the safety of constructors is ensured.
Drawings
Fig. 1 is a schematic plan view of the present utility model.
Fig. 2 is a schematic elevational view of the present utility model.
In the figure: 1. the device comprises a cross beam, 2L-shaped rods, 3 fixing parts, 4 rope-shaped connecting pieces and 5 traction parts.
In order to more clearly illustrate the embodiments of the present utility model or the technical solutions in the prior art, the drawings that are needed in the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present utility model, and other drawings may be obtained according to these drawings without inventive effort for a person skilled in the art.
Detailed Description
In order to make the objects, technical solutions and advantages of the present utility model more apparent, the technical solutions of the present utility model will be described in detail below. It will be apparent that the described embodiments are only some, but not all, embodiments of the utility model. All other embodiments, based on the examples herein, which are within the scope of the utility model as defined by the claims, will be within the scope of the utility model as defined by the claims.
Embodiment 1. A concrete pipe hoist auxiliary device, including crossbeam 1, crossbeam 1 adopts 15cm, and wall thickness 5 mm's square steel, length is 1.2m, the one end of crossbeam 1 and one side fixed connection of L shape pole 2, the minor face of L shape pole 2 adopts 15cm 25cm, and wall thickness 5 mm's square steel, length is 0.5m, the long limit of L shape pole 2 adopts 15cm, wall thickness 5 mm's square steel, length is 1.5m, the minor face of L shape pole 2 passes through welded connection with the long limit, the one end of crossbeam 1 is welded with the minor face department of L shape pole 2, contained angle between crossbeam 1 and the L shape pole 2 is 125, contained angle between the minor face of L shape pole 2 and the long limit is 90, makes crossbeam 1 and L shape pole 2 enclose into a one side open frame, the top of crossbeam 1 is equipped with the hoisting part, makes its accessible with the part hoisting part, hoisting part includes the fixed part 3 and is connected in the annular 4 with the fixed part of fixed part 4, two fixed part 4 are fixed in the annular, the annular 4 is fixed part, the annular 4 is fixed part is fixed together.
Embodiment 2. This embodiment 2 is a further improvement on the basis of embodiment 1, and the improvement is that a traction part 5 is fixed at one end of the beam 1 connected with the L-shaped rod 2, the traction part 5 is a traction rope, and the traction rope can be fixed on a fixed ring at one end of the beam 1 connected with the L-shaped rod 2, so that when the included angle between the lifted pipeline and the ground is too large, the traction part 5 is pulled to slightly adjust the angle between the concrete pipeline and the ground.
In addition, the utility model also discloses the following technical scheme based on the embodiment:
the included angle between the connecting edges of the cross beam 1 and the L-shaped rod 2 is 100-135 degrees, and a person skilled in the art can adjust the included angle according to different pipe diameters, so that the lifted pipeline is parallel to the ground as much as possible.
The traction part 5 can also be a traction mechanism such as a traction belt and a traction chain, so that when the included angle between the lifted pipeline and the ground is overlarge, the traction part 5 is pulled to slightly adjust the angle between the concrete pipeline and the ground.
The hoisting unit of the present utility model is a device that allows the auxiliary device of the present utility model to be hoisted by a crane, and may be a structure such as a hoisting ring or a hoisting rope that can be hoisted by a crane hook.
The operation flow is as follows:
taking the device in embodiment 2 as an example, the auxiliary device for hoisting the pipeline is firstly hoisted by a crane through the hoisting part, then the crane is controlled to deeply penetrate into the concrete pipeline by the long side of the L-shaped rod 2 of the device, and then the auxiliary device for hoisting the pipeline is continuously hoisted so as to hoist the concrete pipeline, if the angle between the hoisted concrete pipeline and the ground is overlarge, the traction part 5 can be used for fine adjustment, so that the angle of the concrete pipeline meets the construction requirement.
It is noted that while the present utility model has been described in detail with respect to specific embodiments thereof, it will be apparent to those skilled in the art that various modifications can be made therein without departing from the spirit and scope thereof.

Claims (9)

1. The utility model provides a concrete pipeline hoist and mount auxiliary device, its characterized in that includes the crossbeam, one end and the one side fixed connection of L shape pole of crossbeam make crossbeam and L shape pole enclose into a one side open-ended frame, the top of crossbeam is equipped with the hoisting accessory, makes it accessible crane hoist the hoisting accessory.
2. A concrete pipe lifting auxiliary device according to claim 1, wherein the angle between the beam and the connecting edge of the L-shaped bar is 100 ° -135 °.
3. A concrete pipe lifting aid according to claim 2, wherein the angle between the beam and the connecting edge of the L-shaped bar is 125 °.
4. The auxiliary device for hoisting a concrete pipeline according to claim 1, wherein the cross beam is fixedly connected with the short side of the L-shaped rod.
5. The auxiliary device for hoisting concrete pipelines according to claim 1, wherein a traction part is fixed at one end of the cross beam connected with the L-shaped rod.
6. The concrete pipeline lifting auxiliary device according to claim 5, wherein the traction part is a traction rope.
7. A concrete pipeline lifting auxiliary device according to any one of claims 1-6, wherein the lifting part comprises two fixing parts and rope-shaped connecting pieces, the two fixing parts are respectively fixed on two sides of the cross beam, and the rope-shaped connecting pieces connect the two fixing parts together.
8. The auxiliary device for hoisting concrete pipelines according to claim 7, wherein the fixing part is a fixing ring, and the rope-shaped connecting piece is an iron chain.
9. A concrete pipe lifting aid according to claim 7, wherein the angle between the short side and the long side of the L-shaped bar is 90 °.
CN202321646474.4U 2023-06-27 2023-06-27 Concrete pipeline hoist and mount auxiliary device Active CN220223211U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321646474.4U CN220223211U (en) 2023-06-27 2023-06-27 Concrete pipeline hoist and mount auxiliary device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321646474.4U CN220223211U (en) 2023-06-27 2023-06-27 Concrete pipeline hoist and mount auxiliary device

Publications (1)

Publication Number Publication Date
CN220223211U true CN220223211U (en) 2023-12-22

Family

ID=89176037

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321646474.4U Active CN220223211U (en) 2023-06-27 2023-06-27 Concrete pipeline hoist and mount auxiliary device

Country Status (1)

Country Link
CN (1) CN220223211U (en)

Similar Documents

Publication Publication Date Title
CN204897151U (en) Transmission line tower integral hoisting specialized tool that acts as go -between
CN102102365B (en) Slurry protection wall bored pile concrete casting device
CN209815490U (en) Hoisting device for rotor magnetic pole in hydraulic generator pit
CN217838063U (en) Concrete pipeline hoists and uses fixture
CN213625576U (en) An underground continuous wall HDPE membrane combination lower frame device
CN208009909U (en) A kind of built with ribbed bricks wall construction reinforced bar guide device
CN212769673U (en) A hydraulic lifting device for construction engineering
CN222864417U (en) Socket-type pipe symmetrical traction docking structure system
CN216741509U (en) Installation device suitable for shaft pipeline
CN214574441U (en) Rain sewage pipeline installation device
CN223411618U (en) Cement pipe hoisting frame
CN220537304U (en) Hoisting device for stably hoisting prefabricated pipeline
CN220467306U (en) Device for hoisting concrete rain sewage pipe
CN217377060U (en) A vertical transport tool for building construction
CN218595881U (en) Tool convenient for hoisting round pipe culvert
CN211473085U (en) Vertical connecting rib and sleeve connecting structure of assembled shear wall
CN221644377U (en) Internal supporting lifting sling for prefabricated groove plate of drainage ditch
CN221644330U (en) A T-shaped box beam outer formwork hanger
CN219410715U (en) Auxiliary positioning device for horizontal support installation
CN222574044U (en) A large integrated high-altitude hoisting pre-storage platform for power plants
CN214789396U (en) Tooling for improving the qualification rate of concrete rainwater pipe installation
CN215364389U (en) Overhanging type steel overlength wall-attached device
CN212953887U (en) Tongue-and-groove concrete pipe hangs sectional fixture fast
CN221662395U (en) Auxiliary device convenient to concrete pipe steel reinforcement cage transport