CN220153585U - Construction is with reference pole - Google Patents

Construction is with reference pole Download PDF

Info

Publication number
CN220153585U
CN220153585U CN202321619081.4U CN202321619081U CN220153585U CN 220153585 U CN220153585 U CN 220153585U CN 202321619081 U CN202321619081 U CN 202321619081U CN 220153585 U CN220153585 U CN 220153585U
Authority
CN
China
Prior art keywords
measuring tube
arc
bottom box
rod
screw rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321619081.4U
Other languages
Chinese (zh)
Inventor
方呈祥
贾明莲
李文达
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liu Dianwen
Original Assignee
Anhui Youshun Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Youshun Construction Engineering Co ltd filed Critical Anhui Youshun Construction Engineering Co ltd
Priority to CN202321619081.4U priority Critical patent/CN220153585U/en
Application granted granted Critical
Publication of CN220153585U publication Critical patent/CN220153585U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • A Measuring Device Byusing Mechanical Method (AREA)

Abstract

本实用新型涉及标杆技术领域,具体为一种建设施工用标杆,包括:底箱,所述底箱的顶部中间处安装有测量管,所述底箱内设有提高稳定的固定机构,所述测量管的底部转动安装有丝杆,所述丝杆的外侧壁上方通过螺纹滑动安装有标杆,所述丝杆的底部贯穿在底箱内且与升降电机的输出端相连接,所述测量管的顶部设有减少外部灰尘杂质进入测量管内的挡灰机构。本实用新型通过丝杆和升降电机的设置,升降电机带动丝杆转动,使标杆升降,且标杆与测量管的内壁滑动连接,空隙较小,大大减少了灰尘通过空隙进入测量管的情况,同时当不需要延长长度时,通过弹簧的恢复力使弧形杆带动挡灰板挡住测量管的顶部,进一步的减少了灰尘进入测量管的情况。

The utility model relates to the technical field of benchmarks, specifically a benchmark for construction, which includes: a bottom box, a measuring tube is installed in the middle of the top of the bottom box, and a fixing mechanism for improving stability is provided in the bottom box. A screw rod is rotatably installed at the bottom of the measuring tube. A standard rod is installed on the outer side wall of the screw rod through thread sliding. The bottom of the screw rod penetrates through the bottom box and is connected to the output end of the lifting motor. The measuring tube The top is equipped with an ash-blocking mechanism to reduce external dust and impurities from entering the measuring tube. The utility model uses the settings of the screw rod and the lifting motor. The lifting motor drives the screw rod to rotate, so that the benchmark rod rises and falls, and the benchmark rod is slidingly connected to the inner wall of the measuring tube. The gap is small, which greatly reduces the dust entering the measuring tube through the gap. At the same time, When there is no need to extend the length, the restoring force of the spring causes the arc-shaped rod to drive the dust shield to block the top of the measuring tube, further reducing the dust entering the measuring tube.

Description

Construction is with reference pole
Technical Field
The utility model relates to the technical field of a marker post, in particular to a marker post for construction.
Background
The construction measurement is directly used for engineering construction, is not only a construction guide, but also penetrates through the whole construction process, and the construction measurement is needed from the working procedures of site leveling, building positioning, foundation construction to wall construction, building component installation and the like to enable the sizes and positions of all parts of the building to meet the design requirements.
Publication No.: CN215335377U relates to the field of bridge construction. The marker post for bridge construction comprises a base and a measuring tube connected to the top of the base, wherein a marker post capable of lifting and a marker post lifting assembly for driving the marker post to lift are arranged in the measuring tube; one side of the measuring tube is connected with a connecting plate, the bottom of the connecting plate is connected with a connecting rope and a vertical measuring ruler matched with the connecting rope, and the bottom of the connecting rope is connected with a first balancing weight; the two sides at two ends of the base are respectively connected with lifting grooves, each lifting groove is internally and respectively connected with a vertically arranged and rotatable screw rod, a slide rod parallel to the screw rod and a threaded plate, the threaded plates are arranged on the corresponding screw rods through threaded sleeves, the slide rod slides through the corresponding threaded plates, one end of each threaded plate extends out of the lifting groove to be connected with a vertically arranged supporting rod, and the top of the screw rod is connected with a base lifting motor for driving the screw rod to rotate. The utility model provides a bridge construction is with stake can fix the stake of vertical arrangement and height-adjusting in order to measure.
The applicant has found that there are some disadvantages to this post in use: through the meshing of gear and rack, drive the sighting rod and rise in survey intraductal to this extension measuring length, but because survey pipe and sighting rod between the space great, outside air's dust gets into survey intraductally through survey pipe top easily, because survey pipe length is longer moreover, the clearance is very inconvenient.
Therefore, the utility model designs a construction marker post to solve the problems in the prior art.
Disclosure of Invention
The utility model aims to provide a construction marker post for solving the problems in the background technology.
In order to achieve the above purpose, the present utility model provides the following technical solutions: a construction pole, comprising: the bottom box, department installs the measuring tube in the middle of the top of bottom box, be equipped with the fixed establishment that improves stability in the bottom box, the bottom of measuring tube rotates and installs the lead screw, there is the marker post lateral wall top of lead screw through screw thread slidable mounting, the bottom of lead screw runs through in the bottom box and is connected with elevator motor's output, the top of measuring tube is equipped with the ash blocking mechanism that reduces outside dust impurity and get into in the measuring tube.
Preferably, electric push rods are arranged at two ends below the outer side walls of two sides of the bottom box, and the output ends of the electric push rods are connected with universal wheels.
Preferably, a level gauge is arranged above one end of the bottom box.
Preferably, the fixing mechanism comprises four electric cylinders, the four electric cylinders are respectively arranged at four corners of the top of the bottom box, the output end of each electric cylinder is connected with a lifting block, a driving motor is arranged on one side of the top of each lifting block, the output end of each driving motor is connected with a threaded cone which is rotatably arranged with the lifting block, and a through hole which is in penetrating connection with the threaded cone is arranged at the bottom of the bottom box.
Preferably, the U-shaped plate which is connected with the lifting block in a sliding way is arranged on the inner wall of the bottom box.
Preferably, the ash blocking mechanism comprises an ash blocking plate, the ash blocking plate is hinged to one side of the top of the measuring tube, an arc-shaped barrel is arranged above one side wall of the measuring tube, an arc-shaped rod is connected in a sliding manner in the arc-shaped barrel, the top of the arc-shaped rod is connected with the top of the ash blocking plate, the bottom of the arc-shaped rod is connected with the measuring tube through a spring, and the spring is located in the arc-shaped barrel.
Compared with the prior art, the utility model has the following beneficial effects:
according to the utility model, through the arrangement of the screw rod and the lifting motor, the lifting motor drives the screw rod to rotate, the marker post is in threaded connection with the screw rod, so that the screw rod is lifted, the marker post is in sliding connection with the inner wall of the measuring tube, the gap is smaller, the condition that dust enters the measuring tube through the gap is greatly reduced, meanwhile, when the length is not required to be prolonged, the arc-shaped rod drives the ash blocking plate to block the top of the measuring tube through the restoring force of the spring, the sealing effect is achieved, and the condition that the dust enters the measuring tube is further reduced.
Drawings
FIG. 1 is a schematic view in front cross-section of the present utility model;
FIG. 2 is an enlarged schematic view of the structure A of FIG. 1 according to the present utility model;
fig. 3 is a schematic front view of the present utility model.
In the figure: 1. a bottom box; 2. a measuring tube; 3. a fixing mechanism; 4. an electric push rod; 5. a universal wheel; 6. a level gauge; 7. a screw rod; 8. a target; 9. a lifting motor; 10. an ash blocking mechanism; 301. an electric cylinder; 302. a lifting block; 303. a driving motor; 304. a thread cone; 305. a through hole; 306. a U-shaped plate; 101. an ash blocking plate; 102. an arc-shaped barrel; 103. an arc-shaped rod; 104. and (3) a spring.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1-3, an embodiment of the present utility model is provided: a construction pole, comprising: the measuring tube 2 is installed to department in the middle of the top of the base box 1, be equipped with in the base box 1 and improve stable fixed establishment 3, the lead screw 7 is installed in the bottom rotation of measuring tube 2, there is the marker post 8 through screw thread slidable mounting in the lateral wall top of lead screw 7, the bottom of lead screw 7 runs through in the base box 1 and is connected with elevator motor 9's output, the top of measuring tube 2 is equipped with the ash blocking mechanism 10 that reduces outside dust impurity and get into in the measuring tube 2, elevator motor 9 drives lead screw 7 and just reverse the rotation, drive marker post 8 and go up and down, the inner wall sliding connection of marker post 8 and measuring tube 2, the space between is less, reducible dust gets into in the measuring tube 2.
Referring to fig. 1, in this embodiment: electric putter 4 is all installed at the below both ends of the lateral wall of base tank 1 both sides, and electric putter 4's output is connected with universal wheel 5, and when needs remove, electric putter 4 drive universal wheel 5 decline and ground contact, be convenient for remove the target.
Referring to fig. 3, in the present embodiment: a level gauge 6 is arranged above one end of the bottom box 1, and a worker can determine whether the marker post is level with the ground by observing the level gauge 6.
Referring to fig. 1, in this embodiment: the fixing mechanism 3 comprises four electric cylinders 301, the four electric cylinders 301 are respectively arranged at four corners of the top of the bottom box 1, the output ends of the electric cylinders 301 are connected with lifting blocks 302, driving motors 303 are arranged on one side of the top of the lifting blocks 302, the output ends of the driving motors 303 are connected with threaded cones 304 rotatably arranged with the lifting blocks 302, through holes 305 penetrating through the threaded cones 304 are formed in the bottom of the bottom box 1, after a measuring point is reached, the driving motors 303 drive the threaded cones 304 to rotate, meanwhile, the electric cylinders 301 drive the lifting blocks 302 to descend, the threaded cones 304 are enabled to descend and rotate into the ground, and the integral stability of a marker post value can be improved.
Referring to fig. 1, in this embodiment: the inner wall of the bottom box 1 is provided with a U-shaped plate 306 which is in sliding connection with the lifting block 302, and the U-shaped plate 306 limits the lifting block 302.
Referring to fig. 3, in the present embodiment: the ash blocking mechanism 10 comprises an ash blocking plate 101, the ash blocking plate 101 is hinged to one side of the top of the measuring tube 2, an arc-shaped barrel 102 is arranged above one side wall of the measuring tube 2, an arc-shaped rod 103 is connected in a sliding mode in the arc-shaped barrel 102, the top of the arc-shaped rod 103 is connected with the top of the ash blocking plate 101, the bottom of the arc-shaped rod 103 is connected with the measuring tube 2 through a spring 104, the spring 104 is located in the arc-shaped barrel 102, when the marker post 8 stretches out and contacts with the ash blocking plate 101, the ash blocking plate 101 is enabled to automatically open in an upward rotating mode, the ash blocking plate 101 drives the arc-shaped rod 103 to stretch into the arc-shaped barrel 102 and squeeze the spring 104, when the marker post 8 stretches back into the measuring tube 2, the arc-shaped rod 103 stretches out through the restoring force of the spring 104, the ash blocking plate 101 is driven to rotate downwards, the top of the measuring tube 2 is sealed, and dust entering the measuring tube 2 is further reduced.
Working principle: the elevating motor 9 drives the screw rod 7 to rotate to enable the marker post 8 to extend out of the measuring tube 2 for measuring the extension length, the top of the marker post 8 is in contact with the ash blocking plate 101, the ash blocking plate 101 is enabled to rotate and drive the arc rod 103 to enter the arc barrel 102 and simultaneously extrude the spring 104, after the marker post 8 descends into the measuring tube 2, the top of the marker post 8 leaves the ash blocking plate 101, the arc rod 103 extends out of the arc barrel 102 through the restoring force of the spring 104, the ash blocking plate 101 is enabled to rotate to block the top of the measuring tube 2, dust entering the measuring tube 2 can be reduced, and the content which is not described in detail in the specification belongs to the prior art known to the person skilled in the art.
Although the present utility model has been described with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described, or equivalents may be substituted for elements thereof, and any modifications, equivalents, improvements and changes may be made without departing from the spirit and principles of the present utility model.

Claims (6)

1. A construction pole, comprising: base case (1), its characterized in that: the measuring pipe (2) is installed to department in the middle of the top of base case (1), be equipped with in base case (1) and improve stable fixed establishment (3), screw rod (7) are installed in the bottom rotation of measuring pipe (2), there is marker post (8) lateral wall top of screw rod (7) through screw thread slidable mounting, the bottom of screw rod (7) runs through in base case (1) and is connected with elevator motor (9)'s output, the top of measuring pipe (2) is equipped with and reduces outside dust impurity and get into ash blocking mechanism (10) in measuring pipe (2).
2. The construction pole according to claim 1, wherein: electric push rods (4) are arranged at two ends below the outer side walls of two sides of the bottom box (1), and the output ends of the electric push rods (4) are connected with universal wheels (5).
3. The construction pole according to claim 1, wherein: a level meter (6) is arranged above one end of the bottom box (1).
4. The construction pole according to claim 1, wherein: the fixing mechanism (3) comprises four electric cylinders (301), the four electric cylinders (301) are respectively arranged at four corners of the top of the bottom box (1), the output end of each electric cylinder (301) is connected with a lifting block (302), a driving motor (303) is arranged on one side of the top of each lifting block (302), the output end of each driving motor (303) is connected with a threaded cone (304) rotatably arranged on the lifting block (302), and a through hole (305) penetrating through the threaded cone (304) is formed in the bottom of the bottom box (1).
5. The construction pole of claim 4, wherein: the inner wall of the bottom box (1) is provided with a U-shaped plate (306) which is in sliding connection with the lifting block (302).
6. The construction pole according to claim 1, wherein: the ash blocking mechanism (10) comprises an ash blocking plate (101), the ash blocking plate (101) is hinged to one side of the top of the measuring tube (2), an arc-shaped barrel (102) is arranged above one side wall of the measuring tube (2), an arc-shaped rod (103) is connected in a sliding mode in the arc-shaped barrel (102), the top of the arc-shaped rod (103) is connected with the top of the ash blocking plate (101), the bottom of the arc-shaped rod (103) is connected with the measuring tube (2) through a spring (104), and the spring (104) is located in the arc-shaped barrel (102).
CN202321619081.4U 2023-06-21 2023-06-21 Construction is with reference pole Active CN220153585U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321619081.4U CN220153585U (en) 2023-06-21 2023-06-21 Construction is with reference pole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321619081.4U CN220153585U (en) 2023-06-21 2023-06-21 Construction is with reference pole

Publications (1)

Publication Number Publication Date
CN220153585U true CN220153585U (en) 2023-12-08

Family

ID=89011267

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321619081.4U Active CN220153585U (en) 2023-06-21 2023-06-21 Construction is with reference pole

Country Status (1)

Country Link
CN (1) CN220153585U (en)

Similar Documents

Publication Publication Date Title
CN212432860U (en) Concrete strength detection device for construction
CN209978897U (en) Building energy conservation engineering measuring apparatu
CN212101481U (en) A pay-off device for engineering measurement
CN219141882U (en) Instrument and meter detection device of fracturing equipment
CN115326015A (en) Gradient detection device for transmission tower
CN114382461A (en) A kind of pile hole measuring equipment for engineering management and using method thereof
CN220395223U (en) Leveling device for cast-in-situ box girder concrete construction
CN220313281U (en) Door and window auxiliary installation structure
CN216669670U (en) Adjustable sensor positioning support for ultraviolet accelerated weather-proof testing machine test
CN221811583U (en) Wall body straightness detection device that hangs down
CN212718902U (en) Monitor shell assembly
CN208886584U (en) A kind of wisdom street lamp with function of monitoring air quality
CN115976961A (en) Hanging device for municipal water construction
CN220152269U (en) Survey fluviograph
CN218375237U (en) High and large formwork supporting structure
CN218729560U (en) An angle-variable sand table
CN109489624B (en) Power transmission line jumper sag measuring device
CN219547881U (en) Multifunctional rock soil inclinometer pipe
CN219100666U (en) Climbing form lower hanging platform stabilizing mechanism
CN220058129U (en) Foundation pit supporting gradient measuring device
CN216283527U (en) Measuring device for architectural design
CN221702357U (en) Sediment thickness detector for foundation engineering
CN221237537U (en) Adjustable mounting bracket
CN215677415U (en) Dynamic balance detection device for air compressor
CN221483248U (en) Engineering supervision perpendicularity detection equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20250723

Address after: 239400 Anhui Province, Chuzhou City, Mingguang City, Zhangbalingshen Town, Jiaotong South Road No. 5

Patentee after: Liu Dianwen

Country or region after: China

Address before: 236000 Anhui Province, Fuyang City, Yingzhou District, Xiqing Road No. 1155, Shuangqingwan Center A Building, B1411, B1412 Room

Patentee before: Anhui Youshun Construction Engineering Co.,Ltd.

Country or region before: China

TR01 Transfer of patent right