CN219864153U - Discharging platform for building construction - Google Patents
Discharging platform for building construction Download PDFInfo
- Publication number
- CN219864153U CN219864153U CN202321055715.8U CN202321055715U CN219864153U CN 219864153 U CN219864153 U CN 219864153U CN 202321055715 U CN202321055715 U CN 202321055715U CN 219864153 U CN219864153 U CN 219864153U
- Authority
- CN
- China
- Prior art keywords
- platform
- sliding
- support frame
- unloading
- material containing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000009435 building construction Methods 0.000 title claims abstract description 18
- 238000007599 discharging Methods 0.000 title abstract description 8
- 239000000463 material Substances 0.000 claims abstract description 43
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 5
- 230000005540 biological transmission Effects 0.000 claims description 14
- 238000010276 construction Methods 0.000 claims description 9
- 239000004566 building material Substances 0.000 abstract description 18
- 230000007547 defect Effects 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model is suitable for the technical field of material transfer equipment for building construction, and particularly relates to a discharging platform for building construction, which comprises a supporting frame, wherein a reinforcing supporting rod is arranged on the lower side of the supporting frame, and the discharging platform for building construction further comprises: the sliding seat is connected to the upper side of the supporting frame in a sliding way, and a threaded hole is formed in the side face of the sliding seat. According to the utility model, the sliding seat, the supporting rod, the material containing platform, the hydraulic telescopic rod, the traction sliding block, the traction sliding rail and the second hinge are arranged, so that building materials received on the material containing platform can be automatically, stably and rapidly transferred into a building, and the unloading operation is completed.
Description
Technical Field
The utility model relates to the technical field of material transfer equipment for building construction, in particular to a discharging platform for building construction.
Background
The unloading platform is a temporary construction platform commonly used in high-rise building construction, is usually erected on one side of a building in a cantilever mode, and a tower crane is used for hanging materials and tools required by construction from the ground to the unloading platform and then transporting the materials and tools into the building through the unloading platform.
At present, when a common unloading platform for building construction is used, the technical defect of single function is commonly existed, and the unloading platform only has the function of transferring building materials, and can not keep the inclined state of the loading platform when unloading the loading platform, so that the unloading efficiency of the loading platform is improved.
Disclosure of Invention
The embodiment of the utility model aims to provide a discharging platform for building construction, which aims to solve the following problems: at present, when a common unloading platform for building construction is used, the technical defect of single function is commonly existed, and the unloading platform only has the function of transferring building materials, and can not keep the inclined state of the loading platform when unloading the loading platform, so that the unloading efficiency of the loading platform is improved.
In order to achieve the above purpose, the present utility model provides the following technical solutions:
the utility model provides a platform of unloading for construction, includes the support frame, and the downside of support frame is provided with the reinforcing support pole, platform of unloading for construction still includes:
the sliding seat is in sliding connection with the upper side of the supporting frame, threaded holes are formed in the side face of the sliding seat, a hydraulic telescopic rod and a supporting rod are respectively arranged on two sides of the upper side of the sliding seat, a first hinge is installed at one end of the supporting rod, the outer side of the first hinge is rotationally connected with a material containing platform, a traction sliding rail is arranged on the lower side of the material containing platform, a traction sliding block is in sliding connection with the inner side of the traction sliding rail, and a second hinge is installed on the outer side of the traction sliding block and one end of the hydraulic telescopic rod together;
the two bearing seats are respectively arranged on two sides of the upper side of the support frame, and the inside of the two bearing seats is jointly provided with a transmission threaded rod which is also meshed and connected in the threaded hole; and
the driving assembly is arranged on the outer side of the supporting frame and used for driving the transmission threaded rod to rotate through the bearing seat.
Further, the upside of support frame is provided with the direction slide rail, and the slider is installed to the downside of sliding seat, and the sliding seat passes through the cooperation sliding connection of slider and direction slide rail in the upside of support frame.
Further, the driving assembly includes:
the mounting panel is connected to the lower side of the support frame, a driving motor is mounted on the side surface of the mounting panel, and a second transmission chain wheel is mounted at the output end of the driving motor; and
the first driving sprocket is sleeved on the outer side of the driving threaded rod, and the outer side of the first driving sprocket and the outer side of the second driving sprocket are sleeved with the linkage chain.
Further, an electric telescopic rod is installed on the upper side of the sliding seat, and one end of the electric telescopic rod is connected with a lifting block.
Further, one side surface of the material containing platform, which is close to the supporting rod, is of an opening structure, and the side surface opening of the material containing platform of the lifting block is attached.
According to the unloading platform for building construction, the sliding seat, the supporting rod, the material containing platform, the hydraulic telescopic rod, the traction sliding block, the traction sliding rail and the second hinge are arranged, so that building materials received on the material containing platform can be automatically, stably and rapidly transferred into a building, and the unloading operation is completed.
Drawings
Fig. 1 is a schematic structural view of a discharging platform for construction.
Fig. 2 is an enlarged view of a point a of a discharging platform for construction.
In the figure: 1. a support frame; 2. reinforcing the support rod; 3. driving a threaded rod; 4. a guide rail; 5. a sliding seat; 6. a slide block; 7. a bearing seat; 8. a material containing platform; 9. a first hinge; 10. a support rod; 11. a lifting block; 12. an electric telescopic rod; 13. a first drive sprocket; 14. a linkage chain; 15. a second drive sprocket; 16. a driving motor; 17. installing a panel; 18. pulling the slide rail; 19. pulling the sliding block; 20. a hydraulic telescopic rod.
Detailed Description
The present utility model will be described in further detail with reference to the drawings and examples, in order to make the objects, technical solutions and advantages of the present utility model more apparent. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the scope of the utility model.
Specific implementations of the utility model are described in detail below in connection with specific embodiments.
As shown in fig. 1-2, the unloading platform for building construction provided by the embodiment of the utility model includes a support frame 1, wherein a reinforcing support rod 2 is arranged at the lower side of the support frame 1, the support frame 1 is of a T-shaped structure, the support frame 1 is usually erected on a building, one side of the support frame 1 is fixedly connected with the ground of the building, and the other side of the support frame 1 extends in mid-air for receiving materials, and the unloading platform for building construction further includes:
the sliding seat 5 is in sliding connection with the upper side of the supporting frame 1, a guide sliding rail 4 is arranged on the upper side of the supporting frame 1, a sliding block 6 is arranged on the lower side of the sliding seat 5, the sliding seat 5 is in sliding connection with the upper side of the supporting frame 1 through the matching of the sliding block 6 and the guide sliding rail 4, a threaded hole is formed in the side face of the sliding seat 5, a hydraulic telescopic rod 20 and a supporting rod 10 are respectively arranged on two sides of the upper side of the sliding seat 5, a first hinge 9 is arranged at one end of the supporting rod 10, a material containing platform 8 is rotatably connected to the outer side of the first hinge 9, a traction sliding rail 18 is arranged on the lower side of the material containing platform 8, a traction sliding block 19 is in sliding connection with the inner side of the traction sliding rail 18, and a second hinge is jointly arranged at one end of the traction sliding block 19 and one end of the hydraulic telescopic rod 20;
the two bearing seats 7 are respectively arranged on two sides of the upper side of the support frame 1, the inside of each bearing seat 7 is jointly provided with a transmission threaded rod 3, and the transmission threaded rods 3 are also in meshed connection with the inside of the threaded holes; and
the driving assembly is arranged on the outer side of the support frame 1 and used for driving the transmission threaded rod 3 to rotate through the bearing seat 7;
the drive assembly includes:
the mounting panel 17 is connected to the lower side of the support frame 1, a driving motor 16 is mounted on the side surface of the mounting panel 17, and a second transmission chain wheel 15 is mounted at the output end of the driving motor 16; and
the first transmission chain wheel 13 is sleeved on the outer side of the transmission threaded rod 3, and the outer side of the first transmission chain wheel 13 and the outer side of the second transmission chain wheel 15 are jointly sleeved with the linkage chain 14.
In this embodiment, after the building material is thrown onto the material containing platform 8 by the external crane, the material containing platform 8 should be transferred into the building, so that the building worker can detach the building material on the material containing platform 8, which specifically operates by opening the driving motor 16, the driving motor 16 drives the second driving sprocket 15 to rotate, so that the second driving sprocket 15 drives the first driving sprocket 13 to rotate through the linkage chain 14, and the first driving sprocket 13 drives the driving threaded rod 3 to rotate through the two bearing seats 7, so that the driving threaded rod 3 drives the sliding seat 5, the outer side of which is in meshed connection with the driving threaded rod 3, to do horizontal linear motion on the surface of the supporting frame 1 through the sliding block 6 and the guiding sliding rail 4 until the material containing platform 8 and the building material carried on the sliding seat 5 are transferred to a proper position;
because building material is put in behind the flourishing material platform 8, it is generally kept flat in the inside of flourishing material platform 8, this is unfavorable for the building staff to carry building material in the flourishing material platform 8, and in this embodiment, the hydraulic telescoping rod 20 can be opened to the building staff, hydraulic telescoping rod 20 drives and pulls slider 19 in the inside of pulling slide rail 18 to make the sliding rail 18 drive flourishing material platform 8 through the cooperation of second hinge and first hinge 9 and rotate on the top of bracing piece 10, and then make flourishing material platform 8 can upwards tilt, and building material on the flourishing material platform 8 can gather together, and then in order to make the building staff artificial or with the help of handling tool come away the building material in the flourishing material platform 8, through above-mentioned technical scheme, the building material that will be received on the flourishing material platform 8 is moved to the building, and accomplish the operation of unloading, and when unloading the operation, can also automatic slope with the building material platform 8, so that building material in the flourishing material platform 8 gathers together, the building material in order to be convenient for the building staff to remove, the material of unloading platform and the practicality of unloading, the material has been unloaded.
As shown in fig. 1, in one embodiment of the present utility model, an electric telescopic rod 12 is installed on the upper side of the sliding seat 5, one end of the electric telescopic rod 12 is connected with a lifting block 11, one side of the material containing platform 8 near the supporting rod 10 is in an open structure, and a side opening of the material containing platform 8 of the lifting block 11 is attached.
In this embodiment, when the building material which is not easy to damage and is similar to a steel pipe is transported in the material containing platform 8, the unloading efficiency of the building material can be further improved, and the concrete operation is that after the material containing platform 8 is moved to a proper position, the electric telescopic rod 12 is opened first, the electric telescopic rod 12 drives the lifting block 11 to move downwards, so that the lifting block 11 does not block the opening on the side surface of the material containing platform 8 any more, and then the material containing platform 8 is inclined, so that the building material in the material containing platform 8 is directly rolled out from the material containing platform 8, and the unloading efficiency of the unloading platform for building construction is greatly improved.
The foregoing description of the preferred embodiments of the utility model is not intended to be limiting, but rather is intended to cover all modifications, equivalents, and alternatives falling within the spirit and principles of the utility model.
Claims (5)
1. The utility model provides a platform of unloading for construction, includes the support frame, and the downside of support frame is provided with the reinforcing support pole, its characterized in that, platform of unloading for construction still includes:
the sliding seat is in sliding connection with the upper side of the supporting frame, threaded holes are formed in the side face of the sliding seat, a hydraulic telescopic rod and a supporting rod are respectively arranged on two sides of the upper side of the sliding seat, a first hinge is installed at one end of the supporting rod, the outer side of the first hinge is rotationally connected with a material containing platform, a traction sliding rail is arranged on the lower side of the material containing platform, a traction sliding block is in sliding connection with the inner side of the traction sliding rail, and a second hinge is installed on the outer side of the traction sliding block and one end of the hydraulic telescopic rod together;
the two bearing seats are respectively arranged on two sides of the upper side of the support frame, and the inside of the two bearing seats is jointly provided with a transmission threaded rod which is also meshed and connected in the threaded hole; and
the driving assembly is arranged on the outer side of the supporting frame and used for driving the transmission threaded rod to rotate through the bearing seat.
2. The unloading platform for building construction according to claim 1, wherein a guide sliding rail is arranged on the upper side of the support frame, a sliding block is arranged on the lower side of the sliding seat, and the sliding seat is connected to the upper side of the support frame in a sliding manner through the matching of the sliding block and the guide sliding rail.
3. A discharge platform for construction according to claim 1, wherein the drive assembly comprises:
the mounting panel is connected to the lower side of the support frame, a driving motor is mounted on the side surface of the mounting panel, and a second transmission chain wheel is mounted at the output end of the driving motor; and
the first driving sprocket is sleeved on the outer side of the driving threaded rod, and the outer side of the first driving sprocket and the outer side of the second driving sprocket are sleeved with the linkage chain.
4. The unloading platform for building construction according to claim 1, wherein an electric telescopic rod is installed on the upper side of the sliding seat, and one end of the electric telescopic rod is connected with a lifting block.
5. The unloading platform for building construction according to claim 4, wherein a side surface of the material containing platform, which is close to the supporting rod, is of an opening structure, and side openings of the material containing platform of the lifting block are attached.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202321055715.8U CN219864153U (en) | 2023-04-27 | 2023-04-27 | Discharging platform for building construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202321055715.8U CN219864153U (en) | 2023-04-27 | 2023-04-27 | Discharging platform for building construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN219864153U true CN219864153U (en) | 2023-10-20 |
Family
ID=88344447
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202321055715.8U Active CN219864153U (en) | 2023-04-27 | 2023-04-27 | Discharging platform for building construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN219864153U (en) |
-
2023
- 2023-04-27 CN CN202321055715.8U patent/CN219864153U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110316674B (en) | Unearthed equipment is used in shaft excavation | |
CN207934467U (en) | A kind of lift push-and-pull discharging platform | |
CN219864153U (en) | Discharging platform for building construction | |
CN110565935A (en) | Attached scaffold for building | |
CN210337935U (en) | Shallow convenient to unload | |
CN217676491U (en) | High-efficient loop wheel machine is used to civil engineering | |
CN215361481U (en) | Material handling equipment for building engineering | |
CN116161527A (en) | Quick lifting and unloading device and method | |
CN213923950U (en) | Civil engineering elevating gear | |
CN210976665U (en) | Cement protection device for construction | |
CN211444939U (en) | Foundation pit earthwork outward transportation equipment | |
CN112392269A (en) | Building platform for outdoor building and indoor decoration | |
CN210735587U (en) | Curb transfer device | |
CN116553377A (en) | Material transfer device for building engineering | |
CN220998398U (en) | Manual hole digging pile lifting frame | |
CN221587920U (en) | Roof lifting equipment based on building whole life cycle building part outer wall introduction | |
CN216945970U (en) | Steel structural component transfer device | |
CN215711418U (en) | Building construction building material lifting equipment | |
CN210528304U (en) | Material transportation frame of conveniently unloading for building | |
CN218596039U (en) | Can be used to open air material transfer car (buggy) | |
CN219603133U (en) | Reverse construction method soil lifting device | |
CN219585704U (en) | Pipe conveying device for building construction | |
CN117284815B (en) | Energy-saving dust removal equipment for green building engineering construction | |
CN216038349U (en) | A hoist device for construction | |
CN215100777U (en) | Side wall dispensing mobile loading system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |