CN219728843U - Temporary supporting device for laying engineering construction pipelines - Google Patents

Temporary supporting device for laying engineering construction pipelines Download PDF

Info

Publication number
CN219728843U
CN219728843U CN202321194825.2U CN202321194825U CN219728843U CN 219728843 U CN219728843 U CN 219728843U CN 202321194825 U CN202321194825 U CN 202321194825U CN 219728843 U CN219728843 U CN 219728843U
Authority
CN
China
Prior art keywords
sides
middle bin
pipeline
bin
shaped supporting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321194825.2U
Other languages
Chinese (zh)
Inventor
冯琦
郭一君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202321194825.2U priority Critical patent/CN219728843U/en
Application granted granted Critical
Publication of CN219728843U publication Critical patent/CN219728843U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses a temporary supporting device for laying engineering construction pipelines, which comprises the following components: the middle part of the top of the middle bin is welded with a U-shaped supporting frame A, and universal balls A are arranged on the inner wall surface of the U-shaped supporting frame A and on two sides of the U-shaped supporting frame A; both sides of the middle bin are provided with side plates. This temporary strutting arrangement is laid to engineering construction pipeline, U type strut A's inside, both sides U type strut B's inside and both sides support the inside in chamber and all can place the pipeline, and play the effect of lifting to the pipeline, 5 groups of pipelines can be supported simultaneously, the inside in support chamber accessible adjusts the interval between curb plate and the middle part storehouse, adjust the inside size of support chamber, lift the pipeline from the bottom, can be quick, high-efficient, accurate help workman carries out the pipeline installation, easy operation can improve the efficiency of construction, shorten construction period, be suitable for the more engineering of pipeline installation.

Description

Temporary supporting device for laying engineering construction pipelines
Technical Field
The utility model relates to the technical field of pipeline installation assistance, in particular to a temporary supporting device for laying engineering construction pipelines.
Background
Because large-scale indoor, underground utility tunnel etc. need carry out pipeline installations such as strong and weak electricity, fire control pipe, shower after the main part is pour and is accomplished, these pipelines are not big in the construction degree of difficulty of installation, and technical is not high, but when installing these pipelines, if do not carry out temporary fixation, the pipeline easily takes place the skew and slides, increases the degree of difficulty of installation, reduces installation effectiveness. In the prior art, during actual installation, the steel pipe and steel mesh sheet welded pushable operation platform is generally utilized by site constructors, and is manually fixed, so that the time and the labor are consumed in the installation process, and especially in the underground comprehensive pipe gallery engineering, as the pipe gallery belongs to a long-strip-shaped building, the spans of strong and weak electric pipelines and fire-fighting pipelines are large, the cross section of the pipe gallery is small, the working face is small, and the pipeline installation is difficult to be carried out, if the movable operation platform is used, the occupied construction space is more, and the integral installation engineering progress of the pipeline is influenced.
Therefore, the pipeline installation such as construction current field intensity weak current, fire protection and the like needs a simple and convenient device to assist, so that the pipeline installation progress is accelerated, and the overall effect of the pipeline installation is ensured.
Disclosure of Invention
The utility model aims to provide a temporary supporting device for laying engineering construction pipelines, which aims to solve the problems in the background technology.
In order to achieve the above purpose, the present utility model provides the following technical solutions:
an engineering construction pipeline layout temporary support device, comprising:
the middle part of the top of the middle bin is welded with a U-shaped supporting frame A, and universal balls A are arranged on the inner wall surface of the U-shaped supporting frame A and on two sides of the U-shaped supporting frame A;
the two sides of the middle bin are provided with side plates, the distance between the side plates and the middle bin is adjustable, and the top of each side plate is welded with a U-shaped supporting frame B;
and a supporting cavity is formed among the middle bin, the universal ball A and the U-shaped supporting frame B, and the universal ball B is arranged on two sides of the top of the middle bin.
As a further scheme of the utility model: the utility model discloses a sliding sleeve, including curb plate, screw rod, screw sleeve, screw rod and screw sleeve threaded connection, the round hole has been seted up to one side of curb plate, and the inside of round hole is rotated through the bearing and is installed the lead screw, the screw rod has been cup jointed in one side that the lead screw is located the curb plate, the screw sleeve has all been inlayed in the middle part of middle part storehouse both sides, and screw rod and screw sleeve threaded connection, the curb plate is close to one side of middle part storehouse and uses the lead screw to install two slide bars as symmetry, and the both sides of middle part storehouse all inlay install with the gliding sliding sleeve of slide bar.
As still further aspects of the utility model: two moving plates are slidably mounted on two sides of the inside of the middle bin, one side end of the screw rod located inside the middle bin is rotationally connected with the moving plates through bearings, and meanwhile, one side end of the slide rod located inside the middle bin is fixedly connected with the moving plates.
As still further aspects of the utility model: the front and the back of the inner wall of the middle bin are both provided with sliding rails, and the front and the back of the moving plate are both provided with sliding blocks sliding on the sliding rails.
As still further aspects of the utility model: the middle part of middle part storehouse bottom has the vertical frame of welding, the bottom welding of vertical frame has the I-shaped frame.
As still further aspects of the utility model: a supporting bar A is welded between the two sides of the bottom of the middle bin and the two sides of the vertical frame, and a supporting bar B is welded between the two sides of the top of the I-shaped frame and the two sides of the vertical frame.
Compared with the prior art, the utility model has the beneficial effects that:
1. the utility model discloses, the inside of U type strut A, the inside of both sides U type strut B and the inside in both sides supporting cavity all can place the pipeline, and play the effect of lifting to the pipeline, 5 groups of pipelines can be supported simultaneously, the inside in supporting cavity accessible adjusts the inside size of supporting cavity through adjusting the interval between curb plate and the middle part storehouse, lift the pipeline from the bottom, help workman that can be quick, high-efficient, accurate carries out the pipeline installation, easy operation can improve the efficiency of construction, shorten construction period, be suitable for the more engineering of pipeline installation.
2. The utility model discloses, through U type strut A, universal ball B and universal ball C's setting, be in rolling contact between pipeline and the it, reduce the frictional force when lifting the contact between it, more conveniently pass the position of moving to the pipeline, also avoid causing the injury of rubbing to the pipeline.
3. The utility model discloses, support bar A and support bar B all play the effect of support to improve the stability that the device used.
4. The utility model discloses, forward and backward rotation through the lead screw to realize the adjustment between middle part storehouse and the curb plate, can remove certain distance back with U type strut B to the side, rethread U type strut B supports, improves the application scope of device, simultaneously, also can adjust the size of supporting the intracavity portion.
5. The utility model discloses, the atress of curb plate is by slide bar and movable plate on the middle part storehouse, and the movable plate installs additional and at the inside lateral shifting in middle part storehouse, avoids the tail end atress perk of lead screw and slide bar, guarantees the normal use of device.
Drawings
FIG. 1 is a schematic view of a contracted structure of a temporary support device for laying an engineering construction pipeline;
FIG. 2 is a schematic view of an expanded structure of a temporary support device for laying an engineering construction pipeline;
fig. 3 is a partial cross-sectional view of a middle silo in an engineering construction pipeline laying temporary support device.
In the figure: the middle bin 1, the U-shaped supporting frame A2, the universal ball A3, the supporting cavity 4, the universal ball B5, the side plate 6, the U-shaped supporting frame B7, the universal ball C8, the supporting bar A9, the vertical frame 10, the supporting bar B11, the I-shaped frame 12, the moving plate 13, the sliding rail 14, the sliding block 15, the screw rod 16, the sliding rod 17, the threaded sleeve 18 and the knob 19.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1 to 3, the present utility model proposes a technical solution, a temporary supporting device for laying engineering construction pipelines, comprising:
the middle part of the top of the middle bin 1 is welded with a U-shaped supporting frame A2, and universal balls A3 are arranged on the inner wall surface of the U-shaped supporting frame A2 and on two sides of the U-shaped supporting frame A2;
the two sides of the middle bin 1 are provided with side plates 6, the distance between the side plates 6 and the middle bin 1 is adjustable, and the top of each side plate 6 is welded with a U-shaped supporting frame B7;
a supporting cavity 4 is formed among the middle bin 1, the universal ball A3 and the U-shaped supporting frame B7, and the universal ball B5 is arranged on two sides of the top of the middle bin 1.
The inside of U type strut A2, the inside of both sides U type strut B7 and the inside of both sides support chamber 4 all can place the pipeline, and play the effect of lifting the pipeline, can support universal ball B5 group pipeline simultaneously, the inside accessible of support chamber 4 adjusts the interval between curb plate 6 and the middle part storehouse 1, adjust the inside size of support chamber 4, lift the pipeline from the bottom, can be quick, high-efficient, accurate help workman carries out the pipeline installation, easy operation, can improve the efficiency of construction, shorten construction period, be suitable for the more engineering of pipeline installation, whether square crane span, electromechanical threading pipe, fire sprinkler tube etc. all can assist the installation, improve the installation effectiveness.
Through the setting of U type strut A2, universal ball B5 and universal ball C8, be in rolling contact between pipeline and it, reduce the frictional force when lifting the contact between it, more conveniently pass the pipeline and move the position, also avoid causing the injury of rubbing to the pipeline.
Round holes are formed in one side of the side plate 6, the screw rods 16 are rotatably arranged in the round holes through bearings, the screw rods 16 are positioned on one side of the side plate 6 and sleeved with the knobs 19, threaded sleeves 18 are embedded in the middle parts of two sides of the middle bin 1, the screw rods 16 are in threaded connection with the threaded sleeves 18, one side of the side plate 6 close to the middle bin 1 and symmetrically provided with two sliding rods 17 by taking the screw rods 16 as symmetry, sliding sleeves sliding with the sliding rods 17 are embedded in two sides of the middle bin 1, forward and reverse rotation of the screw rods 16 is achieved, adjustment between the middle bin 1 and the side plate 6 is achieved, after the U-shaped support frame B7 is moved to the side by a certain distance, the U-shaped support frame B7 is supported, the application range of the device is improved, and meanwhile the size of the inside of the support cavity 4 can be adjusted.
Two movable plates 13 are slidably mounted on two sides of the inside of the middle bin 1, one side end of the screw rod 16, located inside the middle bin 1, is rotatably connected with the movable plates 13 through bearings, meanwhile, the side end of the slide rod 17, located inside the middle bin 1, is fixedly connected with the movable plates 13, and the side plates 6 are stressed by the slide rod 17 and the movable plates 13, so that the movable plates 13 are additionally mounted and transversely moved inside the middle bin 1, the tail ends of the screw rod 16 and the slide rod 17 are prevented from being tilted due to stress, and normal use of the device is guaranteed.
The front and the back of the inner wall of the middle bin 1 are provided with sliding rails 14, and the front and the back of the moving plate 13 are provided with sliding blocks 15 sliding on the sliding rails 14.
The middle part of the bottom of the middle bin 1 is welded with a vertical frame 10, and the bottom of the vertical frame 10 is welded with an I-shaped frame 12.
Support bar A9 is welded between the two sides of the bottom of the middle bin 1 and the two sides of the vertical frame 10, support bar B11 is welded between the two sides of the top of the I-shaped frame 12 and the two sides of the vertical frame 10, and the support bar A9 and the support bar B11 play a supporting role so as to improve the use stability of the device.
The working principle of the utility model is as follows:
when the device is used, the device is placed on the ground, pipelines can be placed in the U-shaped supporting frame A2, the U-shaped supporting frames B7 on two sides and the supporting cavities 4 on two sides, the lifting effect of the pipelines is achieved, and 5 groups of pipelines can be supported simultaneously;
through the arrangement of the U-shaped supporting frame A2, the universal ball B5 and the universal ball C8, the pipeline is in rolling contact with the universal ball C, so that the friction force between the pipeline and the universal ball C in lifting contact is reduced;
the adjustment flow of the space between the side plate 6 and the middle bin 1 is as follows:
the screw rod 16 is driven to rotate through the knob 19, the screw rod 16 is linked with the side plate 6 to transversely move under the transverse thread transmission action of the screw rod 16 and the thread bush 18, and the middle bin 1 and the side plate 6 can be adjusted through forward and reverse rotation of the screw rod 16, so that the U-shaped support frame B7 can be supported through the U-shaped support frame B7 after being moved to a certain distance to the side.
Although the present utility model has been described with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described, or equivalents may be substituted for elements thereof, and any modifications, equivalents, improvements and changes may be made without departing from the spirit and principles of the present utility model.

Claims (6)

1. The utility model provides a temporary support device is laid to engineering construction pipeline which characterized in that: comprising the following steps:
the middle part of the top of the middle bin (1) is welded with a U-shaped supporting frame A (2), and universal balls A (3) are arranged on the inner wall surface of the U-shaped supporting frame A (2) and on two sides of the U-shaped supporting frame A (2);
the two sides of the middle bin (1) are provided with side plates (6), the distance between the side plates (6) and the middle bin (1) is adjustable, and the top of each side plate (6) is welded with a U-shaped supporting frame B (7);
a supporting cavity (4) is formed among the middle bin (1), the universal ball A (3) and the U-shaped supporting frame B (7), and the universal ball B (5) is arranged on two sides of the top of the middle bin (1).
2. An engineering pipeline laying temporary support device according to claim 1, wherein: round holes are formed in one side of the side plate (6), a screw rod (16) is rotatably mounted in the round holes through bearings, a knob (19) is sleeved on one side of the side plate (6) by the screw rod (16), threaded sleeves (18) are mounted in the middle of two sides of the middle bin (1) in an embedded mode, the screw rod (16) is in threaded connection with the threaded sleeves (18), two sliding rods (17) are mounted on one side, close to the middle bin (1), of the side plate (6) in a symmetrical mode through the screw rod (16), and sliding sleeves with the sliding rods (17) are mounted on two sides of the middle bin (1) in an embedded mode.
3. An engineering pipeline laying temporary support device according to claim 1, wherein: two moving plates (13) are slidably mounted on two sides of the inside of the middle bin (1), one side end of the screw rod (16) located inside the middle bin (1) is rotationally connected with the moving plates (13) through bearings, and meanwhile, one side end of the sliding rod (17) located inside the middle bin (1) is fixedly connected with the moving plates (13).
4. A temporary support device for laying an engineering construction pipeline according to claim 3, wherein: the front and the back of the inner wall of the middle bin (1) are provided with sliding rails (14), and the front and the back of the moving plate (13) are provided with sliding blocks (15) sliding on the sliding rails (14).
5. An engineering pipeline laying temporary support device according to claim 1, wherein: the middle part of middle part storehouse (1) bottom has welded vertical frame (10), the bottom welding of vertical frame (10) has I-shaped frame (12).
6. An engineering pipeline layout temporary support device according to claim 5, wherein: support bar A (9) is welded between two sides of the bottom of the middle bin (1) and two sides of the vertical frame (10), and support bar B (11) is welded between two sides of the top of the I-shaped frame (12) and two sides of the vertical frame (10).
CN202321194825.2U 2023-05-17 2023-05-17 Temporary supporting device for laying engineering construction pipelines Active CN219728843U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321194825.2U CN219728843U (en) 2023-05-17 2023-05-17 Temporary supporting device for laying engineering construction pipelines

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321194825.2U CN219728843U (en) 2023-05-17 2023-05-17 Temporary supporting device for laying engineering construction pipelines

Publications (1)

Publication Number Publication Date
CN219728843U true CN219728843U (en) 2023-09-22

Family

ID=88054718

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321194825.2U Active CN219728843U (en) 2023-05-17 2023-05-17 Temporary supporting device for laying engineering construction pipelines

Country Status (1)

Country Link
CN (1) CN219728843U (en)

Similar Documents

Publication Publication Date Title
CN209854734U (en) Foundation pit supporting device
CN210461936U (en) Municipal water supply pipeline strutting arrangement
CN219728843U (en) Temporary supporting device for laying engineering construction pipelines
CN214838854U (en) Hydraulic engineering construction pipeline strutting arrangement
CN204592560U (en) A kind of adjustable cable crane span structure support supported for curved wall
CN216238566U (en) Detachable support for constructional engineering construction
CN210767758U (en) Grouting platform
CN210917382U (en) Foundation pit supporting structure
CN213540398U (en) Super large section class rectangle push pipe originating platform
CN213461027U (en) Simple cable trench support structure
CN218000690U (en) Adjustable supporting structure for pipeline installation
CN221402054U (en) Alignment mounting bracket for basement water supply and drainage main pipeline
CN220102307U (en) Hydraulic engineering pipeline bearing structure with adjustable
CN218894364U (en) Civil engineering construction support
CN219845920U (en) Building fireproof wallboard erecting device
CN215528406U (en) Novel platform of taking one's place is removed to whole dish cabinet
CN217924706U (en) Scaffold for civil engineering building
CN220888664U (en) Combined steel pipe inclined throwing support
CN220747778U (en) Post-cast strip steel pipe temporary supporting structure
CN211219446U (en) Convenient steel pipe welding equipment for building of adjusting
CN219315622U (en) Small river water guiding device
CN212251480U (en) Hydraulic engineering drainage device
CN210289095U (en) Overhanging support device for bowl-buckle type scaffold
CN208981173U (en) A kind of slab culvert assembled rod piece bracket
CN220847612U (en) Supporting device for geotechnical engineering foundation pit

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant