CN219385987U - Multi-column assembled pier system of tie beam expansion combined connection pile - Google Patents
Multi-column assembled pier system of tie beam expansion combined connection pile Download PDFInfo
- Publication number
- CN219385987U CN219385987U CN202223090178.9U CN202223090178U CN219385987U CN 219385987 U CN219385987 U CN 219385987U CN 202223090178 U CN202223090178 U CN 202223090178U CN 219385987 U CN219385987 U CN 219385987U
- Authority
- CN
- China
- Prior art keywords
- steel bars
- pier
- reserved
- column
- bearing platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 34
- 239000010959 steel Substances 0.000 claims abstract description 34
- 239000004567 concrete Substances 0.000 claims abstract description 23
- 239000011374 ultra-high-performance concrete Substances 0.000 claims abstract description 10
- 230000003014 reinforcing effect Effects 0.000 claims 4
- 239000002131 composite material Substances 0.000 claims 2
- 238000010276 construction Methods 0.000 abstract description 12
- 238000005452 bending Methods 0.000 abstract description 6
- 230000002787 reinforcement Effects 0.000 description 7
- 238000010586 diagram Methods 0.000 description 4
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/30—Adapting or protecting infrastructure or their operation in transportation, e.g. on roads, waterways or railways
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域technical field
本实用新型涉及一种系梁扩大组合连接桩柱的多柱式装配式墩体系,属于桥梁工程领域。The utility model relates to a multi-column assembled pier system in which pile columns are connected by expanding and combining tie beams, which belongs to the field of bridge engineering.
背景技术Background technique
相对一般建筑工程来说,桥涵结构具有结构尺寸大、构件重量重、总体呈带状分布、各个构件之间相对独立的特点,且受地震作用,其抗震性能差,抗裂强度不高,如此便极大的增加了施工成本和施工难度。此装配式桥梁,墩柱和承台连接使用后浇混凝土层UHPC,提高了抗裂性,提升了桥墩的整体性能和强度。相邻承台之间用系梁连接使得其连成整体受力,整体刚度加强。Compared with general construction projects, the bridge and culvert structure has the characteristics of large structural size, heavy component weight, overall band-shaped distribution, and relatively independent components, and is affected by earthquakes. Its seismic performance is poor and its crack resistance is not high. This will greatly increase the construction cost and construction difficulty. In this prefabricated bridge, the post-cast concrete layer UHPC is used for the connection between the pier column and the cap, which improves the crack resistance and improves the overall performance and strength of the pier. The adjacent caps are connected by tie beams so that they can be connected as a whole to bear the force, and the overall rigidity is strengthened.
实用新型内容Utility model content
鉴于现有技术的不足,本实用新型所要解决的技术问题是提供一种系梁扩大组合连接桩柱的多柱式装配式墩体系。In view of the deficiencies in the prior art, the technical problem to be solved by the utility model is to provide a multi-column assembled pier system in which the tie beams are expanded and combined to connect the piles.
为了解决上述技术问题,本实用新型的技术方案是:一种系梁扩大组合连接桩柱的多柱式装配式墩体系,包括自上往下依次设置的盖梁、墩柱、承台、桩基,承台的上表面设置凹槽,墩柱底部放置在凹槽内,盖梁和墩柱的内底部均预留有连接套管,墩柱内部的若干预留纵向钢筋上部与盖梁内埋设的若干预留钢筋通过连接套管搭接,墩柱内部的若干预留纵向钢筋下部与承台的若干预留钢筋通过连接套管搭接,墩柱与凹槽之间的间隙处填充浇筑有后浇混凝土层,后浇混凝土层采用UHPC混凝土,相邻承台之间通过系梁连接。In order to solve the above-mentioned technical problems, the technical solution of the utility model is: a multi-column assembled pier system with beams enlarged and combined to connect piles, including cover beams, pier columns, caps, and pile foundations arranged sequentially from top to bottom. Grooves are arranged on the upper surface of the caps, and the bottom of the pier columns is placed in the grooves. Connecting sleeves are reserved at the inner bottoms of the cover beams and pier columns. The lower part of the steel bars and some reserved steel bars of the caps are overlapped by connecting sleeves, and the gap between the pier column and the groove is filled with a post-cast concrete layer. The post-cast concrete layer is made of UHPC concrete, and the adjacent caps are connected by tie beams.
优选的,所述盖梁、墩柱、承台、系梁、桩基均采用混凝土结构。Preferably, the cover beams, pier columns, caps, tie beams, and pile foundations all adopt concrete structures.
优选的,承台和盖梁内部的预留钢筋为L形钢筋,分别固定于承台和盖梁中,L形钢筋的竖直段部分分别预先通过混凝土浇灌固定在承台和盖梁内,盖梁中的预留钢筋局部延伸至盖梁的连接套管中,承台中的预留钢筋局部延伸至承台的凹槽外。Preferably, the reserved steel bars inside the cap and the cap beam are L-shaped steel bars, which are respectively fixed in the cap and the cap beam, and the vertical sections of the L-shaped steel bars are fixed in the cap and the cap beam by concrete pouring in advance, the reserved steel bars in the cap beam partially extend into the connecting sleeve of the cap beam, and the reserved steel bars in the cap partially extend outside the groove of the cap.
与现有技术相比,本实用新型具有以下有益效果:预制墩柱与承台间隙处浇筑UHPC混凝土层,提高了抗裂性,增加连接整体性,并且由于UHPC具有早期强度高发展快的特点,使得施工速度大大提升;相邻承台之间用系梁连接使得其连成整体受力,整体刚度加强;系梁中使用局部弯曲钢筋,弯曲钢筋承受弯矩作用,提高了其抗弯承载力。Compared with the prior art, the utility model has the following beneficial effects: the UHPC concrete layer is poured in the gap between the prefabricated pier column and the cap, which improves the crack resistance and increases the integrity of the connection, and because UHPC has the characteristics of high early strength and fast development, the construction speed is greatly improved; the tie beams are used to connect adjacent caps so that they are connected as a whole to bear the force and the overall rigidity is strengthened; local curved steel bars are used in the tie beams, and the curved steel bars bear the bending moment, which improves its bending resistance.
下面结合附图和具体实施方式对本实用新型做进一步详细的说明。Below in conjunction with accompanying drawing and specific embodiment, the utility model is described in further detail.
附图说明Description of drawings
图1为本实用新型实施例的墩柱结构示意图;Fig. 1 is the pier column structure schematic diagram of the utility model embodiment;
图2为本实用新型实施例的盖梁、墩柱与桩基连接结构示意图;Fig. 2 is the schematic diagram of the connection structure of the cover beam, the pier column and the pile foundation of the utility model embodiment;
图3为本实用新型实施例的整体结构示意图;Fig. 3 is the overall structure schematic diagram of the utility model embodiment;
图4为本实用新型实施例的系梁钢筋图。Fig. 4 is a diagram of the tie beam reinforcement of the utility model embodiment.
图中:1-墩柱;2-纵向钢筋;3-连接套管;4-预留钢筋;5-后浇混凝土层;6-桩基;7-盖梁;8-系梁;9-承台;10-系梁钢筋。In the figure: 1-pier column; 2-longitudinal reinforcement; 3-connecting casing; 4-reserved reinforcement; 5-post-cast concrete layer; 6-pile foundation;
具体实施方式Detailed ways
下面结合附图及实施例对本实用新型做进一步说明。Below in conjunction with accompanying drawing and embodiment the utility model is described further.
应该指出,以下详细说明都是示例性的,旨在对本申请提供进一步的说明。除非另有指明,本文使用的所有技术和科学术语具有与本申请所属技术领域的普通技术人员通常理解的相同含义。It should be pointed out that the following detailed description is exemplary and is intended to provide further explanation to the present application. Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs.
需要注意的是,这里所使用的术语仅是为了描述具体实施方式,而非意图限制根据本申请的示例性实施方式。如在这里所使用的,除非上下文另外明确指出,否则单数形式也意图包括复数形式,此外,还应当理解的是,当在本说明书中使用术语“包含”和/或“包括”时,其指明存在特征、步骤、操作、器件、组件和/或它们的组合。It should be noted that the terminology used here is only for describing specific implementations, and is not intended to limit the exemplary implementations according to the present application. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should also be understood that when the terms "comprising" and/or "comprises" are used in this specification, they indicate the presence of features, steps, operations, means, components and/or combinations thereof.
如图1~4所示,本实施例提供了一种系梁扩大组合连接桩柱的多柱式装配式墩体系,包括自上往下依次设置的盖梁、墩柱、承台、桩基,承台的上表面设置凹槽,墩柱底部放置在凹槽内,盖梁和墩柱的内底部均预留有连接套管,墩柱内部的若干预留纵向钢筋上部与盖梁内埋设的若干预留钢筋通过连接套管搭接,墩柱内部的若干预留纵向钢筋下部与承台的若干预留钢筋通过连接套管搭接,墩柱与凹槽之间的间隙处填充浇筑有后浇混凝土层,后浇混凝土层采用UHPC混凝土,相邻承台之间通过系梁连接。As shown in Figures 1 to 4, this embodiment provides a multi-column fabricated pier system in which tie beams are expanded and combined to connect piles, including cap beams, pier columns, caps, and pile foundations arranged in sequence from top to bottom. Grooves are arranged on the upper surface of the caps, and the bottom of the pier columns is placed in the grooves. Connecting sleeves are reserved at the inner bottom of the cap beams and pier columns. A number of reserved steel bars at the base and caps are overlapped by connecting sleeves, and the gap between the pier column and the groove is filled with a post-cast concrete layer. The post-cast concrete layer is made of UHPC concrete, and adjacent caps are connected by tie beams.
在本实用新型实施例中,所述盖梁、墩柱、承台、系梁、桩基均采用混凝土结构。In the embodiment of the utility model, the cover beams, pier columns, caps, tie beams, and pile foundations all adopt concrete structures.
在本实用新型实施例中,承台和盖梁内部的预留钢筋为L形钢筋,分别固定于承台和盖梁中,L形钢筋的竖直段部分分别预先通过混凝土浇灌固定在承台和盖梁内,盖梁中的预留钢筋局部延伸至盖梁的连接套管中,承台中的预留钢筋局部延伸至承台的凹槽外。In the embodiment of the utility model, the reserved steel bars inside the cap and the cap beam are L-shaped steel bars, which are respectively fixed in the cap and the cap beam. The vertical sections of the L-shaped steel bars are respectively fixed in the cap and the cap beam by concrete pouring in advance. The reserved steel bars in the cap beam partially extend into the connecting sleeve of the cap beam, and the reserved steel bars in the cap partially extend outside the groove of the cap.
在本实用新型实施例中,所述连接套管为灌浆波纹管。In the embodiment of the utility model, the connecting sleeve is a grouting corrugated pipe.
在本实用新型实施例中,系梁使用局部弯曲钢筋。In the embodiment of the utility model, the tie beam uses local bent steel bars.
一种系梁扩大组合连接桩柱的多柱式装配式墩体系的施工方法,按以下步骤进行:1)在工厂预制墩柱,墩柱中预留若干纵向钢筋,在墩柱底部预埋灌浆波纹管,其中预留纵向钢筋穿入灌浆波纹管中;2)对盖梁、承台和桩基进行施工,盖梁中预留L形钢筋和预埋灌浆波纹管,L形钢筋穿入灌浆波纹管中,承台中预埋L形钢筋,承台上部设有凹槽,L形钢筋延伸至承台的凹槽外;3)在施工现场,进行墩柱与桩基和盖梁的拼装,利用起吊设备吊起预制好的墩柱,将墩柱下部放置于承台凹槽正中心,承台凹槽中局部伸出的钢筋插入墩柱底部预留的灌浆波纹管中,墩柱上部局部伸出的预留纵向钢筋插入盖梁所留的灌浆波纹管中,使墩柱中预留纵向钢筋与承台和盖梁中预留钢筋搭接;4)在灌浆波纹管中灌入混凝土完成盖梁与墩柱纵向钢筋的搭接,承台与墩柱纵向钢筋的搭接;5)在墩柱与承台凹槽之间的间隙处填充浇筑UHPC混凝土;6)相邻承台之间进行系梁连接施工,采用现有的支模板现浇技术,待系梁固化后,完成施工。A construction method for a multi-column assembled pier system with beams enlarged and combined to connect piles, which is carried out according to the following steps: 1) Prefabricate pier columns in a factory, reserve a number of longitudinal steel bars in the pier columns, pre-embed grouting bellows at the bottom of the pier columns, wherein the reserved longitudinal steel bars penetrate into the grouting bellows; L-shaped steel bar, with a groove on the upper part of the cap, and the L-shaped steel bar extends out of the groove of the cap; 3) At the construction site, assemble the pier column, pile foundation and cover beam, use the lifting equipment to lift the prefabricated pier column, place the lower part of the pier column in the center of the cap groove, insert the partially protruding steel bar in the cap groove into the grouting bellows reserved at the bottom of the pier column, and insert the reserved longitudinal steel bars protruding from the upper part of the pier column into the grouting bellows reserved for the cover beam, so that the longitudinal reinforcement in the pier column 4) Pour concrete into the grouting bellows to complete the lapping of the longitudinal reinforcement of the cap beam and the pier column, and the lapping of the longitudinal reinforcement of the cap and the pier column; 5) Fill and pour UHPC concrete in the gap between the pier column and the groove of the cap; 6) Carry out the tie beam connection construction between the adjacent caps, using the existing cast-in-place technology of the support formwork, and complete the construction after the tie beam is cured.
本构造中预制墩柱、承台和盖梁内预留纵筋使得施工更加方便,提高了施工效率,降低了现场浇筑的难度;预制墩柱与承台的间隙处浇筑UHPC,提高了抗裂性,增加连接整体性,并且由于UHPC具有早期强度高发展快的特点,使得施工速度大大提升;相邻承台之间用系梁连接使其连成整体受力,整体刚度加强;系梁中使用局部弯曲钢筋,弯曲钢筋承受弯矩作用,提高了其抗弯承载力。In this structure, the reserved longitudinal reinforcement in the prefabricated pier columns, caps and cap beams makes the construction more convenient, improves the construction efficiency, and reduces the difficulty of on-site pouring; UHPC is poured in the gap between the prefabricated pier columns and the caps, which improves the crack resistance and increases the integrity of the connection, and because UHPC has the characteristics of high early strength and rapid development, the construction speed is greatly improved; the adjacent caps are connected by tie beams to make them connected as a whole. its flexural capacity.
以上所述,仅是本实用新型的较佳实施例而已,并非是对本实用新型作其它形式的限制,任何熟悉本专业的技术人员可能利用上述揭示的技术内容加以变更或改型为等同变化的等效实施例。但是凡是未脱离本实用新型技术方案内容,依据本实用新型的技术实质对以上实施例所作的任何简单修改、等同变化与改型,仍属于本实用新型技术方案的保护范围。The above is only a preferred embodiment of the utility model, and is not intended to limit the utility model in other forms. Any skilled person who is familiar with this field may use the technical content disclosed above to change or modify it into an equivalent embodiment with equivalent changes. However, any simple modifications, equivalent changes and modifications made to the above embodiments according to the technical essence of the present utility model without departing from the content of the technical solution of the utility model still belong to the protection scope of the technical solution of the utility model.
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202223090178.9U CN219385987U (en) | 2022-11-17 | 2022-11-17 | Multi-column assembled pier system of tie beam expansion combined connection pile |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202223090178.9U CN219385987U (en) | 2022-11-17 | 2022-11-17 | Multi-column assembled pier system of tie beam expansion combined connection pile |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN219385987U true CN219385987U (en) | 2023-07-21 |
Family
ID=87170699
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202223090178.9U Active CN219385987U (en) | 2022-11-17 | 2022-11-17 | Multi-column assembled pier system of tie beam expansion combined connection pile |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN219385987U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115652773A (en) * | 2022-11-17 | 2023-01-31 | 福州大学 | Multi-column type assembled pier system for connecting piles by expanding and combining tie beams and construction method |
-
2022
- 2022-11-17 CN CN202223090178.9U patent/CN219385987U/en active Active
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115652773A (en) * | 2022-11-17 | 2023-01-31 | 福州大学 | Multi-column type assembled pier system for connecting piles by expanding and combining tie beams and construction method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN206109970U (en) | Prefabricated assembled pier suitable for well meizoseismal area | |
| CN110396918B (en) | Assembled hollow pier system equivalent to cast-in-situ and construction method thereof | |
| CN211368352U (en) | Connecting structure for assembly type pier and bearing platform anchoring steel bar sleeving and inserting post-pouring RPC | |
| CN107190635B (en) | Dumbbell-shaped concrete-filled steel tubular composite pier and its connection structure and method with bearing platform | |
| CN108867342B (en) | High-durability earthquake collapse-resistant multi-column pier system and construction method | |
| CN109056506A (en) | Plug-in type post-tensioning prestressing without bondn section assembling concrete pier of steel tube | |
| CN108571070A (en) | A kind of Prefabricated concrete-filled steel tube ring beam connection structure and construction method | |
| CN110042741A (en) | A kind of casing constraint Precast Concrete Segmental Bridges pier stud and its construction method | |
| CN114592436A (en) | Pier capping beam lower support system and construction method thereof | |
| CN106958259B (en) | A kind of concrete towers column foundation and its construction method | |
| CN202000251U (en) | Cylindrical hollow prefabricated prestressed concrete pier structure | |
| WO2024036684A1 (en) | Fabricated bent cap and pier column combined structure and construction method therefor | |
| CN205369295U (en) | Basis precast prestressed beam slab formula wind power generation column foot plinth | |
| CN203403358U (en) | Latticed bridge tower of concrete filled steel pipe | |
| CN219385987U (en) | Multi-column assembled pier system of tie beam expansion combined connection pile | |
| CN110184903A (en) | A kind of prefabricated tubing string assembly bridge pier of truss-like | |
| CN218596898U (en) | Nondestructive control's multicolumn assembled mound structure system | |
| CN102392417A (en) | Dual-cantilever bearing support structure for large steel pipe and installation method | |
| CN211772934U (en) | Zero number block support system of bridge | |
| CN209816632U (en) | Arch foot structure for special-shaped space arch bridge | |
| CN209292868U (en) | Prefabricated assembled pile foundation pier | |
| CN218116110U (en) | Prefabricated double-layer steel pipe concrete composite pier structure | |
| CN114737608B (en) | Anti-seismic system and construction method of superimposed underground structure based on self-resetting truncated columns | |
| CN206941372U (en) | Concrete-filled steel tube with dumbbell sections assembled pier and the attachment structure with cushion cap | |
| CN216688997U (en) | Pier is assembled in prefabrication of removable part |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |