CN219045306U - A support structure for tall girder formwork - Google Patents
A support structure for tall girder formwork Download PDFInfo
- Publication number
- CN219045306U CN219045306U CN202223483755.0U CN202223483755U CN219045306U CN 219045306 U CN219045306 U CN 219045306U CN 202223483755 U CN202223483755 U CN 202223483755U CN 219045306 U CN219045306 U CN 219045306U
- Authority
- CN
- China
- Prior art keywords
- formwork
- supporting
- support
- rod
- length direction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000009415 formwork Methods 0.000 title claims description 59
- 230000008093 supporting effect Effects 0.000 claims abstract description 37
- 238000010276 construction Methods 0.000 description 4
- 238000009434 installation Methods 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000003466 welding Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域technical field
本实用新型属于建筑施工技术领域,涉及一种用于高大梁模板的支撑结构。The utility model belongs to the technical field of building construction, and relates to a supporting structure for a formwork for high beams.
背景技术Background technique
随着社会和工程技术的发展,越来越多的高大建筑拔地而起,高大模板的应用也越来越普遍,根据相关要求:搭设高度8m及以上,搭设跨度18m及以上,施工总荷载15KN/㎡及以上,集中线荷载20KN/m及以上模板支撑系统,属于超过一定规模的危险性较大的分部分项工程范围。With the development of society and engineering technology, more and more tall buildings rise from the ground, and the application of tall formwork is becoming more and more common. According to relevant requirements: the erection height is 8m and above, the erection span is 18m and above, and the total construction load 15KN/㎡ and above, and the concentrated line load 20KN/m and above formwork support system, which belongs to the scope of sub-project projects with greater danger beyond a certain scale.
实际施工中,高大梁模板支撑系统具有荷载大、高度高、多样性、复杂性及高危性等特点,过去几年发生的坍塌事故大多是由于在荷载作用下产生过大的变形或荷载,进而导致高大模板支撑体系失稳,导致建筑坍塌,严重影响着大型建筑的施工安全,因此,高大梁模板支撑系统的稳定性对工程建设的成功与否起到至关重要的作用,目前通常是通过重叠性地多设支撑杆(立杆和水平杆等)来提高支撑体的强度,但是上述支撑方式结构复杂且笨重,占用空间多,需要耗费大量的人力物力,且拆卸起来也非常耗时。In actual construction, the high girder formwork support system has the characteristics of large load, high height, diversity, complexity and high risk. Most of the collapse accidents in the past few years are due to excessive deformation or load under load, and then It leads to the instability of the tall formwork support system and the collapse of the building, which seriously affects the construction safety of large buildings. Therefore, the stability of the formwork support system of tall beams plays a vital role in the success of the project construction. Overlapping support rods (vertical rods and horizontal rods, etc.) are provided to increase the strength of the support body, but the structure of the above-mentioned support method is complex and cumbersome, takes up a lot of space, requires a lot of manpower and material resources, and is also very time-consuming to disassemble.
实用新型内容Utility model content
本实用新型的目的在于针对背景技术中高大梁模板支撑存在结构复杂且笨重,占用空间多,搭设和拆除时需要耗费大量的人力的问题,提供一种结实可靠、结构简单的用于高大梁模板的支撑结构。The purpose of the utility model is to provide a solid, reliable and simple structure for the high beam formwork support in view of the problems in the background technology that the structure is complex and heavy, takes up a lot of space, and requires a lot of manpower when erecting and dismantling. supporting structure.
为此,本实用新型采取如下技术方案:For this reason, the utility model takes following technical scheme:
一种用于高大梁模板的支撑结构,包括呈水平设置的横模板,所述横模板长度方向的两侧各设有一个呈竖直设置的竖模板,横模板的下表面沿横模板长度方向设有多个支撑横梁,所述支撑横梁沿横模板宽度方向设置,所述横模板的下方设有多个与支撑横梁一一对应且呈直线排布的立杆,所述立杆的顶端固定于支撑横梁的底部,所述支撑横梁长度方向的两端各设有一个呈倾斜且相互镜像设置的斜支撑杆,所述两个斜支撑杆之间连接有至少一个呈水平设置的对拉螺杆。A support structure for high girder formwork, comprising a horizontal formwork, a vertical formwork is arranged on each side of the length direction of the transverse formwork, and the lower surface of the transverse formwork is along the length direction of the transverse formwork. A plurality of supporting beams are provided, and the supporting beams are arranged along the width direction of the horizontal formwork, and a plurality of vertical poles corresponding to the supporting beams and arranged in a straight line are arranged under the horizontal formwork, and the top ends of the vertical poles are fixed At the bottom of the supporting beam, two ends in the length direction of the supporting beam are each provided with an oblique supporting rod that is inclined and mirrored with each other, and at least one horizontally arranged pull screw is connected between the two oblique supporting rods .
进一步地,所述斜支撑杆与水平面形成60-85度夹角。Further, the inclined support rod forms an included angle of 60-85 degrees with the horizontal plane.
进一步地,所述对拉螺杆通过连接件与斜支撑杆相连接,所述连接件包括呈竖直设置的拉板,所述拉板的上下两端各固定有一个连杆,所述连杆远离拉板的一端固定于斜支撑杆上,拉板的中部设有第二通孔,所述对拉螺杆的端部从第二通孔中穿过,对拉螺杆还套设有螺母。Further, the paired pull screw is connected to the diagonal support rod through a connecting piece, the connecting piece includes a vertically arranged pull plate, and a connecting rod is respectively fixed at the upper and lower ends of the pull plate, and the connecting rod The end far away from the pull plate is fixed on the inclined support rod, the middle part of the pull plate is provided with a second through hole, the end of the pull screw passes through the second through hole, and the pull screw is also sleeved with a nut.
进一步地,所述支撑横梁呈水平设置。Further, the supporting beams are arranged horizontally.
进一步地,所述立杆呈竖直设置。Further, the pole is arranged vertically.
进一步地,所述横模板的下方沿横模板长度方向设有呈水平设置的横杆,所述横杆与支撑立杆的中部连接。Further, horizontal bars are arranged below the horizontal formwork along the length direction of the transverse formwork, and the crossbars are connected to the middle of the support poles.
进一步地,所述斜支撑杆的顶端固定有连接板,所述连接板上设有第一通孔,所述支撑横梁的端部设有与第一通孔对应的螺孔,所述螺孔内安装有螺栓,所述螺栓从第一通孔中穿过。Further, a connection plate is fixed on the top end of the inclined support rod, and a first through hole is provided on the connection plate, and a screw hole corresponding to the first through hole is provided at the end of the support beam, and the screw hole Bolts are installed inside, and the bolts pass through the first through holes.
进一步地,所述竖模板的外侧沿竖模板长度方向设有多个与支撑横梁对应且呈倾斜设置的侧支撑杆,所述侧支撑杆的底端固定于支撑横梁的外端。Further, the outer side of the vertical formwork is provided with a plurality of side support bars corresponding to the support beams and inclined along the length direction of the vertical formwork, and the bottom ends of the side support bars are fixed to the outer ends of the support beams.
进一步地,所述立杆的底端设有垫底木块。Further, the bottom end of the pole is provided with a base wooden block.
本实用新型的有益效果在于:设置支撑横梁并在支撑横梁两端设置斜支撑杆,构成类似拱桥的结构,结构简单,可减少立柱的适用数量,节省空间,并能承受较大的外力;在两个斜支撑杆之间设置对拉螺杆,进一步提高支撑结构的稳定性,适用于高大梁模板的支撑;安装拆卸便捷,省事省力。The beneficial effect of the utility model is that: the support beam is set and the inclined support rods are arranged at both ends of the support beam to form a structure similar to an arch bridge. A pull screw is set between the two oblique support rods to further improve the stability of the support structure, which is suitable for the support of high beam formwork; the installation and disassembly are convenient and labor-saving.
附图说明Description of drawings
图1为本实用新型的结构示意图;Fig. 1 is the structural representation of the utility model;
图2为本实用新型的结构示意侧视图;Fig. 2 is a schematic side view of the structure of the utility model;
图3为图1中B部的局部放大图;Fig. 3 is a partial enlarged view of part B in Fig. 1;
图4为图1中A部的局部放大图;Fig. 4 is a partial enlarged view of part A in Fig. 1;
图中,1-横模板,2-竖模板,3-支撑横梁,4-立杆,5-垫底木块,6-斜支撑杆,7-对拉螺杆,8-连接件,801-拉板,802-连杆,803-第二通孔,804-螺母,9-横杆,10-侧支撑杆,11-连接板,12-第一通孔,13-螺孔,14-螺栓。In the figure, 1-horizontal formwork, 2-vertical formwork, 3-supporting beam, 4-vertical pole, 5-bottom wood block, 6-slanting support rod, 7-pair pull screw, 8-connector, 801-drawing plate , 802-connecting rod, 803-second through hole, 804-nut, 9-cross bar, 10-side support rod, 11-connecting plate, 12-first through hole, 13-screw hole, 14-bolt.
具体实施方式Detailed ways
下面结合附图对本实用新型做详细说明:Below in conjunction with accompanying drawing, the utility model is described in detail:
如图1-4所示,一种用于高大梁模板的支撑结构,包括呈水平设置的横模板1,横模板1即为横梁下侧模板,横模板1长度方向的两侧各设有一个呈竖直设置的竖模板2,竖模板2即为横梁两侧模板,横模板1的下表面沿横模板1长度方向设有多个呈水平设置的支撑横梁3,支撑横梁3沿横模板1宽度方向设置,通过支撑横梁3对横模板1进行支撑,支撑横梁3支撑面积大,对横模板1的压强小,横模板1的下方设有多个与支撑横梁3一一对应且呈直线排布的立杆4,立杆4呈竖直设置,立杆4的顶端固定于支撑横梁3的底部,立杆4的底端设有垫底木块5,通过立杆4和支撑横梁3对横模板1进行支撑,支撑横梁3长度方向的两端各设有一个呈倾斜且相互镜像设置的斜支撑杆6,斜支撑杆6与水平面形成60-85度夹角,本实施例中,斜支撑杆6与水平面形成80度夹角,通过斜支撑杆6对支撑横梁3进行辅助支撑,以提高稳定性,两个斜支撑杆6和支撑横梁3构成类似拱桥的结构,支撑稳定且效果好,同时节省材料,无需使用大量立杆,具体地,斜支撑杆6的顶端固定有连接板11,连接板11上设有第一通孔12,支撑横梁3的端部设有与第一通孔12对应的螺孔13,螺孔13内安装有螺栓14,螺栓14从第一通孔12中穿过,即通过螺栓14将斜支撑杆6的顶端与支撑横梁3固定连接,为了进一步提高支撑的稳定性,两个斜支撑杆6之间连接有至少一个呈水平设置的对拉螺杆7,本实施例中设置两个对拉螺杆7,分别位于斜支撑杆6的上侧和下侧,通过对拉螺杆7向两个斜支撑杆6施加向内侧的拉力,进而确保斜支撑杆6的稳定,具体地,对拉螺杆7通过连接件8与斜支撑杆6相连接,连接件8包括呈竖直设置的拉板801,拉板801的上下两端各采用焊接的方式固定有一个连杆802,连杆802远离拉板801的一端采用焊接的方式固定于斜支撑杆6上,拉板801的中部设有第二通孔803,对拉螺杆6的端部从第二通孔803中穿过,对拉螺杆7的端部还设有螺母804,采用螺母拧紧后可使得对拉螺杆6对斜支撑杆6施加拉力,进一步使得斜支撑杆6保持稳定,有效保持对支撑横梁3的支撑效果。As shown in Figure 1-4, a support structure for high beam formwork, including a horizontal formwork 1, the transverse formwork 1 is the lower side formwork of the beam, and each side of the length direction of the transverse formwork 1 is provided with a The vertical formwork 2 arranged vertically, the vertical formwork 2 is the formwork on both sides of the beam, the lower surface of the horizontal formwork 1 is provided with a plurality of horizontally arranged
横模板1的下方沿横模板1长度方向设有呈水平设置的横杆9,横杆9与立杆4的中部连接,连接方式采用现有常规方式即可,竖模板2的外侧沿,竖模板2的长度方向设有多个与支撑横梁3对应且呈倾斜设置的侧支撑杆10,侧支撑杆10的底端固定于支撑横梁3的外端,通过侧支撑杆10对竖模板2进行常规支撑。The bottom of the horizontal formwork 1 is provided with a
本实用新型的使用方式如下:The usage of the utility model is as follows:
在使用过程中首先进行立杆4和支撑横梁3的搭设,搭设完成后安装斜支撑杆6,安装斜支撑杆6时先安装一侧斜支撑杆6,将对拉螺杆7的一端插入连接件8的第二通孔803中,然后安装另一侧对应的斜支撑杆6,安装好后将螺杆7的另一端插入另一个插入连接件8的第二通孔803中,最后进行螺母804,完成斜支撑杆6的安装,最后安装横杆9和侧支撑杆10,横杆9采用脚手架扣件安装即可,侧支撑杆10采用现有常规安装方式。整个支撑结构简单占用空间少,两个斜支撑杆6和支撑横梁3构成类似拱桥的结构,可减少立柱的数量,并能承受较大的外力且结构稳定,适用于高大梁模板的支撑。In the process of use, the
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202223483755.0U CN219045306U (en) | 2022-12-27 | 2022-12-27 | A support structure for tall girder formwork |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202223483755.0U CN219045306U (en) | 2022-12-27 | 2022-12-27 | A support structure for tall girder formwork |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN219045306U true CN219045306U (en) | 2023-05-19 |
Family
ID=86318550
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202223483755.0U Expired - Fee Related CN219045306U (en) | 2022-12-27 | 2022-12-27 | A support structure for tall girder formwork |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN219045306U (en) |
-
2022
- 2022-12-27 CN CN202223483755.0U patent/CN219045306U/en not_active Expired - Fee Related
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN204690596U (en) | Viaduct bent cap sizing bed die support | |
| CN208039827U (en) | Building templates fixing device | |
| CN206530056U (en) | Construction beam adjustable supporting device | |
| CN219045306U (en) | A support structure for tall girder formwork | |
| CN102127962B (en) | The bidirectional stress base section of the attached lift scaffold improved | |
| CN218862104U (en) | Column formwork reinforced structure | |
| CN218150027U (en) | Novel box ladder cage | |
| CN214739106U (en) | A curtain wall steel frame joint | |
| CN214364939U (en) | A fastener type steel tube lattice column support structure | |
| CN214220599U (en) | Batter post bearing structure | |
| CN220889484U (en) | Template supporting system with outer extending platform | |
| CN116104018A (en) | Construction method of installation device for variable cross-section special-shaped steel tower crown | |
| CN210263392U (en) | Simple detachable temporary assembly type steel structure processing shed | |
| CN203684749U (en) | Recyclable prefabricated steel processing shed | |
| CN210365423U (en) | Trestle support with light steel structure | |
| CN208415294U (en) | Steam turbine bedplate construction device | |
| CN218912897U (en) | Side wall template support structure of deep foundation pit working well | |
| CN210049630U (en) | A kind of rainproof shelter for ancient buildings | |
| CN220645154U (en) | Socket type disc buckle type shaping tripod outer protection frame | |
| CN221194255U (en) | A frame anti-dumping structure for supporting formwork of building beams | |
| CN223562518U (en) | Diagonal column template supporting system | |
| CN223088635U (en) | Disassembly-assembly type factory building steel structure of multi-layer industrial factory building | |
| CN205224579U (en) | Steel framework template and self -supporting truss board combination concrete quick detach system | |
| CN223880732U (en) | Support truss | |
| CN222101545U (en) | A movable lifting steel bar protection platform |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20230519 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |