CN218754514U - Fixture for hoisting steel pipe pile with cross pile tip - Google Patents

Fixture for hoisting steel pipe pile with cross pile tip Download PDF

Info

Publication number
CN218754514U
CN218754514U CN202222954377.3U CN202222954377U CN218754514U CN 218754514 U CN218754514 U CN 218754514U CN 202222954377 U CN202222954377 U CN 202222954377U CN 218754514 U CN218754514 U CN 218754514U
Authority
CN
China
Prior art keywords
cross
fixture
steel pipe
pipe pile
hoisting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222954377.3U
Other languages
Chinese (zh)
Inventor
谢丹
张清政
周燕飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Civil Engineering Construction Corp
Original Assignee
China Civil Engineering Construction Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Civil Engineering Construction Corp filed Critical China Civil Engineering Construction Corp
Priority to CN202222954377.3U priority Critical patent/CN218754514U/en
Application granted granted Critical
Publication of CN218754514U publication Critical patent/CN218754514U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model provides a fixture for lifting by crane steel-pipe pile that has cross stake point, this fixture includes: the fixture comprises a fixture body, wherein the fixture body is provided with a clamping part and a hoisting part, and the clamping part is provided with a limiting clamping hole for clamping the cross pile tip of the steel pipe pile. The hoisting part is also provided with a hoisting hole for fixing the rope. The fixture is simple in structure, convenient to mount and dismount, and the hoisting speed of the steel pipe pile is greatly increased. In addition, the fixture can firmly sleeve the cross pile tip, the steel pipe pile is prevented from rotating, and the safety and stability of the hoisting process are guaranteed.

Description

Fixture for hoisting steel pipe pile with cross pile tip
Technical Field
The utility model relates to a steel-pipe pile fixture technical field specifically is a fixture that is used for lifting by crane the steel-pipe pile that has cross stake point.
Background
The steel pipe pile is a foundation suitable for construction of wharf ports, and the diameter range of the steel pipe pile is generally 400-2000 mm. The hoisting of the steel pipe pile is not provided with a special fixture, the construction site is often narrow in space, the steel pipe pile is long, and the steel pipe pile cannot be transferred by a forklift, so that a steel wire rope or a binding belt is mostly adopted to penetrate through the bottom of the steel pipe pile to be embraced, then the steel pipe pile is hoisted by a crane, and the steel pipe pile is turned in the air and then landed. The method needs to manually thread the steel wire rope or the binding belt every time, has low efficiency and is not suitable for the condition of transferring a large number of steel pipe piles.
Therefore, a clamp which has a simple structure and low production cost and can quickly clamp the steel pipe pile is urgently needed by the technical personnel in the field.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to overcome prior art not enough, provide a fixture for lifting by crane the steel-pipe pile that has cross stake point to solve the problem that steel-pipe pile transfer process is inefficient among the prior art.
The utility model provides a fixture for lifting by crane steel-pipe pile that has cross stake point, this fixture includes: the fixture comprises a fixture body, wherein the fixture body is provided with a clamping part and a hoisting part, wherein the clamping part is provided with a limiting clamping hole for clamping a cross pile tip of the steel pipe pile; the hoisting part is also provided with a hoisting hole for fixing a rope.
Furthermore, the limiting clamping hole is a cross-shaped through hole and used for clamping the cross-shaped pile tip.
Furthermore, the maximum length of the cross-shaped through hole in the radial direction is 300-2000 mm.
In an embodiment of the present invention, the thickness of the lifting portion is greater than the thickness of the positioning portion, for increasing the structural strength of the lifting portion.
The utility model discloses an among the embodiment, be provided with a plurality of strengthening ribs on the portion of hoisting, be used for increasing the structural strength of portion of hoisting.
According to the above embodiment, the utility model provides a fixture for lifting by crane steel-pipe pile that has cross stake point has following benefit: the clamp is convenient for on-site processing, mounting and dismounting, saves the process of binding the steel pipe pile by using a rope, saves the labor for hoisting preparation, and greatly improves the hoisting speed. In addition, the cross pile point can be firmly sleeved by the fixture, the steel pipe pile is prevented from rotating, and the hoisting process is safe and stable.
It is to be understood that both the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the invention, as claimed.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of the specification of the invention, illustrate exemplary embodiments of the invention and together with the description, serve to explain the principles of the invention.
Fig. 1 is a first structural diagram of an embodiment of the first clamping apparatus for hoisting a steel pipe pile with a cross pile tip provided by the present invention.
Fig. 2 is a first usage state diagram of the first embodiment of the fixture for lifting a steel pipe pile with a cross pile tip provided by the present invention.
Fig. 3 is a second structure diagram of the embodiment of the fixture for lifting the steel pipe pile with the cross pile tip provided by the utility model.
Fig. 4 is a third structural view of the embodiment of the fixture for lifting the steel pipe pile with the cross pile tip provided by the utility model.
Fig. 5 is a structural diagram of a fourth embodiment of the fixture for lifting a steel pipe pile with a cross pile tip provided by the present invention.
Description of the reference numerals:
1-a clamp body, 2-a limiting clamp hole, 3-a steel pipe pile, 4-a lifting hole, 5-a rope, 6-a reinforcing rib and 7-a hook clamp;
11-clamping part, 12-hoisting part and 31-cross pile tip.
Detailed Description
Reference will now be made in detail to various exemplary embodiments of the invention, which should not be considered limiting of the invention, but rather should be understood to be a more detailed description of certain aspects, features and embodiments of the invention.
It will be apparent to those skilled in the art that various modifications and variations can be made in the embodiments of the present disclosure without departing from the scope or spirit of the disclosure. Other embodiments will be apparent to those skilled in the art from consideration of the specification. The specification and examples are exemplary only.
The utility model provides a fixture for lifting by crane steel-pipe pile that has cross stake point, be the structure diagram of this fixture embodiment one as shown in figure 1. In a particular embodiment, the clip comprises: the jig main body 1 includes a positioning portion 11 and a lifting portion 12 in the jig main body 1. The limiting clamping hole 2 is arranged on the clamping part 11 and used for clamping a cross pile tip 31 of the steel pipe pile 3; the hoisting part 12 is also provided with a hoisting hole 4 for fixing the rope 5.
Furthermore, the limiting clamping hole 2 is a cross-shaped through hole and used for clamping the cross-shaped pile tip 31. As shown in fig. 2, the cross-shaped through hole corresponds to the cross-shaped pile tip 31, and the rotation in the circumferential direction after the cross-shaped pile tip 31 is inserted into the cross-shaped through hole can be limited, so that the steel pipe pile 3 can be prevented from rotating during hoisting, and the risk of falling of the steel pipe pile caused by rotation can be avoided.
In the embodiment shown in fig. 1, the cross-shaped through hole is two through holes perpendicular to each other, one of the through holes is arranged in the vertical direction, and the other through hole is arranged in the horizontal direction.
In addition, as shown in the embodiment of fig. 3, both through holes have a certain angle with the horizontal line.
Furthermore, the maximum length of the cross-shaped through hole in the radial direction is 300-2000 mm. The larger the radial maximum length of the cross-shaped through hole is, the more steel pipe piles with different sizes can be adapted to.
In the embodiment shown in fig. 4, the thickness of the lifting portion 12 is greater than that of the positioning portion 11, so as to increase the structural strength of the lifting portion 12, greatly increase the tensile strength of the lifting portion 12, and prolong the service life.
In the embodiment shown in fig. 5, a plurality of reinforcing ribs 6 are provided on the suspended portion 12 for increasing the structural strength of the suspended portion 12. In this embodiment, the strengthening rib 6 is along the vertical setting of pulling force direction, can promote the tensile strength who hangs 12 of portion greatly, promotes life.
When in use, as shown in fig. 2, one end of the steel pipe pile 3 with the cross pile tip 31 is inserted into the cross through hole of the clamp, and the steel pipe wall at the other end is clamped with the hook clamp 7. The hanging hole 4 and the hook clamp 7 are fixedly connected by a rope 5 respectively. Then, the rope 5 is fixedly connected to a boom of the hoisting device, and the steel-pipe pile 3 is hoisted by the rope 5.
The foregoing is only an illustrative embodiment of the present invention, and any equivalent changes and modifications made by those skilled in the art without departing from the spirit and principles of the present invention should fall within the protection scope of the present invention.

Claims (5)

1. A fixture for lifting a steel pipe pile having a cross-shaped pile tip, the fixture comprising: a fixture body (1), wherein the fixture body (1) is provided with a clamping part (11) and a hoisting part (12),
the clamping part (11) is provided with a limiting clamping hole (2) for clamping a cross pile tip (31) of the steel pipe pile (3);
the hoisting part (12) is also provided with a hoisting hole (4) for fixing the rope (5).
2. The clamp for lifting a steel pipe pile with a cross-shaped pile tip as claimed in claim 1, wherein the limiting clamp hole (2) is a cross-shaped through hole for clamping the cross-shaped pile tip (31).
3. The jig for hoisting a steel pipe pile having a cross-shaped pile tip as claimed in claim 2, wherein the maximum length of the cross-shaped through hole in the radial direction is 300mm to 2000mm.
4. The jig for hoisting a steel pipe pile having a cross-shaped pile tip as claimed in claim 1, wherein the thickness of the hoisting part (12) is greater than the thickness of the retainer part (11) for increasing the structural strength of the hoisting part (12).
5. A fixture for lifting a steel pipe pile with a cross pile tip according to claim 1, characterized in that a plurality of reinforcing ribs (6) are provided on the lifting part (12) for increasing the structural strength of the lifting part (12).
CN202222954377.3U 2022-11-07 2022-11-07 Fixture for hoisting steel pipe pile with cross pile tip Active CN218754514U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222954377.3U CN218754514U (en) 2022-11-07 2022-11-07 Fixture for hoisting steel pipe pile with cross pile tip

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222954377.3U CN218754514U (en) 2022-11-07 2022-11-07 Fixture for hoisting steel pipe pile with cross pile tip

Publications (1)

Publication Number Publication Date
CN218754514U true CN218754514U (en) 2023-03-28

Family

ID=85647858

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222954377.3U Active CN218754514U (en) 2022-11-07 2022-11-07 Fixture for hoisting steel pipe pile with cross pile tip

Country Status (1)

Country Link
CN (1) CN218754514U (en)

Similar Documents

Publication Publication Date Title
CN107215765A (en) Lift shackle
CN218754514U (en) Fixture for hoisting steel pipe pile with cross pile tip
CN206502521U (en) A kind of construction suspender for being used to lift tube
CN211769786U (en) Culvert pipe lifting device for municipal construction
CN210682955U (en) Hoisting clamp for crane
CN220537296U (en) Pipeline overhead hoist
JP2007022789A (en) Suspension tool and vertical pipe construction method
CN206599363U (en) Vertical transferring apparatus
CN108689298B (en) Hoisting device for pipe fitting
CN218754569U (en) Pipeline hoisting fixture
CN218371197U (en) Hoisting device for preventing orifice deformation of secant pile steel sleeve
CN224000874U (en) Auxiliary hoisting device for short pipe pile
CN220148983U (en) Pipeline lifting device
CN211521357U (en) Through-flow rotor hoisting tool
CN214087302U (en) Lifting appliance for foundation pit supporting construction
CN214359746U (en) Bulk steel bar vertical lifting device
CN213569132U (en) Efficient concrete piping erection is with safe practical lifting hook
CN211948442U (en) Lower reinforcement cage guiding device for bridge construction
CN213387440U (en) A PHC pipe pile hoisting device
CN204778295U (en) Novel multi -functional lifting by crane device
CN210366642U (en) Large-scale bearing hanging device
CN115092810A (en) Hoisting device for epoxy steel parts of pier body
CN206927467U (en) A kind of lifting pipeline instrument
CN216360354U (en) Building engineering building material hoist device
CN219116960U (en) Triangle-shaped glass plate hoist and mount anchor clamps

Legal Events

Date Code Title Description
GR01 Patent grant