CN218733133U CN202222636089.3U CN202222636089U CN218733133U CN 218733133 U CN218733133 U CN 218733133U CN 202222636089 U CN202222636089 U CN 202222636089U CN 218733133 U CN218733133 U CN 218733133U
Authority
CN
China
Prior art keywords
assembling
calandria
piece
rail
cable duct
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222636089.3U
Other languages
Chinese (zh)
Inventor
张健华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Chuangchuan Cement Pre Products Co ltd
Original Assignee
Jiangsu Chuangchuan Cement Pre Products Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Chuangchuan Cement Pre Products Co ltd filed Critical Jiangsu Chuangchuan Cement Pre Products Co ltd
Priority to CN202222636089.3U priority Critical patent/CN218733133U/en
Application granted granted Critical
Publication of CN218733133U publication Critical patent/CN218733133U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The utility model discloses a prefabricated cable duct bank structure is prevented subsiding by fast-assembling, use in prefabricated cable duct bank technical field, assemble the rail through the setting, assemble calandria mechanism, fixed subassembly, assemble the extension subassembly, a plurality of rails of assembling can carry out the unlimited extension of assembling through assembling the extension subassembly, it can be carrying out a plurality of combinations concatenations to assemble calandria mechanism on assembling the rail, no matter how many cable pipes that need arrange all can arrange and fix like this, fixed subassembly fixes assembling calandria mechanism this moment, the top that makes the calandria mechanism of assembling is fixed, calandria mechanism is fixed this moment, can assemble the calandria mechanism of assembling with the extension this moment according to the demand, the whole heavy condition of traditional calandria mechanism can be avoided to assembling calandria mechanism of pin-connected panel simultaneously.

Description

Prefabricated cable duct bank structure is prevented subsiding by fast-assembling
Technical Field
The utility model belongs to the technical field of the prefabricated cable duct bank, in particular to prefabricated cable duct bank structure is prevented subsiding by fast-assembling.
Background
The power calandria is a device for meeting the requirements of a cable access channel and an overhead line access ground of a transformer substation and providing a power channel for power supply matching of a ground block along the line, and is also called a cable pipe, a power cable pipe, a cement cable pipe, a power calandria and the like.
The current announcements are: CN 216819293U's chinese utility model discloses a prefabricated cable duct pipe is prevented subsiding by fast-assembling, relate to the cable duct pipe field, the utility model discloses a cable duct pipe, the bottom of cable duct pipe is fixed with the mount pad through the backup pad, the both sides below of cable duct pipe is fixed with prevents sinking the board, one side of cable duct pipe runs through there is the calandria mouth, calandria mouth's inside runs through there is the cable duct, one side of calandria mouth is provided with anti-skidding subassembly, this utility model discloses a be provided with the mount pad and prevent sinking the board, bury fixed back at the mount pad, can fix through the mount pad, and prevent sinking the board and be in the lifting surface area of multiplicable cable duct pipe, make the cable duct pipe more be difficult for appearing subsiding the slope, this utility model discloses a be provided with anti-skidding subassembly, when the cable duct inserts to calandria mouth, can make the upset of flexible bur, thereby strengthen the frictional force of its contact through the flexible bur, make the cable duct installation more stable, and the cooperation locating plate is spacing, can further improve the security of cable duct.
The prefabricated cable calandria mechanism is prevented subsiding by current fast-assembling is whole huge heavy, has increaseed constructor's engineering time and has hung up and put down when installing because heavy calandria mechanism brings the potential safety hazard easily, and this kind of calandria mechanism that hole quantity is fixed simultaneously, the hole causes the waste of hole more for a long time than the cable pipe that will arrange, and the hole will produce the unable fixed problem of being arranged of partial cable pipe than the small in quantity of cable pipe
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a prefabricated cable duct bank structure is prevented subsiding by fast-assembling, its advantage is assembled and the calandria mechanism of extension according to the demand, and the calandria mechanism of pin-connected panel can avoid the whole heavy condition of calandria mechanism simultaneously.
The above technical purpose of the utility model is realized through following technical scheme, a prefabricated cable calandria structure is prevented subsiding by fast-assembling, including assembling the rail, the top joint of assembling the rail has assembles calandria mechanism, the top of assembling calandria mechanism is provided with fixed subassembly, the one side of assembling the rail is provided with assembles the extension subassembly.
Adopt above-mentioned technical scheme, assemble the rail through the setting, assemble calandria mechanism, fixed subassembly, assemble the extension subassembly, a plurality of rails of assembling can carry out unlimited extension of assembling through assembling the extension subassembly, it can carry out a plurality of combinations concatenations to assemble calandria mechanism on assembling the rail, no matter how many cable pipes that need arrange like this can all arrange and fix, fixed subassembly is fixed assembling calandria mechanism this moment, the top that makes the calandria mechanism of assembling is fixed, it is fixed to assemble calandria mechanism this moment, can assemble the calandria mechanism of assembling with the extension this moment according to the demand, the calandria mechanism of assembling of pin-connected panel can avoid the whole heavy condition of traditional calandria mechanism simultaneously.
The utility model discloses further set up to: it includes calandria piece, income pipe box, joint piece and joint groove to assemble calandria mechanism, calandria piece joint is in the inside of assembling the rail, go into the pipe box and set up in the inside and the align to grid of calandria piece, the joint piece welds in the lateral wall of calandria piece, one side of calandria piece is set up in the joint groove, joint piece joint in the joint groove of adjacent calandria piece one side, the quantity of calandria piece is a plurality of.
Adopt above-mentioned technical scheme, through setting up the calandria piece, going into tub groove, joint piece and joint groove, a plurality of calandria pieces make up the concatenation on assembling the rail, and the joint piece of calandria piece one side inserts the joint inslot this moment, and a plurality of calandria pieces can be assembled according to the demand.
The utility model discloses further set up to: the fixing assembly comprises a fixing bolt and a fixing nut, the fixing bolt sequentially penetrates through the plurality of calandria blocks, and the fixing nut is in threaded connection with two ends of the fixing bolt respectively.
Adopt above-mentioned technical scheme, through setting up gim peg and fixation nut, the gim peg passes a plurality of calandria blocks, and two fixation nut are twisted at the both ends of gim peg this moment, and a plurality of calandria blocks that are fixed this moment can not scatter.
The utility model discloses further set up to: assemble extension subassembly including installation protruding board, insertion groove and insert the pole, protruding board welds in the one end of assembling the rail, the one end of assembling the rail is seted up in the insertion groove, the insert pole welds in the interior bottom of insertion groove, the insert pole runs through protruding board.
Adopt above-mentioned technical scheme, through setting up protruding board, insertion groove and insert the pole, assemble the inside that the protruding board of one side of rail inserted another insertion groove of assembling the rail, two this moment assemble the rail and place according to the demand extension, assemble the ground of rail simultaneously and also increase with the area of contact on ground, avoid calandria piece to subside.
The utility model discloses further set up to: the two sides of the assembly rail are welded with supporting plates which increase the contact area with the ground.
By adopting the technical scheme, the contact area between the assembly rail and the ground is increased by arranging the support plate, and the pipe discharging block is prevented from settling.
The utility model discloses further set up to: the calandria piece is located the top of bellying board.
By adopting the technical scheme, the pipe arranging block and the protruding plate are arranged, the pipe arranging block presses the protruding plate, and the protruding plate is prevented from being disassembled by the two spliced assembling rails due to uneven upwarping of the ground.
The utility model discloses further set up to: and a plurality of flexible spurs are arranged inside the pipe inlet groove.
By adopting the technical scheme, the friction force of the cable pipe is increased by arranging the flexible spurs, and the cable pipe is prevented from being damaged by the rotation of the cable pipe in the pipe entering groove.
To sum up, the utility model discloses following beneficial effect has:
assemble the rail through the setting, assemble calandria mechanism, fixed subassembly, assemble the extension subassembly, a plurality of rails of assembling can carry out the unlimited extension of assembling through assembling the extension subassembly, it can carry out a plurality of combinations concatenations to assemble calandria mechanism on assembling the rail, no matter how many cable pipes that need arrange like this can all arrange and fix, fixed subassembly is fixed assembling calandria mechanism this moment, the top that makes the calandria mechanism of assembling is fixed, it is fixed to assemble calandria mechanism this moment, can assemble the calandria mechanism of assembling with the extension according to the demand this moment, the calandria mechanism of assembling of pin-connected panel can avoid the whole heavy condition of traditional calandria mechanism simultaneously.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention;
fig. 2 is a schematic structural view of the pipe arranging mechanism assembled in the present invention;
FIG. 3 is a schematic structural view of the middle split-joint extension assembly of the present invention;
fig. 4 is a schematic structural view of the fixing assembly of the present invention;
fig. 5 is a schematic structural diagram of an enlarged view of a portion a in fig. 2 according to the present invention.
In the figure, 1, assembling rails; 2. assembling a calandria mechanism; 5. a fixing assembly; 6. assembling the extension component; 7. a support plate; 8. flexible stabbing; 201. a pipe arrangement block; 202. a pipe inlet groove; 203. a clamping block; 204. a clamping groove; 501. a fixing bolt; 502. fixing a nut; 601. a raised plate; 602. and inserting the groove.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
The embodiment is as follows:
referring to fig. 1-5, the present invention provides a technical solution: the utility model provides a prefabricated cable duct bank structure is prevented subsiding by fast-assembling, including assembling rail 1, it assembles calandria mechanism 2 to assemble to connect the top joint of rail 1, the top of assembling calandria mechanism 2 is provided with fixed subassembly 5, one side of assembling rail 1 is provided with assembles extension subassembly 6, assemble rail 1 through the setting, assemble calandria mechanism 2, fixed subassembly 5, assemble extension subassembly 6, a plurality of rails 1 of assembling can carry out the unlimited extension of assembling through assembling extension subassembly 6, it can carry out a plurality of combinations concatenation to assemble calandria mechanism 2 on assembling rail 1, no matter how many cable pipes that need arrange like this can all arrange and fix, fixed subassembly 5 fixes assembling calandria mechanism 2 this moment, the top that makes assembling calandria mechanism 2 is fixed this moment, can assemble calandria mechanism 2 according to the demand this moment and be assembled calandria mechanism 2, the whole bulky condition of traditional calandria mechanism can be avoided to assembling calandria mechanism 2 of pin-lock simultaneously.
Referring to fig. 2, it includes calandria piece 201 to assemble calandria mechanism 2, go into tub groove 202, joint piece 203 and joint groove 204, calandria piece 201 joint is in the inside of assembling rail 1, it offers in calandria piece 201 inside and align to grid to go into tub groove 202, joint piece 203 welds in the lateral wall of calandria piece 201, joint groove 204 offers in one side of calandria piece 201, joint piece 203 joint is in the joint groove 204 of adjacent calandria piece 201 one side, the quantity of calandria piece 201 is a plurality of, through setting up calandria piece 201, go into tub groove 202, joint piece 203 and joint groove 204, a plurality of calandria pieces 201 are assembling the concatenation on assembling rail 1, the joint piece 203 of calandria piece 201 one side inserts in joint groove 204 this moment, a plurality of calandria pieces 201 can be assembled according to the demand.
Referring to fig. 4, the fixing assembly 5 includes a fixing bolt 501 and a fixing nut 502, the fixing bolt 501 sequentially penetrates through the plurality of pipe arrangement blocks 201, the fixing nut 502 is respectively screwed at two ends of the fixing bolt 501, by providing the fixing bolt 501 and the fixing nut 502, the fixing bolt 501 penetrates through the plurality of pipe arrangement blocks 201, at this time, the two fixing nuts 502 are screwed at two ends of the fixing bolt 501, and at this time, the plurality of pipe arrangement blocks 201 fixed are fixed without being scattered.
Referring to fig. 3, the assembly extension assembly 6 includes an installation protrusion plate 601, an insertion groove 602 and an insertion rod 603, the protrusion plate 601 is welded at one end of the assembly rail 1, the insertion groove 602 is opened at one end of the assembly rail 1, the insertion rod 603 is welded at the inner bottom of the insertion groove 602, the insertion rod 603 penetrates through the protrusion plate 601, by providing the protrusion plate 601, the insertion groove 602 and the insertion rod 603, the protrusion plate 601 at one side of the assembly rail 1 is inserted into the insertion groove 602 of the other assembly rail 1, at this time, the two assembly rails 1 are extended according to requirements, meanwhile, the ground of the assembly rail 1 also increases the contact area with the ground, and the discharge pipe block 201 is prevented from settling.
Referring to fig. 1, the support plates 7 increasing the contact area with the ground are welded on the two sides of the assembling rail 1, and by arranging the support plates 7, the contact area between the assembling rail 1 and the ground is increased by the support plates 7, so that the pipe arrangement block 201 is prevented from settling.
Referring to fig. 2 and 3, the calandria block 201 is located on top of the convex plate 601, and by arranging the calandria block 201 and the convex plate 601, the calandria block 201 presses the convex plate 601, so as to prevent the convex plate 601 from being tilted due to uneven ground to separate the two spliced splicing rails 1.
Referring to fig. 5, the flexible spurs 8 are disposed inside the pipe entering groove 202, and friction of the cable pipe is increased by the flexible spurs 8, so that damage to cables inside the cable pipe caused by rotation of the cable pipe inside the pipe entering groove 202 is avoided.
The using process is briefly described as follows: a plurality of calandria piece 201 are assembling the concatenation of making up on assembling rail 1, the joint piece 203 of calandria piece 201 one side inserts in joint groove 204 this moment, a plurality of calandria pieces 201 can be assembled according to the demand, gim peg 501 passes a plurality of calandria pieces 201, two fixation nuts 502 are twisted at the both ends of gim peg 501 this moment, a plurality of calandria pieces 201 fixed can not scatter this moment, assemble the inside that the protruding board 601 of one side of rail 1 inserted another insertion groove 602 of assembling rail 1, two of assembling rail 1 place according to the demand extension this moment, it also increases the area of contact with ground to assemble the ground of rail 1 simultaneously, avoid calandria piece 201 to subside, backup pad 7 increases the area of contact of assembling rail 1 and ground, avoid calandria piece 201 to subside, avoid protruding board 601 to make two assembling rails 1 of splicing decompose because the ground is not flat perk, flexible thorn 8 makes the cable duct increase frictional force, avoid the cable duct to rotate in the inside of income chase 202 and cause the cable damage of cable duct.
The specific embodiments are only for explaining the present invention, and it is not a limitation to the present invention, and those skilled in the art can make modifications to the embodiments without inventive contribution as required after reading the present specification, but all the embodiments are protected by patent law within the scope of the claims of the present invention.

Claims (7)

1. The utility model provides a prefabricated cable duct bank structure is prevented subsiding by fast-assembling, is including assembling rail (1), its characterized in that: it assembles calandria mechanism (2) to assemble the top joint of rail (1), the top of assembling calandria mechanism (2) is provided with fixed subassembly (5), the one side of assembling rail (1) is provided with assembles extension subassembly (6).
2. The fast-assembling anti-settlement prefabricated cable duct bank structure according to claim 1, characterized in that: assemble calandria mechanism (2) including calandria piece (201), income tube seat (202), joint piece (203) and joint groove (204), calandria piece (201) joint is in the inside of assembling rail (1), go into tube seat (202) and set up in the inside and the align to grid of calandria piece (201), joint piece (203) weld in the lateral wall of calandria piece (201), one side of calandria piece (201) is set up in joint groove (204), joint piece (203) joint is in joint groove (204) of adjacent calandria piece (201) one side, the quantity of calandria piece (201) is a plurality of.
3. The fast-assembling anti-settlement prefabricated cable duct bank structure according to claim 2, characterized in that: the fixing component (5) comprises a fixing bolt (501) and a fixing nut (502), the fixing bolt (501) penetrates through the plurality of pipe arranging blocks (201) in sequence, and the fixing nut (502) is in threaded connection with two ends of the fixing bolt (501) through threads.
4. The fast-assembling anti-settlement prefabricated cable duct bank structure according to claim 2, characterized in that: assemble extension subassembly (6) including installation protruding board (601), insertion groove (602) and inserted bar (603), protruding board (601) welds in the one end of assembling rail (1), insertion groove (602) are seted up in the one end of assembling rail (1), inserted bar (603) weld in the interior bottom of insertion groove (602), inserted bar (603) run through protruding board (601).
5. The fast-assembling anti-settlement prefabricated cable duct bank structure according to claim 1, characterized in that: the two sides of the assembly rail (1) are welded with supporting plates (7) which increase the contact area with the ground.
6. The quick-install anti-settling prefabricated cable duct bank structure according to claim 4, wherein: the calandria block (201) is positioned on the top of the convex plate (601).
7. The fast-assembling anti-settlement prefabricated cable duct bank structure according to claim 2, characterized in that: the interior of the pipe-entering groove (202) is provided with a plurality of flexible spurs (8).
CN202222636089.3U 2022-10-08 2022-10-08 Prefabricated cable duct bank structure is prevented subsiding by fast-assembling Active CN218733133U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222636089.3U CN218733133U (en) 2022-10-08 2022-10-08 Prefabricated cable duct bank structure is prevented subsiding by fast-assembling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222636089.3U CN218733133U (en) 2022-10-08 2022-10-08 Prefabricated cable duct bank structure is prevented subsiding by fast-assembling

Publications (1)

Publication Number Publication Date
CN218733133U true CN218733133U (en) 2023-03-24

Family

ID=85640492

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222636089.3U Active CN218733133U (en) 2022-10-08 2022-10-08 Prefabricated cable duct bank structure is prevented subsiding by fast-assembling

Country Status (1)

Country Link
CN (1) CN218733133U (en)

Similar Documents

Publication Publication Date Title
CN218733133U (en) Prefabricated cable duct bank structure is prevented subsiding by fast-assembling
CN217215814U (en) Connecting assembly for cable bridge
CN210800990U (en) Concatenation formula solar street lamp convenient to equipment
CN214659327U (en) Mounting structure of fence
CN219697014U (en) Fixing device of distribution box on light steel keel wall
CN212023873U (en) Guide rail mounting structure for input electric iron tower lifting equipment
CN213508129U (en) Warning sign is used in municipal construction
CN220928197U (en) Wood structure beam column connection node device
CN218667256U (en) Detachable sign support rod for highway
CN219100905U (en) Surrounding baffle for civil engineering construction
CN220553763U (en) Safety device is used in building electrical engineering construction
CN210069140U (en) Pipeline fixing device is used in municipal works pipe network construction
CN210422140U (en) Removable rail is used to building safety
CN219875540U (en) Solar module fixing frame
CN204794879U (en) Prevent solar control ware wiring fastener that terminal pine takes off
CN221201233U (en) Support device
CN212784406U (en) Preassembled transformer substation base
CN216197136U (en) Rail for municipal works with regulatory function
CN211472709U (en) Non-negative pressure energy-saving water supply equipment
CN214615795U (en) Novel electric power rail railing
CN219755018U (en) Connection structure between steel members
CN217507700U (en) Connection fixing structure of board-to-board connector
CN219993358U (en) Fence reinforcement device
CN217030719U (en) Fixing device for fixing electric meter box and service wire
CN220245776U (en) River ecological management floating bed

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant