Suspension type bridge floor drainage construction work platform Download PDFInfo
- Publication number
- CN218580464U CN218580464U CN202222085165.6U CN202222085165U CN218580464U CN 218580464 U CN218580464 U CN 218580464U CN 202222085165 U CN202222085165 U CN 202222085165U CN 218580464 U CN218580464 U CN 218580464U
- Authority
- CN
- China
- Prior art keywords
- angle steel
- drainage construction
- bridge deck
- deck drainage
- suspension type
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域technical field
本实用新型涉及桥梁施工技术领域,尤其涉及一种悬吊式桥面排水施工作业平台。The utility model relates to the technical field of bridge construction, in particular to a suspended bridge deck drainage construction operation platform.
背景技术Background technique
随着国内环保要求日益提高,目前桥梁工程中,均要求在桥面两侧设置纵向集水管道(槽)用于收集桥面汇水,并将桥面汇水统一汇集到桥头的水处理装置中,经处理合格后方可排放。由于桥面排水纵向集水管道(槽)一般位于桥面翼缘板下方,传统的桥面排水施工多采用桥梁检修车,桥梁检修车可将作业平台伸入到桥面以下,从而实现作业工人安全便捷的进行桥面排水管道(槽)的安装,但由于桥梁检修车属于特种机械设备,租赁费用较高,同时该设备对作业区域要求较高,需待桥梁桥面铺装完成后方可施工,并且大多数市政、公路桥梁设置有人行道,如果人行道较宽则桥梁检修车也无法将作业平台伸入到桥梁下部。因此,为了减小桥面排水施工成本,同时克服有人行道桥梁桥梁检修车无法提供作业平台的缺点,急需一种用于桥梁翼缘板侧面及下部施工的桥面排水施工作业平台。With the increasing domestic environmental protection requirements, in current bridge projects, longitudinal water collection pipes (troughs) are required to be installed on both sides of the bridge deck to collect water from the bridge deck and collect the water from the bridge deck to the water treatment device at the bridgehead. Among them, it can be discharged only after passing the treatment. Since the vertical water collection pipes (troughs) of bridge deck drainage are generally located under the bridge deck flange, traditional bridge deck drainage construction mostly uses bridge maintenance vehicles, which can extend the operating platform below the bridge deck, so that workers It is safe and convenient to install the bridge deck drainage pipes (troughs), but because the bridge maintenance vehicle is a special mechanical equipment, the rental fee is high, and the equipment has high requirements on the working area, and the construction can only be carried out after the bridge deck pavement is completed , and most municipal and highway bridges are provided with sidewalks. If the sidewalks are wider, the bridge maintenance vehicle cannot extend the operating platform into the lower part of the bridge. Therefore, in order to reduce the cost of bridge deck drainage construction and overcome the disadvantage that bridge repair vehicles with sidewalks cannot provide a working platform, there is an urgent need for a bridge deck drainage construction work platform for bridge flange side and lower construction.
实用新型内容Utility model content
本实用新型的目的在于克服上述现有技术中的不足,旨在提供一种能够减小桥面排水施工成本,便于现场施工,安全可靠、减少机械租赁成本的桥面排水施工作业平台。The purpose of the utility model is to overcome the deficiencies in the above-mentioned prior art, aiming to provide a bridge deck drainage construction operation platform that can reduce the construction cost of the bridge deck drainage, facilitate on-site construction, be safe and reliable, and reduce the cost of machinery rental.
为达到上述目的,本实用新型是通过下述技术方案予以实现的:In order to achieve the above object, the utility model is achieved through the following technical solutions:
一种悬吊式桥面排水施工作业平台,由架体构成,所述架体包括并列设置的立柱,所述立柱之间通过由上至下等间距设置的横撑固定连接,所述立柱的上端连接有上横梁,所述上横梁的上端面设置有由角钢立杆和角钢横杆相互连结构成的梯步吊篮,所述上横梁下端面的一侧边,悬固有与牵引动力相连,且作用于桥梁翼缘的吊车,所述立柱的下端连接有下横梁,所述下横梁的上端面设置有由角钢立杆和角钢横杆相互连结构成的作业吊篮。A suspended bridge deck drainage construction operation platform, which is composed of a frame body, the frame body includes uprights arranged side by side, and the uprights are fixedly connected by cross braces arranged at equal intervals from top to bottom, and the uprights of the uprights The upper end is connected with an upper beam, and the upper end surface of the upper beam is provided with a ladder hanging basket formed by connecting angle steel vertical rods and angle steel cross bars. One side of the lower end surface of the upper beam is suspended and connected with traction power. And the crane acting on the flange of the bridge, the lower end of the column is connected with the lower beam, and the upper end surface of the lower beam is provided with a working basket formed by connecting angle steel vertical rods and angle steel cross rods.
所述吊车包括底部四端分别设置有行走轮的框架,所述框架内底面铺设有托板,所述托板上设置有由混凝土浇筑构成的配重块。The crane comprises a frame with four ends of the bottom respectively provided with traveling wheels, a supporting plate is laid on the inner bottom surface of the frame, and a counterweight made of concrete pouring is arranged on the supporting plate.
所述上横梁与立柱之间设置有加强斜梁。A reinforcing inclined beam is arranged between the upper beam and the column.
所述下横梁与立柱之间设置有加强梁。A reinforcing beam is arranged between the lower beam and the column.
所述横撑之间的间距为200-300mm。The distance between the cross braces is 200-300mm.
所述梯步吊篮内底面铺设有托板。A supporting plate is laid on the inner bottom surface of the step hanging basket.
所述作业吊篮内底面铺设有托板。A supporting plate is laid on the inner bottom surface of the working hanging basket.
本实用新型的有益效果是:客服了目前存在的,大多数市政公路或桥梁设置的人行道较宽,则桥梁检修车也无法将作业平台伸入到桥梁下部的弊端,本实用新型悬吊式施工作业平台,利用悬固有与牵引动力的吊车,将作业吊篮方便的伸入到桥梁翼缘的下方,作业吊篮可满足两名作业人在主梁翼缘板下操作的需要,且吊车通过动力牵引,快速移动到所需的施工地点,因此便于现场施工,成本低廉、行走稳定、安全可靠、减少现有技术中机械设备租赁的成本,极大的提高了工作效率。The beneficial effects of the utility model are: customer service currently exists, most municipal roads or bridges are set with wide sidewalks, and bridge maintenance vehicles cannot extend the working platform into the lower part of the bridge. The work platform uses a crane with fixed and traction power to conveniently extend the work gondola under the bridge flange. The work gondola can meet the needs of two workers operating under the main girder flange plate, and the crane is pulled by power. , quickly move to the required construction site, so it is convenient for on-site construction, low cost, stable walking, safe and reliable, reduces the cost of mechanical equipment rental in the prior art, and greatly improves work efficiency.
附图说明Description of drawings
图1为本实用新型结构示意图;Fig. 1 is the structural representation of the utility model;
图2是图1中吊车的结构示意图;Fig. 2 is the structural representation of crane in Fig. 1;
图3是图1中配重块的结构示意图;Fig. 3 is the structural representation of counterweight in Fig. 1;
附图标记:立柱1横撑2上横梁3梯步吊篮4吊车5下横梁6作业吊篮7行走轮8框架9托板10配重块11加强斜梁12桥梁翼缘13吊耳14Reference signs:
具体实施方式Detailed ways
下面结合附图对本实用新型做进一步的说明:Below in conjunction with accompanying drawing, the utility model is further described:
如图1-3所示,一种悬吊式桥面排水施工作业平台,由架体构成,所述架体包括并列设置的立柱1,所述立柱1之间通过由上至下等间距设置的横撑2固定连接,本实施例所述横撑2之间的间距为200-300mm,优选为250mm;在所述立柱1的上端连接有上横梁3,为了加固其连接,本实施例所述上横梁3与立柱1之间还设置有加强斜梁12;在所述上横梁3的上端面设置有由角钢立杆和角钢横杆相互连结构成的梯步吊篮4,所述梯步吊篮4内底面铺设有托板10,梯步吊篮4的设置是为了满足作业人员上、下转换的阶梯;在所述上横梁3下端面的一侧边,悬固有与牵引动力相连,且作用于桥梁翼缘13的吊车5,所述吊车5包括底部四端分别设置有行走轮8的框架9,所述框架9内底面铺设有托板10,所述托板10上设置有由混凝土浇筑构成的配重块11,本实施例所述配重块11可以是正六面体构成,在浇筑时,可先设置一吊耳14预埋在混凝土内,以方便配重块的吊装;在所述立柱1的下端,本实用新型还连接有下横梁6,为了加固其连接,本实施例所述下横梁6与立柱1之间还设置有加强斜梁12;在所述下横梁6的上端面设置有由角钢立杆和角钢横杆相互连结构成的作业吊篮7,所述作业吊篮7内底面铺设有托板10,作业人员可站立于托板10上进行安全施工。As shown in Figure 1-3, a suspended bridge deck drainage construction operation platform is composed of a frame body, which includes
以上所述仅为本实用新型的较佳实施例而已,并不用以限制本实用新型,凡在本实用新型的技术范围之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。The above descriptions are only preferred embodiments of the present utility model, and are not intended to limit the present utility model. Any modifications, equivalent replacements, improvements, etc. made within the technical scope of the present utility model shall be included in this utility model. within the scope of protection of utility models.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202222085165.6U CN218580464U (en) | 2022-08-09 | 2022-08-09 | Suspension type bridge floor drainage construction work platform |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202222085165.6U CN218580464U (en) | 2022-08-09 | 2022-08-09 | Suspension type bridge floor drainage construction work platform |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN218580464U true CN218580464U (en) | 2023-03-07 |
Family
ID=85360144
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202222085165.6U Active CN218580464U (en) | 2022-08-09 | 2022-08-09 | Suspension type bridge floor drainage construction work platform |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN218580464U (en) |
-
2022
- 2022-08-09 CN CN202222085165.6U patent/CN218580464U/en active Active
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN203347251U (en) | Movable protective canopy for road-spanning construction | |
| CN106012824A (en) | Movable bridge anti-collision guardrail construction operation trolley | |
| CN106592438A (en) | Two-column pier and middle tie beam construction method employing integral movement of trusses | |
| CN210262739U (en) | Bridge drainage pipe installation trolley system | |
| CN204455841U (en) | A kind of highway bridge crash barrier steel form hoisting machine tool | |
| CN112664235A (en) | Walking type pipe gallery formwork supporting device | |
| CN114351625B (en) | Reinforced concrete flower box guardrail and construction method | |
| CN215714714U (en) | Hanging basket equipment for installing bridge guardrail | |
| CN222990595U (en) | Multifunctional portal for suspension bridge construction | |
| CN205857026U (en) | A kind of movable type bridge anticollision barrier construction operation chassis | |
| CN202543799U (en) | Hanging bracket hinging type bridge maintenance vehicle | |
| CN210134344U (en) | Trolley for mounting bridge center joint drain pipe | |
| CN112726426A (en) | Novel movable protective shed of bracket and steel pipe column combined gantry type | |
| CN210049105U (en) | Self-propelled bridge formwork operation trolley | |
| CN111851301A (en) | a bridge erecting machine | |
| CN208167484U (en) | The steel construction overline bridge being easily installed | |
| CN217325024U (en) | Wet seam construction trolley for ultra-wide prefabricated box girder | |
| CN208009267U (en) | A kind of middle cross beam tensioning protective platform | |
| CN218373343U (en) | Movable bridge floor hogging moment stretch-draw operating means | |
| CN211228177U (en) | Slurry splashing prevention device used during bridge flange plate dismantling | |
| CN215052146U (en) | Walking type operation platform adopting continuous box girder flange plates | |
| CN214497216U (en) | Novel movable protective shed of bracket and steel pipe column combined gantry type | |
| CN206986736U (en) | A kind of box girder bridge transverse prestress construction mobile closed formula platform | |
| CN103790388B (en) | Greatly install improve one's methods across the waft high-altitude of eaves of cantilever roofing steel | |
| CN210194435U (en) | A mobile trolley for transverse prestressing construction of continuous beams |