CN218493144U - Steel construction stand pre-buried clamping screw positioner - Google Patents
Steel construction stand pre-buried clamping screw positioner Download PDFInfo
- Publication number
- CN218493144U CN218493144U CN202222326345.9U CN202222326345U CN218493144U CN 218493144 U CN218493144 U CN 218493144U CN 202222326345 U CN202222326345 U CN 202222326345U CN 218493144 U CN218493144 U CN 218493144U
- Authority
- CN
- China
- Prior art keywords
- positioning plate
- positioning
- fixing screw
- steel structure
- support rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 51
- 239000010959 steel Substances 0.000 title claims abstract description 51
- 238000010276 construction Methods 0.000 title claims abstract description 37
- 238000000034 method Methods 0.000 abstract description 9
- 239000004567 concrete Substances 0.000 abstract description 6
- 230000009286 beneficial effect Effects 0.000 abstract 1
- 238000009434 installation Methods 0.000 description 9
- 239000011150 reinforced concrete Substances 0.000 description 8
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
A positioning device for a pre-buried fixing screw of a steel structure upright post comprises a positioning plate, a level gauge and an adjusting support rod; the positioning plates comprise an upper positioning plate and a lower positioning plate which are arranged in parallel along the vertical direction, the plate bodies are fixedly installed and connected through equidistant struts, and the upper positioning plate and the lower positioning plate are respectively and correspondingly provided with an upper positioning hole and a lower positioning hole along the vertical direction; the level gauge is fixedly arranged on the upper positioning plate; the adjusting support rods are fixedly and uniformly arranged at the bottom of the positioning plate. The control method has the beneficial effects that the verticality and the distance of the steel structure upright post fixing screw rods can be effectively controlled, and the problems of toppling and deviation of the steel structure upright post fixing screw rods in the concrete pouring process are avoided; the construction process is convenient and rapid, the problem of rework is avoided, and the construction method can be repeatedly recycled, thereby not only improving the construction quality, but also improving the construction efficiency.
Description
Technical Field
The utility model belongs to the technical field of the building engineering construction, concretely relates to a positioner that is used for the pre-buried clamping screw of steel construction stand to lay construction use.
Background
In the building construction process, the installation of steel structure stand needs predetermine mounting base and clamping screw when concrete foundation ground is pour, guarantees through the pre-buried base of steel stand and clamping screw that the installation of steel stand is fixed. In the traditional work progress, after installing steel construction stand fixing screw on the pre-buried base of steel stand, lay at predetermined position welded fastening when reinforced concrete rack is laid, then condense through concrete placement and make steel construction stand fixing screw erect along the vertical direction is fixed, install through steel construction stand fixing screw and steel construction stand base cooperation at last, fix the steel construction stand on the pre-buried base on reinforced concrete foundation ground. The defect of above-mentioned traditional work progress lies in, steel construction stand clamping screw is at pre-buried and pouring in-process, the straightness that hangs down can't effectively be guaranteed, because the screw rod stretches out ground and has certain length, there is the problem of slope skew always, slope and skew between the adjacent screw rod are inconsistent, the problem of location installation difficulty has been brought for subsequent steel construction stand installation, consequently need adopt again before steel construction stand installation to force the means with the screw rod along the vertical direction correction restoration, this process can cause clamping screw's damage, sometimes need demolish welding installation again even, not only consuming time and wasting power, and construction quality can't be ensured.
Disclosure of Invention
The utility model aims at solving the pre-buried construction operation of pouring of steel construction stand clamping screw and having slope and skew, cause steel construction stand clamping screw's the predetermined interval and hang down the poor problem of straightness construction quality, provide a supplementary steel construction stand pre-buried clamping screw carries out interval and the positioner who hangs down the straightness location in the work progress.
In order to realize the purpose, the technical scheme adopted by the steel structure upright post pre-embedded fixing screw positioning device comprises a positioning plate, a level gauge and an adjusting support rod; the positioning plates comprise an upper positioning plate and a lower positioning plate which are arranged in parallel along the vertical direction, the plate bodies are fixedly installed and connected through equidistant struts, and the upper positioning plate and the lower positioning plate are respectively and correspondingly provided with an upper positioning hole and a lower positioning hole along the vertical direction; the gradienter is fixedly arranged on the upper positioning plate; the adjusting support rods are fixedly and uniformly arranged at the bottom of the positioning plate.
The gradienter comprises a transverse gradienter and a longitudinal gradienter, the transverse gradienter is transversely arranged along the upper positioning plate, and the longitudinal gradienter is longitudinally arranged along the upper positioning plate.
And a transverse positioning clamping groove used for mounting a transverse level meter is transversely arranged on the upper top surface of the upper positioning plate, and a longitudinal positioning clamping groove used for mounting a longitudinal level meter is longitudinally arranged.
The upper positioning hole and the lower positioning hole are arranged in a matched mode according to the arrangement distance and the diameter of the steel structure column pre-embedded fixing screw.
And the upper positioning hole and the lower positioning hole are respectively provided with a positioning sleeve, and the positioning sleeves are arranged in a flange structure in a matching way.
The adjusting support rod comprises an upper support rod, a lower support rod and an adjusting shaft sleeve, one end of the upper support rod is fixedly installed at the bottom of the positioning plate along the vertical direction, and the other end of the upper support rod is adjusted, assembled and connected with the lower support rod through an adjusting shaft sleeve threaded structure.
The utility model has the advantages that the verticality and the space of the steel structure upright post fixing screw rod can be effectively controlled by utilizing the double-layer positioning plate structure, and the problems of toppling and deviation of the steel structure upright post fixing screw rod in the concrete pouring process are effectively avoided; the verticality adjusting problem of the steel structure upright post fixing screw is conveniently and effectively realized by utilizing the adjusting support rod and the level device, and the installation quality is ensured; the construction process is convenient and rapid, the problem of rework is avoided, and the construction method can be repeatedly recycled, thereby not only improving the construction quality, but also improving the construction efficiency.
Drawings
FIG. 1 is a schematic three-dimensional structure of the present invention;
FIG. 2 is a schematic plane structure of the present invention;
FIG. 3 is a schematic view of the construction and installation structure of the present invention;
in the drawings: the device comprises a positioning plate 1, an upper positioning plate 11, an upper positioning hole 111, a transverse positioning clamping groove 112, a longitudinal positioning clamping groove 113, a lower positioning plate 12, a lower positioning hole 121, equidistant struts 13, a positioning sleeve 2, a level gauge 3, a transverse level gauge 31, a longitudinal level gauge 32, an adjusting support rod 4, an upper support rod 41, a lower support rod 42, an adjusting shaft sleeve 43 and a steel structure upright post embedded screw 5.
Detailed Description
To make the objects, technical solutions and advantages of the present invention clearer, the technical solutions of the present invention will be described in detail with reference to the embodiments.
Example 1
As shown in the attached drawings 1-2, the positioning device for the pre-buried fixing screw of the steel structure upright post comprises a positioning plate 1, a level 3 and an adjusting support rod 4.
The locating plate 1 has included top board 11 and lower locating plate 12, top board 11 and lower locating plate 12 are along vertical direction parallel arrangement, connect through equidistance pillar 13 fixed mounting between the plate body, top board 11 and lower locating plate 12 go up respectively along vertical direction corresponding laying of locating hole 111 and lower locating hole 121, top hole 111 and lower locating hole 121 match the setting according to laying interval and diameter size of the pre-buried fixing screw of steel construction stand, install position sleeve 2 on top hole 111 and the lower locating hole 121 respectively, position sleeve 2 is the flange structure cooperation installation.
The spirit level 3 is fixedly installed on the upper positioning plate 11, the spirit level 3 comprises a transverse spirit level 31 and a longitudinal spirit level 32, the transverse spirit level 31 is installed and arranged along the transverse direction of the upper positioning plate 11, and the longitudinal spirit level 32 is installed and arranged along the longitudinal direction of the upper positioning plate 11. The upper top surface of the upper positioning plate 11 is transversely provided with a transverse positioning clamping groove 112 for mounting a transverse level 31, and longitudinally provided with a longitudinal positioning clamping groove 113 for mounting a longitudinal level 32.
The adjusting support rods 4 are fixedly and uniformly arranged and installed at the bottom of the positioning plate 1, the adjusting support rods 4 comprise upper support rods 41, lower support rods 42 and adjusting shaft sleeves 43, one ends of the upper support rods 41 are fixedly installed at the bottom of the positioning plate 1 along the vertical direction, and the other ends of the upper support rods 41 are adjusted, assembled and connected with the lower support rods 42 through thread structures of the adjusting shaft sleeves 43.
Example 2
With reference to the attached drawing 3, the construction and use processes and the principle of the positioning device for the pre-buried fixing screw of the steel structure upright post are as follows:
1) When the reinforced concrete foundation ground is poured, after the foundation ground is laid, firstly, the reinforced concrete net rack is laid, meanwhile, the steel structure stand column base embedded part is arranged according to the laying level of the reinforced concrete foundation ground, and the steel structure stand column embedded screw 5 is installed and arranged.
2) Install the pre-buried set screw positioner of steel construction stand on upright steel construction stand pre-buried screw rod 5, wear out through 5 top ends of steel construction stand pre-buried screw rod with last locating plate 11 and lower locating plate 12 on locating plate 1 along the last locating hole 111 and the lower locating hole 121 that the vertical direction was counterpointed and is set up in proper order, utilize locating sleeve 2 on last locating hole 111 and the lower locating hole 121 to fix the distance between the pre-buried screw rod 5 of steel construction stand, and fix steel construction stand pre-buried screw rod 5 along the vertical direction.
3) The positioning device for the pre-buried fixing screw of the steel structure stand column is moved to the bottom position along the pre-buried screw 5 of the steel structure stand column, so that the adjusting support rod 4 is supported on the pre-buried plate or the fixing reinforcing steel bar net to fix the positioning plate 1 along the vertical direction.
4) Wrench movement rotation regulation bracing piece 4 on the regulation axle sleeve 43, connecting length regulation bracing piece 4 length through bracing piece 41 and lower bracing piece 42 on the helicitic texture changes, through the horizontal precision to four regulation control locating plate 1 of adjusting bracing piece 4, utilize horizontal spirit level 31 and the vertical spirit level 32 cooperation regulation bracing piece 4 regulation operation that set up on locating plate 1, ensure that locating plate 1 is horizontal and the horizontal vertical holding level of level along the level, thereby accomplish the fixed along the vertical direction to steel construction stand embedded screw 5.
5) And grouting and pouring concrete, filling the reinforced concrete net rack with the concrete, and pouring and fixing the steel structure embedded part and the steel structure upright post embedded screw 5 on the ground of the reinforced concrete foundation.
6) And after the reinforced concrete is solidified, taking down the steel structure upright post pre-embedded fixing screw positioning device from the steel structure upright post pre-embedded screw 5.
Claims (6)
1. The utility model provides a pre-buried clamping screw positioner of steel construction stand, its characterized in that: comprises a positioning plate (1), a level gauge (3) and an adjusting support rod (4); the positioning plate (1) comprises an upper positioning plate (11) and a lower positioning plate (12), the upper positioning plate (11) and the lower positioning plate (12) are arranged in parallel along the vertical direction, the plate bodies are fixedly installed and connected through equidistant struts (13), and an upper positioning hole (111) and a lower positioning hole (121) are correspondingly distributed on the upper positioning plate (11) and the lower positioning plate (12) along the vertical direction respectively; the gradienter (3) is fixedly arranged on the upper positioning plate (11); the adjusting support rods (4) are fixedly and uniformly arranged at the bottom of the positioning plate (1).
2. The steel structure column embedded fixing screw positioning device as claimed in claim 1, wherein: the level (3) comprises a transverse level (31) and a longitudinal level (32), the transverse level (31) is transversely arranged along the upper positioning plate (11), and the longitudinal level (32) is longitudinally arranged along the upper positioning plate (11).
3. The steel structure column embedded fixing screw positioning device as claimed in claim 1 or 2, wherein: a transverse positioning clamping groove (112) used for installing a transverse level gauge (31) is transversely arranged on the upper top surface of the upper positioning plate (11), and a longitudinal positioning clamping groove (113) used for installing a longitudinal level gauge (32) is longitudinally arranged.
4. The steel structure column embedded fixing screw positioning device as claimed in claim 1, wherein: the upper positioning hole (111) and the lower positioning hole (121) are arranged in a matched mode according to the arrangement distance and the diameter of the steel structure column embedded fixing screw.
5. The steel structure column embedded fixing screw positioning device as claimed in claim 1, wherein: and the upper positioning hole (111) and the lower positioning hole (121) are respectively provided with a positioning sleeve (2), and the positioning sleeves (2) are installed in a flange structure in a matching way.
6. The steel structure column embedded fixing screw positioning device as claimed in claim 1, wherein: the adjusting support rod (4) comprises an upper support rod (41), a lower support rod (42) and an adjusting shaft sleeve (43), one end of the upper support rod (41) is fixedly installed at the bottom of the positioning plate (1) along the vertical direction, and the other end of the upper support rod (41) is connected with the lower support rod (42) in an adjusting mode through the adjusting shaft sleeve (43) in a threaded structure in an adjusting mode in an assembling mode.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222326345.9U CN218493144U (en) | 2022-09-02 | 2022-09-02 | Steel construction stand pre-buried clamping screw positioner |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222326345.9U CN218493144U (en) | 2022-09-02 | 2022-09-02 | Steel construction stand pre-buried clamping screw positioner |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218493144U true CN218493144U (en) | 2023-02-17 |
Family
ID=85189020
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202222326345.9U Expired - Fee Related CN218493144U (en) | 2022-09-02 | 2022-09-02 | Steel construction stand pre-buried clamping screw positioner |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218493144U (en) |
-
2022
- 2022-09-02 CN CN202222326345.9U patent/CN218493144U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208009467U (en) | A kind of foundation bolt installation control device | |
CN105735319B (en) | A kind of large diameter steel pipe stand column pile fast positioning plumbing device and construction method | |
CN210216479U (en) | Positioning device for pre-embedding large foundation bolt group | |
CN112127641A (en) | Accurate fixing method for anchor plate foundation bolt | |
CN101864825B (en) | Reinforced concrete prefabricated column positioning device and construction method thereof | |
CN205776795U (en) | Rectangular column foundation bolt batch positioner | |
CN112127637A (en) | Construction method for pre-buried vertical component steel bars of foundation layer of fabricated building | |
CN111206613A (en) | Positioning tooling and positioning method for anchor bolts of steel structure columns in cap foundation reinforcement | |
CN108755395B (en) | A method of installing a ball bearing | |
CN212104166U (en) | Accurate positioning device for embedded bolt of safety injection box of nuclear power station | |
CN105804110A (en) | Construction method of foundation bolts of railway contact net and mounting bracket | |
CN218493144U (en) | Steel construction stand pre-buried clamping screw positioner | |
CN215052897U (en) | Assembled guide wall supporting structure | |
CN212477455U (en) | Pre-buried positioner of bridge suspension cable anchor cylinder | |
CN110670873B (en) | Support system of steel formwork of ultrahigh large-section concrete column and construction method | |
CN116516983B (en) | Tide-affected steel-concrete combined inner support for deep foundation pit in river and construction method | |
CN118774266A (en) | High-precision control device and control method for horizontal heavy embedded parts | |
CN211114901U (en) | Bracket device convenient to precast beam is under construction fast | |
CN205421321U (en) | Precast reinforced concrete base | |
CN206859658U (en) | A kind of adjustable slab form support system | |
CN211341189U (en) | Steel construction embedded foundation bolt positioner | |
CN214116620U (en) | Adjustable support for accurate positioning of permanent double-steel-pipe column | |
CN211973555U (en) | Steel construction stand rag bolt location frock in cushion cap foundation reinforcement | |
CN113529774B (en) | Construction method for mounting large foundation steel bars | |
CN201747071U (en) | Precast reinforced concrete column positioning device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20230217 |
|
CF01 | Termination of patent right due to non-payment of annual fee |