CN218400557U - PE pipeline transfer device for municipal construction - Google Patents

PE pipeline transfer device for municipal construction Download PDF

Info

Publication number
CN218400557U
CN218400557U CN202221207482.4U CN202221207482U CN218400557U CN 218400557 U CN218400557 U CN 218400557U CN 202221207482 U CN202221207482 U CN 202221207482U CN 218400557 U CN218400557 U CN 218400557U
Authority
CN
China
Prior art keywords
supporting plate
plate
bracket
pipeline
transfer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221207482.4U
Other languages
Chinese (zh)
Inventor
诸葛祥瑞
高洋
郇恒迁
赵小彬
陈云鹏
白俊胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Linyi Municipal Group Co Ltd
Original Assignee
Linyi Municipal Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Linyi Municipal Group Co Ltd filed Critical Linyi Municipal Group Co Ltd
Priority to CN202221207482.4U priority Critical patent/CN218400557U/en
Application granted granted Critical
Publication of CN218400557U publication Critical patent/CN218400557U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Handcart (AREA)

Abstract

The utility model discloses a PE pipeline transfer device for municipal construction, which comprises a frame, a transfer bracket and a fixing mechanism; the transfer brackets are positioned at the top ends of the frames, and the fixing mechanisms are provided with a pair of fixing mechanisms which are symmetrically arranged at the top ends of the transfer brackets; the frame comprises a wheel shaft, a handle and a bracket; the two ends of the wheel shaft are provided with wheels, the bracket is formed by welding a plurality of support rods, the bracket and the handle are welded on the wheel shaft, the top end of the bracket is provided with a bearing, and the bearing connects the frame with the transfer bracket; the transfer bracket comprises a lower supporting plate, an upper supporting plate, a supporting block and a buffer spring; the bottom end of the supporting block is provided with a rotating shaft, and the rotating shaft is connected with a bearing at the top end of the support; the lower supporting plate is fixed on the supporting block, and the upper supporting plate is positioned above the lower supporting plate; the buffer spring is positioned between the upper supporting plate and the lower supporting plate, one end of the buffer spring is connected to the upper supporting plate, and the other end of the buffer spring is connected to the lower supporting plate. The utility model discloses can control the direction of transportation of PE pipeline, prevent PE pipeline off tracking, reduce the potential safety hazard, improve the efficiency of construction.

Description

PE pipeline transfer device for municipal construction
Technical Field
The utility model belongs to the technical field of the PE pipeline is transported, in particular to PE pipeline transfer device for municipal construction.
Background
The PE pipeline has the characteristics of high strength, corrosion resistance, no toxicity and the like, and is mainly applied to the fields of urban water supply, urban fuel gas supply, farmland irrigation and the like; PE pipeline is long after the butt fusion finishes, during the transportation and inconvenient, and traditional PE pipeline's transfer device has following shortcoming:
1) The traditional PE pipeline transfer device cannot control the movement direction of a PE pipeline in the transfer process, and the PE pipeline is deviated due to the long size of the PE pipeline after fusion welding is completed, so that potential safety hazards exist; moreover, a large amount of workers are needed for assisting in transferring, so that the construction efficiency is low;
2) Traditional PE pipeline transfer device lacks fixed establishment, consequently to PE pipeline inconvenient control in the transportation, leads to PE pipeline to be damaged.
Disclosure of Invention
The utility model aims at overcoming not enough among the prior art, providing a PE pipeline transfer device for municipal construction, can control the direction of transportation of PE pipeline, prevent the PE pipeline off tracking, reduce the potential safety hazard, improve the efficiency of construction.
In order to realize the purpose, the utility model discloses a technical scheme is:
a PE pipeline transfer device for municipal construction comprises a frame, a transfer bracket and a fixing mechanism; the transfer bracket is positioned at the top end of the frame, and the fixing mechanisms are provided with a pair of fixing mechanisms which are symmetrically arranged at the top end of the transfer bracket; the frame comprises a wheel shaft, a handle and a bracket; the two ends of the wheel axle are provided with wheels, the support is formed by welding a plurality of support rods, the support and the handle are welded on the wheel axle, the top end of the support is provided with a bearing, and the frame is connected with the transfer bracket through the bearing.
The transfer bracket comprises a lower supporting plate, an upper supporting plate, a supporting block and a buffer spring; the bottom end of the supporting block is provided with a rotating shaft, and the rotating shaft is connected with a bearing at the top end of the bracket; the lower supporting plate is fixed on the supporting block, the upper supporting plate is positioned above the lower supporting plate, and the top end of the upper supporting plate is provided with an installation groove; the buffer spring is positioned between the upper supporting plate and the lower supporting plate, one end of the buffer spring is connected to the upper supporting plate, and the other end of the buffer spring is connected to the lower supporting plate.
The upper supporting plate and the lower supporting plate are both of arc structures.
The fixing mechanism comprises a baffle plate, a fixing plate, a moving plate and a bolt; the fixing plate is T-shaped and is arranged in an installation groove at the top end of the upper supporting plate, a groove is arranged at the bottom end of the fixing plate, a spring and a stop block are arranged in the groove, and one end of the stop block is connected to the spring; the moving plate penetrates through the fixed plate, the bolt is positioned at the top end of the fixed plate, and the moving plate is fixed on the fixed plate by the bolt; the baffle is fixed in movable plate one end, and the one end of baffle contact PE pipeline is equipped with the rubber pad.
Compared with the prior art, the utility model beneficial effect shows:
1) The bearing connects the frame with the transfer bracket, so that the rotation between the frame and the transfer bracket is more flexible, the direction of the PE pipeline is conveniently controlled in the transfer process, the PE pipeline is prevented from deviating, the potential safety hazard is reduced, and the construction efficiency is improved; the buffer spring can generate a buffering effect on the upper supporting plate and the PE pipeline, so that damage to the PE pipeline is reduced.
2) After the PE pipeline is lifted to the transfer bracket, the fixing plate is installed in the installation groove, the upper supporting plate extrudes the stop block, the stop block moves upwards, and the spring is compressed; when the stop block is far away from the upper supporting plate, the spring is restored to drive the stop block to move downwards, so that the fixing plate is installed on the upper supporting plate; the moving plate moves to drive the baffle plate to move; when the rubber pad at one end of the baffle is tightly attached to the PE pipeline, the bolt is screwed down to fix the PE pipeline on the transfer bracket; but also can adapt to PE pipelines with different diameters, so that the transportation is more convenient.
Drawings
FIG. 1 is a first schematic structural view of a PE pipeline transfer device for municipal construction;
FIG. 2 is a structural schematic diagram II of the PE pipeline transfer device for municipal construction of the utility model;
FIG. 3 is an enlarged view of the portion A of FIG. 2;
FIG. 4 is a schematic structural view of a fixing mechanism in the PE pipeline transfer device for municipal construction of the utility model;
FIG. 5 is a schematic view of a cross-sectional structure of a fixing plate in the PE pipeline transfer device for municipal construction according to the present invention;
in the figure: 1. a frame; 101. a wheel shaft; 1011. a wheel; 102. a handle; 103. a support; 1031. a bearing; 2. a transfer carriage; 201. a lower supporting plate; 202. an upper supporting plate; 2021. mounting grooves; 203. a support block; 2031. a rotating shaft; 204. a buffer spring; 3. a fixing mechanism; 301. a baffle plate; 3011. a rubber pad; 302. a fixing plate; 3021. a stopper; 3022. a spring; 3023. a groove; 303. moving the plate; 304. a bolt; 4. PE pipeline.
Detailed Description
For the understanding of the technical field, the technical solution of the present invention is further described in detail with reference to the accompanying fig. 1-5.
A PE pipeline transfer device for municipal construction comprises a frame 1, a transfer bracket 2 and a fixing mechanism 3; the transfer bracket 2 is positioned at the top end of the frame 1, and the fixing mechanisms 3 are provided with a pair and symmetrically arranged at the top end of the transfer bracket 2; the frame 1 comprises a wheel axle 101, a handle 102 and a bracket 103; wheels 1011 are arranged at two ends of the wheel shaft 101, the bracket 103 is formed by welding a plurality of support rods, the bracket 103 and the handle 102 are welded on the wheel shaft 101, and a bearing 1031 is arranged at the top end of the bracket 103; frame 1 and transport and connect through bearing 1031 between the bracket 2, make frame 1 and transport the pivoted more nimble between the bracket 2, the convenience is controlled PE pipeline 4's orientation in the transportation, prevents PE pipeline 4 off tracking, has reduced the potential safety hazard, has improved the efficiency of construction.
The transfer bracket 2 comprises a lower supporting plate 201, an upper supporting plate 202, a supporting block 203 and a buffer spring 204; the bottom surface of the supporting block 203 is provided with a rotating shaft 2031, and the rotating shaft 2031 is connected with a bearing 1031 at the top end of the bracket 103; the lower supporting plate 201 is fixed on the supporting block 203, the upper supporting plate 202 is positioned above the lower supporting plate 201, and the top end of the upper supporting plate 202 is provided with a mounting groove 2021; the buffer spring 204 is positioned between the upper supporting plate 202 and the lower supporting plate 201, one end of the buffer spring 204 is connected to the upper supporting plate 202, and the other end is connected to the lower supporting plate 201; the buffer spring 204 can generate a buffer effect on the upper support plate 202 and the PE pipe 4, thereby reducing damage to the PE pipe 4.
The upper supporting plate 202 and the lower supporting plate 201 are both designed to be arc-shaped structures, so that the PE pipeline 4 is more stably installed in the upper supporting plate 202.
The fixing mechanism 3 comprises a baffle plate 301, a fixing plate 302, a moving plate 303 and a bolt 304; the fixing plate 302 is T-shaped and is arranged in the mounting groove 2021 at the top end of the upper supporting plate 202, the bottom end of the fixing plate 302 is provided with a groove 3023, a spring 3022 and a stop 3021 are arranged in the groove 3023, and one end of the stop 3021 is connected to the spring 3022; the moving plate 303 penetrates through the fixed plate 302, a bolt 304 is positioned at the top end of the fixed plate 302, and the bolt 304 fixes the moving plate 303 on the fixed plate 302; the baffle 301 is fixed at one end of the moving plate 303, a rubber pad 3011 is arranged at one end of the baffle 301 contacting the PE pipeline 4, and the rubber pad 3011 can prevent the baffle 301 from damaging the PE pipeline 4; after the PE pipe 4 is lifted to the transfer bracket 2, the fixing plate 302 is installed in the installation groove 2021, the upper supporting plate 202 presses the block 3021, the block 3021 moves upwards, and the spring 3022 is compressed; when the block 3021 moves away from the upper plate 202, the spring 3022 returns to move the block 3021 downward, so that the fixing plate 302 is mounted on the upper plate 202; the moving plate 303 moves to drive the baffle 301 to move; when the rubber gasket 3011 at one end of the baffle 301 is tightly attached to the PE pipeline 4, the bolt 304 is screwed down, and the PE pipeline 4 is fixed on the transfer bracket 2; but also can adapt to PE pipelines 4 with different diameters, so that the transportation is more convenient.
The utility model provides a PE pipeline transfer device for municipal construction, the working process as follows: firstly, lifting the PE pipeline 4 to the transfer bracket 2, then installing the fixed plate 302 in the installation groove 2021 to enable the movable plate 303 to move, and when the baffle plate 301 is tightly attached to the PE pipeline 4, screwing the bolt 304 to fix the PE pipeline 4 on the transfer bracket 2; moreover, the device can adapt to PE pipelines 4 with different diameters, so that the transportation is more convenient; finally, the handle 102 drives the transfer device to transfer the PE pipeline 4.
The foregoing is merely exemplary and illustrative of the structure of the invention, and various modifications, additions and substitutions as described in the detailed description may be made by those skilled in the art without departing from the structure or exceeding the scope of the invention as defined in the claims.

Claims (3)

1. A PE pipeline transfer device for municipal construction comprises a frame, a transfer bracket and a fixing mechanism; the device is characterized in that the transfer bracket is positioned at the top end of the frame, and the fixing mechanisms are provided with a pair of fixing mechanisms which are symmetrically arranged at the top end of the transfer bracket; the frame comprises a wheel shaft, a handle and a bracket; the two ends of the wheel shaft are provided with wheels, the bracket is formed by welding a plurality of support rods, the bracket and the handle are welded on the wheel shaft, the top end of the bracket is provided with a bearing, and the frame is connected with the transfer bracket through the bearing;
the transfer bracket comprises a lower supporting plate, an upper supporting plate, a supporting block and a buffer spring; the bottom end of the supporting block is provided with a rotating shaft, and the rotating shaft is connected with a bearing at the top end of the support; the lower supporting plate is fixed on the supporting block, the upper supporting plate is positioned above the lower supporting plate, and the top end of the upper supporting plate is provided with an installation groove; the buffer spring is positioned between the upper supporting plate and the lower supporting plate, one end of the buffer spring is connected to the upper supporting plate, and the other end of the buffer spring is connected to the lower supporting plate.
2. The PE pipeline transfer device for municipal construction according to claim 1, wherein the upper supporting plate and the lower supporting plate are both arc-shaped.
3. The PE pipeline transfer device for municipal construction according to claim 1, wherein the fixing mechanism comprises a baffle plate, a fixing plate, a moving plate and a bolt; the fixing plate is T-shaped and is arranged in an installation groove at the top end of the upper supporting plate, a groove is arranged at the bottom end of the fixing plate, a spring and a stop block are arranged in the groove, and one end of the stop block is connected to the spring; the moving plate penetrates through the fixed plate, the bolt is positioned at the top end of the fixed plate, and the moving plate is fixed on the fixed plate by the bolt; the baffle is fixed in movable plate one end, and the one end of baffle contact PE pipeline is equipped with the rubber pad.
CN202221207482.4U 2022-05-18 2022-05-18 PE pipeline transfer device for municipal construction Active CN218400557U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221207482.4U CN218400557U (en) 2022-05-18 2022-05-18 PE pipeline transfer device for municipal construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221207482.4U CN218400557U (en) 2022-05-18 2022-05-18 PE pipeline transfer device for municipal construction

Publications (1)

Publication Number Publication Date
CN218400557U true CN218400557U (en) 2023-01-31

Family

ID=85010167

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221207482.4U Active CN218400557U (en) 2022-05-18 2022-05-18 PE pipeline transfer device for municipal construction

Country Status (1)

Country Link
CN (1) CN218400557U (en)

Similar Documents

Publication Publication Date Title
CN204374777U (en) The oblique uniaxial tracking bracket of a kind of photovoltaic generation
CN218400557U (en) PE pipeline transfer device for municipal construction
CN201815781U (en) Novel automatic pipeline welding dolly frame
CN213061799U (en) Vehicle restriction device for bridge engineering
CN206474874U (en) Back axle pressing machine floats press-loading device entirely
CN219623383U (en) Fixing device for pipeline construction
CN203330611U (en) Adjustable pipeline assembly welding bracket
CN212709596U (en) Small-size pipeline transfer device
CN220302960U (en) Heating power pipeline laying device
CN221584573U (en) Chemical pipeline interfacing apparatus
CN211010410U (en) Pressure pipeline inner wall repair equipment
CN205855821U (en) A kind of modularity trolley frame
CN219268440U (en) Pipeline mounting rack
CN220761552U (en) Steel pipe butt welding angle fixing device
CN217130514U (en) Pipeline laying device for oil and gas field development
CN216943358U (en) Transport trolley in hole with angle steering
CN218112727U (en) Large-scale flexible compensation festival flange transfer car (buggy)
CN219379601U (en) Horizontal pipeline maintenance auxiliary assembly
CN218618727U (en) Steel bifurcated pipe transportation mould device
CN218926787U (en) Lever-type adjusting device for butt joint of gas pipelines
CN218120729U (en) Tubular heat exchanger
CN211772788U (en) Support for civil structure
CN220097550U (en) Pipeline support for pipeline transportation
CN209426801U (en) A kind of station-service plastic tube transport vehicle
CN203978456U (en) Water-conveyance tunnel curved plate transport vehicle

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant