CN218323151U - Assembled steel construction fast assembly module of shelter hospital - Google Patents

Assembled steel construction fast assembly module of shelter hospital Download PDF

Info

Publication number
CN218323151U
CN218323151U CN202221675938.XU CN202221675938U CN218323151U CN 218323151 U CN218323151 U CN 218323151U CN 202221675938 U CN202221675938 U CN 202221675938U CN 218323151 U CN218323151 U CN 218323151U
Authority
CN
China
Prior art keywords
assembly module
assembly
ground
steel structure
shelter hospital
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221675938.XU
Other languages
Chinese (zh)
Inventor
王成虎
岳洪滔
刘方成
寇晓娜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Zhimou Planning Engineering Design Consulting Co ltd
Original Assignee
Hunan Zhimou Planning Engineering Design Consulting Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Zhimou Planning Engineering Design Consulting Co ltd filed Critical Hunan Zhimou Planning Engineering Design Consulting Co ltd
Priority to CN202221675938.XU priority Critical patent/CN218323151U/en
Application granted granted Critical
Publication of CN218323151U publication Critical patent/CN218323151U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The utility model relates to a steel construction work piece technical field, more specifically relate to a shelter hospital assembled steel construction fast assembly module. The device comprises upright columns supported between a top beam and a ground beam, wherein two ends of each upright column are detachably connected with the top beam and the ground beam, so that the two upright columns, the top beam and the ground beam are enclosed to form a module base group; the end part of the upright post is provided with a mounting plate which is abutted with the top beam and the ground beam; the stand is provided with the connecting plate with back timber and ground beam link relatively, install the bracing structure on the connecting plate, the bracing structure cross arrangement is firm with module base group. Through the bearing capacity and the connection mode of each structure in the assembly module, through with the detachable connection between stand and back timber, floorbar, not only enable whole assembly module to dismantle simple to operate, in order to guarantee the requirement that anti side force, wind load sidesway simultaneously, adopted the bracing structure. Can arrange the equipment module according to actual demand wantonly, the commonality is strong, receives external influence for a short time.

Description

Square cabin hospital assembled steel construction fast assembly module
Technical Field
The utility model relates to a steel construction work piece technical field, more specifically relate to, a shelter hospital assembled steel structure fast assembly module.
Background
The shelter hospital takes a field warfare mobile medical system of a liberation army as a template, and aims to fully utilize the existing buildings, construct and reform a temporary reception and treatment place in the shortest time and at the lowest cost, thereby realizing the aims of effectively controlling the infection source and maximally curing patients. The shelter hospital has the characteristics of large space and large capacity, and the design and reconstruction of the shelter hospital follow the principle of safety and supreme, so that the safety of medical personnel and patients, the safety of building structures, the operation safety of facility equipment, the fire safety and the environmental safety are ensured.
The shelter hospital is of a temporary structure, construction requires short construction period, and the design is safe in structure, convenient to construct and capable of saving construction period. The structure grade is not lower than two grades, and the design service life is not less than 5 years. The container type (specification: 3mX 6m) is generally adopted, the container plate is generally thin, and if under large horizontal acting force, such as large wind force, large displacement or deformation can occur due to insufficient lateral movement resistance rigidity.
How to transport the use material of shelter hospital conveniently, easily dismouting, bearing capacity is strong, and it is strong to obtain anti sidesway rigidity, and the equipment module that is difficult for taking place great displacement or deformation has huge actual meaning in the life use.
SUMMERY OF THE UTILITY MODEL
The utility model provides a be not enough to above-mentioned prior art, the utility model provides a shelter hospital assembled steel structure fast assembly module through the reasonable chooseing for use and the connection of each section bar component in the equipment module, through with the connection of dismantling between stand and back timber, floorbar, not only enables whole equipment module and dismantles simple to operate, in order to guarantee the requirement that anti side force, wind load side were moved simultaneously, has adopted the bracing structure. Can arrange the equipment module according to the actual demand wantonly, the commonality is strong, receives external influence for a short time.
The utility model discloses a following technical scheme realizes:
the assembled steel structure rapid assembly module comprises an upright post supported between a top beam and a ground beam, wherein two ends of the upright post are detachably connected with the top beam and the ground beam, so that the two upright posts, the top beam and the ground beam are enclosed to form a module base group; the stand is provided with the connecting plate with back timber and ground beam link relatively, install the bracing structure on the connecting plate, the bracing structure cross arrangement is firm with module base group.
This shelter hospital assembled steel construction fast assembly module optimizes through the structure of module base group, sets up to dismantling the connection between back timber, grade beam and the stand, realizes the quick installation and the dismantlement of whole equipment module. And connecting plates are respectively arranged at the connecting ends of the upright columns and the top beam and the ground beam and used for installing a diagonal bracing structure so as to increase the stability and the lateral force resistance of the assembled module.
Further, back timber and grade beam are H shaped steel roof beam, the web of H shaped steel roof beam sets up with the installation horizontal plane of equipment module is perpendicular.
Furthermore, flanges perpendicular to the web are arranged on two sides of the web of the H-shaped steel beam, and first screw holes for mounting the stand columns are formed in the flanges.
Further, the welding of the both ends of stand has the mounting panel with the edge of a wing butt, set up the screw two that correspond the setting with screw one on the mounting panel. During installation, the first screw hole and the second screw hole are in butt joint to form a through hole, and then the first screw hole and the second screw hole are locked by bolts.
Further, the bracing structure is hinged on the connecting plate.
Further, angle steel or channel-section steel are chooseed for use to the bracing structure, and two cross arrangement's bracing structure is the plane and counterpoints the laminating and connect. The inclined strut structure is stably installed and is arranged in a fit mode without mutual influence; the installation is also more convenient.
Furthermore, the upright column is any one of a square tube, a circular tube, H-shaped hot-rolled section steel and cold-formed thin-walled section steel.
Furthermore, the bottom of the ground beam is connected with the foundation by an anchor bolt.
The beneficial effects of the utility model are that:
this shelter hospital assembled steel construction fast assembly module optimizes through the structure of module base group, sets up to dismantling the connection between back timber, grade beam and the stand, realizes the quick installation and the dismantlement of whole equipment module. And connecting plates are respectively arranged at the connecting ends of the upright posts, the top beam and the ground beam and used for installing an inclined strut structure so as to increase the stability and the lateral resistance of the assembled module.
The utility model discloses an assembled steel construction fast assembly module of shelter hospital is connected top of column and for the column bottom bolt with back timber and grade beam respectively. The bottom of the ground beam is connected with the foundation by an anchor bolt. The support and the upright post are connected on the connecting plate through bolts. The two supports can be overlapped or connected by bolts. The upright posts and the supports can be assembled into a whole in a factory, and only bolt assembly is needed on site. The position of the support can be flexibly arranged according to the lateral resistance requirement of the whole structure.
This shelter hospital's assembled steel construction fast assembly module not only enables whole equipment module and dismantles simple to operate, in order to guarantee the requirement that anti side force, wind load sidesway simultaneously, has adopted the bracing structure. Can arrange the equipment module according to the actual demand wantonly, the commonality is strong, receives external influence for a short time.
Drawings
Figure 1 is the structure schematic diagram of assembled steel structure fast assembly module of cabin hospital.
Detailed Description
For the convenience of explanation and understanding of the present invention, the following terms are first explained.
Example 1
As shown in fig. 1, the shelter hospital assembly type steel structure rapid assembly module in this embodiment includes a vertical column 3 supported between a top beam 1 and a ground beam 2, and two ends of the vertical column 3 are detachably connected with the top beam 1 and the ground beam 2, so that the two vertical columns 3, the top beam 1 and the ground beam 2 enclose a module base set. In this embodiment, the column 3 may be any one of a square tube, a circular tube, H-section hot-rolled section steel, and cold-rolled thin-walled section steel. This embodiment is a round tube.
The end part of the upright post 3 is provided with a mounting plate 7 which is respectively abutted with the top beam 1 and the ground beam 2; the mounting plate 7 can effectively connect the three parts, increase the contact area and ensure firm mounting and high reliability.
Simultaneously in order to increase the lateral force resistance of the whole assembled module, the connecting plates 4 are oppositely arranged at the connecting ends of the upright posts 3, the top beam 1 and the ground beam 2, the inclined strut structures 5 are arranged on the connecting plates 4, and the inclined strut structures 5 are arranged in a crossed mode to stabilize the module base group. The inclined strut structure 5 of the embodiment is angle steel or channel steel, and the two inclined strut structures 5 which are arranged in a crossed manner are in planar alignment, fitting and connection; namely, the contact parts of the two inclined strut structures 5 are in surface contact, so that the use stability of the assembled module is improved.
The top beam 1 and the ground beam 2 in the embodiment are both H-shaped steel beams, and the web plate 11 of the H-shaped steel beam is perpendicular to the installation horizontal plane of the assembly module. Flanges 12 perpendicular to the web 11 are arranged on two sides of the web 11 of the H-shaped steel beam, and first screw holes for mounting the upright posts 3 are formed in the flanges 12. And mounting plates 7 which are abutted to the flange 12 are welded at two ends of the upright post 3, and screw holes II which correspond to the screw holes I are formed in the mounting plates 7. During installation, the first screw hole and the second screw hole are in butt joint to form a through hole, and then the first screw hole and the second screw hole are locked by bolts.
And the width of the mounting plate 7 is set to be equal to or less than the width of the flange 12 in consideration of the mounting convenience. The bottom of the ground beam 2 is connected with the foundation by an anchor bolt 6.
The utility model provides a shelter hospital assembled steel construction fast assembly module, through the reasonable chooseing for use and the connection of each section bar component in the equipment module, through with the connection of dismantling between stand and back timber, floorbar, not only enable whole equipment module and dismantle simple to operate, in order to guarantee the requirement that anti side force, wind load side moved simultaneously, adopted the bracing structure. Can arrange the equipment module according to actual demand wantonly, the commonality is strong, receives external influence for a short time.
The above embodiments are provided only for the purpose of illustration, not for the limitation of the present invention, and those skilled in the relevant art can make various changes or modifications without departing from the spirit and scope of the present invention, so all equivalent technical solutions should also belong to the protection scope of the present invention, and the protection scope of the present invention should be defined by the claims.

Claims (9)

1. A quick assembly module of a square cabin hospital assembly type steel structure comprises an upright post (3) supported between a top beam (1) and a ground beam (2), and is characterized in that two ends of the upright post (3) are detachably connected with the top beam (1) and the ground beam (2), so that the two upright posts (3), the top beam (1) and the ground beam (2) are enclosed to form a module base group; the end part of the upright post (3) is provided with a mounting plate (7) which is abutted against the top beam (1) and the ground beam (2); the module base is characterized in that connecting plates (4) are oppositely arranged at the connecting ends of the upright columns (3) and the top beams (1) and the ground beams (2), inclined strut structures (5) are installed on the connecting plates (4), and the inclined strut structures (5) are arranged in a crossed mode to stabilize the module base.
2. The shelter hospital assembly steel structure rapid assembly module according to claim 1, wherein the top beam (1) and the ground beam (2) are both H-shaped steel beams, and the web (11) of the H-shaped steel beams is arranged perpendicular to the installation horizontal plane of the assembly module.
3. The shelter hospital assembly steel structure rapid assembly module according to claim 2, wherein flanges (12) perpendicular to the web (11) are provided on both sides of the web (11) of the H-beam, and first screw holes for mounting the columns (3) are provided on the flanges (12).
4. The shelter hospital assembly steel structure rapid assembly module according to claim 3, wherein mounting plates (7) abutting against the flange (12) are welded to both ends of the upright column (3), and a second screw hole corresponding to the first screw hole is formed in the mounting plates (7).
5. The shelter hospital assembly steel structure quick assembly module of claim 4 wherein the width of the mounting plate (7) is less than or equal to the width of the flange (12).
6. The shelter hospital assembly steel structure quick assembly module according to claim 1, characterized in that the bracing structure (5) is hinged on a connecting plate (4).
7. The shelter hospital assembly type steel structure rapid assembly module according to claim 5, wherein the inclined strut structures (5) are angle steels or channel steels, and the two inclined strut structures (5) which are arranged in a crossed mode are connected in a plane alignment fit mode.
8. The shelter hospital assembly type steel structure rapid assembly module according to any one of claims 1 to 7, wherein the upright column is any one of a square tube, a circular tube, an H-shaped hot rolled section steel and a cold-formed thin-walled section steel.
9. The shelter hospital assembly steel structure quick assembly module as claimed in claim 8, characterized in that the bottom of the ground beam (2) is connected with the ground foundation with anchor bolts (6).
CN202221675938.XU 2022-07-01 2022-07-01 Assembled steel construction fast assembly module of shelter hospital Active CN218323151U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221675938.XU CN218323151U (en) 2022-07-01 2022-07-01 Assembled steel construction fast assembly module of shelter hospital

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221675938.XU CN218323151U (en) 2022-07-01 2022-07-01 Assembled steel construction fast assembly module of shelter hospital

Publications (1)

Publication Number Publication Date
CN218323151U true CN218323151U (en) 2023-01-17

Family

ID=84869137

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221675938.XU Active CN218323151U (en) 2022-07-01 2022-07-01 Assembled steel construction fast assembly module of shelter hospital

Country Status (1)

Country Link
CN (1) CN218323151U (en)

Similar Documents

Publication Publication Date Title
CN210603852U (en) A fully assembled steel structure reaction frame
US20180187406A1 (en) Building structure, building, and building construction method
CN214062433U (en) Temporary supporting structure of assembled steel structure
CN206233639U (en) movable shed
CN111894130A (en) Modular multi-story high-rise fabricated steel structure frame body
CN215329999U (en) Pile group type tower crane foundation
CN213390842U (en) Local bearing and supporting structure of steel truss
CN212896443U (en) Assembled steel construction tower machine basis
CN211949691U (en) Movable protective shed for construction on running light rail
CN114046080A (en) Self-resetting energy-dissipation supporting cold-formed steel shear wall
CN217054545U (en) Trade power station room frame construction and trade power station
CN111608328A (en) Wind-resistant structure for metal roof
CN217782350U (en) Steel frame supporting structure adopting assembly construction
CN212866335U (en) H-shaped steel beam connecting joint
CN215857736U (en) Foundation pit combined profile steel supporting system
CN215716098U (en) Full bolt connection stub beam formula beam column node structure
CN216516159U (en) Peripheral revetment body braced system of fast-assembling
CN109113750A (en) Shield end reinforces the emergency set and its construction method of failure
CN111472536B (en) Template support, steel template and spliced single-side vertical die structure
CN210947903U (en) Container prefabricated house frame
CN223907835U (en) Rotatable hanging flower basket landing leg fixing device
CN217149856U (en) Node column for underground construction site
CN219118807U (en) Construction structure is built to slope steel column
CN219491816U (en) Column-beam connection reinforcing structure
CN117052156B (en) Modularized reusable sliding rail beam device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant