CN218320207U - An auxiliary device for hoisting steel structure profiles - Google Patents

An auxiliary device for hoisting steel structure profiles Download PDF

Info

Publication number
CN218320207U
CN218320207U CN202222517484.XU CN202222517484U CN218320207U CN 218320207 U CN218320207 U CN 218320207U CN 202222517484 U CN202222517484 U CN 202222517484U CN 218320207 U CN218320207 U CN 218320207U
Authority
CN
China
Prior art keywords
hoisting
auxiliary device
main
connection
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222517484.XU
Other languages
Chinese (zh)
Inventor
曹心兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Zhongguangyuan Construction Technology Co., Ltd.
Original Assignee
Zhongguangyuan Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongguangyuan Construction Co ltd filed Critical Zhongguangyuan Construction Co ltd
Priority to CN202222517484.XU priority Critical patent/CN218320207U/en
Application granted granted Critical
Publication of CN218320207U publication Critical patent/CN218320207U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

本实用新型涉及吊装装置技术领域,公开了一种钢结构型材吊装辅助装置,包括三个主吊梁和吊装头,所述主吊梁下端面开设有连接槽,所述连接槽的两侧均开设有连接螺孔,所述连接槽的内部滑动设置有多个连接块,多个所述连接块下端面均固定连接有连接环,所述连接块的下端面两侧均开设有连接螺槽,所述连接块通过贯穿连接螺孔和连接螺槽的固定螺钉进行固定。本实用新型中,能够通过两侧的主吊梁同时起吊两捆钢结构型材,吊装时更加高效,同时也可单独使用中间的主吊梁进行起吊,从而进行单捆起吊,使用方式灵活多样,连接环的安装位置能够改变,便于适配不同长度的钢结构型材,吊装时更加稳定,适用范围广。

Figure 202222517484

The utility model relates to the technical field of hoisting devices, and discloses an auxiliary device for hoisting a steel structure profile, which comprises three main hanging beams and a hoisting head. A connection screw hole is provided, and a plurality of connection blocks are slidably arranged inside the connection groove, and connection rings are fixedly connected to the lower end surfaces of the plurality of connection blocks, and connection screw grooves are provided on both sides of the lower end surface of the connection blocks , the connecting block is fixed by a fixing screw passing through the connecting screw hole and the connecting screw groove. In the utility model, two bundles of steel structural profiles can be lifted at the same time through the main hanging beams on both sides, and the hoisting is more efficient. At the same time, the main hanging beam in the middle can also be used for lifting alone, so as to perform single-bundle lifting, and the use methods are flexible and diverse. The installation position of the connecting ring can be changed, which is convenient for adapting to steel structural profiles of different lengths, and it is more stable during hoisting and has a wide range of applications.

Figure 202222517484

Description

一种钢结构型材吊装辅助装置An auxiliary device for hoisting steel structure profiles

技术领域technical field

本实用新型涉及吊装装置技术领域,尤其涉及一种钢结构型材吊装辅助装置。The utility model relates to the technical field of hoisting devices, in particular to an auxiliary device for hoisting steel structure profiles.

背景技术Background technique

在施工现场钢结构型材是重要的建筑材料,钢结构型材在施工现场往往为多个叠放,多个之间使用卡销留出空间,便于吊装,装卸钢结构型材宜采用两点吊,吊运时,吊运方式有成捆起吊和单根起吊。Steel structural profiles are important building materials at the construction site. Steel structural profiles are often stacked on the construction site, and bayonet pins are used to leave space between them, which is convenient for hoisting. Two-point hoisting should be used for loading and unloading steel structural profiles. When transporting, the lifting methods include bundled lifting and single lifting.

目前多通过起吊机连接绳索来起吊钢结构型材,一般一次最多只能够起吊一捆钢板桩,工作效率较低。因此,本领域技术人员提供了一种钢结构型材吊装辅助装置,以解决上述背景技术中提出的问题。At present, steel structure profiles are mostly lifted by connecting ropes with a hoist. Generally, only one bundle of steel sheet piles can be lifted at most at a time, and the work efficiency is low. Therefore, those skilled in the art provide an auxiliary device for hoisting steel structure profiles to solve the problems raised in the above-mentioned background technology.

实用新型内容Utility model content

本实用新型的目的是为了解决现有技术中存在的缺点,而提出的一种钢结构型材吊装辅助装置,本吊装辅助装置能够通过两侧的主吊梁同时起吊两捆钢结构型材,吊装时更加高效,同时也可单独使用中间的主吊梁进行起吊,从而进行单捆起吊,使用方式灵活多样,连接环的安装位置能够改变,便于适配不同长度的钢结构型材,吊装时更加稳定,适用范围广。The purpose of this utility model is to solve the shortcomings existing in the prior art, and propose a steel structure profile hoisting auxiliary device, the hoisting auxiliary device can lift two bundles of steel structure profiles at the same time through the main hanging beams on both sides. It is more efficient. At the same time, the main lifting beam in the middle can also be used alone for lifting, so as to perform single-bundle lifting. The use method is flexible and diverse. The installation position of the connecting ring can be changed, which is convenient for adapting to steel structural profiles of different lengths. It is more stable during hoisting. Wide range of applications.

为实现上述目的,本实用新型提供了如下技术方案:In order to achieve the above object, the utility model provides the following technical solutions:

一种钢结构型材吊装辅助装置,包括三个主吊梁和吊装头,所述主吊梁下端面开设有连接槽,所述连接槽的两侧均开设有连接螺孔,所述连接槽的内部滑动设置有多个连接块,多个所述连接块下端面均固定连接有连接环,所述连接块的下端面两侧均开设有连接螺槽,所述连接块通过贯穿连接螺孔和连接螺槽的固定螺钉进行固定;An auxiliary device for hoisting steel structure profiles, including three main hanging beams and hoisting heads, the lower end surface of the main hanging beams is provided with connecting grooves, and both sides of the connecting grooves are provided with connecting screw holes. A plurality of connecting blocks are slidingly arranged inside, and the lower end faces of the plurality of connecting blocks are fixedly connected with connecting rings, and both sides of the lower end faces of the connecting blocks are provided with connecting screw grooves, and the connecting blocks pass through connecting screw holes and The fixing screw connecting the screw groove is fixed;

通过上述技术方案,主吊梁的下方均设置有连接环,使得该辅助装置在使用时能够通过两侧的主吊梁同时起吊两捆钢结构型材,吊装时更加高效,同时也可单独使用中间的起吊梁进行起吊,从而进行单捆起吊,拧出固定螺钉即可将连接块解锁,从而改变连接块的位置,进而改变连接环的安装位置,便于适配不同长度的钢结构型材,吊装时更加稳定。Through the above technical scheme, connecting rings are provided under the main hanging beam, so that the auxiliary device can simultaneously lift two bundles of steel structural profiles through the main hanging beams on both sides when in use, which is more efficient in hoisting, and can also be used alone. The lifting beam is used for lifting, so as to carry out single-bundle lifting. Unscrew the fixing screw to unlock the connecting block, thereby changing the position of the connecting block, and then changing the installation position of the connecting ring, which is convenient for adapting to steel structural profiles of different lengths. When hoisting more stable.

进一步地,三个所述主吊梁之间均固定连接有支撑框架;Further, a support frame is fixedly connected between the three main suspension beams;

通过上述技术方案,支撑框架能够增强主吊梁之间的连接强度。Through the above technical solution, the support frame can enhance the connection strength between the main hanging beams.

进一步地,三个所述主吊梁之间固定连接有两个补强架;Further, two reinforcement frames are fixedly connected between the three main suspension beams;

通过上述技术方案,补强架用以增强主吊梁之间的连接稳定性。Through the above technical solution, the reinforcement frame is used to enhance the connection stability between the main hanging beams.

进一步地,位于两侧的所述主吊梁的上端面固定连接有多个吊装环,所述吊装头设置在主吊梁上侧;Further, the upper end surfaces of the main suspension beams on both sides are fixedly connected with a plurality of hoisting rings, and the hoisting head is arranged on the upper side of the main suspension beam;

通过上述技术方案,设置的吊装环用以连接吊装绳索。Through the above technical solution, the provided hoisting ring is used for connecting hoisting ropes.

进一步地,多个所述吊装环均与吊装头连接有吊装绳索;Further, a plurality of hoisting rings are connected to hoisting heads with hoisting ropes;

通过上述技术方案,拉动吊装绳索从而起吊主吊梁。Through the above technical proposal, the hoisting rope is pulled to hoist the main suspension beam.

进一步地,所述吊装头的上端面固定连接有主吊环;Further, the upper end surface of the hoisting head is fixedly connected with a main hoisting ring;

通过上述技术方案,通过吊装环连接起吊机。Through the above technical proposal, the hoist is connected through the hoisting ring.

本实用新型具有如下有益效果:The utility model has the following beneficial effects:

1、本实用新型提出的一种钢结构型材吊装辅助装置,该装置在使用时,通过设置三个主吊梁,且在三个主吊梁的下方均设置有连接环,使得该辅助装置在使用时能够通过两侧的主吊梁同时起吊两捆钢结构型材,吊装时更加高效,同时也可单独使用中间的主吊梁进行起吊,从而进行单捆起吊,使用方式灵活多样。1. The utility model proposes an auxiliary device for hoisting steel structure profiles. When the device is in use, three main hanging beams are provided, and connecting rings are arranged under the three main hanging beams, so that the auxiliary device can When in use, two bundles of steel structural profiles can be lifted at the same time through the main lifting beams on both sides, which is more efficient during hoisting. At the same time, the main lifting beam in the middle can also be used for lifting alone, so as to perform single-bundle lifting, and the use methods are flexible and diverse.

2、本实用新型提出的一种钢结构型材吊装辅助装置,该装置在使用时,通过设置连接块和固定螺钉以及连接螺孔,拧出固定螺钉即可将连接块解锁,从而改变连接块的位置,进而改变连接环的安装位置,便于适配不同长度的钢结构型材,吊装时更加稳定,适用范围广。2. The utility model proposes an auxiliary device for hoisting steel structure profiles. When the device is in use, by setting the connecting block, fixing screws and connecting screw holes, the connecting block can be unlocked by unscrewing the fixing screw, thereby changing the connection block. position, and then change the installation position of the connecting ring, which is convenient to adapt to steel structural profiles of different lengths, more stable when hoisting, and has a wide range of applications.

附图说明Description of drawings

图1为本实用新型提出的一种钢结构型材吊装辅助装置的正视图;Fig. 1 is the front view of a kind of steel structure profile hoisting auxiliary device proposed by the utility model;

图2为本实用新型提出的一种钢结构型材吊装辅助装置的主吊梁的俯视图;Fig. 2 is the plan view of the main suspension beam of a kind of steel structure profile hoisting auxiliary device proposed by the utility model;

图3为本实用新型提出的一种钢结构型材吊装辅助装置的主吊梁的底视图;Fig. 3 is a bottom view of the main hanging beam of a steel structure profile hoisting auxiliary device proposed by the utility model;

图4为本实用新型提出的一种钢结构型材吊装辅助装置的主吊梁的内部结构示意图。Fig. 4 is a schematic diagram of the internal structure of the main hanging beam of a steel structure profile hoisting auxiliary device proposed by the utility model.

图例说明:illustration:

1、主吊梁;2、连接环;3、吊装环;4、吊装绳索;5、吊装头;6、主吊环;7、补强架;8、支撑框架;9、连接槽;10、固定螺钉;11、连接螺孔;12、连接块;13、连接螺槽。1. Main hoisting beam; 2. Connecting ring; 3. Hoisting ring; 4. Hoisting rope; 5. Hoisting head; 6. Main hoisting ring; 7. Reinforcing frame; 8. Supporting frame; Screw; 11, connecting screw hole; 12, connecting block; 13, connecting screw groove.

具体实施方式detailed description

下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. example. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.

参照图1-4,本实用新型提供的一种实施例:一种钢结构型材吊装辅助装置,包括三个主吊梁1和吊装头5,通过两侧的主吊梁1同时起吊两捆钢结构型材,吊装时更加高效,同时也可单独使用中间的主吊梁1进行起吊,从而进行单捆起吊,主吊梁1下端面开设有连接槽9,连接槽9的两侧均开设有连接螺孔11,连接槽9的内部滑动设置有多个连接块12,多个连接块12下端面均固定连接有连接环2,连接块12的下端面两侧均开设有连接螺槽13,连接块12通过贯穿连接螺孔11和连接螺槽13的固定螺钉10进行固定,拧出固定螺钉10即可将连接块12解锁,从而改变连接块12的位置,进而改变连接环2的安装位置,便于适配不同长度的钢结构型材。Referring to Figures 1-4, an embodiment provided by the utility model: an auxiliary device for hoisting steel structure profiles, including three main hoisting beams 1 and hoisting heads 5, through which two bundles of steel beams 1 are hoisted at the same time Structural profile, more efficient when hoisting, and can also use the main hanging beam 1 in the middle alone for lifting, so as to perform single-bundle lifting. The lower end surface of the main hanging beam 1 is provided with a connecting groove 9, and both sides of the connecting groove 9 are provided with connecting grooves. Screw holes 11, the inside of the connecting groove 9 are slidably provided with a plurality of connecting blocks 12, and the lower end faces of the plurality of connecting blocks 12 are fixedly connected with the connecting ring 2, and the lower end faces of the connecting blocks 12 are both provided with connecting screw grooves 13. The block 12 is fixed by the fixing screw 10 passing through the connecting screw hole 11 and the connecting screw groove 13, and the connecting block 12 can be unlocked by unscrewing the fixing screw 10, so as to change the position of the connecting block 12, and then change the installation position of the connecting ring 2, It is easy to adapt to steel structure profiles of different lengths.

三个主吊梁1之间均固定连接有支撑框架8,支撑框架8能够增强主吊梁1之间的连接强度,三个主吊梁1之间固定连接有两个补强架7,补强架7用以增强主吊梁1之间的连接稳定性,位于两侧的主吊梁1的上端面固定连接有多个吊装环3,吊装头5设置在主吊梁1上侧,设置的吊装环3用以连接吊装绳索4,多个吊装环3均与吊装头5连接有吊装绳索4,拉动吊装绳索4从而起吊主吊梁1,吊装头5的上端面固定连接有主吊环6,通过吊装环3连接起吊机。The support frame 8 is fixedly connected between the three main suspension beams 1, and the support frame 8 can enhance the connection strength between the main suspension beams 1, and there are two reinforcement frames 7 fixedly connected between the three main suspension beams 1 to supplement The strong frame 7 is used to enhance the connection stability between the main hanging beams 1. The upper end faces of the main hanging beams 1 on both sides are fixedly connected with a plurality of hoisting rings 3, and the hoisting head 5 is arranged on the upper side of the main hanging beams 1. The hoisting ring 3 is used to connect the hoisting rope 4, a plurality of hoisting rings 3 are connected with the hoisting head 5 with a hoisting rope 4, the hoisting rope 4 is pulled to lift the main hoisting beam 1, and the upper end surface of the hoisting head 5 is fixedly connected with the main hoisting ring 6 , connect the hoist through hoisting ring 3.

工作原理:本装置在使用时,在三个主吊梁1的下方均设置有连接环2,连接环2用以连接绳索来捆绑钢结构型材,使得该辅助装置在使用时能够通过两侧的主吊梁1同时起吊两捆钢结构型材,吊装时更加高效,同时也可使用中间的主吊梁1进行起吊,从而进行单捆起吊,使用方式灵活多样,同时,拧出固定螺钉10即可将连接块12解锁,从而改变连接块12的位置,进而改变连接环2的安装位置,便于适配不同长度的钢结构型材,吊装时更加稳定,适用范围广。Working principle: when the device is in use, a connecting ring 2 is provided under the three main hanging beams 1, and the connecting ring 2 is used to connect ropes to bind steel structure profiles, so that the auxiliary device can pass through the two sides when in use. The main lifting beam 1 lifts two bundles of steel structural profiles at the same time, which is more efficient during hoisting. At the same time, the middle main lifting beam 1 can also be used for lifting, so as to perform single-bundle lifting. The connecting block 12 is unlocked, thereby changing the position of the connecting block 12, and further changing the installation position of the connecting ring 2, which is convenient for adapting to steel structural profiles of different lengths, more stable during hoisting, and has a wide range of applications.

最后应说明的是:以上所述仅为本实用新型的优选实施例而已,并不用于限制本实用新型,尽管参照前述实施例对本实用新型进行了详细的说明,对于本领域的技术人员来说,其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换,凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。Finally, it should be noted that: the above is only a preferred embodiment of the utility model, and is not intended to limit the utility model, although the utility model has been described in detail with reference to the foregoing embodiments, for those skilled in the art , it can still modify the technical solutions recorded in the foregoing embodiments, or perform equivalent replacements on some of the technical features. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present utility model, All should be included within the protection scope of the present utility model.

Claims (6)

1. The utility model provides a steel structure section bar hoist and mount auxiliary device, includes three main hanging beam (1) and hoisting head (5), its characterized in that: connecting groove (9) have been seted up to terminal surface under main hanging beam (1), connection screw (11) have all been seted up to the both sides of connecting groove (9), the inside slip of connecting groove (9) is provided with a plurality of connecting blocks (12), and is a plurality of the equal fixedly connected with go-between (2) of terminal surface under connecting block (12), connection thread groove (13) have all been seted up to the lower terminal surface both sides of connecting block (12), fixing screw (10) through-connection screw (11) and connection thread groove (13) are fixed in connecting block (12).
2. The steel structural section hoisting auxiliary device as claimed in claim 1, wherein: and supporting frames (8) are fixedly connected among the three main hoisting beams (1).
3. The steel structural section hoisting auxiliary device as claimed in claim 1, wherein: two reinforcing frames (7) are fixedly connected between the three main hanging beams (1).
4. The steel structural section hoisting auxiliary device as claimed in claim 1, wherein: the upper end face of the main hoisting beam (1) positioned on two sides is fixedly connected with a plurality of hoisting rings (3), and the hoisting heads (5) are arranged on the upper side of the main hoisting beam (1).
5. The steel structural section hoisting auxiliary device as claimed in claim 4, wherein: and the hoisting rings (3) are connected with hoisting ropes (4) with the hoisting heads (5).
6. The steel structural section hoisting auxiliary device as claimed in claim 1, wherein: the upper end face of the hoisting head (5) is fixedly connected with a main hoisting ring (6).
CN202222517484.XU 2022-09-22 2022-09-22 An auxiliary device for hoisting steel structure profiles Active CN218320207U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222517484.XU CN218320207U (en) 2022-09-22 2022-09-22 An auxiliary device for hoisting steel structure profiles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222517484.XU CN218320207U (en) 2022-09-22 2022-09-22 An auxiliary device for hoisting steel structure profiles

Publications (1)

Publication Number Publication Date
CN218320207U true CN218320207U (en) 2023-01-17

Family

ID=84838833

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222517484.XU Active CN218320207U (en) 2022-09-22 2022-09-22 An auxiliary device for hoisting steel structure profiles

Country Status (1)

Country Link
CN (1) CN218320207U (en)

Similar Documents

Publication Publication Date Title
CN201686432U (en) 800 tons of hanging row
CN211846850U (en) Hoisting device for prefabricated building installation
CN209455933U (en) A kind of spreader for lamination board hoisting
CN201809034U (en) Lifting appliance applied to adjusting posture of large member in air
CN204847752U (en) Be used for hanging small -size sectionalised gallows of hook type crane handling
CN210944509U (en) Plate hoisting clamping part for building construction
CN218320207U (en) An auxiliary device for hoisting steel structure profiles
CN216038140U (en) Assembly type house PC hoisting stair structure
CN214059608U (en) PC superimposed sheet transportation frame hoist
CN116145937A (en) An all-round operation platform for the outer wall of a large storage tank
CN221396859U (en) Hanging beam structure for hoisting bobbins
CN221500315U (en) Middle-large precast slab precast beam lifting appliance
CN216836735U (en) Dry-type transformer hoisting device
CN217211450U (en) A large bridge crane load test device
CN216945864U (en) Become prefabricated tubular pile of size self-tightening formula hoist device
CN213976601U (en) Steel reinforcement cage hoisting device with double hoisting structures for building construction
CN219771495U (en) A composite beam hoisting device
CN217676307U (en) Combined stay bar structure for hoisting cable reel
CN208087049U (en) A lifting tool for power cables
CN223561088U (en) Balance hanging beam lifting appliance
CN213569108U (en) Precast beam template hoist and mount system
CN219753631U (en) Cement assembled floor convenient to hoist and mount
CN220564116U (en) U rib hoisting tool
CN112079148A (en) a brick tool
CN222935009U (en) Self-balancing adjustable telescopic lifting device for superimposed sheet

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20260106

Address after: 530228 Guangxi Zhuang Autonomous Region Nanning City Jiangnan District Suxu Town East side of the Nanyou Expressway Connection Road

Patentee after: Guangxi Zhongguangyuan Construction Technology Co., Ltd.

Country or region after: China

Address before: 530317 Guangxi Zhuang Autonomous Region Nanning City Hengzhou Liu Jing Guangxi Beigang Liu Jing Industrial Park

Patentee before: Zhongguangyuan Construction Co.,Ltd.

Country or region before: China