CN218152950U - Mining type confluence assembly matched with connecting pipe - Google Patents

Mining type confluence assembly matched with connecting pipe Download PDF

Info

Publication number
CN218152950U
CN218152950U CN202222644858.4U CN202222644858U CN218152950U CN 218152950 U CN218152950 U CN 218152950U CN 202222644858 U CN202222644858 U CN 202222644858U CN 218152950 U CN218152950 U CN 218152950U
Authority
CN
China
Prior art keywords
pipe
confluence
connecting pipe
mine
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222644858.4U
Other languages
Chinese (zh)
Inventor
龙渡江
熊军
屠定雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Shipu Mining New Material Co ltd
Original Assignee
Guizhou Shipu Mining New Material Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Shipu Mining New Material Co ltd filed Critical Guizhou Shipu Mining New Material Co ltd
Priority to CN202222644858.4U priority Critical patent/CN218152950U/en
Application granted granted Critical
Publication of CN218152950U publication Critical patent/CN218152950U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sampling And Sample Adjustment (AREA)

Abstract

The utility model discloses a supporting mining formula assembly that converges that has connecting pipe, including the collecting pipe, the side of collecting pipe is provided with the connecting hole, the both ends of collecting pipe are provided with mounting flange, connecting hole department is provided with the connecting pipe, the one end of connecting pipe is provided with the collector link, the other end is provided with takes out a tub link in advance, be provided with the valve in the connecting pipe, the outside of collector link is provided with the first ring of helping of six prism forms, be provided with the detection hole on the connecting pipe, this assembly that converges is supporting to be provided with the connecting pipe and is used for connecting the collector and takes out the pipe in advance, the built-in valve of connecting pipe, can cut the communicating state of collector and taking out the pipe in advance as required, still be provided with the detection hole, whether there is gas and measure gas concentration in this hole of accessible detection pipeline, or whether there is gas and measure gas concentration in the collector under the detection state of cutting, the practicality is splendid, the connecting pipe is simple swift with the connection process of taking out the pipe in advance, it is comparatively convenient during the use.

Description

配套有连接管的矿用式汇流总成Mine-use confluence assembly with connecting pipe

技术领域technical field

本实用新型涉及煤矿设备技术领域,具体为配套有连接管的矿用式汇流总成。The utility model relates to the technical field of coal mine equipment, in particular to a mine-use confluence assembly equipped with connecting pipes.

背景技术Background technique

在抽采瓦斯的过程中,瓦斯预抽管与主管之间的连接需要大量的汇流器,就是将多根预抽管并联汇流到一起后接入主管(汇流器),预抽管与汇流器的连接目前一般采用内外丝连接,通常是将PVC注塑管做成具有内丝的安装头焊接在汇流器上,再通过安装头与预抽管连接,连接结构较为简单,且全体预抽管均与汇流器保持连通状态,无法有选择性的关闭部分预抽管,也只能在预抽管的尾端确定该管道内是否具有瓦斯,使用较为不便。In the process of gas extraction, the connection between the gas pre-extraction pipe and the main pipe requires a large number of confluences, that is, multiple pre-extraction pipes are connected in parallel and then connected to the main pipe (confluencer), and the pre-extraction pipe and the confluence At present, the connection is generally connected by inner and outer wires. Usually, the PVC injection pipe is made into a mounting head with an inner wire and welded on the confluence, and then connected to the pre-pumping pipe through the mounting head. The connection structure is relatively simple, and all the pre-pumping pipes are uniform. Keeping in communication with the confluence, part of the pre-extraction pipe cannot be selectively closed, and it is only at the end of the pre-extraction pipe to determine whether there is gas in the pipe, which is inconvenient to use.

实用新型内容Utility model content

本实用新型要解决的技术问题是克服现有的缺陷,提供一种配套有连接管的矿用式汇流总成,可以有效解决背景技术中的问题。The technical problem to be solved by the utility model is to overcome the existing defects and provide a mine-use confluence assembly equipped with connecting pipes, which can effectively solve the problems in the background technology.

为实现上述目的,本实用新型提供如下技术方案:一种配套有连接管的矿用式汇流总成,包括汇流管,汇流管的侧面设置有连接孔,汇流管的两端设置有安装法兰,所述连接孔处设置有连接管,连接管的一端设置有汇流器连接端,另一端设置有预抽管连接端,连接管内设置有阀门,阀门的阀柄位于连接管外部,汇流器连接端包括用于连接汇流器的第一螺部,第一螺部上套设有第一密封环,汇流器连接端的外部设置有六棱柱状的第一助拧环,连接管上设置有探测孔,探测孔位于阀门与预抽管连接端之间。In order to achieve the above purpose, the utility model provides the following technical solutions: a mine-use confluence assembly equipped with connecting pipes, including a confluence pipe, connecting holes are provided on the side of the confluence pipe, and mounting flanges are provided on both ends of the confluence pipe , the connecting hole is provided with a connecting pipe, one end of the connecting pipe is provided with a confluencer connecting end, the other end is provided with a pre-pumping pipe connecting end, a valve is arranged in the connecting pipe, the valve handle of the valve is located outside the connecting pipe, and the confluencer is connected The end includes a first screw part for connecting the confluence, the first screw part is sleeved with a first sealing ring, the outside of the confluence connection end is provided with a hexagonal column-shaped first screwing ring, and the connecting pipe is provided with a detection hole , The detection hole is located between the valve and the connection end of the pre-sitting pipe.

作为本实用新型的一种优选技术方案,所述汇流器连接端通过螺接的方式与连接管连接,预抽管连接端通过粘接的方式与连接管连接。As a preferred technical solution of the present invention, the connecting end of the confluence is connected to the connecting pipe by screwing, and the connecting end of the pre-pumping pipe is connected to the connecting pipe by bonding.

作为本实用新型的一种优选技术方案,所述阀柄的外侧面压制有滚花纹。As a preferred technical solution of the present invention, the outer surface of the valve handle is pressed with knurling patterns.

作为本实用新型的一种优选技术方案,所述阀门为球阀。As a preferred technical solution of the utility model, the valve is a ball valve.

作为本实用新型的一种优选技术方案,所述探测孔为凸出的圆柱形,探测孔外套设有密封胶帽。As a preferred technical solution of the utility model, the detection hole is a protruding cylinder, and the detection hole is covered with a sealant cap.

作为本实用新型的一种优选技术方案,所述所述预抽管连接端包括第二螺部及其外部的锁紧套,第二螺部的内部设置有同心的内筒,第二密封环套设在内筒的根部,内筒上套设有锁紧套,预抽管连接端的外部设置有六棱柱状的第二助拧环。As a preferred technical solution of the present invention, the connecting end of the pre-pumping pipe includes a second screw part and a locking sleeve outside the second screw part. A concentric inner cylinder is arranged inside the second screw part. The second sealing ring The inner cylinder is sheathed at the root, the inner cylinder is overlaid with a locking sleeve, and the outside of the connection end of the pre-pumping pipe is provided with a second hexagonal prism-shaped screwing aid ring.

作为本实用新型的一种优选技术方案,所述预抽管连接端包括套管,套管外侧面设置有环形凹槽,环形凹槽内套设有套筒,套筒外配套设置有绑带。As a preferred technical solution of the utility model, the connection end of the pre-pumping pipe includes a sleeve, the outer surface of the sleeve is provided with an annular groove, the inner sleeve of the annular groove is provided with a sleeve, and the sleeve is provided with a strap .

作为本实用新型的一种优选技术方案,所述套筒由具有弹性的软质材料制成。As a preferred technical solution of the utility model, the sleeve is made of elastic soft material.

作为本实用新型的一种优选技术方案,所述连接孔的内壁设置有金属制成的衬套,衬套内设置有内螺纹,汇流器连接端通过第一螺部与衬套螺接。As a preferred technical solution of the present invention, the inner wall of the connection hole is provided with a bush made of metal, and the bush is provided with an internal thread, and the connecting end of the confluence is screwed to the bush through the first screw part.

与现有技术相比,本实用新型的有益效果是:本配套有连接管的矿用式汇流总成,配套设置有连接管用于连接汇流器与预抽管,连接管内置阀门,可根据实际需要截断汇流器与预抽管的连通状态,还设置有探测孔,可通过该孔探测管道内是否存在瓦斯及测量瓦斯浓度,或是在截断状态下探测汇流器内是否存在瓦斯及测量瓦斯浓度,实用性极佳,连接管与预抽管的连接过程简单快捷,使用时较为方便。Compared with the prior art, the beneficial effect of the utility model is: the mine-use confluence assembly equipped with a connecting pipe is equipped with a connecting pipe for connecting the confluence and the pre-pumping pipe. The connecting pipe has a built-in valve, which can be used according to the actual situation. It is necessary to cut off the connection state between the manifold and the pre-pumping pipe, and also set a detection hole, through which the presence of gas in the pipeline can be detected and the gas concentration can be measured, or the presence of gas in the manifold can be detected and the gas concentration can be measured in the cut-off state , Excellent practicability, the connection process of the connecting pipe and the pre-pumping pipe is simple and fast, and it is more convenient to use.

附图说明Description of drawings

图1为本实用新型结构示意图;Fig. 1 is the structural representation of the utility model;

图2为本实用新型A处结构放大示意图;Fig. 2 is the enlarged schematic view of the structure at A place of the utility model;

图3为本实用新型第一实施例结构示意图;Fig. 3 is a structural schematic diagram of the first embodiment of the utility model;

图4为本实用新型第二实施例结构示意图。Fig. 4 is a schematic structural diagram of the second embodiment of the utility model.

图中:1连接管、2阀门、21阀柄、3汇流器连接端、31第一螺部、32 第一助拧环、33第一密封环、4预抽管连接端、41第二螺部、42第二助拧环、43锁紧套、44第二密封环、45套管、46套筒、47绑带、48锁紧筒、49内筒、 5探测孔、6汇流管、7安装法兰、8连接孔、9衬套。In the figure: 1 connecting pipe, 2 valve, 21 valve handle, 3 confluence connecting end, 31 first screw part, 32 first screwing ring, 33 first sealing ring, 4 pre-pumping pipe connecting end, 41 second screw part, 42 second screwing ring, 43 locking sleeve, 44 second sealing ring, 45 casing, 46 sleeve, 47 strap, 48 locking cylinder, 49 inner cylinder, 5 detection hole, 6 manifold, 7 Mounting flange, 8 connecting holes, 9 bushings.

具体实施方式detailed description

下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. example. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.

请参阅图1-2,本实用新型提供一种技术方案:一种配套有连接管的矿用式汇流总成,包括汇流管6,汇流管6的侧面设置有连接孔8,汇流管6的两端设置有安装法兰7,连接孔8处设置有连接管1,连接管1的一端设置有汇流器连接端3,另一端设置有预抽管连接端4,汇流器连接端3通过螺接的方式与连接管1连接,预抽管连接端4通过粘接的方式与连接管1连接,连接管1内设置有阀门2,阀门2为球阀,生产成本低,易维护,阀门2的阀柄 21位于连接管1外部,阀柄21的外侧面压制有滚花纹,起到防滑作用,阀门 2可根据实际需要截断汇流器与预抽管的连通状态,关闭无需连通的预抽管,可有效避免瓦斯从这些预抽管处泄露;Please refer to Figure 1-2, the utility model provides a technical solution: a mine-use confluence assembly equipped with a connecting pipe, including a confluence pipe 6, the side of the confluence pipe 6 is provided with a connection hole 8, the confluence pipe 6 Mounting flanges 7 are provided at both ends, and a connecting pipe 1 is provided at the connecting hole 8. One end of the connecting pipe 1 is provided with a confluence connection end 3, and the other end is provided with a pre-pumping pipe connection end 4. The confluence connection end 3 passes through the screw Connected to the connecting pipe 1, the pre-pumping pipe connecting end 4 is connected to the connecting pipe 1 by bonding, the connecting pipe 1 is provided with a valve 2, the valve 2 is a ball valve, the production cost is low, and the maintenance is easy. The valve handle 21 is located outside the connecting pipe 1, and the outer surface of the valve handle 21 is pressed with a knurling pattern, which plays an anti-slip effect. The valve 2 can cut off the connection between the confluence and the pre-pumping pipe according to actual needs, and close the pre-pumping pipe that does not need to be connected. It can effectively avoid gas leakage from these pre-pumping pipes;

汇流器连接端3包括用于连接汇流器的第一螺部31,第一螺部31上套设有第一密封环33,汇流器连接端3的外部设置有六棱柱状的第一助拧环32,方便借助扳手或管钳将汇流器连接端3与连接管1及汇流管6的连接孔8进行连接,连接孔8的内壁设置有金属制成的衬套9,衬套9内设置有内螺纹,汇流器连接端3通过第一螺部31与衬套9螺接,提高连接稳定性及其使用寿命;The confluence connection end 3 includes a first screw part 31 for connecting the confluence. The first screw part 31 is covered with a first sealing ring 33, and the outside of the confluence connection end 3 is provided with a hexagonal column-shaped first screwing aid. The ring 32 is convenient to use a wrench or a pipe wrench to connect the confluence connection end 3 with the connection pipe 1 and the connection hole 8 of the confluence pipe 6. The inner wall of the connection hole 8 is provided with a metal bushing 9, and the bushing 9 is set There is an internal thread, and the connecting end 3 of the confluence is screwed to the bushing 9 through the first screw part 31, so as to improve the connection stability and its service life;

连接管1上设置有探测孔5,探测孔5位于阀门2与预抽管连接端4之间,可通过探测孔5探测连接管1内是否有瓦斯流通及其瓦斯浓度,或是在截断状态下探测汇流器内是否存在瓦斯及其瓦斯浓度,实用性极佳,探测孔5为凸出的圆柱形,探测孔5外套设有密封胶帽,避免瓦斯泄露。The connecting pipe 1 is provided with a detection hole 5, which is located between the valve 2 and the connection end 4 of the pre-pumping pipe. Through the detection hole 5, it is possible to detect whether there is gas circulation and gas concentration in the connecting pipe 1, or whether it is in a cut-off state. It is very practical to detect whether there is gas and its concentration in the confluence. The detection hole 5 is a protruding cylinder, and the detection hole 5 is covered with a sealing rubber cap to avoid gas leakage.

实施例一Embodiment one

请参阅图3,预抽管连接端4包括第二螺部41及其外部的锁紧套43,第二螺部43的内部设置有同心的内筒49,第二密封环44套设在内筒49的根部,在连接预抽管时,预抽管端部套设在内筒49上,锁紧筒48套设在预抽管端部外,锁紧套43拧紧在第二螺部41上后,将锁紧套48压紧形变,使其压制在预抽管端部上,提高连接稳定性,此时预抽管端口与第二密封环44接触,提高了连接处的密封性;Please refer to Fig. 3, the pre-pumping pipe connection end 4 includes a second threaded part 41 and a locking sleeve 43 outside it, and a concentric inner cylinder 49 is arranged inside the second threaded part 43, and a second sealing ring 44 is sleeved inside When the root of the tube 49 is connected to the pre-pumping tube, the end of the pre-pumping tube is sleeved on the inner tube 49, the locking tube 48 is set outside the end of the pre-pumping tube, and the locking sleeve 43 is tightened on the second screw part 41 After being installed, the locking sleeve 48 is compressed and deformed so that it is pressed on the end of the pre-pumping pipe to improve the connection stability. At this time, the port of the pre-pumping pipe is in contact with the second sealing ring 44, which improves the sealing of the connection;

预抽管连接端4的外部设置有六棱柱状的第二助拧环42,方便借助扳手或管钳将预抽管连接端4与连接管1进行连接。A hexagonal prism-shaped second screwing aid ring 42 is arranged outside the connecting end 4 of the pre-pumping tube, which facilitates the connection between the connecting end 4 of the pre-pumping tube and the connecting pipe 1 by means of a wrench or pipe wrench.

实施例二Embodiment two

请参阅图4,预抽管连接端4包括套管45,套管45外侧面设置有环形凹槽,环形凹槽内套设有套筒46,套筒46外配套设置有绑带47,套筒46由具有弹性的软质材料制成,以便套设在套管45外侧面的环形凹槽内,在连接时,预抽管端部套设在套筒46的外部,绑带47将预抽管端部绑紧,此时套筒46 发生弹性形变,提高了连接处的密封性。Please refer to Fig. 4, the pre-pumping pipe connection end 4 includes a sleeve 45, the outer surface of the sleeve 45 is provided with an annular groove, the inner sleeve of the annular groove is provided with a sleeve 46, and the sleeve 46 is equipped with a strap 47, the sleeve 46 Sleeve 46 is made of elastic soft material so that it can be sleeved in the annular groove on the outer surface of sleeve pipe 45. When connecting, the end of the pre-pumping tube is sleeved on the outside of sleeve 46, and strap 47 will The end of the suction pipe is tied tightly, and at this time, the sleeve 46 is elastically deformed, which improves the sealing performance of the joint.

尽管已经示出和描述了本实用新型的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本实用新型的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本实用新型的范围由所附权利要求及其等同物限定。Although the embodiments of the present invention have been shown and described, those skilled in the art can understand that various changes and modifications can be made to these embodiments without departing from the principle and spirit of the present invention , replacements and modifications, the scope of the present utility model is defined by the appended claims and their equivalents.

Claims (9)

1.一种配套有连接管的矿用式汇流总成,包括汇流管(6),汇流管(6)的侧面设置有连接孔(8),汇流管(6)的两端设置有安装法兰(7),其特征在于:所述连接孔(8)处设置有连接管(1),连接管(1)的一端设置有汇流器连接端(3),另一端设置有预抽管连接端(4),连接管(1)内设置有阀门(2),阀门(2)的阀柄(21)位于连接管(1)外部;1. A mine-use confluence assembly equipped with connecting pipes, comprising a confluence pipe (6), a connection hole (8) is provided on the side of the confluence pipe (6), and an installation method is provided at both ends of the confluence pipe (6). Lan (7), characterized in that: the connecting hole (8) is provided with a connecting pipe (1), one end of the connecting pipe (1) is provided with a confluence connecting end (3), and the other end is provided with a pre-pumping pipe connecting end (4), the connecting pipe (1) is provided with a valve (2), and the valve handle (21) of the valve (2) is located outside the connecting pipe (1); 汇流器连接端(3)包括用于连接汇流器的第一螺部(31),第一螺部(31)上套设有第一密封环(33),汇流器连接端(3)的外部设置有六棱柱状的第一助拧环(32);The confluence connection end (3) includes a first screw part (31) for connecting the confluence, and a first sealing ring (33) is sleeved on the first screw part (31), and the outside of the confluence connection end (3) A first screwing aid ring (32) in the shape of a hexagonal column is provided; 连接管(1)上设置有探测孔(5),探测孔(5)位于阀门(2)与预抽管连接端(4)之间。The connecting pipe (1) is provided with a detection hole (5), and the detection hole (5) is located between the valve (2) and the connection end (4) of the pre-pumping pipe. 2.根据权利要求1所述的配套有连接管的矿用式汇流总成,其特征在于:所述汇流器连接端(3)通过螺接的方式与连接管(1)连接,预抽管连接端(4)通过粘接的方式与连接管(1)连接。2. The mine-use confluence assembly equipped with connecting pipes according to claim 1, characterized in that: the connecting end (3) of the confluence is connected to the connecting pipe (1) by screwing, and the pre-pumping pipe The connecting end (4) is connected with the connecting pipe (1) by bonding. 3.根据权利要求1所述的配套有连接管的矿用式汇流总成,其特征在于:所述阀柄(21)的外侧面压制有滚花纹。3. The mine-use confluence assembly equipped with connecting pipes according to claim 1, characterized in that: the outer surface of the valve handle (21) is pressed with knurling patterns. 4.根据权利要求1所述的配套有连接管的矿用式汇流总成,其特征在于:所述阀门(2)为球阀。4. The mine-use confluence assembly equipped with connecting pipes according to claim 1, characterized in that: the valve (2) is a ball valve. 5.根据权利要求1所述的配套有连接管的矿用式汇流总成,其特征在于:所述探测孔(5)为凸出的圆柱形,探测孔(5)外套设有密封胶帽。5. The mine-use confluence assembly equipped with connecting pipes according to claim 1, characterized in that: the detection hole (5) is a protruding cylindrical shape, and the detection hole (5) is covered with a sealant cap . 6.根据权利要求1或2所述的配套有连接管的矿用式汇流总成,其特征在于:所述预抽管连接端(4)包括第二螺部(41)及其外部的锁紧套(43),第二螺部(41)的内部设置有同心的内筒(49),第二密封环(44)套设在内筒(49)的根部,内筒(49)上套设有锁紧筒(48),预抽管连接端(4)的外部设置有六棱柱状的第二助拧环(42)。6. The mine-use confluence assembly equipped with connecting pipes according to claim 1 or 2, characterized in that: the connecting end (4) of the pre-pumping pipe includes a second screw part (41) and a lock outside it Tight sleeve (43), the inside of the second screw part (41) is provided with a concentric inner cylinder (49), the second sealing ring (44) is sleeved at the root of the inner cylinder (49), and the inner cylinder (49) is sleeved A locking cylinder (48) is provided, and a hexagonal column-shaped second screwing aid ring (42) is provided outside the pre-pumping pipe connection end (4). 7.根据权利要求1所述的配套有连接管的矿用式汇流总成,其特征在于:所述预抽管连接端(4)包括套管(45),套管(45)外侧面设置有环形凹槽,环形凹槽内套设有套筒(46),套筒(46)外配套设置有绑带(47)。7. The mine-use confluence assembly equipped with connecting pipes according to claim 1, characterized in that: the connecting end (4) of the pre-pumping pipe includes a sleeve (45), and the outer surface of the sleeve (45) is set There is an annular groove, the inner sleeve of the annular groove is provided with a sleeve (46), and the sleeve (46) is equipped with a strap (47). 8.根据权利要求7所述的配套有连接管的矿用式汇流总成,其特征在于:所述套筒(46)由具有弹性的软质材料制成。8. The mine-use confluence assembly equipped with connecting pipes according to claim 7, characterized in that: the sleeve (46) is made of elastic soft material. 9.根据权利要求1所述的配套有连接管的矿用式汇流总成,其特征在于:所述连接孔(8)的内壁设置有金属制成的衬套(9),衬套(9)内设置有内螺纹,汇流器连接端(3)通过第一螺部(31)与衬套(9)螺接。9. The mine-use confluence assembly equipped with connecting pipes according to claim 1, characterized in that: the inner wall of the connecting hole (8) is provided with a metal bushing (9), and the bushing (9) ) is provided with an internal thread, and the confluence connection end (3) is screwed to the bushing (9) through the first screw portion (31).
CN202222644858.4U 2022-10-09 2022-10-09 Mining type confluence assembly matched with connecting pipe Active CN218152950U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222644858.4U CN218152950U (en) 2022-10-09 2022-10-09 Mining type confluence assembly matched with connecting pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222644858.4U CN218152950U (en) 2022-10-09 2022-10-09 Mining type confluence assembly matched with connecting pipe

Publications (1)

Publication Number Publication Date
CN218152950U true CN218152950U (en) 2022-12-27

Family

ID=84567373

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222644858.4U Active CN218152950U (en) 2022-10-09 2022-10-09 Mining type confluence assembly matched with connecting pipe

Country Status (1)

Country Link
CN (1) CN218152950U (en)

Similar Documents

Publication Publication Date Title
CN202305129U (en) Quick connector for air tightness test
CN218152950U (en) Mining type confluence assembly matched with connecting pipe
CN112145115B (en) Oil recovery well head connecting device
CN218152949U (en) Mining gas collector assembly
CN205027476U (en) Inner tube fluid pressure measuring device of multilayer pipeline
CN201242015Y (en) Pipeline connector
CN206002263U (en) Pipe end pressure-detecting device
CN211082993U (en) Air tightness detection structure of large-diameter cryogenic valve with thread
CN212933729U (en) A safety monitoring system for gas leakage alarm in long-distance natural gas pipeline network
CN210739711U (en) Natural gas safety protection pressure regulating device
CN220527666U (en) Double-horn-mouth FT type cable joint
CN202901637U (en) Gas chamber connecting device for SF6 gas condition monitoring
CN205824252U (en) A kind of pressure measurement gas valve
CN205243825U (en) A bypass valve for helium compressor
CN224150390U (en) A pressure valve calibrator with variable diameter device
CN222561145U (en) A pipeline temperature measuring element installation device
CN222417107U (en) Gas pipeline with safety detection device
CN206801485U (en) Portable marine riser auxiliary line pressure testing device
CN207515986U (en) A kind of oil tank for oil immersion type transformer leakage testing device
CN223910638U (en) Quick pressure testing frock of screw thread
CN218762012U (en) Metal pipeline angle iron flange seal structure
CN220688288U (en) A metal hard sealing joint device
CN223375351U (en) A conversion joint for explosion-proof online monitoring of excavator oil pipes
CN114252211B (en) Pressure pipeline leakage monitoring device and manufacturing method
CN219317923U (en) A three-way pipe fitting

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: Mining type busbar assembly with connecting pipes

Granted publication date: 20221227

Pledgee: Huangshong branch of rural credit cooperative association of Pingba District, Anshun City

Pledgor: Guizhou Shipu mining new material Co.,Ltd.

Registration number: Y2024980025079

PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Granted publication date: 20221227

Pledgee: Huangshong branch of rural credit cooperative association of Pingba District, Anshun City

Pledgor: Guizhou Shipu mining new material Co.,Ltd.

Registration number: Y2024980025079