CN218027576U - A drilling platform for deep-water shallow overburden riverbed - Google Patents
A drilling platform for deep-water shallow overburden riverbed Download PDFInfo
- Publication number
- CN218027576U CN218027576U CN202222287926.6U CN202222287926U CN218027576U CN 218027576 U CN218027576 U CN 218027576U CN 202222287926 U CN202222287926 U CN 202222287926U CN 218027576 U CN218027576 U CN 218027576U
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- drilling platform
- riverbed
- pile
- deep
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
本实用新型公开了一种用于深水浅覆盖层河床的钻孔平台,涉及钻孔平台技术领域,所述钻孔平台包括:多个桩基和连接梁,多个桩基与浅覆盖层河床固定连接,每个所述桩基均包括钢管桩和混凝土锚桩,每个所述桩基的钢管桩插设在浅覆盖层河床上,每个所述桩基的钢管桩的内部灌注混凝土形成对应的混凝土锚桩,所述连接梁固定设在多个所述钢管桩顶端,所述连接梁上用于设置顶面板。本实用新型的每个桩基的钢管桩插设在浅覆盖层河床上,一方面,钢管桩可以为对应的混凝土锚桩施工进行导向;另一方面,钢管桩可以作为支撑用于钻孔平台上部的连接梁的施工,且桩基施工和连接梁施工互不干扰,可提高施工效率,节省施工工期。
The utility model discloses a drilling platform for deep-water shallow overburden riverbeds, and relates to the technical field of drilling platforms. Fixedly connected, each of the pile foundations includes steel pipe piles and concrete anchor piles, the steel pipe piles of each of the pile foundations are inserted on the shallow overburden river bed, and the inside of the steel pipe piles of each of the pile foundations Concrete is poured to form corresponding concrete anchor piles, and the connecting beams are fixedly arranged at the tops of the plurality of steel pipe piles, and the connecting beams are used for setting roof panels. The steel pipe piles of each pile foundation of the utility model are inserted on the shallow overburden river bed. On the one hand, the steel pipe piles can guide the construction of corresponding concrete anchor piles; on the other hand, the steel pipe piles can be used as supports for The construction of the connecting beam on the upper part of the drilling platform, and the construction of the pile foundation and the construction of the connecting beam do not interfere with each other, which can improve the construction efficiency and save the construction period.
Description
技术领域technical field
本实用新型涉及钻孔平台技术领域,特别涉及一种用于深水浅覆盖层河床的钻孔平台。The utility model relates to the technical field of drilling platforms, in particular to a drilling platform used for deep-water shallow overburden riverbeds.
背景技术Background technique
深水桥梁基础一般采用“先平台后围堰”的施工方法,其中钻孔平台是钻孔灌注桩施工最常用的平台结构。针对深水、风大、浪急、流速大的浅覆盖层河床地质,现有技术钻孔平台的施工思路为:在桩基桩位附近进行冲孔或者爆破,然后在孔内下放钢筋笼,灌注水下混凝土形成混凝土锚桩,待混凝土达到设计强度后,再在混凝土锚桩上安装钢管桩,混凝土锚桩和钢管桩共同作为钻孔平台的桩基,在钢管桩上施工钻孔平台上部结构。该方案的不足之处在于:钻孔平台的桩基施工需要搭设临时施工平台,且需要等桩基的混凝土锚桩及钢管桩施工完毕后,才能进行钻孔平台上部结构施工,使得整个钻孔平台施工速度较慢,费用较高。The construction method of "platform first, then cofferdam" is generally adopted for the foundation of bridges in deep water. The drilled platform is the most commonly used platform structure for the construction of bored piles. For shallow overburden river bed geology with deep water, strong wind, strong waves, and high flow velocity, the construction idea of the existing drilling platform is: to punch or blast near the pile foundation pile position, then lower the steel cage in the hole, pour Underwater concrete forms concrete anchor piles. After the concrete reaches the design strength, steel pipe piles are installed on the concrete anchor piles. The concrete anchor piles and steel pipe piles are used as the pile foundation of the drilling platform, and drilling is carried out on the steel pipe piles. Platform superstructure. The disadvantage of this scheme is that the construction of the pile foundation of the drilling platform needs to set up a temporary construction platform, and the construction of the upper structure of the drilling platform can only be carried out after the construction of the concrete anchor piles and steel pipe piles of the pile foundation is completed, so that the entire drilling platform The construction speed of the hole platform is slower and the cost is higher.
实用新型内容Utility model content
本实用新型实施例提供一种用于深水浅覆盖层河床的钻孔平台,以解决相关技术中现有钻孔平台施工速度较慢,费用较高的技术问题。The embodiment of the utility model provides a drilling platform for deep-water shallow overburden riverbeds to solve the technical problems of relatively slow construction speed and high cost in the existing drilling platforms in the related art.
本实用新型实施例提供了一种用于深水浅覆盖层河床的钻孔平台,包括:The embodiment of the utility model provides a drilling platform for deep-water shallow overburden riverbed, including:
多个与浅覆盖层河床固定连接的桩基,每个所述桩基均包括钢管桩和混凝土锚桩,每个所述桩基的钢管桩插设在浅覆盖层河床上,每个所述桩基的钢管桩的内部灌注混凝土形成对应的混凝土锚桩;A plurality of pile foundations fixedly connected with the shallow overburden riverbed, each of which includes steel pipe piles and concrete anchor piles, and the steel pipe piles of each of the pile foundations are inserted on the shallow overburden riverbed, each Concrete is poured into the steel pipe pile of the pile foundation to form a corresponding concrete anchor pile;
连接梁,所述连接梁固定设在多个所述钢管桩顶端,所述连接梁上用于设置顶面板。A connecting beam, the connecting beam is fixedly arranged at the tops of a plurality of steel pipe piles, and the connecting beam is used for setting a top panel.
一些实施例中,所述连接梁包括:In some embodiments, the connecting beam includes:
多个横梁,多个所述横梁横向间隔,每个所述横梁固设在横向的多个所述钢管桩上;A plurality of crossbeams, a plurality of said crossbeams are spaced apart laterally, and each said crossbeam is fixed on a plurality of said steel pipe piles in the transverse direction;
多个纵梁,多个所述纵梁纵向间隔,每个所述纵梁固设在所有所述横梁上。A plurality of longitudinal beams, the plurality of longitudinal beams are longitudinally spaced, and each of the longitudinal beams is fixed on all the transverse beams.
一些实施例中,每个所述横梁均包括两片连接成一体的H型钢,两片所述H型钢均与对应的所述钢管桩连接。In some embodiments, each of the beams includes two pieces of H-shaped steel connected as one, and the two pieces of H-shaped steel are connected to the corresponding steel pipe piles.
一些实施例中,所述钻孔平台还包括:In some embodiments, the drilling platform also includes:
与每个所述钢管桩一一对应的支撑牛腿,每个所述支撑牛腿设在对应的所述钢管桩顶部且与对应的一个所述横梁的两片H型钢连接。A support bracket corresponding to each of the steel pipe piles, each of the support brackets is arranged on the top of the corresponding steel pipe pile and connected with two pieces of H-shaped steel of the corresponding one of the cross beams.
一些实施例中,每个所述支撑牛腿均包括:In some embodiments, each said support bracket includes:
环向加强板,所述环向加强板与对应的所述钢管桩的顶部连接;a hoop reinforcement plate, the hoop reinforcement plate is connected to the top of the corresponding steel pipe pile;
环形盖顶板,所述环形盖顶板设于所述环向加强板的顶端;An annular cover top plate, the annular cover top plate is arranged on the top end of the annular reinforcement plate;
第一加劲板,所述第一加劲板与所述环向加强板和所述环形盖顶板连接。A first stiffening plate, the first stiffening plate is connected with the circumferential reinforcing plate and the annular cover top plate.
一些实施例中,每个所述横梁均还包括多个片型钢桁架,多个所述片型钢桁架间隔设在两片所述H型钢之间且与两片所述H型钢连接;In some embodiments, each of the beams further includes a plurality of sheet-shaped steel trusses, and the plurality of sheet-shaped steel trusses are spaced between two pieces of the H-shaped steel and connected to the two pieces of the H-shaped steel;
每个所述横梁在靠近对应的所述钢管桩设有第二加劲板,所述第二加劲板对应的所述钢管桩连接。Each of the beams is provided with a second stiffening plate close to the corresponding steel pipe pile, and the second stiffening plate is connected to the corresponding steel pipe pile.
一些实施例中,所述钻孔平台还包括:In some embodiments, the drilling platform also includes:
多个连接杆系,每个所述连接杆系与相邻两个所述钢管桩连接。A plurality of connecting rod systems, each of which is connected to two adjacent steel pipe piles.
一些实施例中,每个所述连接杆系均包括:In some embodiments, each connecting rod system includes:
上弦杆,所述上弦杆与对应的相邻两个所述钢管桩连接;an upper chord, the upper chord is connected to the corresponding two adjacent steel pipe piles;
下弦杆,所述下弦杆位于所述上弦杆下侧且与对应的相邻两个所述钢管桩连接;a lower chord, the lower chord is located on the lower side of the upper chord and is connected to the corresponding two adjacent steel pipe piles;
多根斜杆,每根所述斜杆均与所述上弦杆和下弦杆连接。A plurality of oblique rods, each of which is connected to the upper chord and the lower chord.
一些实施例中,每个所述钢管桩内均设有钢筋笼,所述钢筋笼下端伸入浅覆盖层河床。In some embodiments, each of the steel pipe piles is provided with a reinforcement cage, and the lower end of the reinforcement cage extends into the shallow overburden riverbed.
本实用新型提供的技术方案带来的有益效果包括:The beneficial effects brought by the technical solution provided by the utility model include:
本实用新型实施例提供了一种用于深水浅覆盖层河床的钻孔平台,所述钻孔平台的每个桩基的钢管桩插设在浅覆盖层河床上,一方面,钢管桩可以为对应的混凝土锚桩施工进行导向,另一方面,钢管桩可以作为支撑用于钻孔平台上部的连接梁的施工,且桩基施工和连接梁施工互不干扰,可提高施工效率,节省施工工期。另外,本实用新型实施例也不需要提前搭设临时施工平台来进行桩基施工,可节省材料用量,降低工程成本。The embodiment of the utility model provides a drilling platform for deep-water and shallow overburden riverbeds. The steel pipe piles of each pile foundation of the drilling platform are inserted on the shallow overburden riverbed. On the one hand, the steel pipe piles It can guide the corresponding concrete anchor pile construction. On the other hand, the steel pipe pile can be used as a support for the construction of the connecting beam on the upper part of the drilling platform, and the construction of the pile foundation and the construction of the connecting beam do not interfere with each other, which can improve the construction efficiency. Save construction period. In addition, the embodiment of the utility model does not need to build a temporary construction platform in advance for pile foundation construction, which can save material consumption and reduce engineering costs.
附图说明Description of drawings
为了更清楚地说明本实用新型实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本实用新型的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the accompanying drawings that need to be used in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings in the following description are only some implementations of the present invention. For example, those of ordinary skill in the art can also obtain other drawings based on these drawings on the premise of not paying creative efforts.
图1为本实用新型实施例提供的一种用于深水浅覆盖层河床的钻孔平台的示意图;Fig. 1 is the schematic diagram of a kind of drilling platform that is used for deep-water shallow overburden river bed that the utility model embodiment provides;
图2为本实用新型实施例提供的图1的侧视图;Fig. 2 is the side view of Fig. 1 that the utility model embodiment provides;
图3为本实用新型实施例提供的图2的俯视图;Fig. 3 is the top view of Fig. 2 provided by the utility model embodiment;
图4为本实用新型实施例提供的横梁与钢管桩连接的俯视图;Fig. 4 is a top view of the connection between the beam and the steel pipe pile provided by the embodiment of the utility model;
图5为本实用新型实施例提供的图4的侧视图;Fig. 5 is the side view of Fig. 4 provided by the utility model embodiment;
图6为本实用新型实施例提供的支撑牛腿与钢管桩连接的示意图;Fig. 6 is a schematic diagram of the connection between the support bracket and the steel pipe pile provided by the embodiment of the present invention;
图7为本实用新型实施例提供的图6的俯视图;Fig. 7 is the top view of Fig. 6 provided by the embodiment of the present utility model;
图8为本实用新型实施例提供的连接杆系与钢管桩连接的示意图;Fig. 8 is a schematic diagram of the connection between the connecting rod system and the steel pipe pile provided by the embodiment of the present invention;
图9为本实用新型实施例提供的桩基的示意图;Fig. 9 is the schematic diagram of the pile foundation that the utility model embodiment provides;
图中:In the picture:
1、桩基;11、钢管桩;12、混凝土锚桩;13、钢筋笼;1. Pile foundation; 11. Steel pipe pile; 12. Concrete anchor pile; 13. Reinforcement cage;
2、连接梁;21、横梁;211、H型钢;212、片型钢桁架;213、第二加劲板;22、纵梁;2. Connecting beam; 21. Beam; 211. H-shaped steel; 212. Sheet steel truss; 213. Second stiffening plate; 22. Longitudinal beam;
3、支撑牛腿;31、环向加强板;32、环形盖顶板;33、第一加劲板;331、第一竖向加劲板;332、第二竖向加劲板;3. Support corbel; 31. Ring reinforcement plate; 32. Ring top plate; 33. First stiffening plate; 331. First vertical stiffening plate; 332. Second vertical stiffening plate;
4、连接杆系;41、上弦杆;42、下弦杆;43、斜杆。4. Connecting bar system; 41, upper chord; 42, lower chord; 43, inclined bar.
具体实施方式detailed description
为使本实用新型实施例的目的、技术方案和优点更加清楚,下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例是本实用新型的一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动的前提下所获得的所有其他实施例,都属于本实用新型保护的范围。In order to make the purpose, technical solutions and advantages of the embodiments of the utility model more clear, the technical solutions in the embodiments of the utility model will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the utility model. Obviously, the described The embodiments are some embodiments of the present utility model, but not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.
本实用新型实施例提供了一种用于深水浅覆盖层河床的钻孔平台,其能解决现有钻孔平台施工速度较慢,费用较高的技术问题。The embodiment of the utility model provides a drilling platform for deep-water shallow overburden riverbed, which can solve the technical problems of slow construction speed and high cost of the existing drilling platform.
参见图1和图2所示,本实用新型实施例提供了一种用于深水浅覆盖层河床的钻孔平台,包括:多个桩基1和连接梁2。Referring to Fig. 1 and Fig. 2, the embodiment of the utility model provides a drilling platform for deep-water shallow overburden riverbed, including: a plurality of pile foundations 1 and connecting
多个所述桩基1与浅覆盖层河床固定连接,每个所述桩基1均包括钢管桩11和混凝土锚桩12,每个所述桩基1的钢管桩11插设在浅覆盖层河床上,每个所述桩基1的钢管桩11的内部灌注混凝土形成对应的混凝土锚桩12。具体地,以每个桩基1的钢管桩11作为导向钻孔,在孔内灌注混凝土形成对应的混凝土锚桩12,每个桩基1的钢管桩11和混凝土锚桩12与浅覆盖层河床固结成一个整体,可提供较大的水平刚度和竖向刚度,共同承受钻孔平台钻孔时产生的竖向力以及波浪、水流力和风荷载产生的水平力,降低了钻孔平台在水深、风大、浪急、流速大的复杂海域进行钻孔施工的难度,安全性较高。A plurality of said pile foundations 1 are fixedly connected with the shallow overburden riverbed, each of said pile foundations 1 includes steel pipe piles 11 and concrete anchor piles 12, and the steel pipe piles 11 of each said pile foundation 1 are inserted in shallow Concrete is poured into the steel pipe piles 11 of each pile foundation 1 to form corresponding concrete anchor piles 12 on the overlying river bed. Specifically, the
所述连接梁2固定设在多个所述钢管桩11顶端,所述连接梁2上用于设置顶面板,方便施工人员进行后续钻孔施工。The connecting
本实用新型实施例中的用于深水浅覆盖层河床的钻孔平台,其每个桩基的钢管桩插设在浅覆盖层河床上,一方面,钢管桩可以为对应的混凝土锚桩施工进行导向;另一方面,钢管桩可以作为支撑用于钻孔平台上部的连接梁的施工,且桩基施工和连接梁施工互不干扰,可提高施工效率,节省施工工期。另外,本实用新型实施例也不需要提前搭设临时施工平台来进行桩基施工,可节省材料用量,降低工程成本。In the drilling platform for deep-water shallow overburden riverbed in the embodiment of the utility model, the steel pipe piles of each pile foundation are inserted on the shallow overburden riverbed. On the one hand, the steel pipe piles can be corresponding concrete anchor piles The construction is guided; on the other hand, the steel pipe pile can be used as a support for the construction of the connecting beam on the upper part of the drilling platform, and the construction of the pile foundation and the construction of the connecting beam do not interfere with each other, which can improve the construction efficiency and save the construction period. In addition, the embodiment of the utility model does not need to build a temporary construction platform in advance for pile foundation construction, which can save material consumption and reduce engineering costs.
作为可选的实施方式,在一个实用新型实施例中,参见图3所示,所述连接梁2包括:多个横梁21和多个纵梁22。As an optional implementation, in an embodiment of the utility model, as shown in FIG. 3 , the connecting
多个所述横梁21横向间隔,每个所述横梁21固设在横向的多个所述钢管桩11上,多个所述纵梁22纵向间隔,每个所述纵梁22固设在所有所述横梁21上。A plurality of
进一步地,参见图4所示,每个所述横梁21均包括两片连接成一体的H型钢211,两片所述H型钢211均与对应的所述钢管桩11连接。两片所述H型钢之间间隔一定距离,保证型钢稳定性,便于承受荷载。Further, as shown in FIG. 4 , each of the
所述纵梁22是将钻孔平台竖向荷载均匀传递至所述横梁21的结构,所述纵梁22可采用贝雷梁,其方向与所述横梁21方向垂直。钻孔平台施工时,待所述横梁21搭设完成后,先铺设钢管桩11附近位置的纵梁22和顶面板,作为混凝土锚桩12施工平台,待混凝土锚桩12施工完毕后,再铺设钢管桩11顶部的纵梁22和顶面板,最终完成整个钻孔平台的搭设。The
作为可选的实施方式,在一个实用新型实施例中,参见图6和图7所示,所述钻孔平台还包括:与每个所述钢管桩11一一对应的支撑牛腿3,每个所述支撑牛腿3设在对应的所述钢管桩11顶部且与对应的一个所述横梁21的两片H型钢211连接。As an optional implementation, in a utility model embodiment, as shown in Fig. 6 and Fig. 7, the drilling platform further includes: a
进一步地,每个所述支撑牛腿3均包括:环向加强板31、环形盖顶板32和第一加劲板33。所述环向加强板31与对应的所述钢管桩11的顶部连接,所述环形盖顶板32设于所述环向加强板31的顶端,所述第一加劲板33与所述环向加强板31和所述环形盖顶板32连接。Further, each of the supporting
具体地,所述支撑牛腿3是将横梁21承受的荷载均匀传递至钢管桩11的结构,所述支撑牛腿3布置于钢管桩11顶部,方便后期施工桩基1的混凝土锚桩12和钻孔平台上部的连接梁2,桩基1的施工与连接梁2施工互不干扰,可提高施工效率,节省施工工期。Specifically, the
所述支撑牛腿3的安装步骤如下:首先,在钢管桩11顶部焊接环向加强板31,环向加强板31顶部与钢管桩11顶部齐平、底部与钢管桩11用周圈角焊缝连接,环向加强板31中间开设槽型焊接孔与钢管桩11连接,焊后磨平,可提高钢管桩11的承压及抗剪强度;然后将环形盖顶板32和第一加劲板33用双面角焊缝焊接成一个整体,所述第一加劲板33包括第一竖向加劲板331和第二竖向加劲板332,所述第一竖向加劲板331位置应和两片H型钢211腹板位置上下对应;最后,将环形盖顶板32和第一加劲板33焊接成的整体结构套入钢管桩11顶部,环形盖顶板32与钢管桩11顶部用周圈角焊缝连接,第一加劲板33的第一竖向加劲板331与钢管桩11之间采用坡口对接焊缝连接。The installation steps of the supporting
作为可选的实施方式,在一个实用新型实施例中,参见图4和图5所示,每个所述横梁21均还包括多个片型钢桁架212,多个所述片型钢桁架212间隔设在两片所述H型钢211之间且与两片所述H型钢211连接。每个所述横梁21在靠近对应的所述钢管桩11设有第二加劲板213,所述第二加劲板213对应的所述钢管桩11连接,多个片型钢桁架212保证两片所述H型钢211连接的稳定性,所述第二加劲板213保证横梁21与钢管桩11连接的可靠性。As an optional implementation, in an embodiment of the utility model, as shown in Fig. 4 and Fig. 5, each of the
作为可选的实施方式,在一个实用新型实施例中,参见图8所示,所述钻孔平台还包括:多个连接杆系4,每个所述连接杆系4与相邻两个所述钢管桩11连接,所述连接杆系4可以增强钻孔平台的整体刚度和稳定性。As an optional implementation, in a utility model embodiment, as shown in FIG. 8, the drilling platform further includes: a plurality of connecting
进一步地,每个所述连接杆系4均包括:上弦杆41、下弦杆42和多根斜杆43。所述上弦杆41与对应的相邻两个所述钢管桩11连接,所述下弦杆42位于所述上弦杆41下侧且与对应的相邻两个所述钢管桩11连接,每根所述斜杆43均与所述上弦杆41和下弦杆42连接,所述上弦杆41、下弦杆42和斜杆43均采用钢管。可在工厂提前焊接成一个整体,再在现场吊装,与上述钢管桩11用周圈焊接成整体,结构简单,施工方便。Further, each connecting
作为可选的实施方式,参见图9所示,在一个实用新型实施例中,每个所述钢管桩11内均设有钢筋笼13,所述钢筋笼13下端伸入浅覆盖层河床提高混凝土锚桩12成型后的强度。As an optional implementation, as shown in Figure 9, in a utility model embodiment, each of the steel pipe piles 11 is provided with a
本实用新型实施例提供了一种用于深水浅覆盖层河床的钻孔平台的施工方法,包括以下步骤:The embodiment of the utility model provides a construction method for a drilling platform used in a deep-water shallow overburden riverbed, comprising the following steps:
将多个钢管桩11插设在浅覆盖层河床上。A plurality of steel pipe piles 11 are inserted on the shallow overburden river bed.
在每个钢管桩11内灌注混凝土形成对应的混凝土锚桩12,使多个桩基1的钢管桩11和混凝土锚桩12与浅覆盖层河床固定连接。Concrete is poured into each
在多个钢管桩11顶端设置连接梁2,并在连接梁2上设置顶面板。A connecting
本实用新型实施例中的用于深水浅覆盖层河床的钻孔平台的施工方法,其将每个桩基的钢管桩插设在浅覆盖层河床上,一方面,钢管桩可以为对应的混凝土锚桩施工进行导向;另一方面,钢管桩可以作为支撑用于钻孔平台上部的连接梁的施工,且桩基施工和连接梁施工互不干扰,可提高施工效率,节省施工工期。另外,本实用新型实施例也不需要提前搭设临时施工平台来进行桩基施工,可节省材料用量,降低工程成本。In the construction method of the drilling platform for the deep-water shallow overburden riverbed in the embodiment of the utility model, it inserts the steel pipe piles of each pile foundation on the shallow overburden riverbed. On the one hand, the steel pipe piles can be corresponding On the other hand, the steel pipe pile can be used as a support for the construction of the connecting beam on the upper part of the drilling platform, and the construction of the pile foundation and the construction of the connecting beam do not interfere with each other, which can improve the construction efficiency and save the construction period . In addition, the embodiment of the utility model does not need to build a temporary construction platform in advance for pile foundation construction, which can save material consumption and reduce engineering costs.
在本实用新型的描述中,需要说明的是,术语“上”、“下”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本实用新型和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本实用新型的限制。除非另有明确的规定和限定,术语“安装”、“相连”、“连接”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或一体地连接;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本实用新型中的具体含义。In the description of the present utility model, it should be noted that the orientation or positional relationship indicated by the terms "upper", "lower", etc. is based on the orientation or positional relationship shown in the accompanying drawings, and is only for the convenience of describing the utility model and simplifying the Describes, but does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore should not be construed as limiting the present invention. Unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be interpreted in a broad sense, for example, it may be a fixed connection, a detachable connection, or an integral connection; it may be a mechanical connection, It can also be an electrical connection; it can be a direct connection, or an indirect connection through an intermediary, or an internal communication between two components. Those of ordinary skill in the art can understand the specific meanings of the above terms in the present utility model according to specific situations.
需要说明的是,在本实用新型中,诸如“第一”和“第二”等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。在没有更多限制的情况下,由语句“包括一个……”限定的要素,并不排除在包括所述要素的过程、方法、物品或者设备中还存在另外的相同要素。It should be noted that in this utility model, relative terms such as "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or Any such actual relationship or order between such entities or operations is implied. Furthermore, the term "comprises", "comprises" or any other variation thereof is intended to cover a non-exclusive inclusion such that a process, method, article, or apparatus comprising a set of elements includes not only those elements, but also includes elements not expressly listed. other elements of or also include elements inherent in such a process, method, article, or device. Without further limitations, an element defined by the phrase "comprising a ..." does not exclude the presence of additional identical elements in the process, method, article or apparatus comprising said element.
以上所述仅是本实用新型的具体实施方式,使本领域技术人员能够理解或实现本实用新型。对这些实施例的多种修改对本领域的技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本实用新型的精神或范围的情况下,在其它实施例中实现。因此,本实用新型将不会被限制于本文所示的这些实施例,而是要符合与本文实用新型的原理和新颖特点相一致的最宽的范围。The above descriptions are only specific implementation methods of the present utility model, so that those skilled in the art can understand or realize the present utility model. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the invention. Therefore, the present invention will not be limited to these embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features of the present invention.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202222287926.6U CN218027576U (en) | 2022-08-29 | 2022-08-29 | A drilling platform for deep-water shallow overburden riverbed |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202222287926.6U CN218027576U (en) | 2022-08-29 | 2022-08-29 | A drilling platform for deep-water shallow overburden riverbed |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN218027576U true CN218027576U (en) | 2022-12-13 |
Family
ID=84351516
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202222287926.6U Active CN218027576U (en) | 2022-08-29 | 2022-08-29 | A drilling platform for deep-water shallow overburden riverbed |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN218027576U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115506324A (en) * | 2022-08-29 | 2022-12-23 | 中铁大桥局集团有限公司 | A drilling platform and construction method for deep-water shallow overburden riverbed |
-
2022
- 2022-08-29 CN CN202222287926.6U patent/CN218027576U/en active Active
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115506324A (en) * | 2022-08-29 | 2022-12-23 | 中铁大桥局集团有限公司 | A drilling platform and construction method for deep-water shallow overburden riverbed |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101906754B (en) | Rigid connection method for steel beam and concrete pier | |
| CN104131704A (en) | Steel pipe column concrete lateral pouring method and steel pipe column structure used in method | |
| CN210507829U (en) | Assembly type building connecting node of steel pipe concrete column-precast concrete composite beam | |
| CN105544575A (en) | Underwater bottom sealing concrete construction method using steel truss for reinforcement | |
| CN114673169A (en) | A combined construction method of multi-layer large-span deep foundation pit covering and excavation in urban core area | |
| CN114790757A (en) | Cover-excavation top-down construction V-shaped column structure and construction method thereof | |
| CN220927778U (en) | A large diameter pile foundation operation platform for deep-water karst geology | |
| CN218027576U (en) | A drilling platform for deep-water shallow overburden riverbed | |
| CN203834809U (en) | Steel pipe column structure for steel pipe column concrete side pouring method | |
| CN111962549B (en) | Anti-overturning construction method of existing tower cranes under working conditions adjacent to foundation piles | |
| CN116084370A (en) | Offshore integral steel truss drilling platform and construction method in deep water bare rock | |
| CN210737607U (en) | A hang braced system for reverse construction method beam slab construction | |
| CN219527722U (en) | Pile structure for offshore photovoltaic power station in ice region | |
| CN115506324A (en) | A drilling platform and construction method for deep-water shallow overburden riverbed | |
| CN220013564U (en) | Large-scale ship backing member supporting system suitable for high pile wharf | |
| CN218147843U (en) | A construction system suitable for trestle bridges | |
| CN118639681A (en) | A construction method for underwater structures in complex environments | |
| CN110453710A (en) | A combined multi-tube jacket foundation structure and its construction method | |
| CN217053289U (en) | Self-floating steel truss drilling platform structure | |
| CN215630078U (en) | Reverse steel platform foundation structure | |
| CN202081426U (en) | Tower crane foundation | |
| CN114809043A (en) | Steel pipe and corrugated steel plate combined hanging box cofferdam and construction method | |
| CN116290038A (en) | Construction method of steel sheet pile cofferdam in tidal zone with large water level difference | |
| CN210216415U (en) | Positioning device for bridge pile foundation steel casing in deepwater and rapid stream area | |
| CN113802726A (en) | Overlapped integral prefabricated shear wall edge component and mounting method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |
