CN217921266U - Building engineering material lifting device - Google Patents

Building engineering material lifting device Download PDF

Info

Publication number
CN217921266U
CN217921266U CN202221619575.8U CN202221619575U CN217921266U CN 217921266 U CN217921266 U CN 217921266U CN 202221619575 U CN202221619575 U CN 202221619575U CN 217921266 U CN217921266 U CN 217921266U
Authority
CN
China
Prior art keywords
grudging post
lifting device
base
material lifting
hanging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202221619575.8U
Other languages
Chinese (zh)
Inventor
季亚林
严亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Heilongjiang Hongguan Construction Engineering Co ltd
Original Assignee
Heilongjiang Hongguan Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Heilongjiang Hongguan Construction Engineering Co ltd filed Critical Heilongjiang Hongguan Construction Engineering Co ltd
Priority to CN202221619575.8U priority Critical patent/CN217921266U/en
Application granted granted Critical
Publication of CN217921266U publication Critical patent/CN217921266U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a building engineering material lifting device, the on-line screen storage device comprises a base, base top be equipped with the grudging post of two parallels, be equipped with the guard gate all around, grudging post and base be connected with the auxiliary stay pole, grudging post, base and auxiliary stay pole form three horn-shaped structures, the base both sides be equipped with the hoist engine, the grudging post between be equipped with the hanging flower basket, hanging flower basket top platform fixedly connected with movable pulley, grudging post upper end be equipped with the limit for height platform, the limit for height platform on be equipped with the fixed pulley, hanging flower basket both sides and grudging post department of meeting be equipped with safety hook and guide pulley, hanging flower basket bottom be equipped with the buffer board. The utility model has the advantages that: the safety protection device is provided with the protection door, the hanging basket fence, the falling protector and the buffer plate, so that the safety of the material lifting device is improved; a weight detector is arranged to avoid overload; the vertical frame can be additionally provided with or detached from the upright post to adjust the height, so that the vertical frame is suitable for most building requirements; and a height limiting platform is arranged to prevent top impact.

Description

Building engineering material lifting device
Technical Field
The utility model relates to the building engineering field specifically indicates a building engineering material hoisting device.
Background
The building engineering is an engineering entity which performs various technical works such as planning, surveying, designing, constructing and completing for newly building, reconstructing or extending a house building and an auxiliary structure facility, and installation engineering of lines, pipelines and equipment matched with the engineering entity, and also refers to construction engineering of various houses and buildings. In the work progress, often need carry high-rise from the low floor with building material, only rely on the manpower to be difficult to realize, consequently material lifting device has extensive application in the building engineering field, and current material lifting device loop wheel machine structure is complicated, lacks protector, and poor stability is difficult to satisfy high-rise building engineering's needs.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve is the above technical problem, provides a building engineering material lifting device.
In order to solve the technical problem, the utility model provides a technical scheme does: the utility model provides a building engineering material lifting device, includes the base, base top be equipped with the grudging post of two parallels, be equipped with the guard gate all around, grudging post and base be connected with auxiliary stay pole, grudging post, base and auxiliary stay pole form three horn-shaped structures, the base both sides be equipped with the hoist engine, the grudging post between be equipped with the hanging flower basket, the hanging flower basket top be equipped with the movable pulley, the grudging post upper end be equipped with the limit for height platform, the limit for height platform on be equipped with the fixed pulley, hanging flower basket both sides and grudging post department of meeting be equipped with safety hook and guide pulley, hanging flower basket bottom be equipped with the buffer board.
As an improvement, the vertical frame is formed by combining and splicing a plurality of vertical columns, and the splicing positions of the vertical columns are connected by bolts.
As an improvement, a guide rail is arranged at the joint of the vertical frame and the guide wheel.
As an improvement, fences are arranged around the hanging basket and can be opened.
As an improvement, the bottom of the hanging basket is provided with a weight detector.
As an improvement, the falling protector is provided with six eccentric wheels which are evenly distributed on two sides of a vertical rod of the vertical frame, and the bottom of the falling protector is fixed on the hanging basket.
As an improvement, the buffer plate is connected to the bottom of the hanging basket through a spring.
As an improvement, the winch is connected with the movable pulley and the fixed pulley through a lifting rope.
Compared with the prior art, the utility model the advantage lie in:
1. the safety protection device is provided with the protection door, the hanging basket fence, the falling protector and the buffer plate, so that the safety of the material lifting device is improved, and safety accidents are reduced.
2. The device is provided with a weight detector, and when the weight of the conveyed materials is close to the rated loading weight of the material hoister, an alarm is given out to avoid overload.
3. The grudging post can install additional or dismantle the stand and come the height-adjusting, can be applicable to most building demands.
4. And a height limiting platform is arranged to prevent top impact.
Drawings
Fig. 1 is the utility model relates to a building engineering material hoisting device's schematic structure diagram.
Fig. 2 is a side view of the utility model relates to a building engineering material lifting device.
Fig. 3 is the structure schematic diagram of the utility model relates to a building engineering material lifting device safety hook.
As shown in the figure: 1. a base; 2. erecting a frame; 3. a winch; 4. a hanging basket; 5. a movable pulley; 6. a fixed pulley; 7. a safety catch; 8. a guide wheel; 9. a buffer plate; 10. a height-limiting platform; 11. a guard gate.
Detailed Description
In order to make the technical problem, technical solution and advantageous effects to be solved by the present invention more clearly understood, the following description is given in conjunction with the accompanying drawings and embodiments to illustrate the present invention in further detail. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "top/bottom", and the like indicate orientations or positional relationships based on those shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the referred device or element must have a specific orientation, be constructed in a specific orientation, and be operated, and thus should not be construed as limiting the present invention.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the term "connected" is to be interpreted broadly, for example, as a fixed connection, a detachable connection, or an integral connection; the specific meaning of the above terms in the present invention can be understood as a specific case by those skilled in the art.
The utility model provides a building engineering material hoisting device, as shown in figure 1, 1 top of base be equipped with the grudging post 2 of two parallels, grudging post 2 form by a plurality of stand concatenations, by bolted connection between the stand, can highly freely splice as required, it is simple convenient to install, can be applicable to the promotion demand of high-rise building material, the position of grudging post 2 and the contact of guide pulley 8 is equipped with the guide rail, can make 4 vertical lift of hanging flower basket, increases the stability of hanging flower basket 4, 2 tops of grudging post are equipped with limit for height platform 11, can prevent that hanging flower basket 4 from promoting too high, limit for height platform 11 also is convenient for the workman to install additional or dismantle the stand simultaneously.
The hanging basket 4 all around be equipped with the rail, the rail can be opened, the business turn over material of being convenient for also can play the effect that prevents the material landing to a certain extent, hanging basket 4 bottom is equipped with the weight detector, and when material weight reached the warning value of rated load weight, the weight detector sent out the police dispatch newspaper and reminds, prevents to overload damage equipment.
Hanging flower basket 4 bottom be equipped with buffer board 9, buffer board 9 be connected with hanging flower basket 4 through the spring, play the cushioning effect when hanging flower basket 4 descends to the ground from the eminence, prevent to cause the damage because of impulsive force is too big or overweight to hanging flower basket 4.
The vertical frame 2 and the base 1 are connected with an auxiliary supporting frame, as shown in fig. 2, the auxiliary supporting frame, the vertical frame 2 and the base 1 are triangular, a guy rope is replaced to enable the vertical frame 2 to be more stable, the winches 3 are arranged on two sides of the vertical frame 2, the winches 3 are connected with the fixed pulleys 6 and the movable pulleys 5 through lifting ropes, and the hanging basket 4 is lifted through the winches 3 driving the movable pulleys 5.
The periphery of base 1 be equipped with the guard gate, when material hoisting device carried out work, the guard gate was closed, forbids the workman to stand 2 below on the grudging post, prevents that the material landing from pounding the injury people.
The safety guards 7 are arranged above the hanging basket 4, as shown in fig. 3, the safety guards 7 are provided with eccentric wheels and are distributed on two sides of a vertical rod of the vertical frame 2, the eccentric wheels are in a loose state in normal operation, when a lifting rope is broken, the hanging basket 4 vertically descends due to gravity, the safety guards 7 are clamped and self-locked and are clamped on a cross rod of the vertical frame 2, and the hanging basket 4 is prevented from continuously falling.
The utility model discloses a theory of operation: equipment grudging post 2 before the construction, install grudging post 2 additional to the height that needs, open the fence door in 4 the place ahead of hanging flower basket, convey into hanging flower basket 4 with the material, notice simultaneously whether the weight detector has the alarm suggestion, the material is put into hanging flower basket 4 back, close fence and guard gate 11, the workman opens hoist engine 3 after keeping away from guard gate 11, hoist engine 3 drives fixed pulley 6 and movable pulley 5 motion, thereby promote the material to the floor of wanting or transport the material ground from the high-rise.
The present invention and its embodiments have been described above, but the description is not limited thereto, and what is shown in the drawings is only one of the embodiments of the present invention, and the actual structure is not limited thereto. In summary, those skilled in the art should understand that they should not be limited to the embodiments described above, and that they can design the similar structure and embodiments without departing from the spirit of the invention.

Claims (8)

1. A building engineering material lifting device, includes base (1), its characterized in that: base (1) top be equipped with grudging post (2) of two parallels, be equipped with guard gate (11) all around, grudging post (2) be connected with auxiliary stay pole with base (1), grudging post (2), base (1) and auxiliary stay pole form three horn column structures, base (1) both sides be equipped with hoist engine (3), grudging post (2) between be equipped with hanging flower basket (4), hanging flower basket (4) top platform fixedly connected with movable pulley (5), grudging post (2) upper end be equipped with limit for height platform (10), limit for height platform (10) on be equipped with fixed pulley (6), hanging flower basket (4) both sides and grudging post (2) department of meeting be equipped with safety hook (7) and guide pulley (8), hanging flower basket (4) bottom be equipped with buffer board (9).
2. A construction work material lifting device according to claim 1, characterised in that: the vertical frame (2) is formed by combining and splicing a plurality of upright columns, and the splicing positions of the upright columns are connected by bolts.
3. A construction work material lifting device according to claim 1, characterised in that: and a guide rail is arranged at the joint of the vertical frame (2) and the guide wheel (8).
4. A construction work material lifting device according to claim 1, characterised in that: and fences are arranged around the hanging basket (4), and can be opened.
5. A construction work material lifting device according to claim 1, characterised in that: and a weight detector is arranged at the bottom of the hanging basket (4).
6. A construction work material lifting device according to claim 1, characterised in that: the falling protector (7) is provided with six eccentric wheels which are evenly distributed on two sides of a vertical rod of the vertical frame (2), and the bottom of the falling protector (7) is fixed on the hanging basket (4).
7. A construction work material lifting device according to claim 1, characterised in that: the buffer plate (9) is connected to the bottom of the hanging basket (4) through a spring.
8. A construction work material lifting device according to claim 1, wherein: the winch (3) is connected with the movable pulley (5) and the fixed pulley (6) through a lifting rope.
CN202221619575.8U 2022-06-27 2022-06-27 Building engineering material lifting device Expired - Fee Related CN217921266U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221619575.8U CN217921266U (en) 2022-06-27 2022-06-27 Building engineering material lifting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221619575.8U CN217921266U (en) 2022-06-27 2022-06-27 Building engineering material lifting device

Publications (1)

Publication Number Publication Date
CN217921266U true CN217921266U (en) 2022-11-29

Family

ID=84185629

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221619575.8U Expired - Fee Related CN217921266U (en) 2022-06-27 2022-06-27 Building engineering material lifting device

Country Status (1)

Country Link
CN (1) CN217921266U (en)

Similar Documents

Publication Publication Date Title
CN214734024U (en) Indoor material conveying device in high-rise building construction process
CN205653086U (en) Tower crane who possesses climbing ladder and lift
CN105752826B (en) Movable hanging assembling platform and its construction method
KR100846209B1 (en) Tower Crane Trolley
CN217921266U (en) Building engineering material lifting device
CN201132717Y (en) Single-column and single-cage elevator driven by drawing
CN205555867U (en) Portable hoist and mount platform
CN219909902U (en) Safety device is used in high altitude construction
CN220976195U (en) Lifting device for double-tower construction
CN212893340U (en) A safe elevating gear for housing construction
CN216196501U (en) Construction is with fixed hanging flower basket of no support
CN218757249U (en) A platform of encorbelmenting for pier construction
CN210029781U (en) Anti-shaking device for hoisting
CN110748140A (en) Track beam hanging basket special for stepped curtain wall
CN210825249U (en) A new type of self-lifting material platform
CN209291757U (en) The lifting device of double crossed frame type transport material
CN203624932U (en) Portable indoor material lifter
KR0148135B1 (en) Climing device and method of a crane
CN224032245U (en) Openable protective shed
CN209567730U (en) A kind of small-sized lattice dead man steel construction
CN222924151U (en) Safety protection device for deep foundation pit excavation of building
CN213202145U (en) Novel engineering gantry crane
CN220223340U (en) Safe lifting device for tower crane
CN116025142B (en) A sliding track type hanging basket system
CN221626855U (en) Quick-dismantling movable hanging fence for box girder bridge pier

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20221129

CF01 Termination of patent right due to non-payment of annual fee