CN217897215U - Upright post shaping operation platform - Google Patents

Upright post shaping operation platform Download PDF

Info

Publication number
CN217897215U
CN217897215U CN202221949600.9U CN202221949600U CN217897215U CN 217897215 U CN217897215 U CN 217897215U CN 202221949600 U CN202221949600 U CN 202221949600U CN 217897215 U CN217897215 U CN 217897215U
Authority
CN
China
Prior art keywords
supporting frame
sub
layer
operation platform
standard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221949600.9U
Other languages
Chinese (zh)
Inventor
袁果
刘喜
黄德宝
何锁岩
李杏
莫彬彬
伍梁军
张维
柴龙全
曹兢涛
邓理刚
罗敏
王攀
廖晨帏
周伟民
陈成钟
舒兵
李�杰
邹杰
王志伟
李吉耘
刘文鹏
刘鹏
鲍荣盛
江盈盈
沈志宇
丁成程
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Engineering Group Co Ltd
Original Assignee
China Railway Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Engineering Group Co Ltd filed Critical China Railway Construction Engineering Group Co Ltd
Priority to CN202221949600.9U priority Critical patent/CN217897215U/en
Application granted granted Critical
Publication of CN217897215U publication Critical patent/CN217897215U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Ladders (AREA)

Abstract

The utility model relates to the technical field of building equipment, in particular to a stand column shaping operation platform, which comprises a sub-supporting frame and a pedal; the ladder stand is arranged on one side of each sub-supporting frame, the sub-supporting frames are detachably connected through connecting pieces to form a main supporting frame, a containing cavity capable of containing the stand column is formed in the middle of the main supporting frame, each connecting piece is a steel plate with holes, and the steel plates with the holes are welded at the connecting ends of the sub-supporting frames; the pedal is arranged in the containing cavity of the main body supporting frame and is detachably connected with the main body supporting frame through a hook. The utility model discloses a split type design comprises a plurality of sub-braced frame, folds the connection with a plurality of sub-braced frame around the stand, can drop into operation after setting up the footboard again, installs safe swift more, and application scope is more extensive.

Description

Upright post shaping operation platform
Technical Field
The utility model relates to a construction equipment technical field, concretely relates to stand regularization operation platform.
Background
With the rapid development of cities, in the construction of railway station buildings, more and more station buildings waiting for cars gradually select wide and transparent spaces, and the structural columns of the halls begin to develop towards the direction of being larger and higher. Station room post size is big, the reinforcing bar is complicated, builds in earlier stage and later stage decoration in-process at the structure post and all need set up the scaffold frame and come supplementary construction, and traditional steel pipe scaffold frame is as construction platform, and not only the support template consumption is big, need consume a large amount of manual works, and the period is long, and the security obtains not fine assurance moreover.
Chinese patent document CN210976511U discloses a construction of building engineering stand regularization operation platform, and this operation platform is by shaped steel or steel pipe welding regularization operation platform, divide into three part bottom, middle level, upper strata, is equipped with the ladder cage in the side of frame, is equipped with upper protection railing and middle level protection railing respectively in upper strata and middle level, and the scaffold board is laid as the platform on each layer, and the middle part of each layer is empty.
The utility model discloses a although solved traditional steel pipe scaffold and set up the problem that wastes time and energy and the security performance is poor, nevertheless when installing this utility model, need remove whole operation platform to the top of stand through tower crane or truck crane, make the stand pass operation platform's middle part then fall down, this mounting method is very inconvenient and has certain danger, and can't be applicable to the stand that there is the obstacle in upper portion between basement or the floor.
SUMMERY OF THE UTILITY MODEL
Therefore, the to-be-solved technical problem of the utility model lies in overcoming among the prior art regularization operation platform installation inconvenient, unable be applicable to basement and floor wait the defect of the stand that there is the obstacle in the upper portion to a stand regularization operation platform is provided.
An upright post sizing operation platform comprises a sub-support frame and a pedal; the ladder stand is arranged on one side of each sub-supporting frame, the sub-supporting frames are detachably connected through connecting pieces to form a main supporting frame, a containing cavity capable of containing the stand column is formed in the middle of the main supporting frame, each connecting piece is a steel plate with holes, and the steel plates with the holes are welded at the connecting ends of the sub-supporting frames; the pedal is arranged in the containing cavity of the main body supporting frame and is detachably connected with the main body supporting frame through a hook.
As the utility model discloses well stand regularization operation platform's an preferred, sub-braced frame includes bottom, standard layer and inoxidizing coating, and is a plurality of the vertical setting in standard layer is all through welded connection between bottom and standard layer, standard layer and the inoxidizing coating, bottom, standard layer and cat ladder welding are whole.
As the utility model discloses well stand regularization operation platform's an optimization, the montant that the standard layer is connected including the horizontal pole that is used for supporting the cat ladder and is used for with bottom or standard layer, horizontal pole and montant pass through welded connection.
As the utility model discloses well stand regularization operation platform's an optimization, the standard bed still is provided with the skirting line, its lower part welded connection with the montant.
As the utility model discloses well stand regularization operation platform is preferred, encircles main part braced frame's outside is provided with safety protection net.
As the utility model discloses well stand regularization operation platform's an preferred, sub-braced frame and cat ladder form by the welding of zinc-plated square pipe.
The utility model discloses technical scheme has following advantage: the utility model adopts split design, and can be repeatedly used after being welded and formed once; the utility model discloses only need when using to encircle sub-braced frame and pass through connecting piece and bolted connection formation main part braced frame with the stand, can put into use after setting up the footboard again, the installation with dismantle safe swift more, applicable stand that has the obstacle in upper portion such as between basement or the floor.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the embodiments or the technical solutions in the prior art will be briefly described below, and it is obvious that the drawings in the following description are some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a top view of the operation platform in embodiment 1.
Fig. 2 is a side view of the operation platform in embodiment 1.
Fig. 3 is a schematic structural view of a connection end of a neutron support frame in embodiment 1.
Fig. 4 is an enlarged schematic view of the structure at a in fig. 3.
Fig. 5 is a plan view of the step plate in embodiment 1.
Fig. 6 is a front view of the step plate in embodiment 1.
Fig. 7 is a plan view of the connector in example 1.
Fig. 8 is a front view of the connector in embodiment 1.
Description of reference numerals:
1. a sub-support frame; 101. a bottom layer; 102. a standard layer; 103. a protective layer; 104. a connecting member; 105. bracing; 106. climbing a ladder; 2. a pedal; 201. and (4) hanging hooks.
Detailed Description
The technical solution of the present invention will be described clearly and completely with reference to the accompanying drawings, and obviously, the described embodiments are some, but not all embodiments of the present invention. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Furthermore, the technical features mentioned in the different embodiments of the invention described below can be combined with each other as long as they do not conflict with each other.
Example 1
The embodiment provides a column-based sizing operation platform, which is formed by welding 40mm × 3mm galvanized square tubes, as shown in fig. 1 to 4, and includes two concave sub-support frames 1 and a plurality of pedals 2;
a ladder 106 is arranged on one side of the sub-support frame 1, the two concave sub-support frames 1 are detachably connected through a connecting piece 104 to form a main body support frame, and the upright posts are positioned in the containing cavity in the middle of the main body frame; the pedal 2 is arranged in the cavity of the main body supporting frame, is arranged around the upright post, and is detachably connected with the main body supporting frame through a hook 201. The cavity provides space for operations such as upright steel bar binding, formwork erecting, decoration and the like.
The sub-supporting frame 1 comprises a bottom layer 101 used for being connected with the ground, a standard layer 102 used for supporting the pedal 2 and a protective layer 103, wherein the standard layer 102 comprises a cross rod used for supporting the pedal 2 and a vertical rod used for being connected with the bottom layer 101 or the standard layer 102, and the cross rod and the vertical rod are connected through welding; the plurality of standard layers 102 are vertically arranged between the bottom layer 101 and the protective layer 103, the height and the number of the standard layers 102 can be determined according to the actual working conditions of a construction site, the bottom layer 101 and the standard layers 102, the standard layers 102 and the standard layers 102, and the standard layers 102 and the protective layer 103 are connected through welding, and the bottom layer 101, the standard layers 102 and the ladder 106 are welded into a whole and used for enhancing the overall stability of the support frame 1.
As shown in fig. 5 and 6, said tread plate 2 comprises a steel fence mesh arranged above the frame and a hook 201 arranged below the frame; the thickness of the steel basketry net is 4mm, and the steel basketry net consists of 40mm 80mm rhombic hole steel basketry net pieces; the length of the hook 201 is more than twice the thickness of the pedal 2; which is detachably connected to the standard layer 102 by means of hooks 201.
In this embodiment, inoxidizing coating 103 is the guard rail, and the railing height is 1.2m, and the middle part sets up one horizontal pole, and upper portion sets up the vertical pole setting that is not more than 50 cm.
In this embodiment, a safety net is provided around the main body support frame.
By adopting the structure, the safety protection net is used for preventing high-altitude falling and ensuring construction safety.
In this embodiment, a 20cm high skirting line is provided at the lower part of the standard layer 102.
By adopting the structure, the skirting line is used for preventing safety accidents caused by the rolling falling of fine tools and sundries, and the reflective warning sticker can be pasted on the surface of the skirting line.
As shown in fig. 7 and 8, in this embodiment, the connecting member 104 is a 150mm 5mm steel plate, four through holes with a diameter of 15 are uniformly distributed on the steel plate, and the steel plate is welded at the connecting end of the sub-supporting frame 1.
The operation platform adopts a split design, and can be repeatedly used after being welded and formed at one time; the welding frame structure is adopted, so that the overall stability is good; only need dismouting bolt and footboard 2 when installation and dismantlement, practiced thrift the time and the manual work of dismantlement with the installation, the installation is safe swift more, applicable stand that has the obstacle in upper portion such as between basement or the floor.
In this embodiment, this operation platform accessible tower crane, truck crane, fork truck or people and goods elevator transports two sub-braced frame 1 to the both sides of stand when using, closes two sub-braced frame 1 after adjusting the position, forms main part braced frame through the bolted connection who passes through the through-hole on the steel sheet, lays footboard 2 at suitable standard layer 102 according to on-the-spot operating condition, forms complete operation platform.
Example 2
The embodiment is a manufacturing method of the operation platform in embodiment 1:
s1: firstly, welding a galvanized square pipe to form a bottom layer 101 of the sub-supporting frame 1, wherein the size of the outer contour of the frame of the bottom layer 101 is 4.4m × 2.2m; the height and the number of the standard layers 102 are determined according to the actual working conditions of the field, and the standard layers 102 are connected with the bottom layer 101 or other standard layers 102 in a welding mode through vertical rods. Finally, a top protective layer 103 is soldered to the top standard layer 102. After the connection of the three parts is completed, the bracing 105 is welded in the supporting frame 1 for reinforcement, and a 20 cm-high skirting line is installed at the lower part of the standard layer 102.
S2: the welding connector 104 is welded at the connecting end of the sub-support frame 1 and other sub-support frames 1 by adopting a perforated steel plate with 150mm x 5mm; a60 cm wide ladder 106 is welded by a galvanized square pipe, and is connected with one side of the sub-supporting frame 1 to be used as a vertical channel and connected with a horizontal channel formed by the pedal 2.
S3: after the sub-supporting frames 1 are connected through the connecting pieces 104 and the bolts, a safety protection net is installed around the formed main supporting frame, and safety warning signs are hung around the operating platform.
It should be understood that the above examples are only for clarity of illustration and are not intended to limit the embodiments. Other variations and modifications will be apparent to persons skilled in the art in light of the above description. And are neither required nor exhaustive of all embodiments. And obvious variations or modifications can be made without departing from the scope of the invention.

Claims (6)

1. The utility model provides a stand regularization operation platform which characterized in that: comprises a sub-supporting frame (1) and a pedal (2); a ladder (106) is arranged on one side of each sub-supporting frame (1), the sub-supporting frames (1) are detachably connected through a connecting piece (104) to form a main supporting frame, a containing cavity capable of containing an upright column is formed in the middle of the main supporting frame, the connecting piece (104) is a steel plate with holes, and the steel plate with holes is welded at the connecting end of each sub-supporting frame (1); the pedal (2) is arranged in the containing cavity of the main body supporting frame and is detachably connected with the main body supporting frame through a hook (201).
2. The upright post sizing operation platform according to claim 1, wherein the sub-supporting frame (1) comprises a bottom layer (101), a standard layer (102) and a protective layer (103), a plurality of standard layers (102) are vertically arranged between the bottom layer (101) and the protective layer (103), the bottom layer (101) and the standard layer (102), the standard layer (102) and the standard layer (102), and the standard layer (102) and the protective layer (103) are connected through welding, and the bottom layer (101), the standard layer (102) and the ladder (106) are welded into a whole.
3. The pole-sizing work platform according to claim 2, wherein the standard layer (102) comprises a cross bar for supporting the tread (2) and a vertical bar for connecting with the bottom layer (101) or the standard layer (102), and the cross bar and the vertical bar are connected by welding.
4. The upright sizing operation platform according to claim 3, wherein the standard layer (102) is further provided with a skirting line which is welded with the lower part of the vertical rod.
5. The upright sizing operation platform according to claim 1, wherein a safety net is arranged around the outside of the main body supporting frame.
6. The upright sizing operation platform according to claim 1, wherein the sub-supporting frame (1) and the ladder (106) are welded by galvanized square pipes.
CN202221949600.9U 2022-07-27 2022-07-27 Upright post shaping operation platform Active CN217897215U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221949600.9U CN217897215U (en) 2022-07-27 2022-07-27 Upright post shaping operation platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221949600.9U CN217897215U (en) 2022-07-27 2022-07-27 Upright post shaping operation platform

Publications (1)

Publication Number Publication Date
CN217897215U true CN217897215U (en) 2022-11-25

Family

ID=84136377

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221949600.9U Active CN217897215U (en) 2022-07-27 2022-07-27 Upright post shaping operation platform

Country Status (1)

Country Link
CN (1) CN217897215U (en)

Similar Documents

Publication Publication Date Title
CN100365237C (en) Autolifting type variable-shape diassembllable integrated lifting steel plateform system and construction method thereof
CN206233541U (en) A kind of interior top external climbing mould bases operation platform for construction of super highrise building
CN110685226A (en) Hydraulic integral self-climbing construction platform
CN212771953U (en) No. 0 piece construction bracket braced system of continuous beam
CN202925957U (en) Instrumentalized extension-type safety protection shed
CN217897215U (en) Upright post shaping operation platform
CN218149656U (en) Operating platform in lighting well
CN113152658B (en) Large-span corridor with comprehensive curtain wall at bottom and construction method
CN214462394U (en) High-altitude overhanging scaffold
CN212926984U (en) Movable suspension operating platform
CN213204913U (en) Modular prefabricated staircase operation platform
CN114541354A (en) Assembly positioning method for jacket side sheet body
CN113309008A (en) Steel case roof beam temporary support construction safety work platform
CN206581578U (en) Double-layer basket constructing device for overhanging scaffold
CN221546301U (en) Lighting well matched protection and construction platform
CN201053199Y (en) Large template pylon
CN215331451U (en) Hydraulic self-climbing formwork for narrow space
CN212129932U (en) A supplementary construction operation platform for creeping formwork
CN214738726U (en) Steel construction vestibule with electromechanical installation gallows
CN219118718U (en) Climbing frame horizontal protection
CN218508983U (en) High-rise building component support system that encorbelments
CN220036069U (en) A pylon body structure that is used for balcony, window that wafts, fire control vestibule position
CN219100689U (en) Attachment structure suitable for super high floor attached lifting scaffold
CN214658649U (en) Large-span construction operation platform for mounting super high-rise special-shaped curtain wall
CN218779913U (en) Operating platform for pouring operators

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant