CN217812471U - A green construction site canopy installation structure - Google Patents

A green construction site canopy installation structure Download PDF

Info

Publication number
CN217812471U
CN217812471U CN202220895096.2U CN202220895096U CN217812471U CN 217812471 U CN217812471 U CN 217812471U CN 202220895096 U CN202220895096 U CN 202220895096U CN 217812471 U CN217812471 U CN 217812471U
Authority
CN
China
Prior art keywords
dust
construction site
fixedly connected
steel wire
several
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220895096.2U
Other languages
Chinese (zh)
Inventor
张庆楠
成铮
张军龙
张开全
刘涛
刘洪志
于树民
王丽丽
周长晓
宁天齐
沈培
徐曼
徐鹏程
蔡亚翀
翟丁松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
First Construction Co Ltd of China Construction First Group Corp Ltd
Original Assignee
China Construction First Group Corp Ltd
First Construction Co Ltd of China Construction First Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd, First Construction Co Ltd of China Construction First Group Corp Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN202220895096.2U priority Critical patent/CN217812471U/en
Application granted granted Critical
Publication of CN217812471U publication Critical patent/CN217812471U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Tents Or Canopies (AREA)

Abstract

本申请公开了一种绿色施工工地罩棚安装搭设结构,涉及建筑施工领域,包括若干立柱,若干所述立柱依次排列设置且围成施工区域,相邻所述立柱上端固定连接有横梁,相对所述立柱顶端之间设置有钢丝绳,若干所述钢丝绳纵横交错于若干立柱所围成施工区域的上方,所述钢丝绳下表面固定铺设有防尘网,所述防尘网的侧边固定连接于立柱上端。本申请具有防尘好、绿色施工的效果。

Figure 202220895096

The application discloses a green construction site canopy installation and erection structure, which relates to the field of building construction and includes a number of columns, which are arranged in sequence and enclose a construction area. Steel wire ropes are arranged between the tops of the columns, and several steel wire ropes are criss-crossed above the construction area surrounded by several columns. The lower surface of the steel wire ropes is fixedly laid with dust-proof nets, and the sides of the dust-proof nets are fixedly connected to the upper ends of the columns. . The application has the effects of good dust prevention and green construction.

Figure 202220895096

Description

一种绿色施工工地罩棚安装搭设结构A green construction site canopy installation structure

技术领域technical field

本申请涉及建筑施工领域,尤其是涉及一种绿色施工工地罩棚安装搭设结构。The application relates to the field of building construction, in particular to a green construction site canopy installation and erection structure.

背景技术Background technique

目前在施工过程中,为了减少粉尘扩散,施工人员通常是将防尘网铺设在工地上,同时当施工设备处于停机状态时,施工人员会将防尘网覆盖在施工设备上,但是如遇大风天气时,防尘网很容易被吹走或吹破,防尘效果不好。At present, in the construction process, in order to reduce the spread of dust, construction workers usually lay dust-proof nets on the construction site. In bad weather, the dust-proof net is easily blown away or broken, and the dust-proof effect is not good.

实用新型内容Utility model content

为了提高防尘效果,本申请提供一种绿色施工工地罩棚安装搭设结构。In order to improve the dust-proof effect, the present application provides a green construction site canopy installation structure.

本申请提供的一种绿色施工工地罩棚安装搭设结构,采用如下的技术方案:A green construction site canopy installation and erection structure provided by this application adopts the following technical scheme:

一种绿色施工工地罩棚安装搭设结构,包括若干立柱,包括若干立柱,若干所述立柱依次排列设置且围成施工区域,相邻所述立柱上端固定连接有横梁,相对所述立柱顶端之间设置有钢丝绳,若干所述钢丝绳纵横交错于若干立柱所围成施工区域的上方,所述钢丝绳下表面固定铺设有防尘网,所述防尘网的侧边固定连接于立柱上端。A green construction site canopy installation structure, including a number of columns, including a number of columns, a number of columns are arranged in sequence to enclose a construction area, the upper ends of the adjacent columns are fixedly connected with crossbeams, and the upper ends of the columns are arranged opposite to each other. There are steel wire ropes, several steel wire ropes criss-cross above the construction area surrounded by several columns, the lower surface of the steel wire ropes is fixedly laid with dust-proof nets, and the sides of the dust-proof nets are fixedly connected to the upper ends of the columns.

通过采用上述技术方案,通过设置立柱与横梁,围成施工区域,并将钢丝绳设置在立柱顶端,并通过在若干钢丝绳形成的钢丝网下方铺设防尘网,从而钢丝绳将防尘网保护起来,使防尘网能够更加稳定的覆盖在施工区域上方,提高了防尘效果。By adopting the above-mentioned technical scheme, the construction area is surrounded by setting columns and beams, and the steel wire rope is arranged on the top of the column, and the dust-proof net is laid under the steel wire mesh formed by several steel wire ropes, so that the steel wire rope protects the dust-proof net, so that The dust-proof net can cover the construction area more stably, improving the dust-proof effect.

可选的,所述防尘网侧边固定连接有若干斜拉钢绳,所述斜拉钢绳呈倾斜设置,且所述斜拉钢绳下端固定连接于立柱外侧。Optionally, several cable-stayed steel cables are fixedly connected to the sides of the dust-proof net, the cable-stayed steel cables are arranged obliquely, and the lower ends of the cable-stayed steel cables are fixedly connected to the outside of the column.

通过采用上述技术方案,通过设置斜拉钢绳,斜拉钢绳将防尘网拉直,同时斜拉钢绳使防尘网更加稳固覆盖。By adopting the above technical scheme, by setting the cable-stayed steel rope, the cable-stayed steel cable straightens the dust-proof net, and at the same time, the cable-stayed steel cable makes the dust-proof net more stable to cover.

可选的,若干所述立柱外侧壁固定连接有彩钢板,所述彩钢板上端固定连接于横梁,相邻两所述彩钢板相互拼接。Optionally, color steel plates are fixedly connected to the outer walls of several columns, the upper ends of the color steel plates are fixedly connected to the beams, and two adjacent color steel plates are spliced together.

通过采用上述技术方案,通过设置彩钢板,使立柱更加稳固,同时将施工区域围设起来,便于防止外来人员进入施工区域。By adopting the above-mentioned technical scheme, the column is made more stable by setting the color steel plate, and at the same time, the construction area is surrounded to prevent outsiders from entering the construction area.

可选的,所述钢丝绳的上方铺设有薄膜,所述薄膜的侧边固定连接于立柱。Optionally, a film is laid above the steel wire rope, and the side of the film is fixedly connected to the column.

通过采用上述技术方案,使施工区域封闭,减少噪音扩散,同时减少施工区域内的灰尘飞扬,进一步增强防尘效果。By adopting the above-mentioned technical scheme, the construction area is closed, noise diffusion is reduced, and dust flying in the construction area is reduced at the same time, and the dust-proof effect is further enhanced.

可选的,所述立柱上端外侧壁通过螺钉固定有压条,所述压条压紧于薄膜侧边。Optionally, the outer wall of the upper end of the column is fixed with a bead by screws, and the bead is pressed against the side of the film.

通过采用上述技术方案,方便固定薄膜,同时后续方便拆除。By adopting the above technical solution, it is convenient to fix the film, and at the same time, it is convenient to remove later.

可选的,若干所述立柱顶部均设置有吊耳,所述钢丝绳的端部设置有花篮螺栓,所述花篮螺栓与吊耳可拆卸连接。Optionally, lifting lugs are provided on the tops of several of the uprights, turnbuckle bolts are arranged at the ends of the steel wire ropes, and the turnbuckle bolts are detachably connected to the lifting lugs.

通过采用上述技术方案,通过在钢丝绳的端部设置花篮螺栓,且将花篮螺栓与吊耳可拆卸连接,进而便于后期维护与拆卸。By adopting the above-mentioned technical scheme, by arranging the turnbuckle bolt at the end of the steel wire rope, and detachably connecting the turnbuckle bolt with the lifting lug, it is convenient for later maintenance and disassembly.

可选的,所述横梁内侧固定连接有降尘机构。Optionally, a dust reduction mechanism is fixedly connected to the inner side of the beam.

通过采用上述技术方案,通过设置降尘机构,减少施工区域内的灰尘飞扬。By adopting the above-mentioned technical scheme and by setting a dust suppression mechanism, the flying dust in the construction area can be reduced.

可选的,所述降尘机构包括固定连接于横梁内侧壁的喷淋管,所述喷淋管固定且连通有若干喷雾头。Optionally, the dust reduction mechanism includes a spray pipe fixedly connected to the inner wall of the beam, and the spray pipe is fixed and communicated with several spray heads.

通过采用上述技术方案,通过喷雾头喷水,进而加快灰尘沉降,减少扬尘。By adopting the above-mentioned technical scheme, water is sprayed through the spray head, thereby speeding up dust settlement and reducing dust raising.

综上所述,本申请包括以下至少一种有益技术效果:In summary, the present application includes at least one of the following beneficial technical effects:

1.通过设置立柱与横梁,围成施工区域,并将钢丝绳设置在立柱顶端,并通过在若干钢丝绳形成的钢丝网下方铺设防尘网,从而钢丝绳将防尘网保护起来,使防尘网能够更加稳定的覆盖在施工区域上方,提高了防尘效果。1. By setting columns and beams, the construction area is surrounded, and the steel wire rope is placed on the top of the column, and the dust-proof net is laid under the steel wire mesh formed by several steel wire ropes, so that the steel wire rope protects the dust-proof net, so that the dust-proof net can More stable coverage above the construction area, improving the dust-proof effect.

2.通过在钢丝绳的端部设置花篮螺栓,且将花篮螺栓与吊耳可拆卸连接,进而便于后期维护与拆卸。2. By setting the turnbuckle bolt at the end of the wire rope and detachably connecting the turnbuckle bolt with the lifting lug, it is convenient for later maintenance and disassembly.

3.通过设置降尘机构,减少施工区域内的灰尘飞扬。3. Reduce dust flying in the construction area by setting up dust suppression mechanism.

附图说明Description of drawings

图1是本申请实施例的整体结构示意图。FIG. 1 is a schematic diagram of the overall structure of an embodiment of the present application.

图2是本申请实施例中立柱内侧结构示意图。Fig. 2 is a schematic diagram of the inner structure of the column in the embodiment of the present application.

图3是本申请实施例中立柱顶端结构示意图。Fig. 3 is a schematic diagram of the top structure of the column in the embodiment of the present application.

附图标记说明:Explanation of reference signs:

1、立柱;2、横梁;3、彩钢板;4、吊耳;41、钢丝绳;42、花篮螺栓;5、防尘网;6、斜拉钢绳;7、薄膜;71、压条;8、降尘机构;81、喷淋管;82、喷雾头。1. Upright column; 2. Beam; 3. Color steel plate; 4. Hanging lug; 41. Steel wire rope; 42. Flower basket bolt; 5. Dust-proof net; 6. Cable-stayed steel rope; 7. Film; Dust suppression mechanism; 81, spray pipe; 82, spray head.

具体实施方式Detailed ways

以下结合附图1-3对本申请作进一步详细说明。The present application will be described in further detail below in conjunction with accompanying drawings 1-3.

本申请实施例公开一种绿色施工工地罩棚安装搭设结构。参照图1与图2,一种绿色施工工地罩棚安装搭设结构包括若干呈竖直的立柱1,立柱1为钢结构,若干立柱1依次等距排列设置,并且围成所需的呈矩形状的施工区域,每一侧立柱1上端共同设置有呈水平的横梁2,横梁2为钢结构,且横梁2与立柱1通过螺钉固定。每一侧立柱1外壁通过射钉固定有呈竖直的彩钢板3,彩钢板3的上端通过射钉固定于横梁2外壁,相邻两彩钢板3之间互相拼接,从而将施工区域更好的封闭起来。The embodiment of the application discloses a green construction site canopy installation and erection structure. Referring to Figures 1 and 2, a green construction site canopy installation structure includes several vertical columns 1, the columns 1 are steel structures, and several columns 1 are arranged equidistantly in sequence, and surround the required rectangular shape. In the construction area, a horizontal beam 2 is arranged on the upper end of the column 1 on each side. The beam 2 is a steel structure, and the beam 2 and the column 1 are fixed by screws. The outer wall of the column 1 on each side is fixed with a vertical color steel plate 3 by nailing, and the upper end of the color steel plate 3 is fixed on the outer wall of the beam 2 by nailing, and the adjacent two color steel plates 3 are spliced with each other, so as to make the construction area better. closed up.

参照图3,立柱1顶部通过螺钉固定有吊耳4,对侧立柱1的吊耳4之间连接有钢丝绳41,且刚绳绳的两端分别设置有花篮螺栓42,花篮螺栓42与吊耳4可拆卸连接,从而使若干钢丝绳41纵横交错成钢丝网并位于立柱1所围成的矩形状施工区域上方。钢丝绳41下表面固定铺设有防尘网5,防尘网5覆盖施工区域的上方,且防尘网5的各个侧边均设置有若干斜拉钢绳6,斜拉钢绳6将防尘网5拉直,且斜拉钢绳6的下端埋设于立柱1外侧的土地内,使斜拉钢绳6呈倾斜设置,从而将防尘网5稳定固定。Referring to Figure 3, the top of the column 1 is fixed with a lifting lug 4 by screws, and a steel wire rope 41 is connected between the lifting lugs 4 of the opposite column 1, and the two ends of the steel rope are respectively provided with turnbuckle bolts 42, and the turnbuckle bolts 42 are connected to the lifting lugs. 4. It is detachably connected, so that several steel wire ropes 41 are criss-crossed to form a steel wire mesh and are located above the rectangular construction area surrounded by the column 1. The lower surface of the steel wire rope 41 is fixedly laid with a dustproof net 5, the dustproof net 5 covers the top of the construction area, and each side of the dustproof net 5 is provided with some cable-stayed steel ropes 6, and the cable-stayed steel rope 6 connects the dustproof net 5 is straightened, and the lower end of the cable-stayed steel rope 6 is buried in the ground outside the column 1, so that the cable-stayed steel cable 6 is inclined to set, thereby stably fixing the dustproof net 5.

参照图1与图2,钢丝绳41的上方铺设有薄膜7,立柱1上端外壁通过螺钉固定有呈水平的压条71,压条71将薄膜7侧边压紧于立柱1外壁,并通过螺钉将压条71固定于立柱1,从而使薄膜7覆盖在若干钢丝绳41所形成的钢丝网上方。Referring to Fig. 1 and Fig. 2, a film 7 is laid on the top of the wire rope 41, and the outer wall of the upper end of the column 1 is fixed with a horizontal bead 71 by screws. It is fixed on the column 1, so that the film 7 is covered on the steel wire mesh formed by several steel wire ropes 41.

参照图2,横梁2内侧设置有降尘机构8,降尘机构8包括通过卡箍固定于横梁2内侧壁的喷淋管81,喷淋管81固定且连通有若干喷雾头82,且喷淋管81与水源连通,进而使喷雾头82喷水,从而起到降尘的作用,绿色施工的效果。Referring to Fig. 2, the inside of the crossbeam 2 is provided with a dust-reducing mechanism 8, and the dust-reducing mechanism 8 includes a spray pipe 81 fixed on the inner side wall of the crossbeam 2 by a clamp. It is connected with the water source, and then the spray head 82 is sprayed with water, so as to play the role of dust reduction and achieve the effect of green construction.

本申请实施例的实施原理为:通过搭设立柱1与横梁2以及彩钢板3,从而将施工区域围设起来,之后将吊耳4设置在立柱1顶部,并将钢丝绳41通过花篮螺栓42与吊耳4连接,从而后续方便拆除,同时将钢丝绳41纵横交错形成位于施工区域上方的钢丝网,再将防尘网5铺设在钢丝绳41的下方,且防尘网5的侧边通过与斜拉钢绳6固定,且斜拉钢绳6的另一端与地面固定,从而将防尘网5能够绷紧,且钢丝绳41能够防护防尘网5受损,之后在钢丝绳41上方铺设薄膜7,构成封闭施工区域,同时可通过喷雾头82喷雾,对施工区域进行降尘,遵循绿色施工的理念。The implementation principle of the embodiment of the present application is as follows: by setting up the column 1, the beam 2 and the color steel plate 3, the construction area is enclosed, and then the lifting lug 4 is set on the top of the column 1, and the steel wire rope 41 is passed through the turnbuckle bolt 42 and the hanger. Ears 4 are connected to facilitate subsequent removal. At the same time, the steel wire ropes 41 are criss-crossed to form a steel wire mesh above the construction area, and then the dust-proof net 5 is laid below the steel wire ropes 41, and the side of the dust-proof mesh 5 passes through the cable-stayed steel mesh. The rope 6 is fixed, and the other end of the cable-stayed steel rope 6 is fixed to the ground, so that the dustproof net 5 can be tightened, and the steel wire rope 41 can protect the dustproof net 5 from being damaged, and then a film 7 is laid on the top of the steel rope 41 to form a closed At the same time, the construction area can be sprayed through the spray head 82 to reduce dust in the construction area, following the concept of green construction.

以上均为本申请的较佳实施例,并非依此限制本申请的保护范围,故:凡依本申请的结构、形状、原理所做的等效变化,均应涵盖于本申请的保护范围之内。All of the above are preferred embodiments of the application, and are not intended to limit the protection scope of the application. Therefore, all equivalent changes made according to the structure, shape, and principle of the application should be covered by the protection scope of the application. Inside.

Claims (8)

1.一种绿色施工工地罩棚安装搭设结构,其特征在于:包括若干立柱(1),若干所述立柱(1)依次排列设置且围成施工区域,相邻所述立柱(1)上端固定连接有横梁(2),相对所述立柱(1)顶端之间设置有钢丝绳(41),若干所述钢丝绳(41)纵横交错于若干立柱(1)所围成施工区域的上方,所述钢丝绳(41)下表面固定铺设有防尘网(5),所述防尘网(5)的侧边固定连接于立柱(1)上端。1. A green construction site canopy is installed and erected structure, it is characterized in that: comprise several upright columns (1), and several described upright columns (1) are arranged in sequence and enclose construction area, the upper end of adjacent described upright columns (1) is fixedly connected There are beams (2), steel wire ropes (41) are arranged between the tops of the columns (1), and several steel wire ropes (41) criss-cross above the construction area surrounded by several columns (1), and the steel wire ropes ( 41) A dust-proof net (5) is fixedly laid on the lower surface, and the side of the dust-proof net (5) is fixedly connected to the upper end of the column (1). 2.根据权利要求1所述的一种绿色施工工地罩棚安装搭设结构,其特征在于:所述防尘网(5)侧边固定连接有若干斜拉钢绳(6),所述斜拉钢绳(6)呈倾斜设置,且所述斜拉钢绳(6)下端固定连接于立柱(1)外侧。2. A green construction site canopy installation and erection structure according to claim 1, characterized in that: the side of the dust-proof net (5) is fixedly connected with several cable-stayed steel cables (6), and the cable-stayed steel cables The rope (6) is arranged obliquely, and the lower end of the cable-stayed steel rope (6) is fixedly connected to the outside of the column (1). 3.根据权利要求1所述的一种绿色施工工地罩棚安装搭设结构,其特征在于:若干所述立柱(1)外侧壁固定连接有彩钢板(3),所述彩钢板(3)上端固定连接于横梁(2),相邻两所述彩钢板(3)相互拼接。3. A green construction site canopy installation and erection structure according to claim 1, characterized in that: the outer walls of several columns (1) are fixedly connected with color steel plates (3), and the upper ends of the color steel plates (3) are fixed Connected to the beam (2), two adjacent color steel plates (3) are spliced together. 4.根据权利要求1所述的一种绿色施工工地罩棚安装搭设结构,其特征在于:所述钢丝绳(41)的上方铺设有薄膜(7),所述薄膜(7)的侧边固定连接于立柱(1)。4. A green construction site canopy installation and erection structure according to claim 1, characterized in that: a film (7) is laid above the steel wire rope (41), and the side of the film (7) is fixedly connected to Column (1). 5.根据权利要求4所述的一种绿色施工工地罩棚安装搭设结构,其特征在于:所述立柱(1)上端外侧壁通过螺钉固定有压条(71),所述压条(71)压紧于薄膜(7)侧边。5. A green construction site canopy installation and erection structure according to claim 4, characterized in that: the outer side wall of the upper end of the column (1) is fixed with a bead (71) by screws, and the bead (71) is pressed against the Film (7) side. 6.根据权利要求1所述的一种绿色施工工地罩棚安装搭设结构,其特征在于:若干所述立柱(1)顶部均设置有吊耳(4),所述钢丝绳(41)的端部设置有花篮螺栓(42),所述花篮螺栓(42)与吊耳(4)可拆卸连接。6. A green construction site canopy installation and erection structure according to claim 1, characterized in that: lifting lugs (4) are provided on the tops of several columns (1), and the ends of the steel wire ropes (41) are provided with There are turnbuckle bolts (42), and the turnbuckle bolts (42) are detachably connected to the lifting lugs (4). 7.根据权利要求1所述的一种绿色施工工地罩棚安装搭设结构,其特征在于:所述横梁(2)内侧固定连接有降尘机构(8)。7 . The green construction site canopy installation and erection structure according to claim 1 , characterized in that: the inner side of the beam ( 2 ) is fixedly connected with a dust suppression mechanism ( 8 ). 8.根据权利要求7所述的一种绿色施工工地罩棚安装搭设结构,其特征在于:所述降尘机构(8)包括固定连接于横梁(2)内侧壁的喷淋管(81),所述喷淋管(81)固定且连通有若干喷雾头(82)。8. A green construction site canopy installation and erection structure according to claim 7, characterized in that: the dust suppression mechanism (8) includes a spray pipe (81) fixedly connected to the inner wall of the beam (2), the The shower pipe (81) is fixed and communicated with several spray heads (82).
CN202220895096.2U 2022-04-18 2022-04-18 A green construction site canopy installation structure Active CN217812471U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220895096.2U CN217812471U (en) 2022-04-18 2022-04-18 A green construction site canopy installation structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220895096.2U CN217812471U (en) 2022-04-18 2022-04-18 A green construction site canopy installation structure

Publications (1)

Publication Number Publication Date
CN217812471U true CN217812471U (en) 2022-11-15

Family

ID=83982678

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220895096.2U Active CN217812471U (en) 2022-04-18 2022-04-18 A green construction site canopy installation structure

Country Status (1)

Country Link
CN (1) CN217812471U (en)

Similar Documents

Publication Publication Date Title
CN211736290U (en) A kind of shell section large-span overhanging eaves high-altitude erecting formwork work platform
CN104533135B (en) Rail device capable of being rapidly installed and detached
CN204781887U (en) Prefabricated assembly type structure's no outrigger construction platform
CN204899184U (en) Hanging flower basket equipment
CN206233102U (en) A kind of packaged type faces side operation work platform
CN103236656B (en) Column suspension type crossing structure and operating method thereof
CN217812471U (en) A green construction site canopy installation structure
CN104652803B (en) Attached electric lifting guide rail scaffold
CN113944108A (en) Supporting device for bridge tower construction and construction method applying supporting device
CN204626915U (en) A kind of large span heavy in section truss is across interior assembling rack platform
CN218623252U (en) Hanging basket installation fixing system at framework
CN206220534U (en) The pump line support meanss of concrete pumping equipment
CN207960030U (en) Distribution box protection canopy with assembling type base
CN211257769U (en) A Truss Bridge Based on Attached Lifting Platform
CN210973666U (en) Simple lifting device for upright post construction cylinder of antiaircraft gun billboard
CN211034805U (en) Device for combining rod piece and logistics channel of construction elevator
CN209958809U (en) A protective shed for a box-type prefab house
CN221920515U (en) Wind-proof dust suppression noise reduction surrounding shield
CN209653548U (en) A kind of horizontal protective device of modularization for construction
CN109402313B (en) Blast furnace downcomer bricklaying lining material transportation system and construction method
CN205875667U (en) Construction operation platform joint construction of platform cylinder
CN208168315U (en) The job platform of Zhongting for super high-rise building
CN218492417U (en) Safety protection device for installing high-pile hoop
CN110395672B (en) Simple lifting device for column construction column of antiaircraft gun billboard
CN207228604U (en) A kind of unilateral suspension type aerial movement steel platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant