CN217762639U - Temporary emergency leakage plugging device for leakage of electric pipeline of power plant - Google Patents

Temporary emergency leakage plugging device for leakage of electric pipeline of power plant Download PDF

Info

Publication number
CN217762639U
CN217762639U CN202221742683.4U CN202221742683U CN217762639U CN 217762639 U CN217762639 U CN 217762639U CN 202221742683 U CN202221742683 U CN 202221742683U CN 217762639 U CN217762639 U CN 217762639U
Authority
CN
China
Prior art keywords
leakage
buckle
support
support frame
pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221742683.4U
Other languages
Chinese (zh)
Inventor
徐忠友
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huaneng Jinan Huangtai Power Generation Co Ltd
Original Assignee
Huaneng Jinan Huangtai Power Generation Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huaneng Jinan Huangtai Power Generation Co Ltd filed Critical Huaneng Jinan Huangtai Power Generation Co Ltd
Priority to CN202221742683.4U priority Critical patent/CN217762639U/en
Application granted granted Critical
Publication of CN217762639U publication Critical patent/CN217762639U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00—Energy generation through renewable energy sources
    • Y02E10/20—Hydro energy

Landscapes

  • Pipe Accessories (AREA)

Abstract

本实用新型公开了一种电厂电气用管道渗漏临时紧急堵漏装置,包括支撑架以及支撑板;所述支撑架用于支撑上方元件,所述支撑板安装在支撑架上,所述支撑架内设有堵漏驱动组件、管道装夹组件以及支撑板拆装组件;其中,堵漏驱动组件,包括:支撑臂、旋转槽、旋转盘、螺纹柱以及手摇盘;所述支撑臂分别安装在支撑架上下部分,所述旋转槽开设在支撑臂内,所述旋转盘安装在旋转槽内,所述螺纹柱安装在旋转盘上;本实用新型涉及电厂电气技术领域,具备以下有益效果:通过将螺栓改用橡胶止流垫将管道渗漏处进行直接密封,可以快速堵漏,解决了不能快速堵漏的问题,通过螺纹柱推动管道夹进行夹紧止流,可以使夹紧更加稳定。

Figure 202221742683

The utility model discloses a temporary emergency plugging device for leakage of electrical pipelines in power plants, which comprises a support frame and a support plate; the support frame is used to support upper elements, the support plate is mounted on the support frame, and the support frame There is a plugging drive assembly, a pipeline clamping assembly and a support plate disassembly assembly; wherein, the leak plugging drive assembly includes: a support arm, a rotating groove, a rotating disk, a threaded column and a hand-operated disk; the support arms are respectively installed In the upper and lower parts of the support frame, the rotating groove is opened in the support arm, the rotating disk is installed in the rotating groove, and the threaded column is installed on the rotating disk; the utility model relates to the field of power plant electrical technology, and has the following beneficial effects: By replacing the bolt with a rubber stop gasket to directly seal the leakage of the pipeline, the leakage can be quickly plugged, which solves the problem of not being able to quickly plug the leakage. The threaded column is used to push the pipeline clamp to clamp the flow stop, which can make the clamping more stable. .

Figure 202221742683

Description

一种电厂电气用管道渗漏临时紧急堵漏装置A temporary emergency plugging device for leakage of electrical pipelines in power plants

技术领域technical field

本实用新型涉及电厂电气领域,具体为一种电厂电气用管道渗漏临时紧急堵漏装置。The utility model relates to the electrical field of power plants, in particular to a temporary emergency plugging device for leakage of electrical pipelines in power plants.

背景技术Background technique

在电厂内有许多室外电气设备,由于长时间运行设备易于出现密封件老化,进而会出现渗漏油漏气现象。若采用停止运输进行修补则会严重影响下游工长的生产,导致严重的经济损失,而现有的堵漏装置,通常采用螺栓进行紧固,而在螺栓未旋进对应位置前管道会不断渗漏,螺栓也承受内部压强而不易旋进。There are many outdoor electrical equipment in the power plant. Due to the long-term operation of the equipment, the seals are prone to aging, and then there will be oil leakage and air leakage. If it is repaired by stopping transportation, it will seriously affect the production of the downstream foreman, resulting in serious economic losses. The existing plugging device is usually fastened with bolts, and the pipeline will continue to leak before the bolts are screwed into the corresponding positions. Leakage, the bolt also bears the internal pressure and is not easy to screw in.

实用新型内容Utility model content

为实现以上目的,本实用新型通过以下技术方案予以实现:一种电厂电气用管道渗漏临时紧急堵漏装置,包括支撑架以及支撑板;所述支撑架用于支撑上方元件,所述支撑板安装在支撑架上,所述支撑架内设有堵漏驱动组件、管道装夹组件以及支撑板拆装组件;In order to achieve the above purpose, the utility model is achieved through the following technical proposals: a temporary emergency plugging device for electrical pipe leakage in a power plant, including a support frame and a support plate; the support frame is used to support the upper components, and the support plate Installed on a support frame, the support frame is provided with a plugging drive assembly, a pipe clamping assembly and a support plate disassembly assembly;

其中,堵漏驱动组件,包括:支撑臂、旋转槽、旋转盘、螺纹柱以及手摇盘;Among them, the plugging drive assembly includes: a support arm, a rotating slot, a rotating disc, a threaded column and a hand cranking disc;

所述支撑臂分别安装在支撑架上下部分,所述旋转槽开设在支撑臂内,所述旋转盘安装在旋转槽内,所述螺纹柱安装在旋转盘上,所述手摇盘安装在螺纹柱上。The support arms are installed on the upper and lower parts of the support frame respectively, the rotation groove is set in the support arm, the rotating disk is installed in the rotation groove, the threaded column is installed on the rotating disk, and the hand cranking disk is installed on the threaded column.

优选的,所述支撑架上设有挡板。Preferably, a baffle is provided on the support frame.

优选的,所述支撑架上设有把手。Preferably, a handle is provided on the support frame.

优选的,所述管道装夹组件,包括:管道夹以及止流垫;Preferably, the pipe clamping assembly includes: pipe clamps and stop pads;

所述管道夹安装在支撑臂上,所述止流垫安装在管道夹上。The pipe clamp is installed on the support arm, and the flow stop pad is installed on the pipe clamp.

优选的,所述止流垫为橡胶材质。Preferably, the stop pad is made of rubber.

优选的,所述支撑板拆装组件,包括:第一卡扣槽、锁紧卡扣槽、第一开关卡扣、第一锁紧卡扣、第一回弹弹簧、第二卡扣槽、第二开关卡扣、第二锁紧卡扣以及第二回弹弹簧;Preferably, the support plate disassembly assembly includes: a first buckle slot, a locking buckle slot, a first switch buckle, a first locking buckle, a first rebound spring, a second buckle slot, the second switch buckle, the second locking buckle and the second rebound spring;

所述第一卡扣槽与第二卡扣槽开设在支撑架上,所述锁紧卡扣槽开设在支撑板上,所述第一开关卡扣安装在第一卡扣槽内,所述第一锁紧卡扣安装在锁紧卡扣槽内,所述第一回弹弹簧安装在第一锁紧卡扣下方,所述第二开关卡扣与第二锁紧卡扣安装在第二卡扣槽内,所述第二回弹弹簧安装在第二锁紧卡扣下方。The first buckle groove and the second buckle groove are opened on the support frame, the locking buckle groove is opened on the support plate, the first switch buckle is installed in the first buckle groove, and the The first locking buckle is installed in the locking buckle groove, the first rebound spring is installed under the first locking buckle, the second switch buckle and the second locking buckle are installed on the second In the buckle groove, the second rebound spring is installed under the second locking buckle.

有益效果Beneficial effect

本一种电厂电气用管道渗漏临时紧急堵漏装置,具备以下有益效果:The present invention is a temporary emergency plugging device for electrical pipe leakage in a power plant, which has the following beneficial effects:

通过将螺栓改用橡胶止流垫将管道渗漏处进行直接密封,可以快速堵漏,解决了不能快速堵漏的问题,通过螺纹柱推动管道夹进行夹紧止流,可以使夹紧更加稳定。By changing the bolts to rubber stop pads to directly seal the leakage of the pipeline, the leak can be quickly plugged, which solves the problem of not being able to quickly plug the leak, and the threaded column is used to push the pipe clamp to clamp and stop the flow, which can make the clamping more stable .

附图说明Description of drawings

图1为本实用新型所述一种电厂电气用管道渗漏临时紧急堵漏装置的主视结构示意图。Fig. 1 is a front structural schematic diagram of a temporary emergency plugging device for electrical pipeline leakage in a power plant according to the utility model.

图2为本实用新型所述一种电厂电气用管道渗漏临时紧急堵漏装置的侧视结构示意图。Fig. 2 is a side view structural schematic diagram of a temporary emergency leak plugging device for electric pipeline leakage in a power plant according to the utility model.

图3为本实用新型所述一种电厂电气用管道渗漏临时紧急堵漏装置的支撑板拆装组件上侧示意图。Fig. 3 is a schematic diagram of the upper side of the support plate dismounting assembly of a temporary emergency plugging device for electrical pipeline leakage in a power plant according to the utility model.

图4为本实用新型所述一种电厂电气用管道渗漏临时紧急堵漏装置的支撑板拆装组件的下侧示意图。Fig. 4 is a schematic diagram of the lower side of the support plate disassembly assembly of a temporary emergency plugging device for electrical pipeline leakage in a power plant according to the utility model.

图中:1、支撑架;2、支撑板;3、支撑臂;4、旋转槽;5、旋转盘;6、螺纹柱;7、手摇盘;8、管道夹;9、止流垫;10、第一卡扣槽;11、锁紧卡扣槽;12、第一开关卡扣;13、第一锁紧卡扣;14、第一回弹弹簧;15、第二卡扣槽;16、第二开关卡扣;17、第二锁紧卡扣;18、第二回弹弹簧;In the figure: 1. Support frame; 2. Support plate; 3. Support arm; 4. Rotary groove; 5. Rotary disc; 6. Threaded column; 10. The first buckle slot; 11. The locking buckle slot; 12. The first switch buckle; 13. The first locking buckle; 14. The first rebound spring; 15. The second buckle slot; 16 , the second switch buckle; 17, the second locking buckle; 18, the second rebound spring;

具体实施方式Detailed ways

基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.

请参阅图1-4,本实用新型提供一种技术方案。Referring to Fig. 1-4, the utility model provides a technical solution.

一种电厂电气用管道渗漏临时紧急堵漏装置,包括支撑架1以及支撑板2;所述支撑架1用于支撑上方元件,所述支撑板2安装在支撑架1上,所述支撑架1内设有堵漏驱动组件、管道装夹组件以及支撑板2拆装组件;A temporary emergency plugging device for electrical pipeline leakage in a power plant, comprising a support frame 1 and a support plate 2; the support frame 1 is used to support the upper components, the support plate 2 is installed on the support frame 1, and the support frame 1 is equipped with plugging drive components, pipe clamping components and support plate 2 disassembly components;

其中,堵漏驱动组件,包括:支撑臂3、旋转槽4、旋转盘5、螺纹柱6 以及手摇盘7;Among them, the plugging drive assembly includes: a support arm 3, a rotating groove 4, a rotating disk 5, a threaded column 6 and a hand-operated disk 7;

所述支撑臂3分别安装在支撑架1上下部分,所述旋转槽4开设在支撑臂3内,所述旋转盘5安装在旋转槽4内,所述螺纹柱6安装在旋转盘5上,所述手摇盘7安装在螺纹柱6上。The support arms 3 are installed on the upper and lower parts of the support frame 1 respectively, the rotating groove 4 is opened in the supporting arm 3, the rotating disk 5 is installed in the rotating groove 4, and the threaded column 6 is installed on the rotating disk 5, The hand pan 7 is installed on the threaded post 6 .

需要说明的是,在对管道进行止流时,转动手摇盘7,使螺纹柱6旋转下移,推动支撑臂3下移,直至加紧管道外壁,旋转盘5用于配合螺纹柱6在旋转槽4内转动。It should be noted that when stopping the flow of the pipeline, turn the hand plate 7 to make the threaded column 6 rotate and move down, and push the support arm 3 to move down until the outer wall of the pipeline is tightened. The rotating plate 5 is used to cooperate with the threaded column 6 to rotate Rotate in slot 4.

作为优选的,更进一步的,所述支撑架1上设有挡板。As a preference, further, the support frame 1 is provided with a baffle.

需要说明的是,挡板用于卡紧固定支撑板2的位置。It should be noted that the baffle is used to fasten and fix the position of the support plate 2 .

作为优选的,更进一步的,所述支撑架1上设有把手。As a preference, further, the support frame 1 is provided with a handle.

需要说明的是,把手用于方便工作人员对装置的携带。It should be noted that the handle is used to facilitate the staff to carry the device.

作为优选的,更进一步的,所述管道装夹组件,包括:管道夹8以及止流垫9;As a preference, further, the pipe clamping assembly includes: a pipe clamp 8 and a stop pad 9;

所述管道夹8安装在支撑臂3上,所述止流垫9安装在管道夹8上。The pipe clamp 8 is mounted on the support arm 3 , and the stop pad 9 is mounted on the pipe clamp 8 .

需要说明的是,管道夹8勇于加紧管道,止流垫9用于防止管道被挤压变形并且可以更好的堵住渗漏口。It should be noted that the pipe clamp 8 is brave enough to tighten the pipe, and the stop pad 9 is used to prevent the pipe from being squeezed and deformed and can better block the leakage port.

作为优选的,更进一步的,所述止流垫9为橡胶材质;Preferably, further, the stop pad 9 is made of rubber;

需要说明的是,橡胶止流垫9可以使止流效果增强;It should be noted that the rubber stop pad 9 can enhance the stop effect;

作为优选的,更进一步的,所述支撑板2拆装组件,包括:第一卡扣槽 10、锁紧卡扣槽11、第一开关卡扣12、第一锁紧卡扣13、第一回弹弹簧14、第二卡扣槽15、第二开关卡扣16、第二锁紧卡扣17以及第二回弹弹簧18;As a preference, further, the disassembly assembly of the support plate 2 includes: a first buckle groove 10, a locking buckle groove 11, a first switch buckle 12, a first locking buckle 13, a first Rebound spring 14, second buckle groove 15, second switch buckle 16, second locking buckle 17 and second rebound spring 18;

所述第一卡扣槽10与第二卡扣槽15开设在支撑架1上,所述锁紧卡扣槽11开设在支撑板2上,所述第一开关卡扣12安装在第一卡扣槽10内,所述第一锁紧卡扣13安装在锁紧卡扣槽11内,所述第一回弹弹簧14安装在第一锁紧卡扣13下方,所述第二开关卡扣16与第二锁紧卡扣17安装在第二卡扣槽15内,所述第二回弹弹簧18安装在第二锁紧卡扣17下方。The first buckle groove 10 and the second buckle groove 15 are opened on the support frame 1, the locking buckle groove 11 is set on the support plate 2, and the first switch buckle 12 is installed on the first card. In the buckle groove 10, the first locking buckle 13 is installed in the locking buckle groove 11, the first rebound spring 14 is installed under the first locking buckle 13, and the second switch buckle 16 and the second locking buckle 17 are installed in the second buckle slot 15 , and the second rebound spring 18 is installed under the second locking buckle 17 .

需要说明的是,在进行支撑板2拆卸时,按压第一开关卡扣12,使第一开关卡扣12在第一卡扣槽10内下移,推动第一锁紧卡扣13中的第一锁紧卡扣13,下移出第一卡扣槽10,完成上方拆卸,按压第二开关卡扣16,使第二开关卡扣16在第二卡扣槽15内与第二锁紧卡扣17配合,使第二锁紧卡扣17 配合下移回收进第二卡扣槽15,完成下方解锁拆卸,取下支撑板2后,通过第一回弹弹簧14与第二回弹弹簧18的回弹,使第一锁紧卡扣13与第二锁紧卡扣17复位。It should be noted that when the support plate 2 is disassembled, the first switch buckle 12 is pressed, so that the first switch buckle 12 moves down in the first buckle groove 10, and the first lock buckle 13 in the first locking buckle 13 is pushed. One locking buckle 13, move down the first buckle groove 10, complete the upper disassembly, press the second switch buckle 16, make the second switch buckle 16 connect with the second locking buckle in the second buckle groove 15 17, so that the second locking buckle 17 is moved down and recovered into the second buckle groove 15, and the bottom unlocking and disassembly is completed. After the support plate 2 is taken off, the first rebound spring 14 and the second rebound spring 18 Rebound to reset the first locking buckle 13 and the second locking buckle 17 .

尽管已经示出和描述了本实用新型的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本实用新型的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本实用新型的范围由所附权利要求及其等同物限定。Although the embodiments of the present invention have been shown and described, those skilled in the art can understand that various changes and modifications can be made to these embodiments without departing from the principle and spirit of the present invention , replacements and modifications, the scope of the present utility model is defined by the appended claims and their equivalents.

Claims (6)

1. A temporary emergency leakage stopping device for leakage of an electric pipeline of a power plant comprises a supporting frame and a supporting plate; the support frame is used for supporting an upper element, and the support plate is arranged on the support frame;
wherein, leaking stoppage drive assembly includes: the support arm, the rotary groove, the rotary disk, the threaded column and the hand-cranking disk;
the support arm is installed respectively in support frame upper and lower part, the swivelling chute is seted up in the support arm, the rotary disk is installed in the swivelling chute, the screw thread post is installed on the rotary disk, hand dish is installed on the screw thread post.
2. The temporary emergency leakage stopping device for leakage of the electric pipeline of the power plant according to claim 1, wherein a baffle is arranged on the supporting frame.
3. The temporary emergency leakage stoppage device for leakage of the electric pipeline of the power plant according to claim 1, wherein the support frame is provided with a handle.
4. The temporary emergency leakage stopping device for leakage of the electric pipeline of the power plant according to claim 1, wherein the pipeline clamping assembly comprises: a pipe clamp and a flow stopping pad;
the pipeline clamp is installed on the support arm, the flow stopping pad is installed on the pipeline clamp.
5. The temporary emergency leakage stoppage device for leakage of the electric pipeline of the power plant according to claim 4, wherein the flow stopping pad is made of rubber.
6. The temporary emergency leakage stopping device for leakage of electric pipelines in power plant according to claim 1, wherein the supporting plate dismounting assembly comprises: the locking device comprises a first buckle groove, a locking buckle groove, a first switch buckle, a first locking buckle, a first rebound spring, a second buckle groove, a second switch buckle, a second locking buckle and a second rebound spring;
the first buckle groove and the second buckle groove are arranged on the support frame, the locking buckle groove is arranged on the support plate, the first switch buckle is arranged in the first buckle groove, the first locking buckle is arranged in the locking buckle groove, the first rebound spring is arranged below the first locking buckle, the second switch buckle is arranged in the second buckle groove with the second locking buckle, and the second rebound spring is arranged below the second locking buckle.
CN202221742683.4U 2022-07-06 2022-07-06 Temporary emergency leakage plugging device for leakage of electric pipeline of power plant Active CN217762639U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221742683.4U CN217762639U (en) 2022-07-06 2022-07-06 Temporary emergency leakage plugging device for leakage of electric pipeline of power plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221742683.4U CN217762639U (en) 2022-07-06 2022-07-06 Temporary emergency leakage plugging device for leakage of electric pipeline of power plant

Publications (1)

Publication Number Publication Date
CN217762639U true CN217762639U (en) 2022-11-08

Family

ID=83872228

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221742683.4U Active CN217762639U (en) 2022-07-06 2022-07-06 Temporary emergency leakage plugging device for leakage of electric pipeline of power plant

Country Status (1)

Country Link
CN (1) CN217762639U (en)

Similar Documents

Publication Publication Date Title
CN111678052B (en) A pipeline seal detection mechanism for air separation plant
CN218440864U (en) Diaphragm type safety relief valve
CN101188228A (en) Thyristor valve with component pressure mechanism
CN221004233U (en) U-shaped mechanical tee joint
CN203732107U (en) Glass float flowmeter
CN209587267U (en) A kind of ready-package valve
CN205447020U (en) Novel draw -in groove locking -type owner become respirator interface device
CN201858352U (en) Plugging head structure
CN217784497U (en) Novel high-precision adapter flange
CN222439036U (en) A water inlet sealing test device
CN208579010U (en) A kind of fixed device of remote control float valve
CN213776534U (en) Fire-fighting signal gate valve with switch signal indicator lamp
CN201462275U (en) Pipe saddle
CN221762878U (en) Maintenance equipment is changed to air supply pipe auxiliary member
CN211924451U (en) Pump cover
CN219866339U (en) Flange valve with flange plate adopting assembled structure
CN218884174U (en) External wet film of air pretreatment
CN221221896U (en) Pipeline plugging device for gas engineering
CN221922120U (en) A quick-release check valve
CN113217655A (en) Detachable drainage pressure relief valve
CN205651038U (en) A rigging equipment for water conservancy valve main valve
CN222460772U (en) Gas metering device convenient to install
CN209533197U (en) Top Magnet Positioning Fixture
CN218441146U (en) Flange convenient to dismantle and adjust
CN221958365U (en) Anticreep formula ring flange

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant