CN217631146U - Scaffold for housing construction engineering - Google Patents

Scaffold for housing construction engineering Download PDF

Info

Publication number
CN217631146U
CN217631146U CN202221451010.3U CN202221451010U CN217631146U CN 217631146 U CN217631146 U CN 217631146U CN 202221451010 U CN202221451010 U CN 202221451010U CN 217631146 U CN217631146 U CN 217631146U
Authority
CN
China
Prior art keywords
platform
scaffold
standing
hole
groups
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202221451010.3U
Other languages
Chinese (zh)
Inventor
朱卫平
耿云
耿虎
项有阔
张振义
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Qiande Construction Engineering Co ltd
Original Assignee
Anhui Qiande Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Qiande Construction Engineering Co ltd filed Critical Anhui Qiande Construction Engineering Co ltd
Priority to CN202221451010.3U priority Critical patent/CN217631146U/en
Application granted granted Critical
Publication of CN217631146U publication Critical patent/CN217631146U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model discloses a scaffold frame for housing construction engineering, including standing platform and elevating system, the left and right sides of the platform of standing is provided with prevents the mechanism of turning on one's side, elevating system sets up in the below of the platform of standing, elevating system includes the fixed column. The utility model discloses a set up elevating system, when the height of scaffold frame is adjusted to needs, loosen the nut on two threaded rods earlier, then take the threaded rod out from last jack and jack down, then hold the removal post, slide from top to bottom along the sliding tray as required, the height-adjusting, stop after reacing satisfied height, reset threaded rod and nut, the universal wheel of fixed column below makes things convenient for the removal of scaffold frame, the stability of the assurance scaffold frame between the fixed column, can not rock after highly rising, at present most scaffold frame height is not good to be adjusted, the device use the effectual practicality of having avoided above-mentioned problem and having improved equipment.

Description

Scaffold for housing construction engineering
Technical Field
The utility model belongs to the technical field of a scaffold frame for housing construction engineering, specifically, relate to a scaffold frame for housing construction engineering.
Background
The scaffold is a work platform which is erected for ensuring that each construction process is smoothly carried out, and is divided into an outer scaffold and an inner scaffold according to the erected position, and the scaffold can be divided into a wood scaffold, a bamboo scaffold and a steel pipe scaffold according to different materials, and is divided into a vertical rod type scaffold, a bridge type scaffold, a door type scaffold, a suspension type scaffold, a hanging type scaffold, a picking type scaffold and a climbing type scaffold according to the structural form.
At present most of scaffolds are not highly good to be adjusted, and when most of workers worked on the platform of standing, sometimes the focus was partial to one side, took place to turn on one's side easily, and the device's the effectual above-mentioned problem of having avoided of application has improved the practicality of equipment, for this reason, we provide a scaffold for housing construction engineering.
SUMMERY OF THE UTILITY MODEL
For solving the not good adjustment of most of scaffold heights that exists among the prior art, when most of workman was in the operation on the platform of standing, sometimes the focus was partial to one side, the technical problem who turns on one's side takes place easily, the utility model provides a scaffold for housing construction engineering.
The purpose of the utility model can be realized by the following technical scheme: a scaffold for building construction engineering comprises a standing platform and lifting mechanisms, wherein anti-rollover mechanisms are arranged on the left side and the right side of the standing platform, the lifting mechanisms are arranged below the standing platform, each lifting mechanism comprises four fixing columns, and the four fixing columns are grouped in pairs;
the side-turning prevention mechanism comprises a support frame and mounting blocks, the mounting blocks are arranged below the standing platform, the number of the mounting blocks is two, and the mounting blocks are two in number and two in number.
Preferably, the upper ends and the lower ends of the two groups of fixing columns are provided with sliding grooves, and lower insertion holes penetrate through the side faces of the two groups of fixing columns.
Preferably, the lower ends of the two groups of fixing columns are fixedly provided with universal wheels, and the middle of the two groups of fixing columns is fixedly connected with a stabilizer bar.
Preferably, the inner parts of the two groups of sliding grooves are connected with moving columns in a sliding mode, and upper insertion holes penetrate through the side faces of the moving columns.
Preferably, the size of the upper jack is consistent with that of the lower jack, threaded rods are inserted into the upper jack and the lower jack, the outer walls of the threaded rods are rotatably connected with nuts, and the standing platform is fixedly mounted on the upper surface of the movable column.
Preferably, the threaded hole coincides with the through hole and is the same in size, the threaded hole and the through hole are connected with a fixing bolt in a rotating mode, the support frame is fixedly installed on the outer side face of the installation block, and the bottom of the support frame is fixedly provided with an anti-slip mat.
Preferably, the upper surface of the standing platform is fixedly provided with stand columns near the four corners, guard rails are fixedly arranged between the stand columns, and through holes penetrate through the right and left sides of the standing platform.
The utility model has the advantages that:
1. the utility model discloses in, through setting up elevating system, when the height of scaffold frame is adjusted to needs, earlier loosen the nut on two threaded rods, then take the threaded rod out from last jack and jack down, then hold the removal post, slide from top to bottom along the sliding tray as required, height-adjusting, stop after reacing satisfied height, reset threaded rod and nut, the universal wheel of fixed column below makes things convenient for the removal of scaffold frame, the stability of scaffold frame is guaranteed to the stabilizer bar between the fixed column, can not rock after highly rising, most scaffold frame height is not well adjusted at present, the device's the effectual practicality of having avoided the above-mentioned problem and having improved equipment of using.
2. The utility model discloses in, prevent the mechanism of turning on one's side through the setting, aim at the through-hole of the platform lower surface of standing with the screw hole on two installation pieces, then rotate fixing bolt from the through-hole and connect in threaded hole portion, screw up fixedly, this moment, slipmat on the support frame offsets with ground, supports scaffold both sides, at present when most of workman are in operation on the platform of standing, and the focus is partial to one side occasionally, takes place to turn on one's side easily, the device use the effectual practicality of having avoided above-mentioned problem and having improved equipment.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the description of the embodiments will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art that other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic perspective view of a scaffold for housing construction engineering according to the present invention;
fig. 2 is an exploded view of the scaffold for housing construction engineering of the present invention;
fig. 3 is an exploded view of the lifting mechanism of the scaffold for housing construction engineering according to the present invention;
fig. 4 is an exploded view of a part of the structure of the lifting mechanism of the scaffold for housing construction engineering according to the present invention;
fig. 5 is an exploded view of the rollover prevention mechanism of the scaffold for housing construction engineering of the present invention.
In the drawings, the reference numbers indicate the following list of parts:
1. a standing platform; 2. a column; 3. protecting a fence; 4. a through hole; 5. a lifting mechanism; 51. fixing the column; 52. a sliding groove; 53. a universal wheel; 54. a lower jack; 55. moving the column; 56. an upper jack; 57. a threaded rod; 58. a nut; 59. a stabilizer bar; 6. an anti-rollover mechanism; 61. a support frame; 62. mounting blocks; 63. a threaded hole; 64. fixing the bolt; 65. a non-slip mat.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by a person of ordinary skill in the art without creative efforts belong to the protection scope of the present invention.
Embodiment 1, please refer to fig. 1 to 5, which illustrate a scaffold for building construction engineering, comprising a standing platform 1, a lifting mechanism 5 and a side-turn preventing mechanism 6.
The specific arrangement and function of the lifting mechanism 5 and the rollover prevention mechanism 6 will be described in detail below.
As shown in fig. 1-4, the lifting mechanism 5 is disposed below the standing platform 1, the lifting mechanism 5 includes four fixed columns 51, the number of the fixed columns 51 is four, two fixed columns are in a group, sliding grooves 52 are disposed at upper and lower ends of two groups of fixed columns 51, lower insertion holes 54 are formed through side surfaces of two groups of fixed columns 51, universal wheels 53 are fixedly mounted at lower ends of two groups of fixed columns 51, stabilizer bars 59 are fixedly connected between the two groups of fixed columns 51, moving columns 55 are slidably connected inside the two groups of sliding grooves 52, upper insertion holes 56 are formed through side surfaces of the moving columns 55, the size of the upper insertion holes 56 is consistent with that of the lower insertion holes 54, threaded rods 57 are inserted inside the upper insertion holes 56 and the lower insertion holes 54, nuts 58 are rotatably connected to outer walls of the threaded rods 57, and the standing platform 1 is fixedly mounted on the upper surfaces of the moving columns 55.
The effect that its whole elevating system 5 reached does, through setting up elevating system 5, when the height of scaffold frame needs to be adjusted, nut 58 on two threaded rods 57 is loosened earlier, then take threaded rod 57 out from last jack 56 and lower jack 54, then hold and remove post 55, slide from top to bottom along sliding tray 52 as required, adjust the height, stop after reaching satisfactory height, reset threaded rod 57 and nut 58, the universal wheel 53 of fixed column 51 below makes things convenient for the removal of scaffold frame, the stability of scaffold frame is guaranteed to stabilizer bar 59 between the fixed column 51, can not rock after the height risees, most of scaffold frame height adjustment well at present, the application of the device is effectual has avoided above-mentioned problem and has improved the practicality of equipment.
As shown in fig. 1, fig. 2 and fig. 5, the left and right sides of the standing platform 1 are provided with the anti-rollover mechanisms 6, the anti-rollover mechanisms 6 include support frames 61 and mounting blocks 62, the mounting blocks 62 are arranged below the standing platform 1, the number of the mounting blocks 62 is two, the upper surfaces of the two sets of mounting blocks 62 are provided with threaded holes 63 near the positions on the two sides, the threaded holes 63 coincide with the through holes 4, and the size is consistent, the threaded holes 63 and the through holes 4 are rotatably connected with fixing bolts 64, the support frames 61 are fixedly mounted on the outer side surfaces of the mounting blocks 62, the bottoms of the support frames 61 are fixedly mounted with anti-skid pads 65, the upper surface of the standing platform 1 is fixedly mounted with upright columns 2 near the four corners, guard rails 3 are fixedly mounted between the upright columns 2, and through holes 4 are formed in the right and left positions of the standing platform 1.
The effect that its whole anti-rollover mechanism 6 reached does, through setting up anti-rollover mechanism 6, aim at the through-hole 4 of the platform 1 lower surface of standing with the screw hole 63 on two installation pieces 62, then rotate fixing bolt 64 from through-hole 4 and connect inside screw hole 63, it is fixed to screw up, at this moment, slipmat 65 on the support frame 61 offsets with ground, support scaffold both sides, when present most of workman is in the operation on the platform 1 of standing, sometimes the focus is partial to one side, easy emergence is turned on one's side, the device's the effectual above-mentioned problem of having avoided and the practicality that has improved equipment of using.
Embodiment 2 is different from embodiment 1 in that, as shown in fig. 1 and 2, upright posts 2 are fixedly mounted on the upper surface of a standing platform 1 near four corners, guard rails 3 are fixedly mounted between the upright posts 2, and through holes 4 penetrate through the right and left sides of the right middle of the standing platform 1.
The working principle is as follows: by arranging the lifting mechanism 5, when the height of the scaffold needs to be adjusted, nuts 58 on two threaded rods 57 are firstly loosened, then the threaded rods 57 are drawn out from an upper jack 56 and a lower jack 54, then the movable columns 55 are held, the height is adjusted by sliding up and down along sliding grooves 52 as required, the scaffold stops after reaching a satisfactory height, the threaded rods 57 and the nuts 58 are reset, universal wheels 53 below fixed columns 51 facilitate the movement of the scaffold, stabilizing rods 59 between the fixed columns 51 ensure the stability of the scaffold, the scaffold cannot shake after the height rises, most of scaffolds at present are not adjusted well in height, the device effectively avoids the problems and improves the practicability of equipment by applying the device, and sometimes one side of gravity center is prone to standing when most workers work on the platform 1 by arranging the anti-rollover mechanism 6, threaded holes 63 on two mounting blocks 62 are aligned with through holes 4 on the lower surface of the standing platform 1, then fixing bolts 64 are rotatably connected inside the threaded holes 63 from the through holes 4 and are screwed and fixed, at this time, anti-skid pads 65 on the support frame 61 abut against the ground, the two sides of the scaffold are supported, and the two sides of the scaffold are inclined to one side of gravity center, and the device effectively avoids the problem and improves the practicability of the equipment.
In the description of the specification, references to the description of "one embodiment," "an example," "a specific example," etc., mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention. In this specification, the schematic representations of the terms used above do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
The foregoing is merely exemplary and illustrative of the structure of the invention and various modifications, additions or substitutions as are known to those skilled in the art may be made to the described embodiments without departing from the scope of the invention as defined in the accompanying claims.

Claims (7)

1. The utility model provides a scaffold frame for housing construction engineering, includes platform (1) and elevating system (5) of standing, its characterized in that: the anti-rollover mechanism (6) is arranged on the left side and the right side of the standing platform (1), the lifting mechanism (5) is arranged below the standing platform (1), the lifting mechanism (5) comprises four fixing columns (51), and every two fixing columns are in a group;
prevent side tumbling mechanism (6) including support frame (61) and installation piece (62), installation piece (62) set up in the below of standing platform (1), the quantity of installation piece (62) is two sets of, and is two sets of the upper surface of installation piece (62) is close to both sides position department and is provided with screw hole (63).
2. A scaffolding for house building engineering according to claim 1, wherein: the upper ends and the lower ends of the two groups of fixing columns (51) are provided with sliding grooves (52), and lower insertion holes (54) penetrate through the side faces of the two groups of fixing columns (51).
3. A scaffolding for house building engineering according to claim 2, wherein: the lower ends of the two groups of fixing columns (51) are fixedly provided with universal wheels (53), and the middle of the two groups of fixing columns (51) is fixedly connected with a stabilizer bar (59).
4. A scaffold for building construction engineering according to claim 3, wherein: the inner parts of the two groups of sliding grooves (52) are connected with moving columns (55) in a sliding mode, and upper insertion holes (56) penetrate through the side faces of the moving columns (55).
5. The scaffold for house building engineering according to claim 4, characterized in that: the size of the upper insertion hole (56) is consistent with that of the lower insertion hole (54), a threaded rod (57) is inserted into the upper insertion hole (56) and the lower insertion hole (54), a nut (58) is rotatably connected to the outer wall of the threaded rod (57), and the standing platform (1) is fixedly mounted on the upper surface of the movable column (55).
6. A scaffolding for house building engineering according to claim 1, wherein: the novel anti-skid device is characterized in that the threaded hole (63) and the through hole (4) are overlapped and are consistent in size, a fixing bolt (64) is rotatably connected to the interior of the threaded hole (63) and the interior of the through hole (4), the support frame (61) is fixedly installed on the outer side face of the installation block (62), and an anti-skid pad (65) is fixedly installed at the bottom of the support frame (61).
7. A scaffolding for house building engineering according to claim 1, wherein: the upper surface of platform of standing (1) is close to four corners department fixed mounting has stand (2), fixed mounting has rail guard (3) between stand (2), the centre of platform of standing (1) is close to left and right sides position department and runs through there is through hole (4).
CN202221451010.3U 2022-06-10 2022-06-10 Scaffold for housing construction engineering Expired - Fee Related CN217631146U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221451010.3U CN217631146U (en) 2022-06-10 2022-06-10 Scaffold for housing construction engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221451010.3U CN217631146U (en) 2022-06-10 2022-06-10 Scaffold for housing construction engineering

Publications (1)

Publication Number Publication Date
CN217631146U true CN217631146U (en) 2022-10-21

Family

ID=83624389

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221451010.3U Expired - Fee Related CN217631146U (en) 2022-06-10 2022-06-10 Scaffold for housing construction engineering

Country Status (1)

Country Link
CN (1) CN217631146U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116765655A (en) * 2023-07-06 2023-09-19 江阴市华骏机械有限公司 A stable welding anti-deformation device for the lower frame of an excavator

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116765655A (en) * 2023-07-06 2023-09-19 江阴市华骏机械有限公司 A stable welding anti-deformation device for the lower frame of an excavator
CN116765655B (en) * 2023-07-06 2025-08-05 江阴市华骏机械有限公司 A stable excavator lower frame welding anti-deformation device

Similar Documents

Publication Publication Date Title
CN217631146U (en) Scaffold for housing construction engineering
CN213626572U (en) Tool type external cantilever operation platform
CN216664939U (en) Scaffold frame protector is used in construction
CN215254436U (en) Scaffold with adjustable height
CN212897455U (en) Prevent portable scaffold frame that topples
CN102733586A (en) Scaffold cart
CN210888010U (en) Construction handling frame
CN212773366U (en) Door type scaffold
CN210263832U (en) Movable cantilever platform
CN216587610U (en) Scaffold with stair climbing fixing mechanism
CN216893370U (en) High and good novel scaffold frame is used in building construction of flexibility of security
CN212715838U (en) Multifunctional assembling scaffold for building decoration
CN210508314U (en) Scaffold structure for building
CN214575505U (en) Scaffold reinforcing apparatus for building engineering
CN210396057U (en) Scaffold for repairing large-scale ancient architecture
CN221143522U (en) Building construction anti-falling scaffold
CN209443737U (en) A kind of outer eaves scaffold for building
CN215670903U (en) Scaffold with firm base
CN214885346U (en) Building scaffold with good base stability
CN221590336U (en) Auxiliary scaffold for building
CN210917032U (en) Bridge construction is with safe support bracket
CN219281195U (en) Scaffold frame
CN213449389U (en) Hydraulic engineering construction is with removing scaffold frame
CN202767484U (en) Scaffold vehicle
CN222413986U (en) A simple scaffold

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20221021