CN217461142U CN202221354891.7U CN202221354891U CN217461142U CN 217461142 U CN217461142 U CN 217461142U CN 202221354891 U CN202221354891 U CN 202221354891U CN 217461142 U CN217461142 U CN 217461142U
Authority
CN
China
Prior art keywords
main
keel
hanging
hanging basket
ceiling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221354891.7U
Other languages
Chinese (zh)
Inventor
龙满红
姜坤
晏黎
王贵生
徐能忠
许忠豪
覃鹤
刘璇
左海宏
赵红霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No 1 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group
Original Assignee
No 1 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No 1 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group filed Critical No 1 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group
Priority to CN202221354891.7U priority Critical patent/CN217461142U/en
Application granted granted Critical
Publication of CN217461142U publication Critical patent/CN217461142U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a gallows structure system of building body furred ceiling, include: the hanging basket seat is provided with mounting bayonets correspondingly in four directions vertical to the same plane; the main keel is clamped and fixed by mounting bayonets which are perpendicular to four directions on the same plane of the hanging basket seat; the secondary keel is fixed between the parallel main keels and is positioned on the same horizontal plane with the main keels; and the tension assembly is connected with the hanging basket seat. Because the pulling force subassembly is connected with the hanging flower basket seat and exerts pulling force and holds main joist and secondary joist through the hanging flower basket seat and install at the building body top surface, when the installation furred ceiling shrouding produces too much gravity in main joist and secondary joist lower part, the main joist and the secondary joist that are in the coplanar can be on average atress and can not take place the bending, the stability of furred ceiling shape structure has been improved, it cup joints on wearing the plug-in components to have solved the activity of bearing fossil fragments both ends, it can use the jib to produce crooked problem as the ascending pulling interlude of initial point to bear the fossil fragments.

Description

Hanging bracket structure system of building suspended ceiling
Technical Field
The utility model relates to a gallows structure system of building body furred ceiling belongs to furred ceiling construction installation technical field.
Background
After the building top surfaces such as houses, subways and underground passages are demolished, suspended ceiling construction and installation are needed to beautify the building top surfaces.
In a green environment-friendly combined keel ceiling structure with Chinese patent publication No. CN215519438U, the disclosed technology is that the upper side of a triangular keel is slidably clamped with a hanging code, the upper surface of the hanging code is welded with a through-insertion piece, and a bearing keel is movably sleeved on the through-insertion piece; bear the weight of on the fossil fragments activity peg graft and have the jib, bear the weight of and set up the through-hole with jib looks adaptation on the fossil fragments, the lower extreme activity of jib is pegged graft on the through-hole, two screw caps are installed to the screw thread on the jib, though, the jib can be pulled and bear the weight of fossil fragments, however, because bear the weight of fossil fragments both ends activity cup joint on the interlude piece, later stage furred ceiling shrouding is installed on the cladding fossil fragments, the gravity of furred ceiling shrouding can stimulate the piece of interlude downwards, in case the gravity increase of installation furred ceiling shrouding, the existence bears the weight of fossil fragments and can use the jib to upwards stimulate the piece of interlude to produce crooked problem as the initial point, the stability of furred ceiling shape structure has been reduced.
SUMMERY OF THE UTILITY MODEL
In order to solve the technical problem, the utility model provides a gallows structure system of building body furred ceiling.
The utility model discloses a following technical scheme can realize.
The utility model provides a pair of gallows structure system of building body furred ceiling, include:
the hanging basket comprises hanging basket seats, wherein mounting bayonets are correspondingly arranged in four directions vertical to the same plane of the hanging basket seats, and the number of the hanging basket seats is at least two;
the hanging basket comprises a hanging basket seat, a main keel, a hanging basket seat and a hanging basket seat, wherein mounting bayonets in four directions perpendicular to the same plane of the hanging basket seat are respectively clamped and fixed with the main keel, and the main keel between the two hanging basket seats is a common one;
the secondary keel is fixed between the parallel main keels and is positioned on the same horizontal plane with the main keels;
the main keel and the secondary keel are connected with the hanging basket seat, the pulling force component is installed on the top surface of the building body by pulling the main keel and the secondary keel through the hanging basket seat, and the pulling force component exerts pulling force on the main keel and the secondary keel from the hanging basket seat.
The tension assembly, comprising: one end of the screw is connected with a turnbuckle arranged at the top of the hanging basket seat through a pin;
and the tension piece is arranged on the top of the turnbuckle.
The end part of the main keel positioned on the side edge of the hanging basket seat is clamped with the mounting seat.
And a cover plate is fixed on the side edge of the top of the hanging basket seat positioned on the mounting bayonet and is in contact with the main keel.
The lifting rod piece is characterized by also comprising a plurality of lifting rod pieces.
The hanger rod pieces are correspondingly and fixedly installed on the main keel and the secondary keel, and the lower part of each hanger rod piece is fixedly provided with a buckling strip.
The top of each buckling strip is fixed to the bottom of the main keel or the bottom of the secondary keel through the hanging rod piece, the two buckling strips are distributed in parallel, a ceiling sealing plate is fixedly mounted between the two buckling strips, and the ceiling sealing plate and the buckling strips are fixedly mounted.
The ceiling sealing plate is provided with an embedding opening to cover the bottom keel.
The beneficial effects of the utility model reside in that: because the pulling force subassembly is connected with the hanging flower basket seat and exerts pulling force and holds main joist and secondary joist through the hanging flower basket seat and install at the building body top surface, when the installation furred ceiling shrouding produces too much gravity in main joist and secondary joist lower part, the main joist and the secondary joist that are in the coplanar can be on average atress and can not take place the bending, the stability of furred ceiling shape structure has been improved, it cup joints on wearing the plug-in components to have solved the activity of bearing fossil fragments both ends, it can use the jib to produce crooked problem as the ascending pulling interlude of initial point to bear the fossil fragments.
Drawings
Fig. 1 is a schematic structural diagram of a top view of the present invention;
FIG. 2 is a schematic view of the right-side view of FIG. 1;
in the figure: 1-hanging basket seat; 11-installing a bayonet; 12-a tension member; 13-turnbuckle; 2-secondary keel; 3-mounting a base; 4-cover plate; 5-hanging the rod piece; 6-buckling strips; 7-ceiling seal plate; 71-a fitting port; 8-bottom keel; 9-main keel.
Detailed Description
The technical solution of the present invention is further described below, but the scope of the claimed invention is not limited to the described.
As shown in fig. 1-2.
The application discloses a gallows structural system of building body furred ceiling includes:
the hanging basket seat is characterized in that a hanging basket seat 1 made of steel plates and other rigid bodies is welded and fixed, mounting bayonets 11 are correspondingly arranged in four directions perpendicular to the same plane of the hanging basket seat 1, and the number of the hanging basket seat 1 is at least two;
the hanging basket comprises a main keel 9 made of hollow square steel or wood and other rigid bodies, mounting bayonets 11 which are perpendicular to four directions on the same plane of a hanging basket seat 1 are respectively clamped with the main keel 9 and fixed through bolts, and the main keel 9 between the two hanging basket seats 1 is a shared one;
the secondary keel 2 is made of hollow square steel or wood and other rigid bodies, the secondary keel 2 is welded and fixed between the parallel main keels 9 or fixed by bolts, and the secondary keel 2 and the main keels 9 are positioned on the same horizontal plane;
being connected with hanging flower basket seat 1 and holding main joist 9 and secondary joist 2 through hanging flower basket seat 1 and installing the pulling force subassembly at the building body top surface, pulling force subassembly from hanging flower basket seat 1 to main joist 9 and secondary joist 2 applys pulling force.
Because the pulling force subassembly is connected with hanging flower basket seat 1 and exerts pulling force and holds main joist 9 and secondary joist 2 through hanging flower basket seat 1 and install at the building body top surface, when producing too much gravity at main joist 9 and secondary joist 2 lower part installation furred ceiling shrouding 7, the main joist 9 and the secondary joist 2 that are in the coplanar can be on average atress and can not take place the bending, the stability of furred ceiling shape structure has been improved, it cup joints on wearing the plug-in components to have solved the activity of bearing the keel both ends, it can use the jib to produce crooked problem as the original point upwards pulling interlude.
The tension assembly, comprising: one end of the turnbuckle 13 is connected with the top of the hanging basket seat 1 through a pin, specifically, a through hole at the bottom of the turnbuckle 13 can be rotatably arranged on the top of the hanging basket seat 1 through a pin;
with the pulling force piece 12 of 13 top installations of turn buckle, specifically can be for 13 top welded fastening of turn buckle have the couple, pulling force piece 12 has the couple to hang the installation with the couple at 13 tops of turn buckle, and pulling force piece 12 is under construction and is held through expansion bolts and the installation of building body top surface during the installation.
The end part of the main keel 9 positioned on the side edge of the hanging basket seat 1 is clamped with the mounting seat 3, and the mounting seat 3 is fixedly mounted with the side surface of the top of the building body through an expansion bolt; also can weld fixation or bolt fixed mounting secondary joist 2 on the main joist 9 with mount pad 3, the secondary joist 2 of here is mutually perpendicular's two (not shown in the figure), and the secondary joist 2 of this position is installed according to specific construction needs to this constitutes to provide the installation atress basis to the furred ceiling shrouding 7 that is close to wall body part.
And a cover plate 4 is fixedly welded on the side edge of the top of the hanging basket seat 1 positioned on the mounting bayonet 11, and the cover plate 4 is in contact with the main keel 9, so that the main keel 9 is guided and limited.
Still include that quantity is a plurality of jib spare 5, jib spare 5 corresponds through welded fastening or bolt fixed mounting on main joist 9, secondary joist 2, 5 low portions of every jib spare all have a profile 6 through welded fastening or bolt fixed mounting, 6 tops of profile are fixed on main joist 9 or secondary joist 2 bottoms through jib spare 5, parallel distribution between two profiles 6, fixed mounting has furred ceiling shrouding 7 between two profiles 6, specifically for furred ceiling shrouding 7 and profile 6 are installed through fixed modes such as bayonet socket chucking (this for prior art no longer state).
The support structure also comprises bottom keels 8 made of steel plates and other rigid bodies through welding and fixing, wherein the bottom keels 8 are vertically distributed with the buckling strips 6 and are positioned below the buckling strips 6, for example, two bottom keels 8 are vertically distributed below the buckling strips 6 and correspondingly form an expected support state; be equipped with on the furred ceiling shrouding 7 and inlay mouth 71 and cover end keel 8, the gomphosis mouth 71 of furred ceiling shrouding 7 can realize under normal conditions the effort of upwards pulling in 8 middle parts of end keel, an holistic end keel 8 can obtain ascending pulling force on a plurality of furred ceiling shrouding 7 and obtain stable condition, but when furred ceiling shrouding 7 drops, the gomphosis mouth 71 of furred ceiling shrouding 7 can not stimulate end keel 8 downwards, end keel 8 both ends can be fixed on the wall body of building body top side through installed part such as mount pad 3 or direct expansion bolts when the construction, even install end keel 8 is guaranteed when furred ceiling shrouding 7 drops, can not produce the whole chain reaction that drops along with the support that can obtain two end keels 8 when dropping when the profile 6, the problem that the furred ceiling shrouding 7 large tracts of land dropped is solved.
The construction method of the hanger structure system of the building suspended ceiling comprises the following steps:
step one, manufacturing a hanging basket seat: and selecting steel plates qualified for inspection, and cutting and welding according to the shape and the size of the hanging basket seat 1 to form mounting bayonets 11 in four directions perpendicular to the same plane on the hanging basket seat 1.
Step two, mounting a hanging basket seat: the 12 tops of the tension components of the tension assembly are fixedly mounted on the top surface of a building body through expansion bolts, the 12 tops of the tension components are mounted with turn-buckle screws 13, and the bottoms of the turn-buckle screws 13 are mounted and connected with the center of the top of a hanging basket seat 1.
Step three, mounting the keels on the same plane: get through main joist 9, secondary joist 2 that warp hanger spare 5 fixed mounting has profile 6, main joist 9 correspond install in the installation bayonet 11 of four perpendicular directions in hanging flower basket seat 1 coplanar, a main joist 9 of sharing between two hanging flower basket seats 1, fixed secondary joist 2 between the parallel main joist 9 and be in the coplanar with main joist 9.
When a plurality of ceiling sealing plates 7 arranged on the lower portions of the main keels 9 and the secondary keels 2 generate excessive downward gravity, the bearing capacity received by the main keels 9 and the secondary keels 2 on the same plane can be evenly stressed in unit area, the situation that the bearing capacity received by the unit area of the keel framework is too concentrated is avoided, and the problem that the bearing capacity received by the unit area of the keel framework is too concentrated and the bearing capacity is poor due to the fact that the secondary keels and the main keels are not located on the same plane is solved.
Step four, installing the ceiling seal plate: the bottom keel 8 is arranged below the buckling strips 6, the ceiling sealing plate 7 and the buckling strips 6 are fixedly arranged, and the bottom keel 8 is covered by the embedding opening 71 of the ceiling sealing plate 7.

Claims (8)

1. A hanger structural system for a building suspended ceiling, comprising:
the hanging basket comprises hanging basket seats (1), wherein mounting bayonets (11) are correspondingly arranged in four directions perpendicular to the same plane of the hanging basket seats (1), and the number of the hanging basket seats (1) is at least two;
the hanging basket comprises main keels (9), mounting bayonets (11) which are perpendicular to four directions on the same plane of the hanging basket seats (1) are fixedly clamped with the main keels (9), and the main keels (9) between the two hanging basket seats (1) are shared;
the secondary keels (2) are fixed between the parallel main keels (9) and are positioned on the same horizontal plane with the main keels (9);
being connected with hanging flower basket seat (1) and holding main joist (9) and secondary joist (2) through hanging flower basket seat (1) and installing the pulling force subassembly at the building body top surface, pulling force subassembly from hanging flower basket seat (1) exerts pulling force main joist (9) and secondary joist (2).
2. The building ceiling hanger structural system of claim 1, wherein said tension assembly comprises: one end of the basket screw (13) is arranged on the top of the basket seat (1) through a pin;
and the tension piece (12) is arranged on the top of the turnbuckle (13).
3. A hanger frame structural system for a building ceiling as claimed in claim 1 wherein: the end part of the main keel (9) positioned at the side edge of the hanging basket seat (1) is clamped with the mounting seat (3).
4. A hanger frame structural system for a building ceiling as claimed in claim 1 wherein: and a cover plate (4) is fixed on the side edge of the top of the hanging basket seat (1) positioned on the mounting bayonet (11), and the cover plate (4) is in contact with the main keel (9).
5. A hanger frame structural system for a building ceiling as claimed in claim 1 wherein: the device also comprises a plurality of lifting rod pieces (5).
6. The building ceiling hanger structural system of claim 5, wherein: the hoisting rod pieces (5) are correspondingly and fixedly arranged on the main keel (9) and the secondary keel (2), and a buckling strip (6) is fixedly arranged at the lower part of each hoisting rod piece (5).
7. The structural system of a hanger for a building ceiling of claim 6 wherein: the top of each buckling strip (6) is fixed to the bottom of the main keel (9) or the bottom of the secondary keel (2) through a hanging rod piece (5), the two buckling strips (6) are distributed in parallel, a ceiling sealing plate (7) is fixedly installed between the two buckling strips (6), and the ceiling sealing plate (7) and the buckling strips (6) are fixedly installed.
8. The building ceiling hanger structural system of claim 7, wherein: the ceiling sealing plate is characterized by further comprising a bottom keel (8), wherein the bottom keel (8) and the buckling strip (6) are vertically distributed and are positioned below the buckling strip (6), and an embedding opening (71) is formed in the ceiling sealing plate (7) to cover the bottom keel (8).
CN202221354891.7U 2022-06-01 2022-06-01 Hanging bracket structure system of building suspended ceiling Active CN217461142U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221354891.7U CN217461142U (en) 2022-06-01 2022-06-01 Hanging bracket structure system of building suspended ceiling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221354891.7U CN217461142U (en) 2022-06-01 2022-06-01 Hanging bracket structure system of building suspended ceiling

Publications (1)

Publication Number Publication Date
CN217461142U true CN217461142U (en) 2022-09-20

Family

ID=83277053

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221354891.7U Active CN217461142U (en) 2022-06-01 2022-06-01 Hanging bracket structure system of building suspended ceiling

Country Status (1)

Country Link
CN (1) CN217461142U (en)

Similar Documents

Publication Publication Date Title
CN116163461B (en) Space structure assembled ultra-large color grain metal plate suspended ceiling and construction method
CN211974027U (en) Adaptor convenient to GRG jib is adjusted location
CN215253811U (en) Inclined inhaul cable type glass curtain wall system
CN217461142U (en) Hanging bracket structure system of building suspended ceiling
CN112196156A (en) Unit curtain wall plate anti-drop hanging joint and construction method thereof
CN219261461U (en) Photovoltaic curtain wall dry-hanging system
CN114809420A (en) Construction method of hanging bracket structure system of building suspended ceiling
CN216195822U (en) Small unit curtain wall connecting device
CN213868520U (en) Light steel keel frame with stable structure for indoor suspended ceiling
CN212336452U (en) Full glass curtain wall suspended structure
CN212026736U (en) Concatenation formula building curtain
CN111009862B (en) Extrusion-molded bracket arm and production method thereof
CN103572879B (en) For the sky well construction of Integral ceiling
CN210421849U (en) Keel support frame for building
CN217811871U (en) A assembled keel structure that is used for double-deck GRG molding to fall level furred ceiling
CN218843478U (en) Mounting structure of metal face heat preservation decoration intergral template
CN113668756B (en) Large-span aluminum square tube multiple-drop-level modeling assembly type installation design structure
CN215636184U (en) Support frame for construction machinery
CN203487680U (en) Courtyard structure for integrated suspended ceiling
CN201972280U (en) Splicing hanging mechanism for unitized curtain wall
CN215829778U (en) Connection structure of upright frame board and furred ceiling elevated plate
CN214246437U (en) Convenient steel sheet hangs wall futilely
CN216276846U (en) Integral type hanging flower basket suspension mechanism
CN216195911U (en) Corridor suspended ceiling
CN219690848U (en) Suspended ceiling conversion assembly under net rack ball

Legal Events

Date Code Title Description
GR01 Patent grant