CN217460577U - Channel concrete pours chute fast - Google Patents

Channel concrete pours chute fast Download PDF

Info

Publication number
CN217460577U
CN217460577U CN202221033088.3U CN202221033088U CN217460577U CN 217460577 U CN217460577 U CN 217460577U CN 202221033088 U CN202221033088 U CN 202221033088U CN 217460577 U CN217460577 U CN 217460577U
Authority
CN
China
Prior art keywords
chute
extension section
rod
sections
channel concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202221033088.3U
Other languages
Chinese (zh)
Inventor
郑会永
段剑平
韩宁宁
张桂林
张辉
李鹏
王梦圆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 11 Co Ltd
PowerChina 11th Bureau Chongqing Construction Co Ltd
Original Assignee
Sinohydro Bureau 11 Co Ltd
PowerChina 11th Bureau Chongqing Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 11 Co Ltd, PowerChina 11th Bureau Chongqing Construction Co Ltd filed Critical Sinohydro Bureau 11 Co Ltd
Priority to CN202221033088.3U priority Critical patent/CN217460577U/en
Application granted granted Critical
Publication of CN217460577U publication Critical patent/CN217460577U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

A channel concrete rapid pouring chute comprises a chute body, a support frame and an extension section, wherein the extension section is used for extending the conveying length of the chute body, the chute body comprises two inclined chute sections which are distributed in an inverted V shape, the ends, close to each other, of the two inclined chute sections are hinged with each other, the ends, far away from each other, of the two inclined chute sections are detachably connected with the extension section, the support frame comprises a vertical support rod used for supporting the inclined chute sections and a transverse support rod connected with the vertical support rod, the end, far away from the inclined chute sections, of the vertical support rod is hinged with the inclined chute sections; the extension section comprises an extension section body and a support connecting rod arranged on the extension section body, and the support connecting rod is hinged with the extension section body. The utility model discloses increase the efficiency of construction, reduce the running die risk.

Description

Channel concrete pours chute fast
Technical Field
The utility model relates to a construction technical field, concretely relates to chute is pour fast to channel concrete.
Background
The channel lining structure mainly comprises side walls which are of rectangular gravity type concrete retaining walls and bottom plate concrete structures, wherein one sides of the side walls are of the rectangular gravity type concrete retaining walls, the other sides of the side walls are of thin-wall concrete slabs and concrete bottom plate structures, the side walls are of the thin-wall concrete slabs and concrete bottom plate structures, and soft foundation treatment is carried out on part of the bottom of a channel by adopting graded broken stones or stones. In the channel construction, need carry out concrete structure side wall construction, if concrete whereabouts apart from pouring the face distance too big can produce the segregation phenomenon at concrete placement in-process, simultaneously because the channel side wall is wide less, the concrete pan feeding is difficult, so pour the in-process and need use the chute. The chute structure that general construction used adopts the mode that the support adds the iron sheet, and the chute becomes certain slope, and the concrete passes through the chute and relies on the dead weight to go into the storehouse, and present chute only can satisfy the demand of pouring of unilateral channel side wall, and the channel is pour and need be divided left and right sides, twice carry out concrete placement, and the construction progress is slow, has the risk of running the mould.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the above technical problem, provide a chute is pour fast to channel concrete, increase the efficiency of construction, reduce the running die risk.
The utility model provides a solve above-mentioned technical problem, the technical scheme who provides is: a channel concrete rapid pouring chute comprises a chute body, a support frame and an extension section, wherein the extension section is used for extending the conveying length of the chute body, the chute body comprises two inclined chute sections which are distributed in an inverted V shape, the ends, close to each other, of the two inclined chute sections are hinged with each other, the ends, far away from each other, of the two inclined chute sections are detachably connected with the extension section, the support frame comprises a vertical support rod used for supporting the inclined chute sections and a transverse support rod connected with the vertical support rod, the end, far away from the inclined chute sections, of the vertical support rod is hinged with the inclined chute sections; the extension section comprises an extension section body and a support connecting rod arranged on the extension section body, and the support connecting rod is hinged with the extension section body.
As the utility model relates to a channel concrete pours further optimization of chute fast: the vertical supporting rod, the transverse supporting rod and the supporting connecting rod are telescopic rods.
As the utility model relates to a channel concrete pours further optimization of chute fast: vertical bracing piece, vertical bracing piece and support link all establish the support sleeve outside adjusting the pole including adjusting pole and cover, have seted up the perforation on the regulation pole, wear to be equipped with the locating pin in this perforation, and a plurality of regulation holes that supply the locating pin to pass are seted up to the symmetry on the support sleeve.
As the utility model relates to a channel concrete pours further optimization of chute fast: the positioning pin is a pin shaft connected with the middle through a spring.
As the utility model relates to a channel concrete pours further optimization of chute fast: the adjusting rod is a hollow rod, and the end parts of the positioning pins and the springs are all provided with annular limiting plates.
As the utility model relates to a channel concrete pours further optimization of chute fast: the extension section is detachably connected with the two inclined chute sections through bolts.
As the utility model relates to a channel concrete pours further optimization of chute fast: and the far end part of the transverse supporting rod is provided with a longitudinal baffle.
As the utility model relates to a channel concrete pours further optimization of chute fast: the chute body and the extension section body are U-shaped grooves, bamboo glue boards are adopted at the bottoms of the chute body and the extension section body, and side boards of the chute body and the extension section body are made of wood boards.
As the utility model relates to a channel concrete pours further optimization of chute fast: and a longitudinal supporting rod stretching across the chute body is fixed at one end of the vertical supporting rod close to the inclined chute section.
Advantageous effects
One, the utility model discloses a chute is pour fast to channel concrete, simple structure, the equipment of being convenient for adopts the channel both sides to pour simultaneously, improves the efficiency of construction greatly, and two sides are pour simultaneously and are reduced the risk of running the mould than unilateral pouring, improve concrete placement quality and construction speed, and the chute body is two oblique chute sections of mutual articulated moreover, the chute transportation of being convenient for.
Two, the setting of a plurality of extension sections has strengthened the utility model discloses a commonality need not to carry out the customization according to the channel construction of difference at every turn and builds, only needs to construct installation extension section according to actual channel, adopts bolted connection, and the mounting means is simple, further improves the construction progress, and the construction need not to build again and pour the chute at every turn simultaneously, improves cyclic utilization, has reduced construction cost, has also reduced the cost of transportation of chute.
But vertical support rod, horizontal bracing piece and supporting link all adopt telescopic link, can adjust according to actual channel construction conditions, have improved steadiness, the reliability of pouring the chute greatly.
Drawings
FIG. 1 is a schematic structural view of a channel concrete rapid pouring chute;
FIG. 2 is a schematic structural view of a chute body;
FIG. 3 is a schematic view of an extension;
FIG. 4 is a schematic view of the structure of the vertical support bar, the horizontal support bar and the support link;
the labels in the figure are: 1. chute body, 101, oblique chute section, 2, horizontal bracing piece, 3, vertical support rod, 4, longitudinal baffle, 5, connect the fastener, 6, longitudinal support rod, 7, extension, 701, extension body, 702, supporting rod, 8, support sleeve, 9, adjust the pole, 10, regulation hole, 11, locating pin, 12, spring, 13, limiting plate.
Detailed Description
The following detailed description of the preferred embodiments of the present invention is provided in connection with the accompanying drawings.
As shown in fig. 1-4: the utility model provides a chute is pour fast to channel concrete, includes chute body 1, support frame and the extension section 7 that is used for extension chute body 1 transport length, and the equipment is simple, reliable, and the practicality is high.
The chute body 1 comprises two inclined chute sections 101 which are distributed in an inverted V shape, the two sides are arranged according to channel side walls, pouring needs are divided into left and right sides, the two inclined chute sections 101 correspond to the two sides of a channel respectively, pouring can be conducted simultaneously, and the risk of mold running is reduced. The ends, close to each other, of the two chute sections 101 are hinged to each other, and the two chute sections 101 are hinged to each other through a rotating shaft so as to adapt to different widths of different channels and facilitate construction. The mounting hole has been seted up to the one end that two oblique chute sections 101 kept away from each other, supplies extension segment 7 can dismantle the connection, according to actual construction demand, connects the extension segment 7 of corresponding quantity.
The support frame includes a plurality of vertical support rods 3 and horizontal bracing piece 2, vertical support rod 3 is used for supporting chute section 101, horizontal bracing piece 2 and vertical support rod 3 keep away from the one end of chute section 101 and connect, a plurality of vertical support rods 3 are respectively along the length direction evenly distributed of two chute sections 101, in order to keep the stability of two chute sections 101, in the length direction evenly distributed along chute section 101, vertical support rod 3 is along the width direction evenly distributed of chute section 101. Considering cost and construction requirements, two vertical support rods 3 are arranged along the width direction of the chute section 101, and the two vertical support rods 3 are arranged at the position, close to the outer side, of the chute section 101, so that the chute section 101 is high in bearing capacity and stability. In order to strengthen the stability of the pouring chute, one end of the vertical support rod 3 close to the chute section 101 is fixed with a longitudinal support rod 6 crossing the chute body 1.
Vertical support bar 3 is connected with chute section 101 hinge, and a plurality of connecting fastener 5 are evenly installed along its length direction to chute section 101's both sides, and vertical support bar 3 is connected with connecting fastener 5 hinge, lies in chute section 101 with the vertical support bar 3 of one side, and the one end of keeping away from chute section 101 is connected with horizontal bracing piece 2, and vertical support bar 3 is connected through connecting fastener 5 with horizontal bracing piece 2. The chute section 101, the vertical supporting rod 3 and the transverse supporting rod 2 are connected together through the connecting fastener 5, so that the disassembly and the assembly of workers are convenient, and the transportation is also facilitated.
According to the different construction conditions of different channels, channel width and the high different isopenistic of difference, chute body 1 need adapt to different channel construction size, and extension section 7 is connected to the one end that two oblique chute sections 101 kept away from each other in chute body 1, increases its distance of carrying concrete, avoids the too big segregation phenomenon that produces of concrete placement face distance that falls at concrete placement in-process concrete. Extension 7 includes extension body 701 and the support connecting rod 702 of setting on extension body 701, and support connecting rod 702 and extension body 701 hinge joint, extension 7 and chute section 101 pass through the bolt can dismantle the connection, connects the extension 7 of a certain quantity according to actual construction conditions, if the transport length of chute body 1 just accords with required transport length when actually being under construction, then need not to connect extension 7.
When required transport length is greater than chute body 1's transport length, the connection extension section 7 can be dismantled to the one end that two oblique chute sections 101 kept away from each other, the height and the width of pouring the chute this moment are bigger than chute body 1, only the supporting rod 702 of terminal extension section 7 plays the supporting role, chute body 1's vertical support bar 3, horizontal support bar 2 can't contact ground and play the effect of actual support, it is unstable to lead to pouring the chute, the slope can take place in concrete transportation process, thereby cause the concrete part to break away from pouring the chute. In order to solve the problem, the vertical support rod 3, the horizontal support rod 2 and the support connecting rod 702 are telescopic rods, and the length of the vertical support rod, the horizontal support rod 2 and the support connecting rod 702 can be changed according to the height of a pouring chute, so that the effect of stable support can be achieved.
Vertical support rod 3, vertical support rod 6 and support connecting rod 702 all include adjust the pole 9 and the cover establishes the support sleeve 8 outside adjusting the pole 9, have seted up the perforation on adjusting the pole 9, wear to be equipped with locating pin 11 in this perforation, and a plurality of regulation holes 10 that supply locating pin 11 to pass are seted up to the symmetry on the support sleeve 8. Through the arrangement of the positioning pin 11, the vertical supporting rod 3, the longitudinal supporting rod 6 and the supporting connecting rod 702 can be fixed at a required length and cannot be in a freely telescopic state. In addition, the positions and the number of the corresponding adjusting holes 10 can be set according to the actual channel construction standard and the construction range so as to meet the length required by most of channel construction, and if the channel size span is large, the vertical supporting rods 3, the longitudinal supporting rods 6 and the supporting connecting rods 702 of several types can be set so as to meet the actual construction requirement.
The positioning pin 11 is a pin shaft connected with the middle through a spring 12, when the length of the vertical support rod 3, the longitudinal support rod 6 or the support connecting rod 702 needs to be adjusted, the two ends of the positioning pin 11 are pressed simultaneously, the positioning pin 11 is located in the support sleeve 8, the adjusting rod 9 is pulled to move to a proper position, and the end of the positioning pin 11 automatically pops out of the support sleeve 8 through the adjusting hole 10. In the moving process of the adjusting rod, the end part of the positioning pin 11 slides in the supporting sleeve 8, in order to facilitate the sliding of the positioning pin 11, the outer end part of the positioning pin 11 is of a hemispherical structure, and meanwhile, a sliding groove is arranged on the inner wall of the supporting sleeve 8 in a matched mode. In order to save materials, the adjusting rod 9 is a hollow rod, and in this case, in order to avoid the positioning pin 11 from being separated from the adjusting rod, the ends of the positioning pin 11 connected with the springs 12 are provided with annular limiting plates 13 for restraining the positions of the positioning pins 11.
Because the width of the side wall of the channel is smaller, the end part far away from the transverse supporting rod 2 is provided with the longitudinal baffle 4, so that concrete can be conveniently fed. Considering the environmental protection problem, chute body 1 and extension section body 701 are the U-shaped groove, and the tank bottom of chute body 1 and extension section body 701 all adopts the bamboo plywood, and the curb plate of chute body 1 and extension section body 701 is the wooden board, all can recycle, accords with the environmental protection requirement of green construction.
The utility model discloses a use method does:
1. the number of the extension sections 7 is determined according to the channel size and the site construction conditions.
2. The channel concrete rapid pouring chute is assembled before construction, and the operation platform of the assembling device is accurately positioned according to the channel size.
3. And concrete is subjected to concrete warehousing construction of side walls on two sides through the assembled chute.
The above description is only a preferred embodiment of the present invention, and the present invention is not limited to the above description in any form, and although the present invention has been disclosed with the preferred embodiment, it is not limited to the present invention, and any skilled person in the art can make some modifications or modifications to equivalent embodiments of the same changes without departing from the technical scope of the present invention, but all the technical matters of the present invention are within the scope of the technical solution of the present invention.

Claims (9)

1. The utility model provides a chute is pour fast to channel concrete which characterized in that: the chute comprises a chute body (1), a support frame and an extension section (7) used for extending the conveying length of the chute body (1), wherein the chute body (1) comprises two inclined chute sections (101) which are distributed in an inverted V shape, the ends, close to each other, of the two inclined chute sections (101) are hinged to each other, the end, far away from each other, of the two inclined chute sections (101) is detachably connected with the extension section (7), the support frame comprises a vertical support rod (3) used for supporting the inclined chute sections (101) and a transverse support rod (2) connected with the end, far away from the inclined chute sections (101), of the vertical support rod (3), and the inclined chute sections (101) are hinged to each other; the extension section (7) comprises an extension section body (701) and a support connecting rod (702) arranged on the extension section body (701), and the support connecting rod (702) is hinged with the extension section body (701).
2. The channel concrete rapid pouring chute as claimed in claim 1, wherein: the vertical supporting rod (3), the transverse supporting rod (2) and the supporting connecting rod (702) are all telescopic rods.
3. The channel concrete rapid pouring chute as claimed in claim 2, wherein: vertical support rod (3), vertical support rod (6) and support connecting rod (702) all include adjust pole (9) and cover establish support sleeve (8) outside adjusting pole (9), have seted up the perforation on adjusting pole (9), wear to be equipped with locating pin (11) in this perforation, and a plurality of regulation holes (10) that supply locating pin (11) to pass are seted up to the symmetry on support sleeve (8).
4. The channel concrete rapid pouring chute as claimed in claim 3, wherein: the positioning pin (11) is a pin shaft connected with the middle through a spring (12).
5. The channel concrete rapid pouring chute as claimed in claim 4, wherein: the adjusting rod (9) is a hollow rod, and annular limiting plates (13) are arranged at the end parts of the positioning pins (11) connected with the springs (12).
6. The channel concrete rapid pouring chute as claimed in claim 1, characterized in that: the extension section (7) is detachably connected with the two chute sections (101) through bolts.
7. The channel concrete rapid pouring chute as claimed in claim 1, wherein: the far end part of the transverse supporting rod (2) is provided with a longitudinal baffle (4).
8. The channel concrete rapid pouring chute as claimed in claim 1, wherein: the chute body (1) and the extension section body (701) are both U-shaped grooves, the bottoms of the chute body (1) and the extension section body (701) are both made of bamboo plywood, and the side plates of the chute body (1) and the extension section body (701) are made of wood boards.
9. The channel concrete rapid pouring chute as claimed in claim 1, wherein: one end of the vertical supporting rod (3) close to the inclined chute section (101) is fixedly provided with a longitudinal supporting rod (6) crossing the chute body (1).
CN202221033088.3U 2022-04-29 2022-04-29 Channel concrete pours chute fast Expired - Fee Related CN217460577U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221033088.3U CN217460577U (en) 2022-04-29 2022-04-29 Channel concrete pours chute fast

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221033088.3U CN217460577U (en) 2022-04-29 2022-04-29 Channel concrete pours chute fast

Publications (1)

Publication Number Publication Date
CN217460577U true CN217460577U (en) 2022-09-20

Family

ID=83272944

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221033088.3U Expired - Fee Related CN217460577U (en) 2022-04-29 2022-04-29 Channel concrete pours chute fast

Country Status (1)

Country Link
CN (1) CN217460577U (en)

Similar Documents

Publication Publication Date Title
CN207315404U (en) Municipal tunnel big cross section culvert and piping lane trolley
CN208152546U (en) The tall and big formwork system of aluminum alloy mould plate
CN217460577U (en) Channel concrete pours chute fast
CN110284904B (en) Lining trolley and construction method thereof
CN113356268A (en) Integrated movable type formwork system for comprehensive pipe rack
CN203582015U (en) Small brick stacking machine
CN105401960A (en) Formwork for railway tunnel inverted arch construction and construction method of formwork
CN211397592U (en) Adjustable template of high-speed railway double-track tunnel lining trolley
CN205063965U (en) A die carrier for construction of railway tunnel inverted arch
CN217327341U (en) Self-propelled long-span variable cross-section hydraulic formwork trolley
CN201394642Y (en) Double-row type grinding section automatic casting machine
CN214272109U (en) Ground beam formwork device
CN211597706U (en) Single side wall formwork device
CN213391217U (en) Building stair template structure
CN210758367U (en) Prefabricated component curing kiln
CN112377218A (en) Tunnel formwork support combined sliding rail truss support lattice system
CN205777523U (en) A kind of aluminum alloy pattern plate fastening structure
CN213562539U (en) Adjustable concrete prefabricated part storage support
CN218803635U (en) Auxiliary feeding device for injection molding machine
CN102251480B (en) Small pier top construction triangular hanging basket
CN216427858U (en) Linear adjusting template device for post-cast section of curved track beam
CN221566857U (en) Cable tower concrete placement cloth machine
CN215564412U (en) Heat absorption tower derrick-free slip form construction platform
CN215202577U (en) Prefabricated U type stand mould slides
CN221297515U (en) A fender support frame for road construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20220920

CF01 Termination of patent right due to non-payment of annual fee