CN217400916U - Underground excavation station construction moving formwork for underground railway underpass - Google Patents

Underground excavation station construction moving formwork for underground railway underpass Download PDF

Info

Publication number
CN217400916U
CN217400916U CN202221238040.6U CN202221238040U CN217400916U CN 217400916 U CN217400916 U CN 217400916U CN 202221238040 U CN202221238040 U CN 202221238040U CN 217400916 U CN217400916 U CN 217400916U
Authority
CN
China
Prior art keywords
rod
sleeve
base
fixing
slide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202221238040.6U
Other languages
Chinese (zh)
Inventor
孙怀宝
黄涛
韩方谨
王文辉
吴志
向思奥
曹攀龙
解令令
黄瑞麟
张云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fourth Engineering Co Ltd Of China Raiway First Group
Original Assignee
Fourth Engineering Co Ltd Of China Raiway First Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Engineering Co Ltd Of China Raiway First Group filed Critical Fourth Engineering Co Ltd Of China Raiway First Group
Priority to CN202221238040.6U priority Critical patent/CN217400916U/en
Application granted granted Critical
Publication of CN217400916U publication Critical patent/CN217400916U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00—Energy generation through renewable energy sources
    • Y02E10/20—Hydro energy

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

本实用新型公开了地铁下穿暗挖车站施工移动模架,属于地铁施工技术领域,包括底座,所述底座的表面安装有辅助组件,所述底座一侧设置有支撑座,所述支撑座的顶部安装有紧刹组件,本实用新型通过设置辅助组件,推动连接滑座使连接块滑入固定套内并带动连接头贴于通槽外口,先转动连接头将其旋入通槽内,然后再将螺栓旋入固定套与连接块内部可完成连接滑座与底座之间的连接固定,使连接滑座于一侧支撑可与另一侧支撑座相互配合使架体平稳移动;本实用新型通过设置紧刹组件,转动螺杆可使固定板带动固定杆与杆套下移,使固定杆落于地面后便可使装置完成紧刹,滑杆弹簧的弹性作用力可很好的与地面接触增大摩擦力。

Figure 202221238040

The utility model discloses a mobile formwork for the construction of a subway underpassing underground excavation station, which belongs to the technical field of subway construction. A tight brake assembly is installed on the top of the utility model. By setting an auxiliary assembly, the utility model pushes the connecting sliding seat to make the connecting block slide into the fixed sleeve and drives the connecting head to be attached to the outer opening of the through groove. First, the connecting head is rotated to be screwed into the through groove. Then, screw the bolts into the fixing sleeve and the inside of the connecting block to complete the connection and fixation between the connecting slide and the base, so that the connecting slide can be supported on one side and can cooperate with the support on the other side to make the frame body move smoothly; The new type is equipped with a tight brake assembly, and by rotating the screw, the fixed plate can drive the fixed rod and the rod sleeve to move down, so that the device can complete the tight brake after the fixed rod falls on the ground, and the elastic force of the sliding rod spring can be well connected to the ground. Contact increases friction.

Figure 202221238040

Description

Underground excavation station construction moving formwork for underground railway underpass
Technical Field
The utility model belongs to the technical field of the subway construction, concretely relates to subway is worn secretly and is dug station construction moving die carrier down.
Background
The mold frame is a semi-finished product of the mold and is composed of various steel plates matched with parts, so to speak, the framework of the whole set of the mold. The construction method of the subway station comprises an open excavation method, a cover excavation method and a subsurface excavation method. When the station passes through a busy traffic section, or the traffic of a closed road is not allowed for other reasons, or the station is positioned in a more complete rock stratum and underground water does not develop, the underground excavation method can be adopted for construction. The underground excavation method is widely used as a shield method, a pipe jacking method, a mining method, and the like. The construction process of the underground excavation station of the subway needs to support the cast-in-place station plate through the formwork.
In the subway underground excavation station construction moving die carrier disclosed in the Chinese patent application No. 202111381801.3, because the die carrier is in the vertical state, the whole center of the device is excessively deviated to the die carrier, the device is extremely easy to topple over in the moving process, the bolt rods are installed at the four corners of the base and are used for positioning and braking, the operation of screwing each other is excessively complicated, and the use is time-consuming and labor-consuming.
SUMMERY OF THE UTILITY MODEL
To solve the problems set forth in the background art described above. The utility model provides a wear undercut station construction moving die carrier under subway has convenient to use, stable in structure's characteristics.
In order to achieve the above object, the utility model provides a following technical scheme: the movable formwork for construction of the underground excavation station under the subway comprises a base, wherein a frame body is installed at the top of the base, a supporting seat is arranged on one side of the base, and an auxiliary assembly is installed on the surface of the base;
the auxiliary assembly is including connecting slide, fixed cover, leading to groove, connector and vaulting pole, the surface mounting of base has fixed cover, the opposite side of base is provided with connects the slide, one side of connecting the slide is connected with the connecting block, connect the top of slide and install two vaulting poles, the one end of vaulting pole all is connected with the connector, logical groove has all been seted up on the both sides surface of support body.
Preferably, two be connected with the anchor strut between the vaulting pole, closely laminate between the surface of connecting block and the inner wall of fixed cover, be sliding connection between connecting block and the fixed cover, two bolts have been inlayed with the inside of fixed cover to the connecting block.
Preferably, the one end of connector all is connected with the turning block, be rotation connection between connector and the vaulting pole, be the thread engagement between the other end of connector and the logical groove and be connected.
Preferably, the top of supporting seat is installed and is tightly stopped the subassembly, the subassembly of tightly stopping including rod cover, dead lever, screw rod and fixed plate, the screw rod is installed at the top of supporting seat, the surface cover of screw rod has the fixed plate, the both ends bottom of fixed plate all is connected with two rod covers, the fixed plate bottom of screw rod both sides all is connected with the dead lever.
Preferably, the bottom of the screw rod is sleeved with a rotating seat, the screw rod is rotatably connected with the supporting seat, the screw rod is in threaded engagement with the fixed plate, and the rod sleeve, the fixed rod and the supporting seat are in sliding connection.
Preferably, a sliding rod is embedded in the rod sleeve, the top of the sliding rod is connected with a spring, and the sliding rod is in sliding connection with the rod sleeve.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses a set up auxiliary assembly, promote to connect the slide and drive in the connecting block slides in fixed cover, can drive the connector simultaneously and paste in the outer mouthful that leads to the groove, rotate the connector and can accomplish under the meshing of connector and logical groove and connect fixedly at the top between connecting slide and the support body, it is fixed to accomplish the bottom between connecting slide and the base with the fixed cover of bolt screw in and the connecting block is inside again, the messenger is connected the slide and can mutually support with opposite side supporting seat in one side and make the support body steadily remove.
2. The utility model discloses a set up the subassembly of tightly stopping, rotate the screw rod and can be connected down at the meshing between screw rod and the fixed plate, make the fixed plate drive dead lever and rod cover move down, the inside slide bar of rod cover falls on ground earlier under the elastic force of spring, make the dead lever fall on ground after alright make the device accomplish tightly stop, the slide bar can be fine with ground contact increase frictional force.
Drawings
Fig. 1 is a front view of the present invention;
FIG. 2 is a side cross-sectional view of the auxiliary assembly of the present invention;
fig. 3 is a cross-sectional view of the support seat of the present invention.
In the figure: 1. a frame body; 2. a base; 3. an auxiliary component; 31. connecting the sliding seat; 32. connecting blocks; 33. Fixing a sleeve; 34. a bolt; 35. a through groove; 36. a connector; 37. rotating the block; 38. a stay bar; 4. A supporting seat; 5. a tight brake assembly; 51. a rotating seat; 52. a slide bar; 53. a spring; 54. a rod sleeve; 55. Fixing the rod; 56. a screw; 57. and (7) fixing the plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example 1
Referring to fig. 1-3, the present invention provides the following technical solutions: the movable formwork for construction of the underground excavation station under the subway comprises a base 2, wherein a frame body 1 is installed at the top of the base 2, a supporting seat 4 is arranged on one side of the base 2, and an auxiliary assembly 3 is installed on the surface of the base 2;
the auxiliary assembly 3 comprises a connecting slide seat 31, a fixing sleeve 33, a through groove 35, a connector 36 and support rods 38, the surface of the base 2 is provided with the fixing sleeve 33, the other side of the base 2 is provided with the connecting slide seat 31, one side of the connecting slide seat 31 is connected with a connecting block 32, the top of the connecting slide seat 31 is provided with the two support rods 38, one end of each support rod 38 is connected with the connector 36, and the surfaces of the two sides of the frame body 1 are provided with the through groove 35.
Specifically, a reinforcing rod is connected between the two support rods 38, the surface of the connecting block 32 is tightly attached to the inner wall of the fixing sleeve 33, the connecting block 32 is slidably connected with the fixing sleeve 33, and the two bolts 34 are embedded in the connecting block 32 and the fixing sleeve 33.
By adopting the technical scheme, the bolt 34 is screwed into the fixed sleeve 33 and the connecting block 32 to complete the bottom connection and fixation between the connecting slide seat 31 and the base 2.
Specifically, one end of the connector 36 is connected to the rotating block 37, the connector 36 is rotatably connected to the stay bar 38, and the other end of the connector 36 is in threaded engagement with the through groove 35.
By adopting the above technical scheme, the rotary connector 36 can complete the top connection and fixation between the connecting slide seat 31 and the frame body 1 under the engagement connection of the connector 36 and the through groove 35.
When the device is used, the connecting slide 31 is pushed to drive the connecting block 32 to slide into the fixing sleeve 33, the connecting head 36 is synchronously driven to stick to the outer opening of the through groove 35, the top connection and fixation between the connecting slide 31 and the frame body 1 can be completed by rotating the connecting head 36 under the meshing connection between the connecting head 36 and the through groove 35, and then the bolt 34 is screwed into the fixing sleeve 33 and the connecting block 32 to complete the bottom connection and fixation between the connecting slide 31 and the base 2, so that the connecting slide 31 can be supported on one side and can be matched with the supporting seat 4 on the other side, and the frame body 1 can stably move;
example 2
The present embodiment is different from embodiment 1 in that: tight subassembly 5 of stopping is installed at the top of supporting seat 4, and tight subassembly 5 of stopping is including rod cover 54, dead lever 55, screw rod 56 and fixed plate 57, and screw rod 56 is installed at the top of supporting seat 4, and the surface cover of screw rod 56 has fixed plate 57, and the both ends bottom of fixed plate 57 all is connected with two rod covers 54, and the fixed plate 57 bottom of screw rod 56 both sides all is connected with dead lever 55.
Specifically, the bottom of the screw 56 is sleeved with the rotating seat 51, the screw 56 is rotatably connected with the supporting seat 4, the screw 56 is in threaded engagement with the fixing plate 57, and the rod sleeve 54, the fixing rod 55 and the supporting seat 4 are in sliding connection.
By adopting the above technical scheme, the fixing plate 57 can drive the fixing rod 55 and the rod sleeve 54 to move downwards by rotating the screw 56, so that the device can complete tight braking after the fixing rod 55 falls on the ground.
Specifically, the inside of the rod sleeve 54 is embedded with a sliding rod 52, the top of the sliding rod 52 is connected with a spring 53, and the sliding rod 52 is in sliding connection with the rod sleeve 54.
By adopting the technical scheme, the sliding rod 52 can be well contacted with the ground under the elastic acting force of the spring 53 to increase the friction force.
When the device is used in the embodiment, the screw rod 56 can be rotated when the device needs to be fixed in position, the fixing plate 57 can drive the fixing rod 55 and the rod sleeve 54 to move downwards under the meshing connection between the screw rod 56 and the fixing plate 57, the sliding rod 52 in the rod sleeve 54 falls on the ground under the elastic action of the spring 53, the device can complete tight braking after the fixing rod 55 falls on the ground, and the sliding rod 52 can be well contacted with the ground to increase friction force.
The utility model provides a support body 1, base 2 and supporting seat 4's structure and theory of use have disclosed in the subway undercut station construction moving die carrier that china patent application number is 202111381801.3 discloses.
The utility model discloses a theory of operation and use flow: when the utility model is used, after the connection and assembly between the base 2, the supporting seat 4 and the frame body 1 are completed, the connecting slide seat 31 is pushed to drive the connecting block 32 to slide into the fixing sleeve 33, the connecting head 36 can be synchronously driven to stick to the outer opening of the through groove 35, the top connection and fixation between the connecting slide seat 31 and the frame body 1 can be completed by rotating the connecting head 36 under the meshing connection between the connecting head 36 and the through groove 35, then the bolt 34 is screwed into the fixing sleeve 33 and the connecting block 32 to complete the bottom connection and fixation between the connecting slide seat 31 and the base 2, the connecting slide seat 31 can be mutually matched with the supporting seat 4 at one side to ensure the frame body 1 to stably move, the screw rod 56 can be rotated when the position of the device is fixed, the fixing plate 57 can drive the fixing rod 55 and the rod sleeve 54 to move downwards under the meshing connection between the screw rod 56 and the fixing plate 57, the slide rod 52 in the rod sleeve 54 falls on the ground under the elastic acting force of the spring 53, after the fixing rod 55 falls on the ground, the device can complete the tight braking, and the sliding rod 52 can well contact with the ground to increase the friction force.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1.地铁下穿暗挖车站施工移动模架,包括底座(2),其特征在于:所述底座(2)的顶部安装有架体(1),所述底座(2)一侧设置有支撑座(4),所述底座(2)的表面安装有辅助组件(3);1. The mobile formwork for underground tunneling station construction, comprising a base (2), characterized in that: a frame body (1) is installed on the top of the base (2), and a support is provided on one side of the base (2) a seat (4), an auxiliary component (3) is mounted on the surface of the base (2); 所述辅助组件(3)包括有连接滑座(31)、固定套(33)、通槽(35)、连接头(36)和撑杆(38),所述底座(2)的表面安装有固定套(33),所述底座(2)的另一侧设置有连接滑座(31),所述连接滑座(31)的一侧连接有连接块(32),所述连接滑座(31)的顶部安装有两个撑杆(38),所述撑杆(38)的一端均连接有连接头(36),所述架体(1)的两侧表面均开设有通槽(35)。The auxiliary assembly (3) includes a connecting slide (31), a fixing sleeve (33), a through groove (35), a connecting head (36) and a strut (38), and the surface of the base (2) is mounted with a A fixing sleeve (33), the other side of the base (2) is provided with a connecting slide (31), one side of the connecting slide (31) is connected with a connecting block (32), and the connecting slide ( 31) two struts (38) are installed on the top of the strut (38), one end of the struts (38) is connected with a connector (36), and both sides of the frame body (1) are provided with through grooves (35). ). 2.根据权利要求1所述的地铁下穿暗挖车站施工移动模架,其特征在于:两个所述撑杆(38)之间连接有加固杆,所述连接块(32)的表面与固定套(33)的内壁之间紧密贴合,所述连接块(32)与固定套(33)之间为滑动连接,所述连接块(32)与固定套(33)的内部嵌有两个螺栓(34)。2. The mobile formwork for underpassing underground excavation station construction in subway according to claim 1, characterized in that: a reinforcing rod is connected between the two support rods (38), and the surface of the connecting block (32) is connected to the The inner walls of the fixing sleeve (33) are closely fitted, the connecting block (32) and the fixing sleeve (33) are in a sliding connection, and two inner walls of the connecting block (32) and the fixing sleeve (33) are embedded. bolts (34). 3.根据权利要求1所述的地铁下穿暗挖车站施工移动模架,其特征在于:所述连接头(36)的一端均连接有转动块(37),所述连接头(36)与撑杆(38)之间均为转动连接,所述连接头(36)的另一端与通槽(35)之间均为螺纹啮合连接。3. The mobile formwork for underpassing underground excavation station construction according to claim 1, characterized in that: one end of the connecting head (36) is connected with a rotating block (37), and the connecting head (36) is connected with the rotating block (37). The struts (38) are all connected in rotation, and the other end of the connecting head (36) and the through groove (35) are all connected by threaded engagement. 4.根据权利要求1所述的地铁下穿暗挖车站施工移动模架,其特征在于:所述支撑座(4)的顶部安装有紧刹组件(5),所述紧刹组件(5)包括有杆套(54)、固定杆(55)、螺杆(56)和固定板(57),所述支撑座(4)的顶部安装有螺杆(56),所述螺杆(56)的表面套有固定板(57),所述固定板(57)的两端底部均连接有两个杆套(54),所述螺杆(56)两侧的固定板(57)底部均连接有固定杆(55)。4. The mobile formwork for the construction of subway underpassing underground excavation station according to claim 1, characterized in that: a tight brake assembly (5) is installed on the top of the support base (4), and the tight brake assembly (5) It includes a rod sleeve (54), a fixing rod (55), a screw rod (56) and a fixing plate (57). There is a fixing plate (57), two rod sleeves (54) are connected to the bottom of both ends of the fixing plate (57), and fixing rods (54) are connected to the bottom of the fixing plate (57) on both sides of the screw (56). 55). 5.根据权利要求4所述的地铁下穿暗挖车站施工移动模架,其特征在于:所述螺杆(56)的底部套有转动座(51),所述螺杆(56)与支撑座(4)之间为转动连接,所述螺杆(56)与固定板(57)之间为螺纹啮合连接,所述杆套(54)、固定杆(55)与支撑座(4)之间均为滑动连接。5. The mobile formwork for underpassing underground excavation station construction according to claim 4, characterized in that: the bottom of the screw (56) is covered with a rotating seat (51), and the screw (56) and the support seat ( 4) is a rotational connection, the screw (56) and the fixing plate (57) are connected by a threaded engagement, and the rod sleeve (54), the fixing rod (55) and the support seat (4) are all connected with each other. Slide to connect. 6.根据权利要求4所述的地铁下穿暗挖车站施工移动模架,其特征在于:所述杆套(54)的内部均嵌有滑杆(52),所述滑杆(52)的顶部均连接有弹簧(53),所述滑杆(52)与杆套(54)之间为滑动连接。6. The mobile formwork for underpassing underground excavation station construction according to claim 4, characterized in that: a sliding rod (52) is embedded in the inside of the rod sleeve (54), and the sliding rod (52) is The tops are all connected with springs (53), and the sliding rod (52) and the rod sleeve (54) are slidingly connected.
CN202221238040.6U 2022-05-20 2022-05-20 Underground excavation station construction moving formwork for underground railway underpass Expired - Fee Related CN217400916U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221238040.6U CN217400916U (en) 2022-05-20 2022-05-20 Underground excavation station construction moving formwork for underground railway underpass

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221238040.6U CN217400916U (en) 2022-05-20 2022-05-20 Underground excavation station construction moving formwork for underground railway underpass

Publications (1)

Publication Number Publication Date
CN217400916U true CN217400916U (en) 2022-09-09

Family

ID=83144923

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221238040.6U Expired - Fee Related CN217400916U (en) 2022-05-20 2022-05-20 Underground excavation station construction moving formwork for underground railway underpass

Country Status (1)

Country Link
CN (1) CN217400916U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115925371A (en) * 2023-01-13 2023-04-07 中交一公局集团有限公司 A kind of ultra-high performance concrete containing coarse aggregate and its preparation method
DE202023102796U1 (en) 2023-05-22 2023-06-19 China Railway Seventh Bureau Group Co., Ltd Multifunctional mobile formwork frame

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115925371A (en) * 2023-01-13 2023-04-07 中交一公局集团有限公司 A kind of ultra-high performance concrete containing coarse aggregate and its preparation method
DE202023102796U1 (en) 2023-05-22 2023-06-19 China Railway Seventh Bureau Group Co., Ltd Multifunctional mobile formwork frame

Similar Documents

Publication Publication Date Title
CN110695825A (en) Production device of nodular cast iron pipe fitting
CN209114455U (en) A high-efficiency leveling device for foundations used in building construction
CN101148990A (en) Suspension-type stepping self-moving advanced support for underground roadway
CN217300623U (en) Temporary support device for coal mine roadway excavation
CN217999616U (en) A movable trolley for culvert construction
CN210141146U (en) Narrow body rotary four-arm jumbolter for coal mine
CN217680351U (en) Highway bridge construction platform
CN209921104U (en) Intelligent mobile electric vehicle charging pile group system
CN115638000B (en) Primary support hole entering reinforcing structure for underground excavation construction of large section of subway
CN110593603A (en) Civil engineering building pillar
CN221220524U (en) Colliery hydraulic support
CN211948358U (en) Tamping device for earthwork engineering
CN111749712B (en) A kind of tunnel construction equipment
CN115478878A (en) A walking trolley for rapid construction of culverts and its use method
CN213148366U (en) Soil sampling device for highway engineering
CN210858761U (en) A safety support structure for underground mining in coal mines
CN223317872U (en) A temporary support device for underground coal mine excavation working surface
CN218716815U (en) Tunnel construction safety device convenient to fixed steel bow member
CN208136748U (en) It is a kind of can warning at night municipal road and bridge security protection dedicated unit
CN224104860U (en) Hydraulic steering platform
CN216947681U (en) Change filling structure for improving roadbed bearing capacity
CN219100942U (en) Road protection structure for highway engineering construction
CN216033867U (en) Outdoor hidden new energy automobile fills electric pile
CN222797348U (en) Fixed door threshold assembly
CN217438874U (en) A soil sampling device for highway engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20220909