CN217400035U - Code member for reinforcing local stress of through-length transverse material and curtain wall - Google Patents

Code member for reinforcing local stress of through-length transverse material and curtain wall Download PDF

Info

Publication number
CN217400035U
CN217400035U CN202221199385.5U CN202221199385U CN217400035U CN 217400035 U CN217400035 U CN 217400035U CN 202221199385 U CN202221199385 U CN 202221199385U CN 217400035 U CN217400035 U CN 217400035U
Authority
CN
China
Prior art keywords
piece
sign indicating
indicating number
horizontal
code
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202221199385.5U
Other languages
Chinese (zh)
Inventor
邹积辉
王法智
卢学彬
朱敏峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Far East Intelligent Manufacturing (Zhuhai) Co.,Ltd.
Far East Lijin Curtain Wall Shanghai Co ltd
China Overseas Construction Ltd
Original Assignee
Far East Curtain Wall Zhuhai Co ltd
China Overseas Construction Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Far East Curtain Wall Zhuhai Co ltd, China Overseas Construction Ltd filed Critical Far East Curtain Wall Zhuhai Co ltd
Priority to CN202221199385.5U priority Critical patent/CN217400035U/en
Application granted granted Critical
Publication of CN217400035U publication Critical patent/CN217400035U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

本申请公开了一种加强通长横料局部受力的码件及幕墙,属于幕墙安装的技术领域。其包括插接于横料内的第一码件和第二码件,所述第一码件和第二码件围设形成有开口朝向下方设置的顶横梁插槽,顶横梁的一端插设于顶横梁插槽内。本申请方案通过在横料内侧安装多个第一码件和第二码件对横料进行加固,可以有效降低成本,节省材料费用以及开模成本,并且保障幕墙的受力要求。

Figure 202221199385

The application discloses a code piece and a curtain wall for strengthening the local force of a through-length horizontal material, belonging to the technical field of curtain wall installation. It includes a first code piece and a second code piece that are inserted into the cross material, the first code piece and the second code piece are surrounded by a top beam slot with an opening facing downward, and one end of the top beam is inserted. in the top beam slot. In the solution of the present application, by installing a plurality of first code pieces and second code pieces on the inner side of the transverse material to reinforce the transverse material, the cost can be effectively reduced, the material cost and the cost of mold opening can be saved, and the force requirement of the curtain wall can be guaranteed.

Figure 202221199385

Description

Code member for reinforcing local stress of through-length transverse material and curtain wall
Technical Field
The application relates to the technical field of curtain installation, especially, relate to a strengthen yard spare and curtain of logical long horizontal bar local atress.
Background
The building curtain wall is composed of a panel and a supporting structure, has certain displacement capacity relative to the main structure, and not only transmits the load borne by the main structure, but also surrounds the periphery of the main structure, so that the whole building achieves the beautiful effect.
In the related art, referring to fig. 1, in the field of building curtain walls, a full length rail 10 is generally vertical and is used for carrying objects or bearing pressure. However, in order to increase the compression resistance of the full length rail, it is common practice to increase the thickness of the full length rail, which often means an increase in cost.
Based on this, this application provides a piece things ready and curtain of strengthening logical long horizontal material local atress to solve above-mentioned technical problem.
SUMMERY OF THE UTILITY MODEL
In order to help strengthening the compressive capacity of logical long horizontal material, this application provides a yard spare and curtain of strengthening logical long horizontal material local atress.
The application provides a pair of strengthen logical long horizontal material local atress sign indicating number piece and curtain adopts following technical scheme:
first aspect of the invention
The utility model provides a strengthen logical long horizontal material local atress sign indicating number piece, includes first sign indicating number piece and the second sign indicating number piece of pegging graft in the horizontal material, first sign indicating number piece and second sign indicating number piece enclose to establish and are formed with the top crossbeam slot that the opening set up downwards, and the one end of top crossbeam is inserted and is located in the top crossbeam slot.
By adopting the technical scheme, the transverse material is reinforced by the first stacking piece and the second stacking piece, and the first stacking piece, the second stacking piece and the transverse material are directly spliced and installed, so that the installation efficiency can be effectively improved; compare in the way through thickening the compressive capacity of violently material in order to strengthen the violently material, this application scheme is consolidated the violently material through installing a plurality of first yards and second yards piece in the violently material inboard, can effective reduce cost, save material expense and die sinking cost to the atress requirement of guarantee curtain.
Optionally, the first yard of spare includes first yard of spare horizontal part and the vertical portion of first yard of spare, the one end of first yard of spare horizontal part and the vertical portion of first yard of spare is perpendicular to be linked to each other, the one end that the vertical portion of first yard of spare was kept away from to first yard of spare horizontal part is connected with the horizontal side joint of crosspiece, the one end of the vertical portion of first yard of spare is used for the vertical side joint with the crosspiece.
Through adopting above-mentioned technical scheme, make first sign indicating number piece wholly be the L type, be favorable to processing, reduce cost to the guarantee improves the compressive capacity of violently material to the reinforcement of violently material.
Optionally, the second sign indicating number piece includes second sign indicating number piece horizontal part and the vertical portion of second sign indicating number piece, the one end of the vertical portion of second sign indicating number piece horizontal part and second sign indicating number piece is perpendicular to be linked to each other, the horizontal side joint of the one end of the vertical portion of second sign indicating number piece and crosspiece is kept away from to second sign indicating number piece horizontal part, the one end of the vertical portion of second sign indicating number piece is used for the tip joint with the buckle.
Through adopting above-mentioned technical scheme, the second sign indicating number piece is whole to be the L type, sets up with first sign indicating number piece symmetry, makes first sign indicating number piece and second sign indicating number piece can effectively fix the crossbeam to this kind of structure simple structure, easily constructor equipment improves the installation effectiveness.
Optionally, horizontal inserting parts are arranged at the end parts of the first stacking part and the second stacking part in the horizontal direction, and the horizontal inserting parts are inserted into horizontal clamping grooves formed by the transverse material clamping parts and the transverse materials.
Through adopting above-mentioned technical scheme, utilize horizontal grafting portion to peg graft in horizontal buckle inslot, be favorable to improving the installation effectiveness to guarantee the steadiness of first yard of piece, second yard of piece installation on the horizontal material.
Optionally, one side of the horizontal insertion part, which is away from the transverse material, is provided with an inclined surface, and the inclined surface is inclined upwards towards the direction close to the transverse material buckling part.
Through adopting above-mentioned technical scheme, improved the convenience of first yard spare, second yard spare and violently material equipment, and then further promoted the efficiency of curtain unit mount.
Optionally, the end portions of the first code piece and the second code piece in the vertical direction are provided with vertical insertion portions, the vertical insertion portions of the first code piece are inserted into the end portions of the transverse materials, and the vertical insertion portions of the second code piece are inserted into the end portions of the pinch plates.
Through adopting above-mentioned technical scheme, during the curtain installation, first sign indicating number piece and violently material are assembled in advance, and reuse screw is fixed it on the major structure, then leans on one side of top crossbeam in the inboard of first sign indicating number piece, then pegs graft in violently the material with second sign indicating number piece, will utilize the buckle to fix second sign indicating number piece to utilize first sign indicating number piece and second sign indicating number piece realization fixed to the top crossbeam. The arrangement of the vertical insertion part ensures the stability of the first stacking piece and the second stacking piece inserted on the transverse material.
Optionally, one side of the first stacking piece and the second stacking piece facing the transverse material is provided with a stacking piece protrusion.
Through adopting above-mentioned technical scheme, utilize sign indicating number piece arch can improve the fastening nature that first sign indicating number piece, second sign indicating number piece and violently material are connected, make connection between them more closely, further improve firm effect, the equipment of also being convenient for simultaneously.
Second aspect of the invention
A code member for reinforcing the local stress of a through long transverse material is installed in the curtain wall.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the first stacking piece and the second stacking piece are used for reinforcing the transverse material, and the first stacking piece, the second stacking piece and the transverse material are directly spliced and installed, so that the installation efficiency can be effectively improved; compare in the way through thickening the compressive capacity of violently material in order to strengthen the violently material, this application scheme is consolidated the violently material through installing a plurality of first yards and second yards piece in the violently material inboard, can effective reduce cost, save material expense and die sinking cost to the atress requirement of guarantee curtain.
2. First sign indicating number piece and second sign indicating number piece can be according to the buckle structure of violently material and atress requirement adjustment tip shape and interface thickness, have the commonality.
3. The setting on inclined plane has improved the convenience of first sign indicating number piece and second sign indicating number piece grafting in the crosspiece, has improved grafting efficiency, and then has improved the holistic installation effectiveness of curtain.
Drawings
Fig. 1 is a schematic vertical sectional view of a transverse bar in the related art.
Fig. 2 is a schematic vertical sectional view of the overall structure of the embodiment of the present application.
Fig. 3 is a schematic view mainly showing the connection between the rail and the first stacking member in the embodiment of the present application.
Fig. 4 is a schematic diagram mainly showing a first code element according to an embodiment of the present application.
Fig. 5 is a schematic view of the first yard member and the second yard member mounted in the rail according to the embodiment of the present application.
Description of the reference numerals:
10. transverse material feeding; 1. transverse material feeding; 11. a horizontal connecting part of the horizontal material; 12. a horizontal material vertical connecting part; 13. a gusset plate connecting portion; 14. a first code member buckling part; 15. a transverse material buckling part; 2. a top beam; 3. a body structure; 31. transferring a code piece; 32. a top spacer; 4. a first code; 40. a first screw; 41. a first stacking member horizontal portion; 42. a first code member vertical portion; 43. a first code piece horizontal insertion part; 44. a first code piece vertical insertion part; 5. buckling the plate; 50. a second screw; 51. a buckle mounting part; 52. a gusset plate support portion; 53. a buckle plate buckling part; 54. the buckle plate is convex; 6. a second code; 61. a second code horizontal part; 62. a second stacking member vertical portion; 63. a second code horizontal plug-in part; 64. a second stacking member vertical insertion part; 7. the code piece is raised; 8. an inclined surface.
Detailed Description
The present application is described in further detail below with reference to figures 2-5.
In the related art, referring to fig. 2, in order to eliminate the structural deviation of the main structure 3, the adaptor code 31 is welded to the main structure 3, and the horizontal position and the elevation of the curtain wall unit are positioned. The bottom side of the transfer code piece 31 is adhered with a top isolation gasket 32, and one side of the top isolation gasket 32, which is far away from the transfer code piece, is provided with a transverse material 1.
Referring to fig. 2 and 3, the rail 1 includes rail horizontal connecting portion 11, rail vertical connecting portion 12 and buckle connecting portion 13, rail horizontal connecting portion 11 and the laminating of top spacer 32 level, rail vertical connecting portion 12 integrated into one piece keeps away from indoor one side in rail horizontal connecting portion 11, rail vertical connecting portion 12 links to each other with rail horizontal connecting portion 11 is perpendicular, rail vertical connecting portion 12 keeps away from one end integrated into one piece of rail horizontal connecting portion 11 and has first sign indicating number piece buckle portion 14, rail horizontal connecting portion 11 deviates from one side of top spacer 32 and is close to position integrated into one piece at its middle part and has rail buckle portion 15, be formed with first inserting groove between rail buckle portion 15 and first sign indicating number piece buckle portion 14.
The embodiment of the application discloses a piece of sign indicating number of reinforcing logical long horizontal material local atress.
Referring to fig. 3 and 4, a first code piece 4 is inserted into the first slot, the first code piece 4 includes a first code piece horizontal portion 41 and a first code piece vertical portion 42, one end of the first code piece horizontal portion 41 is integrally formed with and vertically connected to the first code piece vertical portion 42, a first code piece horizontal insertion portion 43 is integrally formed at an end portion of the first code piece horizontal portion 41, and the first code piece horizontal insertion portion 43 is inserted into a first fastening groove formed by the transverse material fastening portion 15 and the transverse material horizontal connecting portion 11; a first code vertical insertion part 44 is formed on one side of the end part of the first code vertical part 42, and the first code vertical insertion part 44 is inserted into a second clamping groove formed by the first code clamping part 14 and the transverse material vertical connecting part 12.
With reference to fig. 2, the insertion mounting of the first code element 4 in the rail 1 is achieved by means of the features described above. After the first stacking member 4 and the rail 1 are assembled in advance, the first stacking member 4 and the rail 1 are mounted on the transfer stacking member 31 by using the first screw 40.
In the related art, referring to fig. 5, the buckle plate connecting portion 13 is integrally formed at one end of the horizontal connecting portion 11 of the rail, which is far away from the vertical connecting portion 12 of the rail, the buckle plate connecting portion 13 is vertically connected with the horizontal connecting portion 11 of the rail, and the buckle plate 5 is fixed at the end of the buckle plate connecting portion 13 through the second screw 50. Wherein, buckle 5 includes buckle installation department 51, buckle supporting part 52 and buckle portion 53, buckle installation department 51 and buckle supporting part 52 integrated into one piece, is formed with the buckle mounting groove that supplies the one end of buckle connecting portion 13 to wear to locate between buckle installation department 51 and the tip of buckle supporting part 52, and second screw 50 passes buckle installation department 51, buckle connecting portion 13 and buckle supporting part 52 and realizes the three and be connected. Meanwhile, the buckle plate buckling part 53 is integrally formed at one end of the buckle plate supporting part 52 far away from the transverse material 1, and a second inserting groove is formed between the buckle plate buckling part 53 and the transverse material buckling part 15.
Referring to fig. 5, a second stacking piece 6 is inserted into the second inserting groove, the second stacking piece 6 includes a second stacking piece horizontal portion 61 and a second stacking piece vertical portion 62, the second stacking piece horizontal portion 61 and the second stacking piece vertical portion 62 are integrally formed and vertically connected, a second stacking piece horizontal inserting portion 63 is integrally formed at an end portion of the second stacking piece horizontal portion 61, and the second stacking piece horizontal inserting portion 63 is inserted into a third buckling groove formed by the transverse material buckling portion 15 and the transverse material horizontal connecting portion 11; the side surface of the second stacking member vertical part 62 is abutted against the side surface of the pinch plate supporting part 52, and the pinch plate supporting part 52 is used for supporting the second stacking member vertical part 62; a second stacking piece vertical inserting part 64 is formed on one side of the end part of the second stacking piece vertical part 62, and the second stacking piece vertical inserting part 64 is inserted into a fourth clamping groove formed by the clamping plate supporting part 52 and the clamping plate clamping part 53; by utilizing the characteristics, the second stacking piece 6 is inserted and installed in the transverse material 1.
Referring to fig. 5, in order to further improve the stability of the first stacking piece 4 and the second stacking piece 6 inserted in the rail 1, a stacking piece protrusion 7 is integrally formed on one side of the first stacking piece horizontal portion 41 and the second stacking piece horizontal portion 61 facing the rail 1, and the stacking piece protrusion 7 abuts against the inner side of the rail 1. In addition, one side that first sign indicating number piece horizontal insertion part 43 and second sign indicating number piece horizontal insertion part 63 deviate from violently material 1 sets up to inclined plane 8, and inclined plane 8 upwards sets up towards the direction slope that is close to violently material buckle part 15 to improve first sign indicating number piece 4 and the stability of second sign indicating number piece 6 grafting in violently material 1. In order to improve the convenience of the subsequent insertion of the second stacking piece 6 in the transverse material 1, the installation position of the transverse material buckling part 15 is deviated to be close to the indoor space.
Referring to fig. 2, a transverse material 1 is a strip-shaped structure, a plurality of first code pieces 4 and second code pieces 6 with different lengths can be inserted into the inner side of the transverse material 1 at intervals according to requirements, a top beam slot with an opening facing downwards is formed in the first code pieces 4 and the second code pieces 6 in a surrounding mode, and one end of a top beam 2 is inserted into the top beam slot; during the installation, at first fix on switching code piece 31 according to the unwrapping wire location with violently material 1 and first code piece 4, use first screw 40 to run through first code piece 4 and violently material 1 from bottom to top and fix violently material 1 and first code piece 4 on switching code piece 31 afterwards.
Violently expect 1 and first sign indicating number piece 4 fixed back on switching sign indicating number piece 31, lean on one side of roof beam 2 in the side of first sign indicating number piece 4, peg graft second sign indicating number piece 6 in violently material 1 after that, and make the side butt roof beam 2 of second sign indicating number piece 6 the opposite side, then be connected buckle 5 with second sign indicating number piece 6 and violently material 1 respectively, one side tip that violently material 1 and buckle 5 are close to each other is connected with the both sides face sealing of roof beam 2, it is sealed to beat to glue at the receipts mouth department of violently material 1 and switching sign indicating number piece 31 at last.
The implementation principle of the code piece for strengthening the local stress of the through long transverse material is as follows: this application scheme can select the installation quantity of first sign indicating number piece 4 and second sign indicating number piece 6 according to the atress condition, and need not wholly thicken the effect in order to reach reinforcing compressive resistance to violence material 1, compare in traditional way, this application scheme is consolidated violently material 1 through installing a plurality of first sign indicating numbers pieces 4 and second sign indicating number piece 6 in 1 inboard of violently material, can effectively reduce cost, save material expense and die sinking cost, and the atress requirement of guarantee curtain.
The embodiment of the application also discloses a curtain wall, and a stacking piece for reinforcing the local stress of the through long transverse material is installed in the curtain wall.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: equivalent changes in structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides a strengthen logical long horizontal material local atress sign indicating number piece which characterized in that: including pegging graft in first yard spare (4) and second yard spare (6) of violently expecting (1), first yard spare (4) and second yard spare (6) enclose to establish and are formed with the top crossbeam slot that the opening set up downwards, and the one end of top crossbeam (2) is inserted and is located in the top crossbeam slot.
2. The yard tool for reinforcing local stress of a full-length transverse material according to claim 1, wherein: first sign indicating number piece (4) include first sign indicating number piece horizontal part (41) and the vertical portion of first sign indicating number piece (42), the one end of first sign indicating number piece horizontal part (41) and the vertical portion of first sign indicating number piece (42) links to each other perpendicularly, the one end that the vertical portion of first sign indicating number piece (42) was kept away from in first sign indicating number piece horizontal part (41) is connected with the horizontal side joint of crosspiece (1), the one end of the vertical portion of first sign indicating number piece (42) is used for the vertical side joint with crosspiece (1).
3. The stacking piece for reinforcing the local stress of the full-length crossband as claimed in claim 1, wherein: second sign indicating number piece (6) include second sign indicating number piece horizontal part (61) and the vertical portion of second sign indicating number piece (62), the one end of second sign indicating number piece horizontal part (61) and the vertical portion of second sign indicating number piece (62) links to each other perpendicularly, the horizontal side joint of one end and horizontal material (1) of the vertical portion of second sign indicating number piece (62) is kept away from in second sign indicating number piece horizontal part (61), the one end of the vertical portion of second sign indicating number piece (62) be used for with the tip joint of buckle (5).
4. The stacking piece for reinforcing the local stress of the full-length crossband as claimed in claim 1, wherein: the end parts of the first code piece (4) and the second code piece (6) in the horizontal direction are provided with horizontal insertion parts, and the horizontal insertion parts are inserted into horizontal buckling grooves formed by the transverse material buckling parts (15) and the transverse material (1).
5. A yard ware of reinforcing full length violence material local stress of claim 4, characterized by: one side of the horizontal inserting part, which deviates from the transverse material (1), is provided with an inclined surface (8), and the inclined surface (8) is inclined upwards towards the direction close to the transverse material clamping part (15).
6. The stacking piece for reinforcing the local stress of the full-length crossband as claimed in claim 1, wherein: the end parts of the first code piece (4) and the second code piece (6) in the vertical direction are provided with vertical insertion parts, the vertical insertion part of the first code piece (4) is inserted into the end part of the transverse material (1), and the vertical insertion part of the second code piece (6) is inserted into the end part of the buckle plate (5).
7. The stacking piece for reinforcing the local stress of the full-length crossband as claimed in claim 1, wherein: first yard spare (4) and second yard spare (6) are provided with yard spare arch (7) towards one side of horizontal material (1).
8. A curtain wall is provided with a yard member for reinforcing local stress of a through long transverse material according to any one of claims 1 to 7.
CN202221199385.5U 2022-05-18 2022-05-18 Code member for reinforcing local stress of through-length transverse material and curtain wall Active CN217400035U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221199385.5U CN217400035U (en) 2022-05-18 2022-05-18 Code member for reinforcing local stress of through-length transverse material and curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221199385.5U CN217400035U (en) 2022-05-18 2022-05-18 Code member for reinforcing local stress of through-length transverse material and curtain wall

Publications (1)

Publication Number Publication Date
CN217400035U true CN217400035U (en) 2022-09-09

Family

ID=83144507

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221199385.5U Active CN217400035U (en) 2022-05-18 2022-05-18 Code member for reinforcing local stress of through-length transverse material and curtain wall

Country Status (1)

Country Link
CN (1) CN217400035U (en)

Similar Documents

Publication Publication Date Title
CN101956454B (en) Hollow filled plastic-steel building template and composite structure
CN223937406U (en) Unit type partition wall system free of fitting assembly
CN114412016A (en) Brickwork infilled wall
CN211008679U (en) Steel frame for initial support of tunnel
CN112609892A (en) Steel construction building wallboard unit structure of easily assembling
CN214143656U (en) Combined steel sheet pile
CN215253705U (en) A high-rise U-shaped glass installation structure
CN213627170U (en) Splicing type door and window auxiliary frame
CN221823188U (en) Floor support plate of welding-point-free steel bar cudrania frame
CN220254440U (en) Corner connector and photovoltaic module
CN211571440U (en) Variable cross section roof beam prestressing force carbon fiber plate multiple spot anchor segmentation reinforced structure
CN210917325U (en) Anti-slide pile with cross beam on pile body
CN213418813U (en) Single-chain type window opener with anti-bending connector
CN201704931U (en) Cracking-prevention high-strength refractory flue
CN219586901U (en) Novel assembled steel structure beam column node
CN224119640U (en) Water tank template with good torsion resistance
CN220886648U (en) Truss structure suitable for large-span escalator
CN218264540U (en) Glass fiber reinforced plastic building wallboard
KR20170101328A (en) Beam form Joint bracket for structuring concrete
CN220267246U (en) Steel member bracket
CN220014032U (en) Light steel wall panel connection structure
CN219344134U (en) Reinforcing structure for archaize building
CN212837402U (en) High-strength aluminum alloy corner combining bracket
CN221461525U (en) Prefabricated partition plate with high compressive property
CN220167521U (en) Can have enough to meet need vertical concrete pump line fixing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220920

Address after: 518051 5F, ante building, No.5 Qimin Road, Langshan No.2 Road, North District of Science Park, Nanshan District, Shenzhen, Guangdong Province

Patentee after: China Shipping Construction Co.,Ltd.

Patentee after: Far east curtain wall (Zhuhai) Co.,Ltd.

Patentee after: NETFORTUNE (SHANGHAI) ALUMINIUM WORKS CO.,LTD.

Address before: 518051 5F, ante building, No.5 Qimin Road, Langshan No.2 Road, North District of Science Park, Nanshan District, Shenzhen, Guangdong Province

Patentee before: China Shipping Construction Co.,Ltd.

Patentee before: Far east curtain wall (Zhuhai) Co.,Ltd.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 518051 5F, ante building, No.5 Qimin Road, Langshan No.2 Road, North District of Science Park, Nanshan District, Shenzhen, Guangdong Province

Patentee after: China Shipping Construction Co.,Ltd.

Country or region after: China

Patentee after: Far east curtain wall (Zhuhai) Co.,Ltd.

Patentee after: Far East Lijin Curtain Wall (Shanghai) Co.,Ltd.

Address before: 518051 5F, ante building, No.5 Qimin Road, Langshan No.2 Road, North District of Science Park, Nanshan District, Shenzhen, Guangdong Province

Patentee before: China Shipping Construction Co.,Ltd.

Country or region before: China

Patentee before: Far east curtain wall (Zhuhai) Co.,Ltd.

Patentee before: NETFORTUNE (SHANGHAI) ALUMINIUM WORKS CO.,LTD.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 518051 5F, ante building, No.5 Qimin Road, Langshan No.2 Road, North District of Science Park, Nanshan District, Shenzhen, Guangdong Province

Patentee after: China Shipping Construction Co.,Ltd.

Country or region after: China

Patentee after: Far East Intelligent Manufacturing (Zhuhai) Co.,Ltd.

Patentee after: Far East Lijin Curtain Wall (Shanghai) Co.,Ltd.

Address before: 518051 5F, ante building, No.5 Qimin Road, Langshan No.2 Road, North District of Science Park, Nanshan District, Shenzhen, Guangdong Province

Patentee before: China Shipping Construction Co.,Ltd.

Country or region before: China

Patentee before: Far east curtain wall (Zhuhai) Co.,Ltd.

Patentee before: Far East Lijin Curtain Wall (Shanghai) Co.,Ltd.