CN217326622U - Temporary supporting equipment for repairing ancient building stand column - Google Patents

Temporary supporting equipment for repairing ancient building stand column Download PDF

Info

Publication number
CN217326622U
CN217326622U CN202221075033.9U CN202221075033U CN217326622U CN 217326622 U CN217326622 U CN 217326622U CN 202221075033 U CN202221075033 U CN 202221075033U CN 217326622 U CN217326622 U CN 217326622U
Authority
CN
China
Prior art keywords
supporting
worm
block
ancient building
lead screw
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202221075033.9U
Other languages
Chinese (zh)
Inventor
王德平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202221075033.9U priority Critical patent/CN217326622U/en
Application granted granted Critical
Publication of CN217326622U publication Critical patent/CN217326622U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Toys (AREA)

Abstract

The utility model discloses an ancient building stand is interim supporting equipment for restoration relates to supporting equipment technical field. The utility model discloses mainly including the device piece, the supporting leg of vertical to setting is installed to the bottom of device piece, the device chamber has been seted up to the inside of device piece, rotate on the inner wall in device chamber and install the lead screw of vertical to setting, the top activity of lead screw runs through the device piece, the thread bush is equipped with the loop bar on the lead screw, the backup pad is installed on the top of loop bar, the inside in device chamber is provided with the fixed worm wheel of establishing on the lead screw of cover, rotate on the inner wall in device chamber and install the worm that meshes mutually with the worm wheel, the other end activity of worm runs through the device piece and is fixed with the commentaries on classics handle. The utility model discloses when using, rotate and change the drive worm and rotate, the worm drives the worm wheel and rotates to drive the lead screw and rotate, the loop bar risees along the lead screw, and the backup pad supports the roof, is convenient for change the stand, and stability is high, and the use of being convenient for adjusts different heights.

Description

Temporary supporting equipment for repairing ancient building stand column
Technical Field
The utility model relates to a support equipment technical field, concretely relates to ancient building stand is restoreed and is used interim support equipment.
Background
Ancient buildings refer to civil and public buildings of historical significance prior to the establishment of a country, including buildings of the national age. In china, many ancient towns and most of the major cities still retain some ancient buildings. However, in the present of the great interest of civil engineering, we want to see and protect ancient buildings and their cultural traits; the ancient architectural culture is preserved in the world, and the ancient cultural heritage generates modern value.
The stand among the ancient building is wooden structure mostly, after long-time use, especially in southern rainy area, the stand is moist and even the inner structure damages, can't continue to play supporting role to the roof, need change the stand, when changing the stand, need set up strutting arrangement and support temporarily to the roof, traditional supported mode supports through the steel pipe mostly, height through measuring the roof, highly supporting with the steel pipe welding one-tenth looks adaptation, the supporting effect is not good, stability is not high, and the preparation is troublesome, can not adapt to not the roof of co-altitude.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide an: for solving the problem that proposes among the above-mentioned background art, the utility model provides an ancient building stand restores and uses interim supporting equipment.
The utility model discloses a realize above-mentioned purpose and specifically adopt following technical scheme:
the utility model provides an interim supporting equipment is used in ancient building stand restoration, includes the device piece, the supporting leg of vertical to setting is installed to the bottom of device piece, the device chamber has been seted up to the inside of device piece, rotate on the inner wall in device chamber and install the lead screw of vertical to setting, the top activity of lead screw is run through the device piece, the threaded sleeve is equipped with the loop bar on the lead screw, the level is installed to the backup pad that sets up on the top of loop bar, the inside in device chamber is provided with fixed cover and establishes worm wheel on the lead screw, rotate on the inner wall in device chamber install the level to the setting and with worm wheel engaged with worm, the other end activity of worm runs through the device piece just is fixed with the commentaries on classics handle.
Preferably, the top of the device block is fixed with a guide cylinder which is vertical and sleeved on the sleeve rod, the inner wall of the guide cylinder is provided with a guide groove along the height direction, and the outer side wall of the sleeve rod is fixed with a guide block which is slidably arranged in the guide groove.
Preferably, the supporting leg comprises a bearing plate arranged at the bottom of the device block, and four supporting rods vertically arranged are arranged at the bottom of the bearing plate.
Preferably, four T-shaped grooves which are uniformly distributed are formed in the bottom of the bearing plate, the four support rods are respectively and slidably mounted in the four T-shaped grooves, the four support rods correspond to each other in a pairwise manner, one of the two corresponding support rods is provided with a slot, the other one of the two corresponding support rods is provided with a positioning pin in a threaded penetrating manner, and the end portions of the positioning pins correspond to the slots.
Preferably, a fixing cylinder with a downward opening is fixed at the top of the device block, and a fixing column movably inserted in the fixing cylinder is fixed at the top of the bearing plate.
Preferably, an annular fixing groove is formed in the outer peripheral side of the fixing column, and a fixing pin corresponding to the fixing groove is arranged on the fixing cylinder in a penetrating mode through threads.
Preferably, a thread block is fixed at the bottom of the support plate and is inserted into the end of the loop bar in a thread manner.
Has the advantages that:
the utility model discloses when using, with the vertical region of placing supporting the roof of device, rotate and change the drive worm and rotate, the worm rotates the worm wheel that drives the meshing and rotates to drive the lead screw and rotate, the loop bar that the cover was established on the lead screw risees along the lead screw, and the backup pad supports the roof, is convenient for change the stand, and stability is high, is convenient for use, is convenient for adjust different heights, supports the roof of co-altitude.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic perspective view of the present invention;
figure 2 is a front view of the present invention in figure 1;
figure 3 is a side view of the present invention of figure 1;
fig. 4 is a cross-sectional view taken along the line a-a of fig. 2 according to the present invention;
fig. 5 is a cross-sectional view taken along the line B-B of fig. 3 according to the present invention;
fig. 6 is a cross-sectional view taken along the direction C-C in fig. 3 according to the present invention;
fig. 7 is a schematic perspective view of another state of the present invention.
In fig. 1-7:
1. a device block; 2. supporting legs; 3. a screw rod; 4. a loop bar; 5. a support plate; 6. a worm gear; 7. a worm; 8. turning a handle; 11. a device cavity; 12. a guide cylinder; 13. a guide groove; 14. a fixed cylinder; 15. a fixing pin; 21. a carrier plate; 22. a support bar; 23. a T-shaped groove; 24. a slot; 25. positioning pins; 26. fixing a column; 27. fixing grooves; 41. a guide block; 51. a thread block.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the drawings in the embodiments of the present invention are combined below to clearly and completely describe the technical solutions in the embodiments of the present invention.
The embodiment of the invention provides a temporary supporting device for repairing an ancient building column, please refer to fig. 1-7; mainly comprises a device block 1, a supporting leg 2 which is vertically arranged is arranged at the bottom of the device block 1, a device cavity 11 is arranged inside the device block 1, a lead screw 3 which is vertically arranged is rotatably arranged on the inner wall of the device cavity 11, the top end of the lead screw 3 movably penetrates through the device block 1, a loop bar 4 is sleeved on the lead screw 3 in a threaded manner, a supporting plate 5 which is horizontally arranged is arranged at the top end of the loop bar 4, a worm wheel 6 which is fixedly sleeved on the lead screw 3 is arranged inside the device cavity 11, a worm 7 which is horizontally arranged and meshed with the worm wheel 6 is rotatably arranged on the inner wall of the device cavity 11, the other end of the worm 7 movably penetrates through the device block 1 and is fixedly provided with a rotating handle 8, when the device is used, the device is moved to an area which needs to support a roof, the device is vertically arranged, the rotating handle 8 is rotated to drive the worm 7 to rotate, the worm 7 drives the meshed worm wheel 6 to rotate, the worm wheel 6 drives the lead screw 3 to rotate, and under the rotation of lead screw 3, loop bar 4 rises along lead screw 3, tightly contradicts with the roof until backup pad 5, supports the roof this moment, through a plurality of the device, can carry out better support to the roof, can be safe change the stand, and stability is good, convenient to use to be convenient for adjust into different heights, support the roof of co-altitude.
In order to ensure the stable lifting of the support plate 5, please refer to fig. 3 and 5, a guide cylinder 12 is fixed on the top of the device block 1, vertically and sleeved on the loop bar 4, a guide groove 13 is formed on the inner wall of the guide cylinder 12 along the height direction, a guide block 41 slidably mounted inside the guide groove 13 is fixed on the outer side wall of the loop bar 4, the guide groove 13 and the guide block 41 are arranged to ensure the stable lifting of the loop bar 4, and when the screw rod 3 rotates, the guide block 41 and the guide groove 13 can limit the loop bar 4 to rotate along with the rotation of the screw rod 3.
In this embodiment, referring to fig. 2, 5, 6 and 7 for improving stability, the supporting leg 2 includes a bearing plate 21 installed at the bottom of the device block 1, four supporting rods 22 vertically installed at the bottom of the bearing plate 21, the stability of the four supporting rods 22 is higher, the supporting effect on the roof is better, four T-shaped grooves 23 uniformly distributed are formed at the bottom of the bearing plate 21, the four supporting rods 22 are respectively installed inside the four T-shaped grooves 23 in a sliding manner, when the device is in use, the four supporting rods 22 are separated from each other by sliding the supporting rods 22, the contact area with the ground is increased, the stability is improved, when the device is not in use, the four supporting rods 22 are slid to fold the four supporting rods 22 together for storage, the four supporting rods 22 correspond to each other, one of the two corresponding supporting rods 22 is provided with a slot 24, the other upper thread of the two corresponding support rods 22 is provided with a positioning pin 25 in a penetrating mode, the end portions of the positioning pins 25 correspond to the slots 24, and when the four support rods 22 are folded together, the positioning pins 25 are rotated, so that one ends of the positioning pins 25 are inserted into the corresponding slots 24, and the support rods 22 are prevented from sliding along the T-shaped grooves 23 to affect carrying.
Further, referring to fig. 5 and 7, the top of the device block 1 is fixed with a fixing cylinder 14 with a downward opening, the top of the bearing plate 21 is fixed with a fixing column 26 movably inserted in the fixing cylinder 14 for separating the supporting leg 2 from the device block 1 and facilitating storage and carrying, the outer periphery of the fixing column 26 is provided with an annular fixing groove 27, the fixing cylinder 14 is threaded through and provided with a fixing pin 15 corresponding to the fixing groove 27, when the fixing device is installed, the fixing cylinder 14 is sleeved on the fixing column 26, the fixing pin 15 is rotated, one end of the fixing pin 15 is inserted into the fixing groove 27, the installation of the supporting leg 2 and the device block 1 is completed, the fixing groove 27 is formed in an annular shape, the fixing column 26 is inserted into the fixing cylinder 14 in any direction, and the fixing pin 15 is rotated to enable one end of the fixing pin 15 to be inserted into the fixing groove 27, so that the fixing device is convenient to use.
Further, please refer to fig. 4 and 7, the bottom of the supporting plate 5 is fixed with a thread block 51, and the thread block 51 is inserted into the end of the loop bar 4, so as to facilitate the detachment of the supporting plate 5, further facilitate the storage and carrying, and meanwhile, the supporting plate 5 with different specifications and sizes can be replaced according to the structure of the roof, so that the supporting effect is better.
The previous description of the disclosed embodiments is provided to enable any person skilled in the art to make or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the invention. Thus, the present invention is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (7)

1. A temporary supporting device for repairing an ancient building upright post is characterized by comprising a device block (1), the bottom of the device block (1) is provided with a supporting leg (2) which is vertically arranged, a device cavity (11) is arranged inside the device block (1), a lead screw (3) which is vertically arranged is rotatably arranged on the inner wall of the device cavity (11), the top end of the screw rod (3) movably penetrates through the device block (1), a sleeve rod (4) is sleeved on the screw rod (3) in a threaded manner, a supporting plate (5) arranged horizontally is arranged at the top end of the loop bar (4), a worm wheel (6) fixedly sleeved on the screw rod (3) is arranged in the device cavity (11), a worm (7) which is arranged horizontally and is meshed with the worm wheel (6) is rotatably arranged on the inner wall of the device cavity (11), the other end of the worm (7) movably penetrates through the device block (1) and is fixed with a rotating handle (8).
2. The temporary supporting device for repairing the ancient building stand column according to claim 1, wherein a guide cylinder (12) which is vertical and sleeved on the sleeve rod (4) is fixed at the top of the device block (1), a guide groove (13) is formed in the inner wall of the guide cylinder (12) along the height direction, and a guide block (41) which is slidably mounted in the guide groove (13) is fixed on the outer side wall of the sleeve rod (4).
3. The temporary supporting device for repairing the ancient building upright post according to claim 1, wherein the supporting leg (2) comprises a bearing plate (21) arranged at the bottom of the device block (1), and four supporting rods (22) vertically arranged are arranged at the bottom of the bearing plate (21).
4. The temporary supporting device for repairing the ancient building column according to claim 3, wherein four T-shaped grooves (23) are formed in the bottom of the bearing plate (21) and are evenly distributed, the four supporting rods (22) are respectively slidably mounted inside the four T-shaped grooves (23), every two of the four supporting rods (22) correspond to each other, one of the two corresponding supporting rods (22) is provided with a slot (24), the other of the two corresponding supporting rods (22) is provided with a positioning pin (25) in a threaded penetrating manner, and the end portion of the positioning pin (25) corresponds to the slot (24).
5. The temporary supporting device for repairing the ancient building upright post according to claim 4, wherein a fixing cylinder (14) with a downward opening is fixed at the top of the device block (1), and a fixing column (26) movably inserted in the fixing cylinder (14) is fixed at the top of the bearing plate (21).
6. The temporary supporting device for repairing the ancient building column according to claim 5, wherein an annular fixing groove (27) is formed in the outer periphery side of the fixing column (26), and a fixing pin (15) corresponding to the fixing groove (27) penetrates through the fixing cylinder (14) in a threaded mode.
7. The temporary supporting device for repairing the ancient building column according to claim 1, wherein a thread block (51) is fixed at the bottom of the supporting plate (5) and the thread block (51) is inserted at the end of the loop bar (4) in a threaded manner.
CN202221075033.9U 2022-05-06 2022-05-06 Temporary supporting equipment for repairing ancient building stand column Expired - Fee Related CN217326622U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202221075033.9U CN217326622U (en) 2022-05-06 2022-05-06 Temporary supporting equipment for repairing ancient building stand column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202221075033.9U CN217326622U (en) 2022-05-06 2022-05-06 Temporary supporting equipment for repairing ancient building stand column

Publications (1)

Publication Number Publication Date
CN217326622U true CN217326622U (en) 2022-08-30

Family

ID=82951281

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202221075033.9U Expired - Fee Related CN217326622U (en) 2022-05-06 2022-05-06 Temporary supporting equipment for repairing ancient building stand column

Country Status (1)

Country Link
CN (1) CN217326622U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115653213A (en) * 2022-11-17 2023-01-31 昆明理工大学 Multilayer pin-connected panel roof sunshade heat-insulating structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115653213A (en) * 2022-11-17 2023-01-31 昆明理工大学 Multilayer pin-connected panel roof sunshade heat-insulating structure

Similar Documents

Publication Publication Date Title
CN217326622U (en) Temporary supporting equipment for repairing ancient building stand column
CN212226585U (en) Surveying instrument convenient to carry
CN210723986U (en) Cable erecting device for electromechanical installation
CN116753002A (en) Adjustable coal mine side wall supporting column and supporting method thereof
CN215752526U (en) Prevent empting glass rack
CN213964619U (en) Multi-functional infusion support for clinical care
CN214942354U (en) Support frame for municipal administration is built in room
CN214659248U (en) Pole tower erecting device for electric power construction
CN212984717U (en) Slant construction equipment for construction
CN220989761U (en) Movable multistage sedimentation tank
CN214195466U (en) Scaffold frame of convenient regulation
CN216042514U (en) Dual self-lifting type external climbing frame for high-rise building
CN213629592U (en) Support structure of media display screen
CN217542474U (en) Geological engineering investigation is with getting core fixing device
CN221400576U (en) Subway construction tunnel support
CN219931542U (en) City building climbing rack
CN219929581U (en) Easily-operated well lid construction and extraction device
CN215395815U (en) Coffin processing platform that multi-angle was adjusted
CN220414791U (en) High-stability support frame for building technology construction
CN217583822U (en) Power equipment hoisting device for power engineering construction
CN220957523U (en) Novel survey and drawing device
CN220686688U (en) Lifting operation platform
CN219858344U (en) Box is placed to performance stage property
CN215984846U (en) Urban road noise detection device
CN214618162U (en) Gas pipe bracket

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20220830