CN217149922U - A closed can fix and remove and hang basket for construction of bridge railing outside - Google Patents

A closed can fix and remove and hang basket for construction of bridge railing outside Download PDF

Info

Publication number
CN217149922U
CN217149922U CN202220935286.2U CN202220935286U CN217149922U CN 217149922 U CN217149922 U CN 217149922U CN 202220935286 U CN202220935286 U CN 202220935286U CN 217149922 U CN217149922 U CN 217149922U
Authority
CN
China
Prior art keywords
frame
hanging
rod
guardrail
angle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220935286.2U
Other languages
Chinese (zh)
Inventor
张齐飞
敖凌宇
李坤林
丁习斌
李超
刘倩卿
蒙祖泉
夏高
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 5 Engineering Group Co Ltd
Construction Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Original Assignee
China Railway No 5 Engineering Group Co Ltd
Construction Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 5 Engineering Group Co Ltd, Construction Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd filed Critical China Railway No 5 Engineering Group Co Ltd
Priority to CN202220935286.2U priority Critical patent/CN217149922U/en
Application granted granted Critical
Publication of CN217149922U publication Critical patent/CN217149922U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a closed can fix and remove string basket for construction in the bridge railing outside, include: the hanging basket assembly comprises frame rods, pull rods and platform plates which are vertically arranged, adjacent frame rods are connected through the pull rods, and the platform plates are fixedly arranged at the bottom ends of the frame rods; the hanging frame assembly comprises two right-angle frames which are arranged at intervals, the two right-angle frames are connected through a connecting rod, the horizontal free ends of the right-angle frames are connected with the frame rod, and therefore the right-angle frames and the frame rod form a hook structure; the moving assembly comprises a plurality of rollers arranged on the right-angle stand and the frame rod, and the rollers are used for contacting and moving with the guardrail, so that the hanging basket assembly can move along the length direction of the guardrail; the fixed component comprises a rigid rod, one end of the rigid rod is hinged to the frame rod, a hanging buckle is arranged at the other end of the rigid rod and used for being connected with a hanging ring on the guardrail, and the hanging basket has the advantages of being simple to manufacture, easy to install, stable in operation, flexible in moving, safe and reliable, and particularly suitable for being constructed and applied on the bridge guardrail.

Description

A closed can fix and remove and hang basket for construction of bridge railing outside
Technical Field
The utility model relates to a closed can fix and remove string basket for construction outside bridge railing belongs to bridge railing construction technical field.
Background
The bridge guardrail installation or cast-in-place still need carry out pointing and apply paint with a brush to the guardrail after the form removal, and traditional construction mode is, adopts the hanging basket that the steel reinforcement welding formed to hang on the guardrail, however, this kind of construction operation face has the security not enough, inefficiency, mobility subalternation problem. The novel movable hanging basket in recent years is added with a wheel disc, so that the problem of poor moving capability is basically solved. But semi-closed string basket can't ensure workman's safety when the aerial work, and string basket is under construction on the guardrail of slope moreover and can produce the slip often, has the potential safety hazard.
SUMMERY OF THE UTILITY MODEL
Based on the above, the utility model provides a closed can fix and remove string basket for construction outside bridge railing has simple manufacture, easily installation, the operation is stable, remove nimble, safe and reliable's characteristics to overcome prior art's not enough.
The technical scheme of the utility model is that: the utility model provides a can fix removal string basket that is used for construction of bridge railing outside closed, includes:
the hanging basket assembly comprises frame rods, pull rods and a platform plate which are vertically arranged, adjacent frame rods are connected through the pull rods, and the platform plate is fixedly arranged at the bottom ends of the frame rods;
the hanging frame assembly comprises two right-angle frames which are arranged at intervals, the two right-angle frames are connected through a connecting rod, the horizontal free ends of the right-angle frames are connected with the frame rod, and therefore the right-angle frames and the frame rod form a hook structure;
the moving assembly comprises a plurality of rollers arranged on the right-angle stand and the frame rod, and the rollers are used for being in contact with the guardrail to move so that the hanging basket assembly can move along the length direction of the guardrail;
the fixing assembly comprises a rigid rod, one end of the rigid rod is hinged to the frame rod, a hanging buckle is arranged at the other end of the rigid rod, and the hanging buckle is used for being connected with a hanging ring on the guardrail.
As a closed can fix and remove an preferred scheme of hanging the basket, wherein: the frame rod comprises two long rods and two short rods, and the tops of the two long rods are connected with the horizontal free ends of the right-angle frames.
As a closed can fix and remove an preferred scheme of hanging the basket, wherein: the right-angle stand comprises a cross rod and a vertical rod, the vertical rod is connected with the cross rod to form a right angle, and the rollers are arranged on the vertical rod, the cross rod and the long rod.
As a closed can fix and remove an preferred scheme of hanging the basket, wherein: the height of the short bars is at least more than 1.4 meters.
As a closed can fix and remove an preferred scheme of hanging the basket, wherein: the safety belt is used for being connected with another hanging ring on the guardrail.
The utility model has the advantages that:
1. the utility model discloses an at frame pole and the shelf location gyro wheel of right angle, these gyro wheels can remove with guardrail surface contact, can conveniently accomplish the removal regulation of hanging flower basket fast according to the construction progress, and then improve the efficiency of construction.
2. The utility model discloses an articulated rigidity pole on the frame pole, this rigidity pole can be used to hang the circle with the guardrail and link to each other, and the hanging flower basket does not take place to remove when guaranteeing the construction operation, and remain stable, can adapt to the fixed mounting of different positions, slope simultaneously.
3. The utility model discloses a set up the safety belt, the safety belt links to each other with the guardrail hanging ring during construction, can regard as constructor second way safety protection measure, ensures construction safe and reliable.
Drawings
FIG. 1 is a schematic view of a closed type fixable and movable hanging basket;
description of reference numerals:
1 frame pole, 2 guardrails, 3 pull rods, 4 landing slabs, 5 stock, 6 quarter poles, 7 right-angle brackets, 8 horizontal poles, 9 montants, 10 gyro wheels, 11 rigid rods, 12 hanging rings.
Detailed Description
In order to make the above objects, features and advantages of the present invention more comprehensible, embodiments of the present invention are described in detail below with reference to the accompanying drawings. In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present invention. The present invention can be embodied in many different forms other than those specifically described herein, and it will be apparent to those skilled in the art that similar modifications can be made without departing from the spirit and scope of the invention, and it is therefore not to be limited to the specific embodiments disclosed below.
Referring to fig. 1, the closed fixable and movable cradle for construction outside a bridge guardrail of the present embodiment includes a cradle assembly, a movable assembly and a fixed assembly. The hanging flower basket subassembly includes vertical frame pole 1, a plurality of transverse arrangement's pull rod 3 and landing slab 4, connects through pull rod 3 between two adjacent frame poles 1, and landing slab 4 sets firmly in the bottom of frame pole 1. The hanger component comprises two right-angle frames 7 arranged side by side at intervals, the two right-angle frames 7 are connected through a connecting rod arranged horizontally, the horizontal free ends of the right-angle frames 7 are connected with the frame rod 1, the right-angle frames 7 and the frame rod 1 form a hook structure, and the hook structure can be hung on the guardrail 2. The movement assembly comprises a plurality of rollers 10 rotatably mounted on the brackets 7 and the frame bars 1, the rollers 10 being adapted to move in contact with the fence 2 so that the basket assembly can move along the length of the fence 2. The fixed component comprises a rigid rod 11, one end of the rigid rod 11 is hinged to the frame rod 1, a hanging buckle is arranged at the other end of the rigid rod 11 and used for being connected with a hanging ring 12 on the guardrail 2, and the rigid rod 11 is hinged to the frame rod 1 and can be suitable for reliable installation of various gradient positions.
For convenient installation and operation, frame pole 1 includes two stock 5 and two quarter butt 6, and the top of two stock 5 is connected with the horizontal free end of right angle frame 7, forms the space that can hold guardrail 2 between two stock 5 and the right angle frame 7 for but hanging of hanging flower basket subassembly safety and stability carries on guardrail 2.
In order to guarantee the reliable removal of structure, right-angle rack 7 includes horizontal pole 8 and montant 9, and montant 9 is connected with horizontal pole 8 and is formed the right angle, all is equipped with gyro wheel 10 on montant 9, horizontal pole 8 and the stock 5, gyro wheel 10 and 2 surface contact of guardrail that correspond separately.
In order to ensure the safety of construction, the height of the short rod 6 of the frame rod 1 is at least more than 1.4 meters, and the specific height is suitable for actual construction and generally exceeds the chest of a constructor.
In order to further improve constructor's security, still include the safety belt, this safety belt's one end is used for being connected with another link on guardrail 2, and the other end is used for wearing on constructor. When whole removal string basket rocked or dropped, still can rely on the safety belt to guarantee constructor's safety.
In this embodiment, 7 stock 5 of right-angle stand and quarter butt 6 all adopt the angle steel, and pull rod 3 adopts twisted steel and/or steel pipe, and whole hanging flower basket and stores pylon structural weld form.
The construction steps are as follows:
1. the hanging basket is hung on the guardrail 2, and the hanging buckle of the rigid rod 11 at the upper part of the long rod 5 is connected with the hanging ring 12 in threaded connection at the hanging point of the guardrail 2. The hanging ring 12 on the guardrail 2 is a reserved part for hoisting and moving a crane, and the part is not detached firstly when the guardrail 2 is installed and is temporarily used as a fixed point of the rigid rod 11 so as to ensure that the whole hanging basket is reliably fixed during construction.
2. Constructor climbs to hanging the basket and carries out the operation through removing pull rod 3 between two stock 5 on hanging the basket, dresses the safety belt and links to each other (every section of guardrail 2 generally has two hoisting points) with the lifting ring 12 that hangs safety belt in another hoisting point department threaded connection of guardrail 2.
3. When the construction area needs to be changed, constructors take down the rigid rod 11 on the upper part of the long rod 5 and the hanging ring 12 in threaded connection with the hanging point of the guardrail 2, slide the hanging basket to the next construction position, and fix the hanging basket according to the first step.
The above-mentioned embodiments only represent some embodiments of the present invention, and the description thereof is specific and detailed, but not to be construed as limiting the scope of the present invention. It should be noted that, for those skilled in the art, without departing from the spirit of the present invention, several variations and modifications can be made, which are within the scope of the present invention. Therefore, the protection scope of the present invention should be subject to the appended claims.

Claims (5)

1. The utility model provides a closed can fix and remove string basket for construction outside bridge railing, its characterized in that includes:
the hanging basket assembly comprises vertically arranged frame rods (1), pull rods (3) and a platform plate (4), the adjacent frame rods (1) are connected through the pull rods (3), and the platform plate (4) is fixedly arranged at the bottom ends of the frame rods (1);
the hanging rack assembly comprises two right-angle racks (7) arranged at intervals, the two right-angle racks (7) are connected through a connecting rod, the horizontal free ends of the right-angle racks (7) are connected with the frame rod (1), and therefore the right-angle racks (7) and the frame rod (1) form a hook structure;
the moving assembly comprises a plurality of rollers (10) arranged on the right-angle brackets (7) and the frame rods (1), and the rollers (10) are used for being in contact with the guardrail (2) to move so that the hanging basket assembly can move along the length direction of the guardrail (2);
the fixing assembly comprises a rigid rod (11), one end of the rigid rod (11) is hinged to the frame rod (1), the other end of the rigid rod is provided with a hanging buckle, and the hanging buckle is used for being connected with a hanging ring (12) on the guardrail (2).
2. Closed fixable mobile hanging basket according to claim 1, characterised in that the frame bar (1) comprises two long bars (5) and two short bars (6), the top of the two long bars (5) being connected with the horizontal free ends of the right angle brackets (7).
3. Closed fixable and moveable suspension basket according to claim 2, characterised in that the right angle stand (7) comprises a cross bar (8) and a vertical bar (9), the vertical bar (9) is connected with the cross bar (8) to form a right angle, and the vertical bar (9), the cross bar (8) and the long bar (5) are all provided with the roller (10).
4. Closed fixable mobile cradle according to claim 2, characterised in that the height of said short bars (6) is at least more than 1.4 meters.
5. Closed fixable mobile cradle according to claim 1, further comprising a safety belt for connection with another suspension loop on the railing (2).
CN202220935286.2U 2022-04-21 2022-04-21 A closed can fix and remove and hang basket for construction of bridge railing outside Active CN217149922U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220935286.2U CN217149922U (en) 2022-04-21 2022-04-21 A closed can fix and remove and hang basket for construction of bridge railing outside

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220935286.2U CN217149922U (en) 2022-04-21 2022-04-21 A closed can fix and remove and hang basket for construction of bridge railing outside

Publications (1)

Publication Number Publication Date
CN217149922U true CN217149922U (en) 2022-08-09

Family

ID=82661539

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220935286.2U Active CN217149922U (en) 2022-04-21 2022-04-21 A closed can fix and remove and hang basket for construction of bridge railing outside

Country Status (1)

Country Link
CN (1) CN217149922U (en)

Similar Documents

Publication Publication Date Title
CN106088565B (en) Attachment type raise scaffold tiltedly climbs method and attachment type raise scaffold
CN203175023U (en) Counter weight type cantilever hanging basket device
CN206753012U (en) A kind of attachment type raise scaffold just hangs hanging apparatus
CN217149922U (en) A closed can fix and remove and hang basket for construction of bridge railing outside
CN207829430U (en) Lifting type operation platform for suspension operation
CN206784172U (en) Overpass anti-collision wall formwork hoisting conveyance
CN205777428U (en) Elevator is from climbing platforms
CN207919351U (en) Hanging basket
CN108035530B (en) Oil tank inner wall construction hanging basket
CN213476647U (en) Construction hanging basket suspension device for steel structure gallery bridge
CN202865749U (en) Installation equipment of bridge guardrail framework
CN209837646U (en) Movable suspension structure of large-span aerial work platform
CN211547405U (en) Bridge anti-collision wall guardrail template trolley
CN213538695U (en) Bridge anticollision wall template trolley
CN210658016U (en) Trolley for movably dismounting bridge guardrail template
CN210194435U (en) Movable trolley for transverse prestress construction of continuous beam
CN207436477U (en) For the sleigh of installation photovoltaic component
CN213476637U (en) A remove gallows for building bridge railing construction
RU2438963C1 (en) Attachment tower crane with tower connections and device to attach crane tower to high-rise building, method of extending crane tower and device to this end
CN205529939U (en) Bridge testing and maintenance platform of rope type
CN101597956A (en) Suspended scaffold
CN213804934U (en) Lifting and moving tool for traveling rail of bridge girder erection machine
CN110748140A (en) Track beam hanging basket special for stepped curtain wall
CN214786423U (en) Stable type scaffold for shallow round bin slip form construction
CN218345956U (en) A construction equipment that is used for integral bridge railing communication pipeline bracket to punch

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant