CN216892861U - Connecting mechanism of steel structure - Google Patents
Connecting mechanism of steel structure Download PDFInfo
- Publication number
- CN216892861U CN216892861U CN202220504620.9U CN202220504620U CN216892861U CN 216892861 U CN216892861 U CN 216892861U CN 202220504620 U CN202220504620 U CN 202220504620U CN 216892861 U CN216892861 U CN 216892861U
- Authority
- CN
- China
- Prior art keywords
- steel structure
- connection box
- connection
- main body
- sets
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本申请公开了一种钢结构的连接机构,涉及钢结构技术领域,包括连接箱,所述连接箱的一侧安装有第一钢结构主体,所述连接箱的另一侧安装有第二钢结构主体,所述第一钢结构主体和所述第二钢结构主体的顶部和底部分别与所述连接箱之间安装有卡接组件,所述连接箱内腔的两端均通过轴承安装有双向丝杆。本申请通过双向丝杆、升降板、卡接组件、丝母和驱动组件的配合设置,从而能够将凸块紧固地卡合在凹槽连接箱连接箱的内部,方便将第一钢结构主体和第二钢结构主体进行快速连接,解决了现有的连接机构容易出现虚焊或脱落的问题,该连接机构具备方便固定和拆卸的优点,提高了连接机构的实用性,便于使用者的使用。
The application discloses a connection mechanism of a steel structure, which relates to the technical field of steel structures, and includes a connection box, one side of the connection box is installed with a first steel structure main body, and the other side of the connection box is installed with a second steel structure Structural main body, the top and bottom of the first steel structure main body and the second steel structure main body are respectively installed with snap-fit components and the connection box, and both ends of the inner cavity of the connection box are installed with bearings through bearings. Two-way lead screw. In the present application, the two-way screw rod, the lifting plate, the clamping assembly, the screw nut and the driving assembly are arranged in cooperation, so that the bump can be firmly clamped inside the groove connection box connection box, and the first steel structure main body can be easily connected. The quick connection with the second steel structure main body solves the problem that the existing connection mechanism is prone to false welding or falling off. The connection mechanism has the advantages of convenient fixing and disassembly, which improves the practicability of the connection mechanism and is convenient for users to use. .
Description
技术领域technical field
本申请涉及钢结构的技术领域,尤其是涉及一种钢结构的连接机构。The present application relates to the technical field of steel structures, and in particular, to a connection mechanism for steel structures.
背景技术Background technique
钢材的特点是强度高、自重轻、整体刚度好、抵抗变形能力强,故用于建造大跨度和超高、超重型的建筑物特别适宜,因此被广泛应用于大型厂房、场馆、超高层等领域,钢结构在相互连接固定时,需要使用连接机构。The characteristics of steel are high strength, light weight, good overall rigidity and strong resistance to deformation, so it is especially suitable for the construction of large-span, super-high and super-heavy buildings, so it is widely used in large workshops, stadiums, super high-rises, etc. In the field, when steel structures are connected and fixed to each other, a connecting mechanism needs to be used.
在实现本申请过程中,发明人发现该技术中至少存在如下问题,现有的连接机构多为焊接或使用螺丝固定,焊接容易出现虚焊,而螺丝也容易生锈滑丝,出现脱落的情况,这种连接方式安装复杂,不利于快速安装和拆卸,在实际使用过程中局限性过大,降低了钢结构的连接机构的实用性。In the process of realizing this application, the inventor found that there are at least the following problems in this technology. Most of the existing connection mechanisms are welded or fixed with screws, and welding is prone to false welding, and the screws are also prone to rust and slippery threads, and the situation of falling off occurs. , This connection method is complicated to install, which is not conducive to rapid installation and disassembly, and has too many limitations in the actual use process, which reduces the practicability of the connection mechanism of the steel structure.
实用新型内容Utility model content
为了改善上述提到现有的连接机构多为焊接或使用螺丝固定,焊接容易出现虚焊,也不利于拆卸,而螺丝也容易生锈滑丝,出现脱落的问题,本实用新型提供一种钢结构的连接机构。In order to improve the above-mentioned problems that most of the existing connecting mechanisms are welded or fixed with screws, which are prone to false welding, which is not conducive to disassembly, and the screws are also easy to rust and slip, and fall off, the utility model provides a steel structural connection mechanism.
本申请提供一种钢结构的连接机构,采用如下的技术方案:The application provides a connection mechanism of a steel structure, which adopts the following technical solutions:
一种钢结构的连接机构,包括连接箱,所述连接箱的一侧安装有第一钢结构主体,所述连接箱的另一侧安装有第二钢结构主体,所述第一钢结构主体和所述第二钢结构主体的顶部和底部分别与所述连接箱之间安装有卡接组件,所述连接箱内腔的两端均通过轴承安装有双向丝杆,两组所述双向丝杆的顶部安装有用于驱动两组双向丝杆的驱动组件,所述双向丝杆外壁的两端均螺纹连接有丝母,两组所述丝母远离所述连接箱中心的一侧均安装有升降板,所述升降板靠近所述卡接组件的一端安装有凸块,所述卡接组件的内部开设有与所述凸块相互匹配的凹槽。A connection mechanism of a steel structure, comprising a connection box, a first steel structure main body is installed on one side of the connection box, a second steel structure main body is installed on the other side of the connection box, and the first steel structure main body is installed The top and bottom of the main body of the second steel structure and the connecting box are respectively installed with snap-fit assemblies, and both ends of the inner cavity of the connecting box are installed with bidirectional screw rods through bearings. The top of the rod is equipped with a drive assembly for driving two sets of two-way screw rods. Both ends of the outer wall of the two-way screw rod are threadedly connected with a nut, and the two sets of the nut are installed on one side away from the center of the connection box. A lift plate, one end of the lift plate close to the clip assembly is installed with a bump, and a groove matched with the bump is provided inside the clip assembly.
通过采用上述技术方案,通过卡接组件,将第一钢结构主体和第二钢结构主体分别安装在连接箱的两侧,通过驱动组件带动双向丝杆转动,双向丝杆转动带动丝母移动,丝母通过升降板带动凸块移动,直至凸块卡进卡接组件的内部,便可将第一钢结构主体和第二钢结构主体快速固定在一起,当需要对第一钢结构主体和第二钢结构主体拆卸时,反向旋转转盘,使双向丝杆反向旋转,从而使凸块脱离凹槽连接箱连接箱,向外侧拉动钢第一钢结构主体和第二钢结构主体便可拆除,解决了现有的连接机构容易出现虚焊或脱落的问题。By adopting the above technical solution, the first steel structure main body and the second steel structure main body are respectively installed on both sides of the connection box through the clamping assembly, the bidirectional screw rod is driven to rotate by the driving assembly, and the bidirectional screw rod rotation drives the nut to move, The nut drives the bumps to move through the lifting plate until the bumps snap into the interior of the clamping assembly, and the first steel structure body and the second steel structure body can be quickly fixed together. When the first steel structure body and the second steel structure body need to be When the second steel structure main body is disassembled, rotate the turntable in the reverse direction, so that the two-way screw rod rotates in the opposite direction, so that the convex block is separated from the groove connection box connection box, and the first steel structure body and the second steel structure body can be removed by pulling the steel first steel structure body and the second steel structure body to the outside. , which solves the problem that the existing connection mechanism is prone to virtual welding or falling off.
可选的,两组所述双向丝杆外壁的中心处固定有挡块,两组所述挡块的顶部和底部均安装有橡胶垫。Optionally, blocks are fixed at the centers of the outer walls of the two sets of two-way screw rods, and rubber pads are installed on the tops and bottoms of the two sets of blocks.
通过采用上述技术方案,通过挡块的设置,能够限制丝母,便于使用者控制丝母的运动范围,橡胶垫的设置,便于对丝母进行保护,防止丝母与挡块撞击出现受损的情况。By adopting the above technical solution, the setting of the stopper can limit the nut, and it is convenient for the user to control the movement range of the nut. Happening.
可选的,所述连接箱内腔的中心处安装有限位组件,所述限位组件包括限位杆,所述限位杆固定安装在所述连接箱内腔的中心处,所述限位杆的外壁滑动连接有限位套,所述限位套的两侧均安装有连接块,所述连接块远离所述限位套的一端与所述丝母远离升降板的一侧固定连接。Optionally, a limit component is installed in the center of the inner cavity of the connection box, and the limit component includes a limit rod, and the limit rod is fixedly installed in the center of the inner cavity of the connection box, and the limit The outer wall of the rod is slidably connected with a limiting sleeve, and connecting blocks are installed on both sides of the limiting sleeve, and one end of the connecting block away from the limiting sleeve is fixedly connected with the side of the nut away from the lifting plate.
通过采用上述技术方案,当丝母沿着双向丝杆的外壁上下移动时,限位套在限位杆上滑动,并通过连接块对丝母进行限位,使得丝母始终沿着双向丝杆进行垂直升降。By adopting the above technical solution, when the nut moves up and down along the outer wall of the bidirectional screw, the limit sleeve slides on the limit rod, and the nut is limited by the connecting block, so that the nut always follows the bidirectional screw Make vertical lifts.
可选的,所述连接箱的两侧均开设有通孔,所述连接箱上的通孔与所述升降板配合使用。Optionally, both sides of the connection box are provided with through holes, and the through holes on the connection box are used in cooperation with the lifting plate.
通过采用上述技术方案,从而使得升降板在升降时更加顺畅。By adopting the above technical solutions, the lifting plate can be raised and lowered more smoothly.
可选的,所述卡接组件包括卡板,所述卡板安装在所述连接箱两侧的顶部和底部,所述第一钢结构主体和所述第二钢结构主体靠近所述连接箱一侧的顶部和底部均开设有卡槽,所述卡板与所述第一钢结构主体和所述第二钢结构主体上的卡槽之间卡合连接。Optionally, the snap-connection assembly includes a snap-on board installed on the top and bottom of both sides of the connection box, and the first steel structure body and the second steel structure body are close to the connection box The top and bottom of one side are provided with card slots, and the card plate is connected with the card slots on the first steel structure main body and the second steel structure main body.
通过采用上述技术方案,将连接箱上的卡板卡合在卡槽的内部,方便将第一钢结构主体和第二钢结构主体与连接箱快速连接。By adopting the above technical solution, the card plate on the connection box is clamped inside the card slot, so that the first steel structure main body and the second steel structure main body can be quickly connected with the connection box.
可选的,所述驱动组件包括主动轴,所述主动轴通过轴承安装在所述连接箱的顶部,所述主动轴的外壁安装有第二齿轮,所述第二齿轮的两端均啮合连接有第一齿轮,两组所述第一齿轮的内腔均套接有从动轴,两组所述从动轴的底部分别与两组所述双向丝杆的顶部固定连接。Optionally, the drive assembly includes a drive shaft, the drive shaft is mounted on the top of the connection box through a bearing, a second gear is mounted on the outer wall of the drive shaft, and both ends of the second gear are meshed and connected There is a first gear, the inner cavities of the two sets of first gears are sleeved with driven shafts, and the bottoms of the two sets of driven shafts are respectively fixedly connected with the tops of the two sets of bidirectional screw rods.
通过采用上述技术方案,主动轴转动时带动第二齿轮转动,第二齿轮转动带动第一齿轮转动,第一齿轮转动带动从动轴转动,从而能够带动两组双向丝杆同步转动。By adopting the above technical solution, the rotation of the driving shaft drives the second gear to rotate, the rotation of the second gear drives the rotation of the first gear, and the rotation of the first gear drives the rotation of the driven shaft, thereby driving the two sets of bidirectional screw rods to rotate synchronously.
可选的,所述主动轴远离所述连接箱的一端安装有转盘,所述转盘的表面设有防滑纹。Optionally, a turntable is installed at one end of the driving shaft away from the connection box, and the surface of the turntable is provided with anti-skid patterns.
通过采用上述技术方案,增加了工作人员手部与转盘之间的摩擦力,方便工作人员手握转盘带动主动轴转动。By adopting the above technical solution, the friction force between the staff's hand and the turntable is increased, and it is convenient for the staff to hold the turntable and drive the driving shaft to rotate.
综上所述,本申请包括以下至少一种有益效果:To sum up, the present application includes at least one of the following beneficial effects:
(1)通过双向丝杆、升降板、卡接组件、丝母和驱动组件的配合设置,从而能够将凸块紧固地卡合在凹槽连接箱连接箱的内部,方便将第一钢结构主体和第二钢结构主体进行快速连接,解决了现有的连接机构容易出现虚焊或脱落的问题,该连接机构具备方便固定和拆卸的优点,提高了连接机构的实用性,便于使用者的使用。(1) Through the cooperation of the two-way screw rod, the lifting plate, the clamping assembly, the screw nut and the driving assembly, the bump can be firmly clamped inside the groove connection box connection box, which is convenient for connecting the first steel structure. The main body and the second steel structure main body are quickly connected, which solves the problem that the existing connection mechanism is prone to false welding or falling off. use.
(2)通过限位杆、连接块和限位套的配合设置,从而能够对丝母进行限位,使得丝母能够始终沿着双向丝杆的外壁进行升降,从而带动升降板升降时更加平稳。(2) Through the cooperation of the limit rod, the connecting block and the limit sleeve, the nut can be limited, so that the nut can always move up and down along the outer wall of the two-way screw, so as to drive the lifting plate to move more smoothly. .
附图说明Description of drawings
为了更清楚地说明本申请实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本申请的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the following briefly introduces the accompanying drawings required for the description of the embodiments or the prior art. Obviously, the drawings in the following description are only These are some embodiments of the present application. For those of ordinary skill in the art, other drawings can also be obtained based on these drawings without any creative effort.
图1为本申请的剖视结构示意图;Fig. 1 is the sectional structure schematic diagram of the application;
图2为本申请的图1中A处结构示意图;Fig. 2 is the structural representation of place A in Fig. 1 of the application;
图3为本申请的图1中B处结构示意图;Fig. 3 is the structural representation at place B in Fig. 1 of this application;
图4为本申请的正视结构示意图。FIG. 4 is a schematic front view of the structure of the application.
图中:1、第一钢结构主体;2、双向丝杆;3、限位组件;301、限位杆;302、连接块;303、限位套;4、通孔;5、升降板;6、凸块;7、第二钢结构主体;8、凹槽;9、连接箱;10、卡接组件;1001、卡板;1002、卡槽;11、丝母;12、橡胶垫;13、挡块;14、驱动组件;1401、第一齿轮;1402、从动轴;1403、主动轴;1404、第二齿轮;15、转盘。In the figure: 1. The first steel structure main body; 2. The two-way screw; 3. The limit component; 301, the limit rod; 302, the connecting block; 303, the limit sleeve; 4, the through hole; 5, the lifting plate; 6. Bump; 7. Second steel structure body; 8. Groove; 9. Connection box; 10. Snap assembly; 1001, Card plate; 1002, Card slot; 11, Silk nut; 12, Rubber pad; 13 14, the drive assembly; 1401, the first gear; 1402, the driven shaft; 1403, the driving shaft; 1404, the second gear; 15, the turntable.
具体实施方式Detailed ways
以下结合附图1-4对本申请作进一步详细说明。The present application will be further described in detail below in conjunction with accompanying drawings 1-4.
请参看说明书附图中图1,本申请提供的一种实施例:一种钢结构的连接机构,包括连接箱9,连接箱9的一侧安装有第一钢结构主体1,连接箱9的另一侧安装有第二钢结构主体7,第一钢结构主体1和第二钢结构主体7的顶部和底部分别与连接箱9之间安装有卡接组件10。Please refer to FIG. 1 in the accompanying drawings of the description, an embodiment provided by the present application: a connection mechanism of a steel structure, including a
其中,卡接组件10包括卡板1001,卡板1001安装在连接箱9两侧的顶部和底部,第一钢结构主体1和第二钢结构主体7靠近连接箱9一侧的顶部和底部均开设有卡槽1002,卡板1001与第一钢结构主体1和第二钢结构主体7上的卡槽1002之间卡合连接。将连接箱9上的卡板1001卡合在卡槽1002的内部,方便将第一钢结构主体1和第二钢结构主体7与连接箱9快速连接。The
请参看说明书附图中图1和图2,连接箱9内腔的两端均通过轴承安装有双向丝杆2,两组双向丝杆2的顶部安装有用于驱动两组双向丝杆2的驱动组件14,通过驱动组件14能够带动两组双向丝杆2进行同步转动。Please refer to Figure 1 and Figure 2 in the accompanying drawings, both ends of the inner cavity of the
另外,在双向丝杆2外壁的上下两端均螺纹连接有丝母11,两组双向丝杆2外壁的中心处固定有挡块13,两组挡块13的顶部和底部均安装有橡胶垫12。通过挡块13的设置,能够限制丝母11,便于使用者控制丝母11的运动范围,橡胶垫12的设置,便于对丝母11进行保护,防止丝母11与挡块13撞击出现受损的情况。In addition,
同时,在两组丝母11远离连接箱9中心的一侧均安装有升降板5,连接箱9的两侧均开设有通孔4,连接箱9上的通孔4与升降板5配合使用。从而使得升降板5在升降时更加顺畅。At the same time, a
请参看说明书附图中图1和图2,升降板5靠近卡接组件10的一端安装有凸块6,卡接组件10的内部开设有与凸块6相互匹配的凹槽8。将凸块6卡入凹槽8的内部,方便将第一钢结构主体1和第二钢结构主体7进行快速连接。Please refer to FIG. 1 and FIG. 2 in the accompanying drawings. A
另外,在连接箱9内腔的中心处安装有限位组件3,限位组件3包括限位杆301,限位杆301固定安装在连接箱9内腔的中心处,限位杆301的外壁滑动连接有限位套303,限位套303的两侧均安装有连接块302,连接块302远离限位套303的一端与丝母11远离升降板5的一侧固定连接。当丝母11沿着双向丝杆2的外壁上下移动时,限位套303在限位杆301上滑动,并通过连接块302对丝母11进行限位,使得丝母11始终沿着双向丝杆2进行垂直升降。In addition, a
请参看说明书附图中图1-图4,驱动组件14包括主动轴1403,主动轴1403通过轴承安装在连接箱9的顶部,主动轴1403的外壁安装有第二齿轮1404,第二齿轮1404的两端均啮合连接有第一齿轮1401,两组第一齿轮1401的内腔均套接有从动轴1402,两组从动轴1402的底部分别与两组双向丝杆2的顶部固定连接。Please refer to FIGS. 1 to 4 in the accompanying drawings, the
安装时,主动轴1403转动时带动第二齿轮1404转动,第二齿轮1404转动带动第一齿轮1401转动,第一齿轮1401转动带动从动轴1402转动,从而能够带动两组双向丝杆2同步转动。During installation, when the driving
另外,在主动轴1403远离连接箱9的一端安装有转盘15,转盘15的表面设有防滑纹。增加了工作人员手部与转盘15之间的摩擦力,方便工作人员手握转盘15带动主动轴1403转动。In addition, a
工作原理:在使用该装置时,将连接箱9上的卡板1001卡接在第一钢结构主体1和第二钢结构主体7上的卡槽1002内部,旋转转盘15,转盘15通过驱动组件14带动双向丝杆2转动,双向丝杆2转动带动丝母11移动,丝母11通过升降板5带动凸块6移动,直至凸块6卡进卡板1001的凹槽8内部,便可将第一钢结构主体1和第二钢结构主体7快速固定在一起,当需要对第一钢结构主体1和第二钢结构主体7拆卸时,反向旋转转盘15,使双向丝杆2反向旋转,从而使凸块6脱离凹槽8,向外侧拉动第一钢结构主体1和第二钢结构主体7,使得1001卡板和1002卡槽脱离,便可拆除。Working principle: When using the device, the
转盘15带动驱动组件14工作时,转盘15先带动主动轴1403转动,主动轴1403转动带动第二齿轮1404转动,第二齿轮1404转动带动第一齿轮1401转动,第一齿轮1401转动带动从动轴1402转动,从而能够带动两组双向丝杆2同步转动,同时通过第一齿轮1401和第二齿轮1404之间啮合连接,实现了转盘15自锁的效果,防止转盘15出现自转的情况。When the
以上均为本申请的较佳实施例,并非依此限制本申请的保护范围,故:凡依本申请的结构、形状、原理所做的等效变化,均应涵盖于本申请的保护范围之内。The above are all preferred embodiments of the present application, and are not intended to limit the protection scope of the present application. Therefore: all equivalent changes made according to the structure, shape and principle of the present application should be covered within the scope of the present application. Inside.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202220504620.9U CN216892861U (en) | 2022-03-08 | 2022-03-08 | Connecting mechanism of steel structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202220504620.9U CN216892861U (en) | 2022-03-08 | 2022-03-08 | Connecting mechanism of steel structure |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN216892861U true CN216892861U (en) | 2022-07-05 |
Family
ID=82189616
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202220504620.9U Active CN216892861U (en) | 2022-03-08 | 2022-03-08 | Connecting mechanism of steel structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN216892861U (en) |
-
2022
- 2022-03-08 CN CN202220504620.9U patent/CN216892861U/en active Active
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN207451528U (en) | A kind of rectilinear elevator of twin-screw | |
| CN216892861U (en) | Connecting mechanism of steel structure | |
| CN215326707U (en) | Lifting platform based on mechatronic technology | |
| CN217620312U (en) | Auxiliary assembly device for aerospace parts | |
| CN116789037A (en) | Flexible direct current converter valve module overhauls device | |
| CN212605875U (en) | Adjustable take-off and landing platform for aircraft | |
| CN213976569U (en) | Firm building site lift of installation | |
| CN217920917U (en) | Safety device for elevator installation, maintenance and reconstruction | |
| CN218088858U (en) | A conveniently adjustable elevator maintenance platform | |
| CN217622060U (en) | A rubber extruder stabilization mechanism | |
| CN207390919U (en) | Plate folds mold mechanism | |
| CN214425483U (en) | Electromechanical device installs with installation base of angle regulation of being convenient for | |
| CN221905652U (en) | A sports strength training device arm swing | |
| CN112376922A (en) | Assembled steel structure sliding frame with protection function | |
| CN208067377U (en) | One kind being convenient for fixed perforating device | |
| CN220680623U (en) | A desulfurization centrifugal pump maintenance tool | |
| CN223270506U (en) | Friction damping force adjustable marine vibration isolator | |
| CN218092209U (en) | A construction engineering support device | |
| CN221560540U (en) | Curtain wall right angle aluminum profile clamping device | |
| CN222512710U (en) | Building safety protection device | |
| CN222945543U (en) | Guide rail for industrial robot | |
| CN219991025U (en) | Elevator traction sheave installation auxiliary device | |
| CN201669964U (en) | Lifting driving device | |
| CN215445890U (en) | Data processing device suitable for financial big data analysis | |
| CN214570140U (en) | Hoisting device is used in production of aluminum alloy lift platform |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CB03 | Change of inventor or designer information | ||
| CB03 | Change of inventor or designer information |
Inventor after: Li Yugui Inventor after: Liu Chuan Inventor before: Li Yugui Inventor before: Chen Yonglei |
|
| TR01 | Transfer of patent right | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20250711 Address after: Floor 1, No. 4869, Shenfeng Road, Fengxian District, Shanghai, 201400 Patentee after: Shanghai Chengda Steel Structure Construction Co.,Ltd. Country or region after: China Address before: No. 799, Haigang Road, Huangdao District, Qingdao, Shandong 266500 Patentee before: Qingdao Chengtong Construction Engineering Co.,Ltd. Country or region before: China |