CN216764077U - Connecting structure for crane beam - Google Patents
Connecting structure for crane beam Download PDFInfo
- Publication number
- CN216764077U CN216764077U CN202123250389.XU CN202123250389U CN216764077U CN 216764077 U CN216764077 U CN 216764077U CN 202123250389 U CN202123250389 U CN 202123250389U CN 216764077 U CN216764077 U CN 216764077U
- Authority
- CN
- China
- Prior art keywords
- crane
- crane beam
- fastening bolts
- plate
- bolts
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000000853 adhesive Substances 0.000 claims description 4
- 230000001070 adhesive effect Effects 0.000 claims description 4
- 239000000725 suspension Substances 0.000 abstract description 9
- 238000010276 construction Methods 0.000 abstract description 7
- 230000000149 penetrating effect Effects 0.000 abstract description 6
- 238000009435 building construction Methods 0.000 abstract description 2
- 239000011150 reinforced concrete Substances 0.000 description 5
- 239000004567 concrete Substances 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 230000008569 process Effects 0.000 description 2
- 238000006467 substitution reaction Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000004873 anchoring Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model relates to the technical field of factory building construction, and discloses a connecting structure for a crane beam, which comprises a connecting plate, fastening bolts and connecting bolts, wherein the connecting plate comprises a transverse plate and a longitudinal plate which are perpendicular to each other, the transverse plate is provided with the fastening bolts in a penetrating manner and is fixedly connected with a frame beam through the fastening bolts, and the longitudinal plate is provided with the connecting bolts in a penetrating manner and is fixedly connected with the crane beam through the connecting bolts. Compared with the prior art, the connection structure optimizes the connection form of the crane beam and the frame beam, the crane beam arranged below the frame beam is lifted to be parallel to the frame beam, the lifting height of the suspension crane is effectively increased, the structural design is ingenious, and the construction requirement is met.
Description
Technical Field
The utility model relates to the technical field of factory building construction, in particular to a connecting structure for crane beams.
Background
Along with the development of modernization construction, the steel construction form in the building has obtained rapid development and wide application, can hang the transport demand of crane in order to satisfy the material in its inside setting usually to the transformation of old factory building, promotes the efficiency of construction. According to the regulations in the existing standard atlas 05G 359-3, the crane beam of the suspension crane is mostly arranged below the frame beam through a connecting piece, and the hoisting height of the suspension crane is the relative height between the center of the suspension hook and the ground of the factory building.
In the process flow of a factory building, due to the limitation of factors such as the size of a hoisting component and the like, the hoisting height of a hanging crane has corresponding requirements, and due to the limitation of the existing floor height of an old factory building, the hanging crane beam under a frame beam can cause the hoisting height of the hanging crane to not meet the process requirements, so that the hanging crane cannot be normally used. Obviously, how to lift the setting height of the crane beam is the key for solving the technical problem of insufficient lifting height.
SUMMERY OF THE UTILITY MODEL
In order to solve the technical problems, the utility model aims to provide a connecting structure for a crane beam, which has the advantages of ingenious structural design, lifting height improvement and the like.
Based on the above, the utility model provides a connecting structure for a crane beam, which comprises a connecting plate, fastening bolts and connecting bolts, wherein the connecting plate comprises a transverse plate and a longitudinal plate perpendicular to the transverse plate, the fastening bolts penetrate through the transverse plate and are fixedly connected with a frame beam through the fastening bolts, and the connecting bolts penetrate through the longitudinal plate and are fixedly connected with the crane beam through the connecting bolts.
In some embodiments of the present application, the transverse plate is disposed outside the frame beam, and the transverse plate and the frame beam are filled with an adhesive therebetween.
In some embodiments of the present application, two rows of the fastening bolts are arranged, the two rows of the fastening bolts are respectively arranged on two sides of the crane beam, a distance between two adjacent rows of the fastening bolts is 200mm, and a distance between two adjacent fastening bolts in the same row is 200 mm.
In some embodiments of the present application, the fastening bolt is an enlarged-bottomed anchor bolt.
In some embodiments of the present application, the cross plate is embedded in the frame beam and cast as one with the frame beam.
In some embodiments of the present application, two rows of the fastening bolts are provided, the two rows of the fastening bolts are respectively provided on two sides of the crane beam, a distance between two adjacent rows of the fastening bolts is 100mm, and a setting distance between two adjacent fastening bolts in the same row is 100 mm.
In some embodiments of the present application, the connecting bolts are provided in a plurality, and each of the connecting bolts is arranged in a row along a height direction of the longitudinal plate.
In some embodiments of the present application, the connecting bolt is a 20mm diameter high strength bolt of strength class 10.9 s.
In some embodiments of the present application, the top surface of the crane beam is spaced 50mm from the lower surface of the plant ceiling.
The embodiment of the utility model provides a connecting structure for a crane beam, which has the following beneficial effects compared with the prior art:
the embodiment of the utility model provides a connecting structure for a crane beam, which comprises a connecting plate, a fastening bolt and a connecting bolt, wherein the connecting plate comprises a transverse plate and a longitudinal plate which are perpendicular to each other, the transverse plate is provided with the fastening bolt in a penetrating manner and is fixedly connected with a frame beam through the fastening bolt, and the longitudinal plate is provided with the connecting bolt in a penetrating manner and is fixedly connected with the crane beam through the connecting bolt. Based on the structure, the connecting plate is arranged on the side wall of the frame beam through the fastening bolt during assembly and is fixedly connected with the frame beam, then the crane beam is fixedly connected with the connecting plate through the connecting bolt to finally realize the parallel arrangement and the fixed connection of the crane beam and the frame beam, namely the crane beam is fixed at the side of the frame beam instead of the lower side through the connecting plate and the connecting bolt, the arrangement height of the crane beam is effectively improved, the lifting of the lifting height of the suspension crane is further realized by the lifting of the arrangement height of the crane beam, the requirement of the lifting height is met, and the normal use of the suspension crane is ensured. So, this application provides a connection structure for crane beam, its crane beam that will hang the crane is on a parallel with current frame roof beam and arranges, the both ends of crane beam support on current frame roof beam's lateral wall (or at the newly-increased reinforced concrete post of relevant position) through the connecting plate, the connection form of crane beam and frame roof beam has been optimized, the crane beam that will set up in the frame roof beam below promotes to be parallel with the frame roof beam, effectively increased the height of lifting by crane that hangs the crane, structural design is ingenious, construction requirements have been satisfied.
Drawings
FIG. 1 is a schematic structural diagram of an embodiment of the present invention;
FIG. 2 is a schematic cross-sectional view taken along line A-A of FIG. 1;
FIG. 3 is a schematic structural diagram of another embodiment of the present invention;
fig. 4 is a schematic cross-sectional view taken along line D-D in fig. 3.
In the figure, 1, connecting plate; 11. a transverse plate; 12. a longitudinal plate; 2. fastening a bolt; 3. a connecting bolt; 4. a crane beam; 5. a frame beam; 6. a top plate.
Detailed Description
The following detailed description of embodiments of the present invention is provided in connection with the accompanying drawings and examples. The following examples are intended to illustrate the utility model, but are not intended to limit the scope of the utility model.
It should be understood that the terms "front", "back", etc. are used herein to describe various information, but these information should not be limited to these terms, which are used only to distinguish one type of information from another. For example, "front" information may also be referred to as "rear" information, and "rear" information may also be referred to as "front" information without departing from the scope of the present invention.
As shown in fig. 1 to 4, an embodiment of the present invention provides a connecting structure for a crane beam, which includes a connecting plate 1, a fastening bolt 2 and a connecting bolt 3, specifically, the connecting plate 1 includes a transverse plate 11 and a longitudinal plate 12 perpendicular to each other, the transverse plate 11 is provided with the fastening bolt 2 and fixedly connected to a frame beam 5 through the fastening bolt 2, and the longitudinal plate 12 is provided with the connecting bolt 3 and fixedly connected to the crane beam 4 through the connecting bolt 3.
Based on the structure, during assembly, the connecting plate 1 is arranged on the side wall of the frame beam 5 through the fastening bolt 2 and is fixedly connected with the frame beam 5, then the crane beam 4 is fixedly connected with the connecting plate 1 through the connecting bolt 3, and finally the parallel arrangement and the fixed connection of the crane beam 4 and the frame beam 5 are realized, namely, the crane beam 4 is fixed at the side of the frame beam 5 but not below through the connecting plate 1 and the connecting bolt 3, the setting height of the crane beam 4 is effectively improved, the lifting of the lifting height of the suspension crane is further realized by the lifting of the setting height of the crane beam 4, the requirement of the lifting height is met, and the normal use of the suspension crane is ensured. So, this application provides a connection structure for crane beam, its crane beam 4 that will hang the crane is on a parallel with current frame roof beam 5 and arranges, crane beam 4's both ends support on current frame roof beam 5's lateral wall (or at the newly-increased reinforced concrete post of relevant position) through connecting plate 1, the connection form of crane beam 4 with frame roof beam 5 has been optimized, crane beam 4 that will set up in frame roof beam 5 below promotes to be on a parallel with frame roof beam 5, effectively increased the height of lifting by crane that hangs the crane, structural design is ingenious, the construction demand has been satisfied.
It should be noted that, under the prerequisite of realizing crane beam 4 and frame roof beam 5 fixed connection, connecting plate 1 still has other multiple design, specifically speaking, operating personnel can whether frame roof beam 5 accomplishes concrete placement when crane beam 4 installs and choose to bury diaphragm 11 in frame roof beam 5 and pour as an organic wholely with frame roof beam 5, also can choose to locate diaphragm 11 outside frame roof beam 5, and diaphragm 11 hugs closely the setting of frame roof beam 5 this moment, is scribbled the adhesive between the two in order to guarantee the connection effect.
Alternatively, as shown in fig. 1 and 2, in one of the embodiments of the present application, the frame beam 5 is already arranged, and in order to fixedly connect the crane beam 4 and the frame beam 5, an operator fixes the cross plate 11 on the side wall of the frame beam 5 by arranging the fastening bolt 2, and at the same time, applies an adhesive between the cross plate 11 and the frame beam 5. In order to improve the anchoring strength of the fastening bolts 2 and ensure the fixed connection between the transverse plate 11 and the frame beam 5, the fastening bolts 2 are preferably flared anchor bolts with the diameter of 16mm, two rows of the fastening bolts 2 are arranged, the two rows of the fastening bolts 2 are respectively arranged on two sides of the crane beam 4, the arrangement distance B between two adjacent fastening bolts 2 in the same row is 200mm, and the distance C between two adjacent rows of the fastening bolts 2 is 200 mm.
Further, as shown in fig. 3 and 4, in another embodiment of the present application, the frame beam 5 has not been concrete poured or a new reinforced concrete column is added to the crane beam 4, at this time, in order to complete the fixed connection of the crane beam 4, an operator directly sets the fastening bolt 2 and the transverse plate 11 in the frame beam 5 or the reinforced concrete column, and when concrete is poured, the transverse plate 11 and the fastening bolt 2 are poured in the beam or the column, at this time, the transverse plate 11 is poured integrally with the frame beam 5 or the reinforced concrete column. Furthermore, the fastening bolts 2 in the embodiment of the present invention are also provided in two rows, and the two rows of fastening bolts 2 are respectively disposed on two sides of the crane beam 4, except that the arrangement distance E between two adjacent fastening bolts 2 in the same row is 100mm, and the distance F between two adjacent rows of fastening bolts 2 is 100mm in the embodiment of the present invention.
It should be noted that, no matter how the transverse plate 11 is fixedly connected with the frame beam 5, the vertical plate and the crane beam 4 are fixedly connected with each other through the connecting bolts 3, in the above two embodiments, five connecting bolts 3 are provided, each connecting bolt 3 is arranged in a row along the height direction of the longitudinal plate 12, the distance between the adjacent connecting bolts 3 is 70mm, and meanwhile, in order to ensure the connecting strength of the crane beam 4 and the longitudinal plate 12, the connecting bolt 3 is preferably a high-strength bolt with a diameter of 20mm and a strength grade of 10.9 s.
In addition, in order to avoid the too high frame roof beam 5 of causing the influence of the position that sets up of crane roof beam 4, need carry out certain restriction to the top position of crane roof beam 4, it is specific, in some embodiments of this application, the roof beam 4's roof beam and the interval G between the roof slab 6 lower surface are 50mm, set up 50 mm's safe distance and can effectively avoid crane roof beam 4 to cause the influence to other parts of old factory building.
In summary, the utility model provides a connecting structure for a crane beam, which comprises a connecting plate, a fastening bolt and a connecting bolt, wherein the connecting plate comprises a transverse plate and a longitudinal plate which are perpendicular to each other, the transverse plate is provided with the fastening bolt in a penetrating way and is fixedly connected with a frame beam through the fastening bolt, and the longitudinal plate is provided with the connecting bolt in a penetrating way and is fixedly connected with the crane beam through the connecting bolt. Compared with the prior art, the connection structure optimizes the connection form of the crane beam and the frame beam, the crane beam arranged below the frame beam is lifted to be parallel to the frame beam, the lifting height of the suspension crane is effectively increased, the structural design is ingenious, and the construction requirement is met.
The above description is only a preferred embodiment of the present invention, and it should be noted that, for those skilled in the art, various modifications and substitutions can be made without departing from the technical principle of the present invention, and these modifications and substitutions should also be regarded as the protection scope of the present invention.
Claims (9)
1. The utility model provides a connection structure for crane beam, its characterized in that, includes connecting plate, fastening bolt and connecting bolt, the connecting plate includes diaphragm and perpendicular to the longitudinal plate of diaphragm, wear to establish on the diaphragm fastening bolt passes through fastening bolt and frame roof beam fixed connection, wear to establish on the longitudinal plate connecting bolt passes through connecting bolt and crane beam fixed connection.
2. The connecting structure for the crane beam as claimed in claim 1, wherein the cross plate is provided outside the frame beam, and an adhesive is poured between the cross plate and the frame beam.
3. The connecting structure for the crane beam as claimed in claim 2, wherein the fastening bolts are arranged in two rows, the two rows of fastening bolts are respectively arranged on two sides of the crane beam, the distance between two adjacent rows of fastening bolts is 200mm, and the arrangement distance between two adjacent fastening bolts in the same row is 200 mm.
4. A connecting structure for crane beams according to claim 3, characterized in that the fastening bolts are flared anchors.
5. The connecting structure for a crane beam according to claim 1, wherein the cross plate is embedded in the frame beam and cast integrally with the frame beam.
6. The connecting structure for the crane beam as claimed in claim 5, wherein the fastening bolts are arranged in two rows, the two rows of fastening bolts are respectively arranged on two sides of the crane beam, the distance between two adjacent rows of fastening bolts is 100mm, and the arrangement distance between two adjacent fastening bolts in the same row is 100 mm.
7. The connecting structure for a crane beam according to claim 1, wherein the connecting bolts are provided in plural, and each of the connecting bolts is arranged in a row in a height direction of the longitudinal plate.
8. The connecting structure for a crane beam according to claim 7, wherein the connecting bolt is a high-strength bolt having a diameter of 20mm and a strength class of 10.9 s.
9. A connection structure for crane beams according to claim 1, characterized in that the distance between the top surface of the crane beam and the lower surface of the plant ceiling is 50 mm.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202123250389.XU CN216764077U (en) | 2021-12-21 | 2021-12-21 | Connecting structure for crane beam |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202123250389.XU CN216764077U (en) | 2021-12-21 | 2021-12-21 | Connecting structure for crane beam |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN216764077U true CN216764077U (en) | 2022-06-17 |
Family
ID=81969440
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202123250389.XU Active CN216764077U (en) | 2021-12-21 | 2021-12-21 | Connecting structure for crane beam |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN216764077U (en) |
-
2021
- 2021-12-21 CN CN202123250389.XU patent/CN216764077U/en active Active
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN202245617U (en) | Elevator well wall assembled by adopting combined type derricks | |
| CN104989109B (en) | It is a kind of at the same lift room beam purlin method | |
| CN211143305U (en) | Steel structure building | |
| CN205328487U (en) | Dismantlement system of superelevation extra -large -size tower crane | |
| CN209780193U (en) | Suspension type scaffold | |
| CN102080384A (en) | Construction method for mounting lifter on top plate of underground parking garage | |
| CN204899274U (en) | Prefabricated concrete structure goes along with sb. to guard him frame outward | |
| CN110107095A (en) | The installation method of high-altitude long-span steel truss | |
| CN202718127U (en) | Scaffold tube support for underground foundation pit | |
| CN113957919B (en) | Gravity type round caisson concrete breast wall bottom die supporting system | |
| CN114922132B (en) | Construction method for upper structure of high pile wharf based on combined inclined piles | |
| CN216275078U (en) | Precast concrete panel | |
| CN212503718U (en) | Large-scale steel reinforcement cage hangs ann integrated device | |
| CN109680923A (en) | A kind of mounting structure and building method of builder's jack bottom platform | |
| CN202220435U (en) | Reverse construction underground concrete structure formwork descending equipment | |
| CN217458425U (en) | Lifting appliance for lifting bridge deck concrete baffle | |
| CN210103281U (en) | Concrete sleeper gang hoisting device | |
| CN209585654U (en) | Adhesion type goes up and down discharging platform | |
| CN208486272U (en) | A kind of constructing structure of two-tube diagonal brace deep basal pit | |
| CN218264865U (en) | A triangular hanging basket support structure | |
| CN201128882Y (en) | Lifting and supporting brackets integrated construction device for bridge arch rib | |
| CN207244453U (en) | A kind of suspension bridge light anchorage mast apparatus | |
| CN117446632A (en) | Arch bridge steel lattice Liang Xinxing door type lifting appliance and lifting method thereof | |
| CN116281560A (en) | Hanging beam steel frame for T beam hoisting, hanging beam system and T beam prefabrication and hoisting method | |
| CN205367459U (en) | Sharing of many hoisting points of bridge truss steel construction promotes hoist |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |