CN216732311U CN202122701165.XU CN202122701165U CN216732311U CN 216732311 U CN216732311 U CN 216732311U CN 202122701165 U CN202122701165 U CN 202122701165U CN 216732311 U CN216732311 U CN 216732311U
Authority
CN
China
Prior art keywords
pile body
foundation pile
street lamp
fixedly connected
road construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122701165.XU
Other languages
Chinese (zh)
Inventor
姚宏加
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuhai Huijian Garden Engineering Co ltd
Original Assignee
Zhuhai Huijian Garden Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhuhai Huijian Garden Engineering Co ltd filed Critical Zhuhai Huijian Garden Engineering Co ltd
Priority to CN202122701165.XU priority Critical patent/CN216732311U/en
Application granted granted Critical
Publication of CN216732311U publication Critical patent/CN216732311U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a street lamp foundation pile casting die for municipal road construction, which comprises two base die shells, wherein a pile body die shell is arranged above each base die shell, the upper surfaces of the two pile body die shells are jointly provided with a casting opening, the inner side wall of each pile body die shell is provided with clamping grooves which are arranged at equal intervals, and first reinforcing ribs are jointly clamped inside each clamping groove. This street lamp foundation pile casting die utensil is used in town road construction, through mounting bracket and mounting hole to two base mould casings and two mutual fixed connection of pile body mould casing, the mould of the concrete of a mouthful completion foundation pile is built and is watered in the utilization, effectively increase the use flexibility of foundation pile, through the fastening bolt and the screwed pipe that set up, can carry out accurate location to the connecting bolt of foundation pile, make foundation pile connecting bolt and the erection joint hole adaptation more of lamp pole, the staff of being convenient for is to the quick installation of lamp pole, the installation work of the street lamp of being convenient for.

Description

Street lamp foundation pile casting die for municipal road construction
Technical Field
The utility model belongs to the technical field of municipal engineering, and particularly relates to a street lamp foundation pile casting mold for municipal road construction.
Background
Municipal works refer to municipal infrastructure construction engineering, municipal infrastructure generally refers to various buildings, structures, equipment and the like which are arranged in urban areas and town (village) planning construction ranges and provide paid or unpaid public products and services for residents based on government responsibilities and obligations, various public infrastructure constructions matched with urban lives belong to the municipal engineering category, in urban road construction, street lamps are frequently required to be installed, existing street lamps are generally installed with street lamp foundation piles arranged on two sides of a road in advance, bolts are fixed on the foundation piles, and then street lamp poles are fastened and installed, and the mode has certain defects during installation:
(1) at present, the street lamp is installed through a driven foundation pile, the installation mode is complex in procedure and low in flexibility, the foundation pile needs to be poured in advance, and workers are complicated and troublesome in street lamp installation and inconvenient in street lamp installation work of the workers;
(2) when installing street lamp pole through the foundation pile of beating at present, the unable fine adaptation light pole of foundation pile of beating sometimes, inside the mounting hole of inserting light pole bottom mounting disc that fastening bolt above the foundation pile can not be light, often need carry out the reaming to the mounting hole, and is comparatively troublesome when the installation, consequently for solving above problem, we provide a street lamp foundation pile casting die utensil for town road construction.
SUMMERY OF THE UTILITY MODEL
The utility model provides a method for installing a street lamp pole through a drilled foundation pile, and aims to solve the problems that the current street lamp installation method is complex in procedure, low in flexibility, the foundation pile needs to be poured in advance, workers are complex and troublesome in street lamp installation, and are inconvenient for the workers to install the street lamp, and when the current street lamp installation method is used for installing the street lamp pole through the drilled foundation pile, the drilled foundation pile cannot be well matched with the street lamp pole sometimes, fastening bolts on the foundation pile cannot be easily inserted into installation holes of an installation disc at the bottom of the street lamp pole, the installation holes often need to be reamed, and the installation is troublesome.
The utility model is realized in such a way that the street lamp foundation pile casting die for municipal road construction comprises two base die shells, wherein a pile body die shell is arranged above each base die shell, pouring openings are jointly formed in the upper surfaces of the two pile body die shells, clamping grooves which are arranged at equal intervals are arranged on the inner side wall of each pile body die shell, a first reinforcing rib is jointly clamped inside each clamping groove, two grooves are respectively formed in the inner bottom wall of each base die shell, supporting ribs are respectively clamped on the inner walls of the grooves, annular ribs are jointly and fixedly connected to the top ends of the two groups of supporting ribs, a group of second reinforcing ribs are arranged inside the two base die shells, two supporting rods are respectively and fixedly connected to the upper surfaces of the second reinforcing ribs, and the top ends of the supporting rods are respectively and fixedly connected to the bottom surfaces of the annular ribs.
Two the base mould casing is fixed respectively and inlays and has the pile nail casing, two the inside of pile nail casing is equipped with the main reinforcement, the top of main reinforcement runs through two base mould casings and extends to the inside of two pile body mould casings.
Every the inside of pile body mould casing all is equipped with a set of screwed pipe, every the equal threaded connection of upper surface of pile body mould casing has a set of fastening bolt, every fastening bolt's bottom all extends to the inside of screwed pipe.
Two equal fixedly connected with arc mounting bracket of surface of pile body mould casing, every two mounting holes, every have all been seted up to the upper surface of arc mounting bracket the equal fixedly connected with of bottom surface of arc mounting bracket fills up.
Every the equal fixedly connected with two first connecting blocks of surface of pile body mould casing, every the equal fixedly connected with two second connecting blocks of upper surface of base mould casing, every the connecting hole has all been seted up to the right flank of first connecting block and the right flank of second connecting block.
Two the common fixedly connected with two first hasps in base mould casing openly and two base mould casing backs, two the common fixedly connected with two second hasps of pile body mould casing upper surface.
Compared with the prior art, the utility model has the beneficial effects that: the street lamp foundation pile casting mold for municipal road construction can utilize the buckling effect of the first hasp and the second hasp through the arranged base mold shell, the pile body mold shell, the first reinforcing rib, the second reinforcing rib, the annular rib, the first hasp, the second hasp, the mounting frame, the mounting hole and the casting hole, realizes the fastening buckling of the two base mold shells and the two pile body mold shells through the matching of the first connecting block, the second connecting block and the connecting hole, fixedly connects the two base mold shells and the two pile body mold shells through the mounting frame and the mounting hole, completes the mold casting of concrete of a foundation pile by utilizing the casting hole, effectively increases the use flexibility of the foundation pile, can accurately position the connecting bolt of the foundation pile through the arranged fastening bolt and the threaded pipe, and enables the connecting bolt of the foundation pile to be more adaptive to the mounting connecting hole of a lamp post, the staff of being convenient for installs the installation of lamp pole fast, the installation work of the street lamp of being convenient for.
Drawings
Fig. 1 is a schematic perspective view of a pile body mold shell according to the present invention;
fig. 2 is a cross-sectional view of a front view of a shaft die housing of the present invention;
FIG. 3 is a cross-sectional view of a top view of the base mold shell of the present invention;
FIG. 4 is an enlarged view of the structure at A in FIG. 2 according to the present invention.
In the figure: 1. a base mold housing; 2. a gasket; 3. a second connecting block; 4. a first buckle; 5. an arc-shaped mounting rack; 6. mounting holes; 7. connecting holes; 8. a second buckle; 9. pouring a mouth; 10. fastening a bolt; 11. a pile body mold housing; 12. a first connection block; 13. a groove; 14. a support bar; 15. an annular rib; 16. a stud housing; 17. a second reinforcing rib; 18. a first reinforcing rib; 19. a main reinforcing bar; 20. a threaded pipe; 21. supporting ribs; 22. a clamping groove.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the utility model and are not intended to limit the utility model.
In the description of the present invention, it is to be understood that the terms "length", "width", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", and the like, indicate orientations or positional relationships based on the orientations or positional relationships illustrated in the drawings, and are used merely for convenience in describing the present invention and for simplicity in description, and do not indicate or imply that the devices or elements referred to must have a particular orientation, be constructed in a particular orientation, and be operated, and thus, are not to be construed as limiting the present invention. Further, in the description of the present invention, "a plurality" means two or more unless specifically defined otherwise.
Please refer to fig. 1-4, a street lamp foundation pile casting mold for town road construction, includes two base mold housings 1, each base mold housing 1 is provided with a pile body mold housing 11, the upper surfaces of the two pile body mold housings 11 have been provided with a casting opening 9, the inner side wall of each pile body mold housing 11 has been provided with clamping grooves 22 arranged equidistantly, the inside of each group of clamping grooves 22 has been clamped with a first reinforcing rib 18, the inner bottom wall of each base mold housing 1 has been provided with two grooves 13, the inner wall of each groove 13 has been clamped with a support rib 21, the top ends of the two groups of support ribs 21 have been fixedly connected with an annular rib 15, the inside of the two base mold housings 1 has been provided with a group of second reinforcing ribs 17, the upper surface of each second reinforcing rib 17 has been fixedly connected with two support rods 14, and the top end of each support rod 14 has been fixedly connected with the bottom surface of the annular rib 15.
According to the utility model, the two base mold shells 1 are respectively fixedly embedded with the stud shells 16, main reinforcing steel bars 19 are arranged inside the two stud shells 16, the top ends of the main reinforcing steel bars 19 penetrate through the two base mold shells 1 and extend into the two pile body mold shells 11, positioning studs can be poured to position the base pile main body, so that the base pile main body can be placed accurately, a group of threaded pipes 20 are arranged inside each pile body mold shell 11, a group of fastening bolts 10 are in threaded connection with the upper surface of each pile body mold shell 11, the bottom ends of the fastening bolts 10 extend into the threaded pipes 20, and the connecting bolts can be accurately positioned through the poured threaded pipes 20, so that the lamp post connecting disc is more adaptive to the connecting bolts, and the lamp post is convenient to install.
The outer surfaces of the two pile body mould shells 11 are fixedly connected with arc-shaped mounting frames 5, the upper surface of each arc-shaped mounting frame 5 is provided with two mounting holes 6, the bottom surface of each arc-shaped mounting frame 5 is fixedly connected with a sealing gasket 2, the connection and fixation of the pile body mould shells 11 and the base mould shells 1 are realized through the matching of the arc-shaped mounting frames 5 and the mounting holes 6, the pouring work of foundation piles is convenient, the outer surface of each pile body mould shell 11 is fixedly connected with two first connecting blocks 12, the upper surface of each base mould shell 1 is fixedly connected with two second connecting blocks 3, the right side surface of each first connecting block 12 and the right side surface of each second connecting block 3 are provided with connecting holes 7, the two pile body mould shells 11 and the two base mould shells 1 can be fastened and fixed, and the connection stability of the pile body mould shells 11 and the two base mould shells 1 is improved, two first hasps 4 of two base mould casing 1 fronts and two 1 back common fixedly connected with of base mould casing, two second hasps 8 of two 11 upper surface common fixedly connected with of pile body mould casing, the lock joint that can realize two pile body mould casings 11 and two base mould casing 1, the work of pouring of the foundation pile of being convenient for.
The working principle of the utility model is as follows: when in use, firstly, the annular rib 15 is clamped inside the two base mould shells 1 through the supporting rib 21 and clamped inside the groove 13 for supporting, then a plurality of second reinforcing ribs 17 are welded through the supporting rod 14, then the first reinforcing rib 18 is clamped inside the two pile body mould shells 11, the two base mould shells 1 and the two pile body mould shells 11 are buckled through the first hasp 4 and the second hasp 8, the fastening and fixing of the two base mould shells 1 and the two pile body mould shells 11 are realized by utilizing the matching of the first connecting block 12, the second connecting block 3 and the connecting hole 7, the two base mould shells 1 and the two pile body mould shells 11 are simultaneously fixedly connected with each other by utilizing the arc-shaped mounting frame 5 and the mounting hole 6, after the fixing is finished, concrete is injected into the mould through the pouring opening 9, and the mould pouring of the foundation pile main body is realized, increase the use flexibility of foundation pile, pour and accomplish the back and rotate fastening bolt 10 and take out it, then break away from the mould with the foundation pile main part to go into threaded pipe 20's inside with connecting bolt threaded connection, realize the accurate location of connecting bolt, make the better erection joint of lamp pole.
The present invention is not limited to the above preferred embodiments, and any modifications, equivalent substitutions and improvements made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (6)

1. The utility model provides a street lamp foundation pile casting die utensil for town road construction, includes two base mould casing (1), its characterized in that: pile body mould shells (11) are arranged above each base mould shell (1), pouring openings (9) are jointly formed in the upper surfaces of the two pile body mould shells (11), clamping grooves (22) which are arranged equidistantly are formed in the inner side wall of each pile body mould shell (11), a first reinforcing rib (18) is jointly clamped in each clamping groove (22), two grooves (13) are formed in the inner bottom wall of each base mould shell (1), supporting ribs (21) are clamped in the inner wall of each groove (13), annular ribs (15) are fixedly connected to the top ends of the two groups of supporting ribs (21) jointly, a group of second reinforcing ribs (17) are arranged in the two base mould shells (1), and two supporting rods (14) are fixedly connected to the upper surface of each second reinforcing rib (17), the top end of each support rod (14) is fixedly connected with the bottom surface of the annular rib (15).
2. The street lamp foundation pile casting mold for municipal road construction according to claim 1, wherein: two base mould casing (1) is fixed respectively and inlays and have peg casing (16), two the inside of peg casing (16) is equipped with main reinforcement (19), the top of main reinforcement (19) runs through two base mould casings (1) and extends to the inside of two pile body mould casings (11).
3. The street lamp foundation pile casting mold for municipal road construction according to claim 1, wherein: every the inside of pile body mould casing (11) all is equipped with a set of screwed pipe (20), every the equal threaded connection of upper surface of pile body mould casing (11) has a set of fastening bolt (10), every the bottom of fastening bolt (10) all extends to the inside of screwed pipe (20).
4. The street lamp foundation pile casting mold for municipal road construction according to claim 1, characterized in that: two equal fixedly connected with arc mounting bracket (5) in surface of pile body mould casing (11), every two mounting holes (6), every have all been seted up to the upper surface of arc mounting bracket (5) the sealed pad (2) of equal fixedly connected with in bottom surface of arc mounting bracket (5).
5. The street lamp foundation pile casting mold for municipal road construction according to claim 1, wherein: every two first connecting blocks (12) of the equal fixedly connected with in surface of pile body mould casing (11), every two second connecting blocks (3) of the equal fixedly connected with in upper surface of base mould casing (1), every connecting hole (7) have all been seted up to the right flank of first connecting block (12) and the right flank of second connecting block (3).
6. The street lamp foundation pile casting mold for municipal road construction according to claim 1, wherein: two the base mould casing (1) openly and two base mould casing (1) back are two first hasps (4), two the common fixedly connected with of pile body mould casing (11) upper surface has two second hasps (8).
CN202122701165.XU 2021-11-06 2021-11-06 Street lamp foundation pile casting die for municipal road construction Active CN216732311U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122701165.XU CN216732311U (en) 2021-11-06 2021-11-06 Street lamp foundation pile casting die for municipal road construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122701165.XU CN216732311U (en) 2021-11-06 2021-11-06 Street lamp foundation pile casting die for municipal road construction

Publications (1)

Publication Number Publication Date
CN216732311U true CN216732311U (en) 2022-06-14

Family

ID=81924993

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122701165.XU Active CN216732311U (en) 2021-11-06 2021-11-06 Street lamp foundation pile casting die for municipal road construction

Country Status (1)

Country Link
CN (1) CN216732311U (en)

Similar Documents

Publication Publication Date Title
JP2014001542A (en) Foundation for installation of column, and construction method for the column
CN216732311U (en) Street lamp foundation pile casting die for municipal road construction
CN109706959B (en) Installation method of groove type embedded part in underground comprehensive pipe gallery
CN211645985U (en) Outer hanging steel formwork for viaduct anti-collision guardrail
CN111364518A (en) Fixing device for embedded part on side wall of concrete pipe gallery
CN215715471U (en) Prefabricated basis of signal lamp pole stock
CN211517886U (en) A concrete placement workstation for building in room
CN113174994B (en) Construction method of high retaining wall structure in complex steep terrain
CN112065458B (en) Novel steel skeleton structure formwork-free rapid environment-friendly tunnel construction method
CN216142043U (en) Foundation pit support system
CN210164234U (en) One-step forming aluminum die structure of shear wall
CN216810293U (en) Permanent-temporary combined embedded part suitable for roof
CN211250594U (en) Pouring mold for pre-buried hand hole position wallboard
CN215330334U (en) Can have enough to meet need and use cast in situ concrete template strutting arrangement
CN211733529U (en) Fixing device for wall attachment of ultrahigh construction elevator
KR200205807Y1 (en) Precast structure easy to install a street lamp
JP2019120086A (en) Method for constructing retaining wall
CN214674979U (en) Photovoltaic support built-in fitting with leveling function
CN217054359U (en) Template clamping device for building reinforcement
CN212561478U (en) Steel pipe concrete horizontal support device
CN217182872U (en) Construction structure of accurate fixed line box on aluminium template
CN211816291U (en) H-shaped steel positioning clamp node assembly
CN212200503U (en) A secret open caisson for municipal works
CN212053815U (en) Structure that PC prefabricated assembly type structure poured in situ
CN212957567U (en) Assembled enclosure scaffold

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant