Building machine hanger connection components Download PDFInfo
- Publication number
- CN216664932U CN216664932U CN202122203756.4U CN202122203756U CN216664932U CN 216664932 U CN216664932 U CN 216664932U CN 202122203756 U CN202122203756 U CN 202122203756U CN 216664932 U CN216664932 U CN 216664932U
- Authority
- CN
- China
- Prior art keywords
- sliding
- hanger
- building machine
- base
- fixed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 230000000712 assembly Effects 0.000 claims abstract description 7
- 238000000429 assembly Methods 0.000 claims abstract description 7
- 239000000725 suspension Substances 0.000 claims description 12
- 210000000078 claw Anatomy 0.000 claims description 9
- 230000001681 protective effect Effects 0.000 claims description 8
- 229910000831 Steel Inorganic materials 0.000 claims description 6
- 239000010959 steel Substances 0.000 claims description 6
- 230000005012 migration Effects 0.000 abstract 1
- 238000013508 migration Methods 0.000 abstract 1
- 238000010276 construction Methods 0.000 description 4
- 238000009435 building construction Methods 0.000 description 2
- 230000009194 climbing Effects 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
Description
技术领域technical field
本实用新型涉及建筑施工领域,尤其涉及一种造楼机挂架连接组件。The utility model relates to the field of building construction, in particular to a connecting assembly for a hanger of a building machine.
背景技术Background technique
传统的高层建筑施工平台,一般称之为爬架或者脚手架,通过顶升机构,驱动挂架上升,施工人员在挂架上进行施工作业。The traditional high-rise building construction platform is generally called climbing frame or scaffolding. Through the jacking mechanism, the pylon is driven to rise, and the construction personnel carry out construction work on the pylon.
随着近年来人工成本的快速攀升,建筑行业也面临人力资源不足的情况,于是,造楼机的概念被顺势提出,其在传统爬架或者脚手架的顶部设置了大型作业平台,通过顶升机构,驱动大型作业平台和挂架上升,通过大型作业平台和挂架上搭载的自动化设备,从而快速施工,降低人力资源需求。With the rapid rise of labor costs in recent years, the construction industry is also facing the situation of insufficient human resources. Therefore, the concept of building machines was proposed, which sets up a large-scale operation platform on top of traditional climbing frames or scaffolding. Through the jacking mechanism , Drive the large-scale operation platform and the pylon to rise, and through the automatic equipment carried on the large-scale operation platform and the pylon, the construction can be carried out quickly and the demand for human resources can be reduced.
新型造楼机的大型作业平台可采用贝雷架搭建,为了保证大型作业平台与挂架能快速、高强度的连接,就需要重新设计大型作业平台与挂架的连接组件。The large-scale operation platform of the new building machine can be built with Bailey frame. In order to ensure the fast and high-strength connection between the large-scale operation platform and the pylon, it is necessary to redesign the connection components of the large-scale operation platform and the pylon.
挂架一般包括水平设置的走道板、竖直设置的立杆和竖直设置、连接相邻立杆的防护板,并通过立杆连接大型作业平台。由于走道板的宽度往往小于贝雷架宽度,如果直接在贝雷架下方固定挂架,就会出现挂架立杆倾斜设置的问题,其受力与重力方向不重合,长期受力容易发生断裂。The hanger generally includes a horizontally arranged walkway board, a vertically arranged vertical pole, and a vertically arranged protective plate connecting adjacent vertical poles, and is connected to a large work platform through the vertical pole. Since the width of the walkway board is often smaller than the width of the beret, if the hanger is fixed directly under the beret, there will be a problem of tilting the hanger pole, the force of which does not coincide with the direction of gravity, and long-term stress is prone to fracture .
实用新型内容Utility model content
有鉴于此,本实用新型提出了一种造楼机挂架连接组件,能实现立杆之间的间距可调节,从而适应不同宽度和数量的防护板。In view of this, the utility model proposes a building machine hanger connection assembly, which can realize the adjustable spacing between the vertical poles, thereby adapting to different widths and numbers of protective panels.
本实用新型的技术方案是这样实现的:本实用新型提供了一种造楼机挂架连接组件,其包括贝雷架单元和挂架,贝雷架单元包括两个贝雷架桁架和螺杆,贝雷架桁架上、下玄杆两端分别设置有接头,同一贝雷架单元的两个贝雷架桁架并排设置且中间由螺杆紧固连接;所述挂架包括走道板、立杆和防护板,其中,走道板水平设置并与竖直设置的立杆固定,相邻的立杆之间固定连接防护板,还包括两第一滑动吊头组件、悬挂横梁和第二滑动吊头组件,第一滑动吊头组件与贝雷架桁架下玄杆滑动连接且底部连接立杆;悬挂横梁包括两横梁和一挂梁,两横梁相互平行设置且相对固定,二者之间形成一滑动槽,挂梁纵向设置于滑动槽内且两端分别与两横梁固定;同一贝雷架单元的两个贝雷架桁架下玄杆上的第一滑动吊头组件分别穿过滑动槽并与两横梁连接;第二滑动吊头组件呈“n”形,其挂在悬挂横梁并穿过挂梁后底部连接立杆。The technical scheme of the present utility model is achieved as follows: the present utility model provides a building machine hanger connection assembly, which includes a beret frame unit and a hanger, and the beray frame unit includes two beray frame trusses and a screw rod, Joints are respectively provided at both ends of the upper and lower black poles of the belay frame truss, and the two belay frame trusses of the same belay frame unit are arranged side by side and are fastened and connected by screws in the middle; A board, wherein the walkway board is arranged horizontally and fixed to the vertical poles, and the adjacent poles are fixedly connected to the protective plate, and also includes two first sliding lifting head assemblies, a suspension beam and a second sliding lifting head assembly, The first sliding lifting head assembly is slidably connected to the lower rod of the Bailey truss and the bottom is connected to the vertical rod; the suspension beam includes two beams and a suspension beam, the two beams are arranged in parallel with each other and are relatively fixed, and a sliding groove is formed between them. The hanging beam is longitudinally arranged in the sliding groove, and the two ends are respectively fixed with the two beams; the first sliding lifting head components on the lower rods of the two beret trusses of the same beray frame unit respectively pass through the sliding groove and are connected with the two beams ; The second sliding hanging head assembly is in the shape of "n", which is hung on the hanging beam and is connected to the vertical pole at the bottom after passing through the hanging beam.
在以上技术方案的基础上,优选的,所述滑动吊头组件包括第一滑动底座、两组卡爪和第一连接板,其中,第一连接板顶部与第一滑动底座固定且底部连接立杆,第一滑动底座设置于贝雷架桁架下玄杆下方,两组卡爪分别相对固定在第一滑动底座并与贝雷架桁架下玄杆滑动连接。On the basis of the above technical solutions, preferably, the sliding lifting head assembly includes a first sliding base, two sets of claws and a first connecting plate, wherein the top of the first connecting plate is fixed to the first sliding base and the bottom is connected vertically. The rod, the first sliding base is arranged below the lower rod of the berley truss, and the two sets of claws are respectively fixed on the first sliding base and are slidably connected with the lower rod of the bailey truss.
进一步优选的,所述卡爪从外侧环抱贝雷架桁架下玄杆。Further preferably, the clamping claw surrounds the lower rod of the beret truss from the outside.
进一步优选的,所述第一连接板设置有两块,相对设置且二者之间设置有可供立杆伸入的通道,第一连接板上设置有第一通孔,所述立杆伸入两第一连接板之间并通过螺栓穿过第一通孔和立杆进行连接。Further preferably, the first connecting plate is provided with two pieces, which are arranged opposite to each other and a channel through which the vertical rod can be inserted is provided between the two, the first connecting plate is provided with a first through hole, and the vertical rod is extended. It is inserted between the two first connecting plates and connected through the first through hole and the vertical rod by bolts.
更进一步优选的,所述横梁采用槽钢,两横梁背对设置且二者侧面正对开设有两组长条孔,螺栓穿过长条孔和第一通孔并与螺母连接。More preferably, the beams are made of channel steel, the two beams are arranged opposite to each other and two sets of elongated holes are formed on the sides of the two beams, and the bolts pass through the elongated holes and the first through holes and are connected with nuts.
在以上技术方案的基础上,优选的,所述第二滑动吊头组件包括第二底座和两第二连接板,两第二连接板相对设置且顶部连接第二底座,第二底座设置于两横梁上表面,两第二连接板从挂梁侧面穿过且底部连接立杆。On the basis of the above technical solutions, preferably, the second sliding lifting head assembly includes a second base and two second connecting plates, the two second connecting plates are arranged opposite to each other and the top is connected to the second base, and the second base is arranged on the two second bases. On the upper surface of the beam, the two second connecting plates pass through the side of the hanging beam and the bottom is connected to the vertical rod.
在以上技术方案的基础上,优选的,还包括转角柱头,所述转角柱头为立方框架结构,立方框架结构八个顶角处分别水平向外延伸设置有转角接头,并通过所述转角接头与贝雷架单元的接头连接,所述转角柱头设置有至少4个,相邻的转角柱头之间连接若干个贝雷架单元。On the basis of the above technical solutions, it is preferable to further include a corner column head, the corner column head is a cubic frame structure, and corner joints are respectively extended horizontally outward at the eight corners of the cubic frame structure, and are connected to the corner joints through the corner joints. The joints of the Bailey frame units are connected, the corner column heads are provided with at least 4, and several Bailey frame units are connected between adjacent corner column heads.
进一步优选的,还包括固定吊头组件,所述固定吊头组件与转角柱头底部固定并连接立杆。Further preferably, it also includes a fixed lifting head assembly, the fixed lifting head assembly is fixed to the bottom of the corner column head and connected to the vertical pole.
更进一步优选的,固定吊头组件包括第四底座、第四连接板和U形螺栓,其中,第四底座设置于贝雷架桁架下玄杆下表面并通过U形螺栓紧固连接贝雷架桁架与第四底座,第四连接板顶部与第四底座固定且底部连接立杆。Further preferably, the fixed lifting head assembly includes a fourth base, a fourth connecting plate and a U-shaped bolt, wherein the fourth base is arranged on the lower surface of the lower black pole of the beret truss and is fastened and connected to the beret through U-shaped bolts. The truss is connected with the fourth base, the top of the fourth connecting plate is fixed with the fourth base, and the bottom is connected with the vertical rod.
在以上技术方案的基础上,优选的,所述立杆上从上至下依次开设有若干第二通孔,并通过螺栓穿过第一通孔和第二通孔进行连接。On the basis of the above technical solutions, preferably, a plurality of second through holes are formed on the vertical rod in sequence from top to bottom, and are connected by bolts passing through the first through holes and the second through holes.
本实用新型的造楼机挂架连接组件相对于现有技术具有以下有益效果:Compared with the prior art, the building machine hanger connection assembly of the present invention has the following beneficial effects:
(1)通过设置两第一滑动吊头组件、悬挂横梁和第二滑动吊头组件,立杆可沿贝雷架桁架下玄杆左右移动,能方便调节左右立杆之间的间距,适应不同尺寸的挂架;第二滑动吊头组件直接挂在悬挂横梁上,方便快捷,拆装方便;(1) By arranging two first sliding lifting head components, hanging beams and second sliding lifting head components, the vertical pole can move left and right along the lower pole of the Bailey truss, which can easily adjust the distance between the left and right vertical poles to adapt to different The size of the hanger; the second sliding lifting head assembly is directly hung on the hanging beam, which is convenient and quick, and easy to disassemble;
(2)在两横梁上设置长条孔,可调节前后立杆之间的间距,从而克服走道板的宽度小于贝雷架宽度的问题;(2) Long holes are arranged on the two beams to adjust the distance between the front and rear vertical poles, thereby overcoming the problem that the width of the walkway board is smaller than the width of the beret;
(3)设置转角柱头,可快速连接贝雷架,进一步设置固定吊头组件,与第一滑动吊头组件相互配合,防止挂架整体水平移动;(3) The corner column head is provided, which can be quickly connected to the Bailey frame, and the fixed lifting head assembly is further arranged to cooperate with the first sliding lifting head assembly to prevent the overall horizontal movement of the hanger;
(4)本实用新型的造楼机挂架连接组件,具有零部件易得、成本低、强度高,且便于快速组装和拆卸的优点,便于大规模推广应用。(4) The building machine hanger connection assembly of the present invention has the advantages of easy-to-obtain parts, low cost, high strength, convenient quick assembly and disassembly, and is convenient for large-scale popularization and application.
附图说明Description of drawings
为了更清楚地说明本实用新型实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本实用新型的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the embodiments of the present utility model or the technical solutions in the prior art, the following briefly introduces the accompanying drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description These are just some embodiments of the present invention, and for those of ordinary skill in the art, other drawings can also be obtained from these drawings without creative effort.
图1为本实用新型的造楼机挂架连接组件的立体图;1 is a perspective view of a building machine hanger connection assembly of the present invention;
图2为本实用新型的造楼机挂架连接组件的部分结构立体图;2 is a perspective view of a part of the structure of the building machine hanger connection assembly of the present invention;
图3为本实用新型的造楼机挂架连接组件的部分结构立体图;3 is a perspective view of the partial structure of the connecting assembly of the building machine hanger of the present invention;
图4为图2中右侧椭圆区域的放大图;Fig. 4 is an enlarged view of the right elliptical region in Fig. 2;
图5为第一滑动吊头组件的立体图;5 is a perspective view of the first sliding head assembly;
图6为悬挂横梁的立体图;Figure 6 is a perspective view of a suspension beam;
图7为第二滑动吊头组件的立体图;7 is a perspective view of the second sliding head assembly;
图8为图2中左侧椭圆区域的放大图;Figure 8 is an enlarged view of the left elliptical region in Figure 2;
图9为固定吊头组件的立体图。FIG. 9 is a perspective view of the fixed lifting head assembly.
具体实施方式Detailed ways
下面将结合本实用新型实施方式,对本实用新型实施方式中的技术方案进行清楚、完整地描述,显然,所描述的实施方式仅仅是本实用新型一部分实施方式,而不是全部的实施方式。基于本实用新型中的实施方式,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施方式,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the protection scope of the present invention.
如图1所示,结合图2~图9,本实用新型的造楼机挂架连接组件,其包括若干贝雷架单元1、挂架2、两第一滑动吊头组件3、悬挂横梁4、第二滑动吊头组件5、转角柱头6和固定吊头组件7。As shown in FIG. 1 , in conjunction with FIGS. 2 to 9 , the building machine hanger connection assembly of the present invention includes a plurality of Bailey frame units 1 , a
贝雷架单元1,设置有若干个,首尾相互连接,形成直线排列的承重结构,这部分可采用现有技术。具体的,所述承重结构由顶升机构驱动,进行升降。具体的,贝雷架单元1包括两个贝雷架桁架11和螺杆12,贝雷架桁架11上、下玄杆两端分别设置有接头13,同一贝雷架单元1的两个贝雷架桁架11并排设置且中间由螺杆12紧固连接。The Bailey rack unit 1 is provided with several pieces, and the ends are connected to each other to form a load-bearing structure arranged in a straight line, and the existing technology can be used for this part. Specifically, the load-bearing structure is driven by a jacking mechanism to lift and lower. Specifically, the Bailey frame unit 1 includes two Bailey
所述挂架2包括走道板21、立杆22和防护板23,其中,走道板21水平设置并与竖直设置的立杆22固定,相邻的立杆22之间固定连接防护板23。具体的,所述走道板21上对应设置有多个立杆22,多个立杆22分别与顶部的承重结构连接,而相邻的立杆22之间各设置防护板23。The
第一滑动吊头组件3,用于连接贝雷架桁架11和挂架2,并可沿贝雷架桁架11左右滑动。具体的,第一滑动吊头组件3与贝雷架桁架11下玄杆滑动连接且底部连接立杆22。更具体的,所述滑动吊头组件3包括第一滑动底座31、两组卡爪32和第一连接板33,其中,第一连接板33顶部与第一滑动底座31固定且底部连接立杆22,第一滑动底座31设置于贝雷架桁架11下玄杆下方,两组卡爪32分别相对固定在第一滑动底座31并与贝雷架桁架11下玄杆滑动连接。具体的,所述两组卡爪32可从贝雷架桁架11中间通道穿过,也能从贝雷架桁架11外侧环抱设计,在本实施例中,采用后一种方案。具体的,所述卡爪32从外侧环抱贝雷架桁架11下玄杆。具体的,所述第一连接板33设置有两块,相对设置且二者之间设置有可供立杆22伸入的通道,第一连接板33上设置有第一通孔30,所述立杆22伸入两第一连接板33之间并通过螺栓穿过第一通孔30和立杆22进行连接。The first sliding
悬挂横梁4,用于连接第一滑动吊头组件3并悬挂第二滑动吊头组件5,将第二滑动吊头组件5承受的拉力传导到第一滑动吊头组件3。具体的,悬挂横梁4包括两横梁41和一挂梁42,两横梁41相互平行设置且相对固定,二者之间形成一滑动槽40,挂梁42纵向设置于滑动槽40内且两端分别与两横梁41固定;同一贝雷架单元1的两个贝雷架桁架11下玄杆上的第一滑动吊头组件3分别穿过滑动槽40并与两横梁41连接。作为第一滑动吊头组件3与悬挂横梁4的具体连接方式,所述横梁41采用槽钢,两横梁41背对设置且二者侧面正对开设有两组长条孔43,螺栓穿过长条孔43和第一通孔30并与螺母连接。如此,可调节悬挂横梁4相对第一滑动吊头组件3前后移动,从而调节第一滑动吊头组件3上的立杆22与第二滑动吊头组件5连接的立杆22之间的间距,从而适应不同尺寸的走道板21。The
第二滑动吊头组件5,悬挂在悬挂横梁4上并连接立杆22,其呈“n”形,其挂在悬挂横梁4并穿过挂梁42后底部连接立杆22。具体的,所述第二滑动吊头组件5包括第二底座51和两第二连接板52,两第二连接板52相对设置且顶部连接第二底座51,第二底座51设置于两横梁41上表面,两第二连接板52从挂梁42侧面穿过且底部连接立杆22。The second sliding
转角柱头6,设置于转角部位,连接1~4个贝雷架单元1。所述转角柱头6为立方框架结构,立方框架结构八个顶角处分别水平向外延伸设置有转角接头60,并通过所述转角接头40与贝雷架单元1的接头13连接。具体的,转角柱头4包括八根型材、8根斜杆、16个转角接头60,所述八根型材首尾连接形成立方框架,具体的,所述八根型材可采用方管钢材焊接而成。8根斜杆两两交叉设置于立方框架的前、后、左和右四个面内。具体的,所述斜杆起斜向支撑作用,可采用方管钢材,处于避位考虑,每根斜杆可以通过两根方管钢材焊接而成。如此,通过在转角柱头6上连接两个、三个或四个贝雷架单元1,形成“L”形、“丁”字形或“十”字形的承重结构。具体的,所述转角柱头4设置有至少4个,相邻的转角柱头6之间连接若干个贝雷架单元1。The
固定吊头组件7,一方面连接立杆22,另一方面对挂架2进行整体限位,防止其整体沿贝雷架桁架11移动。具体的,所述固定吊头组件7与转角柱头6底部固定并连接立杆22。具体的,固定吊头组件7包括第四底座71、第四连接板72和U形螺栓73,其中,第四底座71设置于贝雷架桁架11下玄杆下表面并通过U形螺栓73紧固连接贝雷架桁架11与第四底座71,第四连接板72顶部与第四底座71固定且底部连接立杆22。The hanging
为了便于与第一滑动吊头组件3、第二滑动吊头组件5和固定吊头组件7快速连接并调节挂架2的高度,所述立杆22上从上至下依次开设有若干第二通孔20,并通过螺栓穿过第一通孔30和第二通孔220进行紧固连接。In order to facilitate quick connection with the first sliding lifting
以上所述仅为本实用新型的较佳实施方式而已,并不用以限制本实用新型,凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。The above descriptions are only the preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included in the within the scope of protection of the present invention.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202122203756.4U CN216664932U (en) | 2021-09-10 | 2021-09-10 | Building machine hanger connection components |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202122203756.4U CN216664932U (en) | 2021-09-10 | 2021-09-10 | Building machine hanger connection components |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN216664932U true CN216664932U (en) | 2022-06-03 |
Family
ID=81757468
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202122203756.4U Active CN216664932U (en) | 2021-09-10 | 2021-09-10 | Building machine hanger connection components |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN216664932U (en) |
-
2021
- 2021-09-10 CN CN202122203756.4U patent/CN216664932U/en active Active
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN216276809U (en) | Building machine bailey frame connecting assembly | |
| CN212002170U (en) | Adjustable support for elevator shaft operating platform | |
| CN212535007U (en) | A cantilever platform for segmental dismantling of cantilever frame | |
| CN216276816U (en) | Connecting assembly for hanging frame of building machine | |
| CN216664932U (en) | Building machine hanger connection components | |
| CN214740171U (en) | Ancient building wall body hoist and mount migration device | |
| CN220599110U (en) | Movable bridge type operation platform | |
| CN216276808U (en) | Building machine is made to intelligence steel bar welding | |
| CN220319071U (en) | A suspension mechanism with adjustable spacing for hanging baskets | |
| CN216276813U (en) | Building machine walkway plate connecting assembly | |
| CN216276814U (en) | Building machine walkway plate connecting assembly | |
| CN216276815U (en) | Connecting assembly for hanging frame of building machine | |
| CN217711647U (en) | Hanging basket suspension device suitable for high parapet | |
| CN211037766U (en) | Attached lifting scaffold body structure | |
| CN110097807A (en) | Hv cable termination experiment porch | |
| CN216276810U (en) | Connecting assembly for hanging frame of building machine | |
| CN116290917A (en) | Temporary support device for construction support of a suspension dome | |
| CN209817424U (en) | A mobile adjustable cantilevered operating platform suitable for super-long cantilevered structures | |
| CN217871732U (en) | Steel construction pergola Liang Muqiang hanging flower basket erects device | |
| CN223119482U (en) | A rear support device for a non-counterweight hanging basket and a hanging basket | |
| CN219952637U (en) | Overlength hanging flower basket support reinforced structure | |
| CN223813901U (en) | Mounting platform for steel plate shear wall | |
| CN219491651U (en) | Floor type scaffold with protective structure | |
| CN217106080U (en) | Aluminum alloy-steel combined attached lifting scaffold | |
| CN223256422U (en) | Multi-span assembled operating platform hung under steel beam |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| PP01 | Preservation of patent right | ||
| PP01 | Preservation of patent right |
Effective date of registration: 20240103 Granted publication date: 20220603 |
|
| PD01 | Discharge of preservation of patent | ||
| PD01 | Discharge of preservation of patent |
Date of cancellation: 20250220 Granted publication date: 20220603 |