CN216553036U - Shear wall template support - Google Patents

Shear wall template support Download PDF

Info

Publication number
CN216553036U
CN216553036U CN202122904354.7U CN202122904354U CN216553036U CN 216553036 U CN216553036 U CN 216553036U CN 202122904354 U CN202122904354 U CN 202122904354U CN 216553036 U CN216553036 U CN 216553036U
Authority
CN
China
Prior art keywords
wall
backplate
fixed
supporting
shear wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202122904354.7U
Other languages
Chinese (zh)
Inventor
黎继忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Shenghong Construction Engineering Co ltd
Original Assignee
Guangdong Shenghong Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Shenghong Construction Engineering Co ltd filed Critical Guangdong Shenghong Construction Engineering Co ltd
Priority to CN202122904354.7U priority Critical patent/CN216553036U/en
Application granted granted Critical
Publication of CN216553036U publication Critical patent/CN216553036U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]
    • Y02B30/90Passive houses; Double facade technology

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The application discloses shear wall template is strutted belongs to construction technical field. It is including setting up in the first backplate and the second backplate of shear force wall both sides, the shear force wall is embedded to be equipped with a plurality of registration arms, all be equipped with the spliced pole in every registration arm, and the one end of spliced pole is fixed with first backplate, the other end of spliced pole runs through the second backplate and outwards extends, the round hole has been seted up to the lateral wall that the spliced pole extends to outside one end, and the round hole rotates and is connected with the fixed axle, fixed cover of fixed axle has connect cam and bull stick, the second is strutted the lateral wall that deviates from shear force wall one side mutually and has been seted up a plurality ofly and cam assorted arc wall, all be equipped with spacing subassembly on every bull stick. This application can be convenient for carry out fast assembly and dismantlement to two fender boards, has improved work efficiency, and the used repeatedly of being convenient for, and energy-concerving and environment-protective can improve the stability of two fender boards support in-process simultaneously.

Description

Shear wall formwork support
Technical Field
The application relates to a shear wall formwork support, and belongs to the technical field of building construction.
Background
In recent years, concepts of 'green building' and 'energy conservation and emission reduction' are gradually deepened in building design, new materials and new technologies for wall heat preservation are continuously developed, and a shear wall is also called as a wind-resistant wall, an earthquake-resistant wall or a structural wall, mainly bears a horizontal load and a vertical load caused by wind load or earthquake action in a house or a structure, and has a heat preservation function.
The shear wall is generally made of reinforced concrete, a steel formwork is required to be used for supporting in the process of pouring the shear wall, the connection of supporting plates in the prior art is mostly completed through screws and nuts, the installation and the disassembly are troublesome, and a large amount of working hours are wasted.
SUMMERY OF THE UTILITY MODEL
The technical problem that this application will solve lies in: the utility model provides a shear wall template is strutted, it has solved the connection of the supporting plate among the prior art and has mostly been accomplished through screw rod and nut, and the installation is all more troublesome with the dismantlement, and then has wasted the problem of a large amount of man-hours.
The technical problem to be solved by the application is realized by adopting the following technical scheme:
shear force wall template is strutted, including setting up in the first backplate and the second backplate of shear force wall both sides, the shear force wall is embedded to be equipped with a plurality of registration arms, every all be equipped with the spliced pole in the registration arm, just the one end of spliced pole is fixed with first backplate, the other end of spliced pole runs through the second backplate and outwards extends, the round hole has been seted up to the lateral wall that the spliced pole extends to outside one end, just the round hole rotates and is connected with the fixed axle, the fixed axle is fixed to cup joint has cam and first bull stick, the second is strutted the lateral wall that deviates from shear force wall one side mutually and has been seted up a plurality ofly and cam assorted arc wall, every all be equipped with spacing subassembly on the first bull stick, one side that first backplate and second strut the board and deviate from mutually all is equipped with supporting component.
Preferably, every the supporting component all includes backup pad, two second bull sticks and connecting plate, two the both ends of second bull stick all rotate with backup pad and connecting plate respectively through the pivot and be connected, the lateral wall symmetry that the connecting plate deviates from second bull stick one side mutually is fixed with a plurality of inserted blocks, first fender board and second are strutted the lateral wall that deviates from one side mutually and all have been seted up a plurality ofly and inserted block assorted slot.
Preferably, every spacing subassembly all includes gag lever post and spring, every the lateral wall that cam one side was kept away from to first bull stick has all seted up the bar hole, gag lever post and spring all are located the bar downthehole, the both ends of spring are fixed with the lateral wall of bar hole and gag lever post respectively, every both sides all are equipped with the spacing seat of C type with gag lever post assorted around the second bull stick, just the spacing seat of C type is fixed with the second supporting plate.
Preferably, a rubber gasket is fixed on the side wall of each arc-shaped groove and abuts against the cam.
Preferably, each strip-shaped hole is internally fixed with a round rod, and the limiting rod and the spring in each strip-shaped hole are movably sleeved with the round rod.
Preferably, the side walls of the opposite sides of the first supporting plate and the second supporting plate are coated with the engine oil.
Preferably, the positioning tube and the connecting column are provided with five.
Preferably, the first supporting plate and the second supporting plate are both steel plates.
Compared with the prior art, the application provides shear wall template is strutted, possesses following beneficial effect:
1. this shear force wall template is strutted, through the registration arm, spliced pole, fixed axle, cam, connecting rod and the spacing subassembly that is equipped with, can be convenient for carry out fast assembly and dismantlement to two fender boards, improved work efficiency.
2. This shear force wall template is strutted, through the supporting component who is equipped with, can improve the stability of two supporting plate support in-process.
The part that does not relate to among the device all is the same with prior art or can adopt prior art to realize, and this application can be convenient for carry out fast assembly and dismantlement to two strutted boards, has improved work efficiency, can improve the stability of two strutted board support in-process simultaneously.
Drawings
FIG. 1 is a schematic structural view of the present application and a shear wall;
FIG. 2 is an enlarged view of a portion A of FIG. 1;
FIG. 3 is a schematic structural view of a first support plate and a support assembly according to the present application;
fig. 4 is a schematic view of the distribution of a plurality of support pillars in fig. 1.
In the figure: 1 shear wall, 2 first protective plates, 3 second protective plates, 4 positioning pipes, 5 connecting columns, 6 fixing shafts, 7 cams, 8 first rotating rods, 9 limiting rods, 10 springs, 11C-shaped limiting seats, 12 supporting plates, 13 second rotating rods, 14 connecting plates, 15 inserting blocks, 16 rubber gaskets, 17 round rods and 18 organic oils.
Detailed Description
In order to make the technical means, the technical features, the objectives and the effects of the present application easier to understand, the present application will be further described with reference to the following specific drawings.
As shown in fig. 1-2, the shear wall formwork support comprises a first support plate 2 and a second support plate 3 which are arranged at two sides of a shear wall 1, wherein the first support plate 2 and the second support plate 3 are both steel plates, the support strength of the first support plate and the second support plate 3 is improved, a plurality of positioning pipes 4 are embedded in the shear wall 1, a connecting column 5 is arranged in each positioning pipe 4, one end of the connecting column 5 is fixed with the first support plate 2, the other end of the connecting column 5 penetrates through the second support plate 3 and extends outwards, a circular hole is formed in the side wall of the connecting column 5, which extends to the outer end, a fixing shaft 6 is rotatably connected with the circular hole, a cam 7 and a first rotating rod 8 are fixedly sleeved on the fixing shaft 6, a plurality of arc-shaped grooves matched with the cam 7 are formed in the side wall of the second support plate 3, which is opposite to the side wall of the shear wall 1, a rubber gasket 16 is fixed on the side wall of each arc-shaped groove, and the rubber gasket 16 abuts against the cam 7, can improve the effect that cam 7 supported tightly, all be equipped with spacing subassembly on every first bull stick 8, one side that first backplate 2 and second backplate 3 deviate from mutually all is equipped with supporting component, and the lateral wall of one side in opposite directions of first backplate 2 and second backplate 3 all is smeared with machine oil 18, can prevent that backplate and concrete from taking place to bond.
As shown in fig. 3, each supporting component includes a supporting plate 12, two second rotating rods 13 and a connecting plate 14, two ends of the two second rotating rods 13 are respectively rotatably connected with the supporting plate 12 and the connecting plate 14 through rotating shafts, a plurality of inserting blocks 15 are symmetrically fixed on the side wall of the connecting plate 14 away from one side of the second rotating rods 13, and a plurality of slots matched with the inserting blocks 15 are respectively formed in the side walls of the first supporting plate 2 and the second supporting plate 3 away from one side.
As shown in fig. 2, every spacing subassembly all includes gag lever post 9 and spring 10, the bar hole has all been seted up to the lateral wall of every first bull stick 8 keep away from cam 7 one side, gag lever post 9 and spring 10 all are located the bar hole, the both ends of spring 10 are fixed with the lateral wall of bar hole and gag lever post 9 respectively, both sides all are equipped with the spacing seat 11 of C type with gag lever post 9 assorted around every first bull stick 8, and spacing seat 11 of C type is fixed with second backplate 3, all be fixed with round bar 17 in every bar hole, gag lever post 9 and spring 10 in every bar hole all establish with round bar 17 movable sleeve, improve the stability in gag lever post 9 and the spring 10 use.
As shown in fig. 4, five positioning pipes 4 and five connecting columns 5 are arranged, and the distribution schematic diagram of the connecting columns 5 is shown in the attached description, so that the stress stability of the two support plates after connection can be improved.
The working principle is as follows: when the shear wall is used, the shear wall is fixed with a steel bar framework of a shear wall 1 through the positioning pipes 4, then the first support plate 1 and the connecting columns 5 are arranged, the connecting columns 5 sequentially penetrate through the positioning pipes 4, the second support plate 3 is buckled on the connecting columns 5, the connecting columns 5 penetrate through the second support plate 3, then the fixing shafts 6 are inserted into round holes of the connecting columns 5 through the fixing shafts 6, at the moment, the limiting rods 9 are pulled and the first rotating rods 8 are rotated, the arc-shaped blocks 7 can be rotated into the arc-shaped grooves, so that the positions of the connecting columns 5 can be limited, the connection stability of the two support plates is ensured, and then the C-shaped limiting seats 11 are arranged, when the limiting rods 9 correspond to openings of the C-shaped limiting seats 11, the limiting rods 9 can be clamped into the C-shaped limiting seats 11 through the elasticity of the springs 10, the positions of the first rotating rods 8 and the cams 7 are limited, guarantee the stability that two supporting plates are connected, convenient operation is swift, and the inserted block 15 that the rethread was equipped with inserts the inserted block 15 to the slot of supporting plate in to fix backup pad 12 through the bolt, thereby make second bull stick 13 can support the supporting plate, guarantee the stability of two supporting plate support in-process.
The foregoing shows and describes the general principles and features of the present application, together with the advantages thereof. It will be understood by those skilled in the art that the present application is not limited to the embodiments described above and that various changes and modifications may be made without departing from the spirit and scope of the application and these changes and modifications are intended to be covered by the appended claims. The scope of the claims herein is defined by the appended claims and equivalents thereof.

Claims (8)

1. Shear force wall template is strutted, including setting up in first backplate (2) and second backplate (3) of shear force wall (1) both sides, its characterized in that: a plurality of positioning pipes (4) are embedded in the shear wall (1), a connecting column (5) is arranged in each positioning pipe (4), one end of the connecting column (5) is fixed with the first supporting plate (2), the other end of the connecting column (5) penetrates through the second supporting plate (3) and extends outwards, a round hole is arranged on the side wall of one end of the connecting column (5) extending to the outside, and the round hole is rotationally connected with a fixed shaft (6), the fixed shaft (6) is fixedly sleeved with a cam (7) and a first rotating rod (8), the side wall of the second support guard plate (3) opposite to the side wall of the shear wall (1) is provided with a plurality of arc-shaped grooves matched with the cams (7), each first rotating rod (8) is provided with a limiting component, and a supporting component is arranged on one side of the first supporting plate (2) and one side of the second supporting plate (3) which are deviated from each other.
2. The shear wall form support of claim 1, wherein: every the supporting component all includes backup pad (12), two second bull stick (13) and connecting plate (14), two the both ends of second bull stick (13) all rotate with backup pad (12) and connecting plate (14) respectively through the pivot and be connected, the lateral wall symmetry that connecting plate (14) deviate from second bull stick (13) one side mutually is fixed with a plurality of inserted blocks (15), a plurality of and inserted block (15) assorted slots have all been seted up to the lateral wall that first backplate (2) and second backplate (3) kept away from one side mutually.
3. The shear wall form support of claim 1, wherein: every spacing subassembly all includes gag lever post (9) and spring (10), every the bar hole has all been seted up to the lateral wall that cam (7) one side was kept away from in first bull stick (8), gag lever post (9) and spring (10) all are located the bar downthehole, the both ends of spring (10) are fixed with the lateral wall of bar hole and gag lever post (9) respectively, every both sides all are equipped with spacing seat (11) of gag lever post (9) assorted C type around first bull stick (8), just spacing seat (11) of C type are fixed with second backplate (3).
4. The shear wall form support of claim 1, wherein: and a rubber gasket (16) is fixed on the side wall of each arc-shaped groove, and the rubber gasket (16) is abutted against the cam (7).
5. The shear wall form support of claim 3, wherein: each bar hole is internally fixed with a round rod (17), and each limiting rod (9) and the spring (10) in the bar hole are movably sleeved with the round rod (17).
6. The shear wall form support of claim 1, wherein: and the side walls of the opposite sides of the first supporting and protecting plate (2) and the second supporting and protecting plate (3) are coated with engine oil (18).
7. The shear wall form support of claim 1, wherein: the positioning pipe (4) and the connecting column (5) are provided with five.
8. The shear wall form support of claim 1, wherein: the first supporting and protecting plate (2) and the second supporting and protecting plate (3) are both steel plates.
CN202122904354.7U 2021-11-24 2021-11-24 Shear wall template support Expired - Fee Related CN216553036U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122904354.7U CN216553036U (en) 2021-11-24 2021-11-24 Shear wall template support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122904354.7U CN216553036U (en) 2021-11-24 2021-11-24 Shear wall template support

Publications (1)

Publication Number Publication Date
CN216553036U true CN216553036U (en) 2022-05-17

Family

ID=81576016

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122904354.7U Expired - Fee Related CN216553036U (en) 2021-11-24 2021-11-24 Shear wall template support

Country Status (1)

Country Link
CN (1) CN216553036U (en)

Similar Documents

Publication Publication Date Title
CN103291065A (en) Prefabricated concrete supporting device and lifting and positioning method
CN212002593U (en) Telegraph pole fixing base convenient to mount
CN216553036U (en) Shear wall template support
CN214302188U (en) Assembled node structure
CN204401628U (en) Large-span steel supports multidirectional connector
CN104499490A (en) Large-span steel support multidirectional connecting piece and large-span deep foundation pit support construction method
CN216713346U (en) Energy-concerving and environment-protective type house construction is with steel construction node component
CN215803206U (en) Framework column formwork structure
CN215107875U (en) Double-locking tent frame mechanism
CN218581184U (en) Anti-tilting device for supporting building template
CN219621941U (en) Fixing structure of steel member for steel structure factory building
CN110805273A (en) Supporting member of concrete frame shear structure and mounting method
CN218911362U (en) PC composite pile convenient for rapid splicing
CN219196494U (en) Civil engineering reinforcing bar positioner for building engineering
CN203308066U (en) Support device for fabricated concrete
CN211736438U (en) Combined positioning regulator
CN220767687U (en) Assembled steel trestle connection system structure
CN221345874U (en) Building steel structure convenient to disassemble
CN220167156U (en) Prefabricated structure of concrete-steel pipe-fiber composite bar combination
CN213626641U (en) Template device is used in civil engineering construction
CN217872233U (en) Safety isolation device
CN214835005U (en) Safety protective guard for construction site
CN214461165U (en) Energy-saving building stress frame structure
CN219315701U (en) A connection structure that is used for steel bushing case to promote removable stand in station
CN221321278U (en) Reinforcing connecting device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20220517